HomeMy WebLinkAbout13-167JOSEPH E. SMITH, CLERK OF THE CIRCUIT COURT
SAINT LUCIE COUNTY
FILE # 3877189 09/18!2013 at 07:27 AM
OR BOOK 3560 PAGE 923 - 930 Doc Type: RESO
RECORDING: $69.50
Resolution 2013-167
File No.: SPMJ OS-028
A RESOLUTION OF THE ST. LUCIE BOARD OF COUNTY
COMMISSIONERS GRANTING APPROVAL TO A MAJOR
SITE PLAN PROJECT TO BE KNOWN AS
ST. LUCIE COMMERCE CENTER
WHEREAS, the Board of County Commissioners of St. Lucie County, Florida, based on
the testimony and evidence, including but not limited to the staff report, has made the
following determinations:
Lucie Rock, LLC, presented a petition for a Major Site Plan project, known as
St. Lucie Commerce Center to provide for the development of a 40 lot
subdivision on 94.26 acres located on North Rock Road approximately one-half
mile north of Orange Avenue, in the IL (Industrial, Light) and IH (Industrial,
Heavy) Zoning Districts for the property described in Section B.
2. The Development Review Committee has reviewed the site plan for the proposed
project and found it to meet all technical requirements and to be consistent with
the future land use maps of the St. Lucie County Comprehensive Plan, subject to
the conditions set forth in Part A of this Resolution.
3. The proposed project is consistent with the general purpose, goals, objectives
and standards of the St. Lucie County Land Development Code, the St. Lucie
County Comprehensive Plan and the Code of Ordinances of St. Lucie County.
4. The proposed project will not have an undue adverse effect on adjacent property,
the character of the neighborhood, traffic conditions, parking, utility facilities, or
other matters affecting the public health, safety and general welfare.
5. All reasonable steps have been taken to minimize any adverse effect of the
proposed project on the immediate vicinity through building design, site design,
landscaping and screening.
6. The proposed project will be constructed, arranged and operated so as not to
interfere with the development and use of neighboring property, in accordance
with applicable district regulations.
7. The proposed project will be served water and sewer services by the Fort Pierce
Utilities Authority (FPUA).
September 3, 2013 Resolution 2013-167
File No.: SPMJ 05-028
Page 1
8. The applicant has applied for and received a revised Certificate of Capacity, a
copy of which is attached to this order as Exhibit A, as required under Chapter V,
St. Lucie County Land Development Code.
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of St.
Lucie County, Florida:
A. Pursuant to Section 11.02.04 of the St. Lucie County Land Development Code, the
Major Site Plan project to be known as St. Lucie Commerce Center is hereby
approved as depicted on the site plan drawings for the project prepared by Cuozzo
Design Group, Inc. dated December 16, 2005, subsequently revised through August
26, 2013, and date stamped received by the St. Lucie County Planning Division on
September 3, 2013, subject to the following conditions:
1. Future development of the project is subject to adoption of the Development
Agreement with the property owner, Lucie Rock, LLC, and a determination of
consistency with the provisions of the Development Agreement, as may be
amended. All terms and conditions of the St. Lucie Commerce Center, LLC
Development Agreement are incorporated herein.
2. Within 90 days of this site plan approval, thirty (30) feet of road right-of-way
along the east side of Emerson Avenue/Laid Back Way, as more specifically
shown on the Major Site Plan shall be dedicated to St. Lucie County. Such
dedication shall be in a form and manner acceptable to the County Attorney.
3. Within 90 days of this site plan approval, twenty (20) feet of road right-of-way
along the west side of Rock Road, within Phase A, as shown on the Major
Site Plan shall be dedicated to St. Lucie County. Such dedication shall be in a
form and manner acceptable to the County Attorney.
4. Within 90 days of this site plan approval, twenty (20) feet of road right-of-way
along the west side of Rock Road, within Phase B, as shown on the Major
Site Plan shall be dedicated to St. Lucie County. Such dedication shall be in a
form and manner acceptable to the County Attorney.
5. Within 90 days of this site plan approval, ten (10) feet of road right-of-way
along Sunnyland Drive (5 feet on the north side of the road and 5 feet on the
south side), as more specifically shown on the Master Site Plan shall be
dedicated to St. Lucie County. Such dedication shall be in a form and manner
acceptable to the County Attorney.
September 3, 2013
File No.: SPMJ 05-028
Resolution 2013-167
Page 2
6. The Final Plat for any phase of development shall not be recorded until
constructible engineering plans are approved, and all common improvements
required for that phase are either:
a) built and accepted or approved by St. Lucie County; or
b) appropriate security is provided to St. Lucie County in a form approved
by the County Attorney and an amount approved by the County Engineer,
including an amount necessary to cover the period of maintenance required
by the Land Development Code.
7. Prior to issuance of the first certificate of occupancy for any portion of the
development, signalization of the Orange Avenue and Rock Road intersection
and the provision of left and right turn lanes shall be constructed and
approved by the County.
8. Prior to issuance of a building permit or Final Plat approval, the developer, or
his assigns, shall provide an executed copy of a final utility service agreement
with Ft. Pierce Utilities Authority, indicating all developer obligations, including
schedules associated with servicing this site.
9. The County's issuance of development approval does not constitute
compliance with any federal and state requirements. Applicable, federal and
state approvals/permits are required prior to the commencement of any
development activity (i.e. clearing, grading, removing structures, etc.). The
responsibility for contacting federal and state agencies, procuring
permits/approvals and compliance with applicable laws are the sole
responsibility of the applicant.
10. Per Florida Statute 125.022, the issuance of development approval does not
create any liability on the part of the county if the applicant fails to obtain
requisite approvals or fulfill the obligations imposed by a state or federal
agency or undertakes actions that result in a violation of state or federal law.
11. Copies of all applicable state or federal permits/written approvals are required
by the County prior to issuance of a Vegetation Removal Permit and any
development activity.
12. Prior to issuance of a Vegetation Removal Permit or Exemption, the applicant
shall schedule and conduct apre-construction meeting with St. Lucie County
staff to ensure that trees and native understory vegetation are protected,
supplemental irrigation is provided where necessary, and any necessary
pruning is conducted by a qualified arborist.
September 3, 2013
File No.: SPMJ 05-028
Resolution 2013-167
Page 3
13. The Landscape Plan for St. Lucie Commerce Center is incorporated in the
Master Site Plan. Landscape buffers, street trees and tree mitigation will be
provided in accordance with the Landscape Plan, provided however, that in
the event of any conflict between the Landscape Plan incorporated into the
Master Site Plan, and a landscape plan incorporated into a site plan for any
individual lot or lots approved by the County, the Landscape Plan
incorporated into the Master Site Plan shall be amended in accordance with
the LDC. The Developer acknowledges that all landscaping for any individual
lot or lots must be completed in accordance with the applicable provisions of
the St. Lucie County Land Development Code.
14. At the time of construction of the first phase of development on the Property,
the Developer shall construct the berm along the west boundary of the
Property (the "Berm") in accordance with the Master Site Plan.
15. When the Developer applies for site plan approval for any phase of
development on the Property, the Developer shall provide the County
Environmental Resources Department with (i) an updated tree survey and
mitigation table for such phase of development, if such phase of development
contains native trees meeting the size requirements of LDR Section
6.00.05. D, Table 1, and (ii) an updated Environmental Impact Report for such
phase of development, if required by LDR Section 11.02.09.A.5.
16. Prior to approval of any phase of development containing the Lake the
Developer shall provide the County Environmental Resources Department
with a Lake Area Monitoring and Management Plan.
B. The subject property on which this site plan approval as described in Part A above
are being granted is described as follows:
PARCEL 1
THE SOUTH ONE-HALF OF THE SOUTHWEST ONE-QUARTER OF SECTION 2,
TOWNSHIP 35 SOUTH, RANGE 39 EAST, ST. LUCIE COUNTY, FLORIDA, LESS AND
EXCEPT ALL RIGHTS-OF-WAY OF RECORD.
TOGETHER WITH:
PARCEL 2:
THAT PART OF THE NE 1/4 OF THE SW 1/4 OF SECTION 2, TOWNSHIP 35 SOUTH,
RANGE 39 EAST, LYING SOUTHWESTERLY OF I-95 LESS AND EXCEPT THE EAST
93 FEET AND THE SOUTH 60 FEET FOR ROAD AND CANAL RIGHT-OF-WAY. ALL
LYING AND BEING IN ST. LUCIE COUNTY, FLORIDA.
TOGETHER WITH:
PARCEL 3:
September 3, 2013
File No.: SPMJ 05-028
Resolution 2013-167
Page 4
FROM THE SOUTHEAST CORNER OF THE NW 1/4 OF THE SW 1/4 OF SECTION 2,
TOWNSHIP 35 SOUTH, RANGE 39 EAST, ST. LUCIE COUNTY, FLORIDA, RUN
NORTH 00°08'13" WEST ALONG THE 1/4 1/4 SECTION LINE 60 FEET TO THE POINT
OF BEGINNING, THENCE CONTINUE NORTH 00°08'13"W 846.63 FEET TO THE
SOUTHERLY RIGHT-OF-WAY LINE FOR INTERSTATE 95 HIGHWAY; THENCE RUN
NORTH 60°08'02" WEST ALONG SAID RIGHT-OF-WAY LINE 107.58 FEET; THENCE
RUN NORTH 62°25'28" WEST 300.24 FEET; THENCE RUN NORTH 60°08'02" WEST
182.77 FEET; THENCE RUN SOUTH 00°11'29" WEST 346.62 FEET; THENCE RUN
SOUTH 60°08'02" EAST 354.41 FEET; THENCE RUN SOUTH 00°08'13" EAST, 607.48
FEET; THENCE RUN NORTH 89°53'47" EAST, 210 FEET TO THE POINT OF
BEGINNING.
BILLBOARD PARCEL:
BEING A PART OF THE NORTHEAST 1/4 OF THE SOUTHWEST 1/4 OF SECTION 2,
TOWNSHIP 35 SOUTH, RANGE 39 EAST, ST. LUCIE COUNTY, FLORIDA, BEING
MORE FULLY DESCRIBED AS FOLLOWS:
COMMENCING AT THE SOUTHEAST CORNER OF THE NORTHWEST 1/4 OF THE
SOUTHWEST 1/4, SECTION 2, TOWNSHIP 35 SOUTH, RANGE 39 EAST, ST. LUCIE
COUNTY, FLORIDA THENCE N00°40'25"W ALONG THE 1/4 1/4 SECTION LINE
904.94 FEET TO THE SOUTH RIGHT-OF-WAY LINE OF INTERSTATE HIGHWAY 95;
THENCE ALONG SAID SOUTH RIGHT-OF-WAY LINE, S60°50'22"E, 700.71 FEET TO
THE POINT OF BEGINNING: THENCE S29°09'38"W, 125.00 FEET; THENCE
S60°50'22"E, 125.00 FEET; THENCE N29°09'38"E, 125.00 FEET TO THE SAID
SOUTH RIGHT-OF-WAY LINE OF INTERSTATE HIGHWAY 95; THENCE N60°50'22"W
ALONG SAID SOUTH RIGHT-OF-WAY LINE 125.00 FEET BACK TO THE POINT OF
BEGINNING.
INGRESS/EGRESS EASEMENT:
BEING A PART OF THE NORTHEAST 1/4 OF THE SOUTHWEST 1/4 OF SECTION 2,
TOWNSHIP 35 SOUTH, RANGE 39 EAST, ST. LUCIE COUNTY, FLORIDA, BEING
MORE FULLY DESCRIBED AS FOLLOWS:
COMMENCING AT THE SOUTHEAST CORNER OF THE NORTHWEST 1/4 OF THE
SOUTHWEST 1/4, SECTION 2, TOWNSHIP 35 SOUTH, RANGE 39 EAST, ST. LUCIE
COUNTY, FLORIDA THENCE N00°40'25"W ALONG THE 1/4 1/4 SECTION LINE
904.94 FEET TO THE SOUTH RIGHT-OF-WAY LINE OF INTERSTATE HIGHWAY 95;
THENCE ALONG SAID SOUTH RIGHT-OF-WAY LINE S60°50'22"E, 825.71 FEET TO
THE POINT OF BEGINNING: THENCE S29°09'38"W, 30.00 FEET; THENCE
S60°50'22"E, 682.21 FEET TO THE WEST RIGHT-OF-WAY LINE OF ROCK ROAD;
THENCE ALONG THE SAID WEST RIGHT-OF-WAY LINE OF ROCK ROAD
N00°45'37"W, 34.61 FEET TO THE SOUTH RIGHT-OF-WAY LINE OF INTERSTATE
HIGHWAY 95; THENCE N60°50'22"W ALONG THE SAID SOUTH RIGHT-OF-WAY
LINE OF INTERSTATE HIGHWAY 95 664.95 FEET BACK TO THE POINT OF
BEGINNING.
CONTAINING 94.258 ACRES, MORE OR LESS.
Location: North Rock Road, approximately 1/2 mile north of Orange Avenue.
September 3, 2013
File No.: SPMJ 05-028
Resolution 2013-167
Page 5
GENERAL PROVISIONS
C. The approvals granted by this Resolution are for the purpose of obtaining a Building
Permit or Zoning Compliance from St. Lucie County, and shall expire on
September 3, 2015, unless a Building Permit or Zoning Compliance is obtained for
the uses described in Part A above, or an extension has been granted in accordance
with Section 11.07.05(F), St. Lucie County Land Development Code, or a
Development Agreement approved in accordance with Section 11.08.00 that
provides for a later expiration date.
D. The approval and authorizations granted by this Resolution are specifically
conditioned to the requirement that the petitioner, Lucie Rock, LLC, shall obtain all
necessary development permits and construction authorizations from the
appropriate State and Federal regulatory authorities, including but not limited to: the
United States Army Corps of Engineers, the Florida Department of Environmental
Protection, and the South Florida Water Management District, prior to the issuance
of any local building permits of authorizations to commence development activities
on the property described in Part B.
E. The Certificate of Capacity, a copy of which is attached to this resolution, shall
remain valid for the period of the Site Plan approval. Should the Site Plan approval
granted by this resolution expire or an extension be sought pursuant to Section
11.07.05(F) of the St. Lucie County Land Development Code, a new Certificate of
Capacity shall be required.
F. The conditions set forth in Part A above are an integral nonseverable part of the Site
Plan approval granted by this Resolution. If any condition set forth in Part A are
determined to be invalid or unenforceable for any reason and the developer declines
to comply voluntarily with that condition, the Site Plan approval granted by this
resolution shall become null and void.
G. A copy of this resolution shall be attached to the site plan drawings described in Part
A, which plan shall be placed on file with the St. Lucie County Planning and
Development Services Director. The St. Lucie Planning and Development Services
Director is hereby authorized and directed to cause the notation of this resolution to
be made on the Official Zoning Map of St. Lucie County, Florida, and to make the
notation of reference to the date of adoption of this resolution.
September 3, 2013
File No.: SPMJ 05-028
Resolution 2013-167
Page 6
After motion and second, the vote on this resolution was as follows:
Chairman Tod Mowery AYE
Vice-Chair Frannie Hutchinson AYE
Commissioner Paula Lewis AYE
Commissioner Chris Dzadovsky AYE
Commissioner Kim Johnson AYE
PASSED AND DULY ADOPTED this 3rd day of September 2013.
BOARD OF COUNTY COMMISSIONERS
ST. LUCIE COUNTY, FLOIRDA
BY ~~
Chairman
ATTEST: ~~,~ ,~~=~u APPROVED AS TO FORM
.~c'a'~~~,_ AND CORRECTNESS:
~ _.~- - ~, ~1~
-.COUNTY A ORNEY
~. r'
September 3, 2013
File No.: SPMJ 05-028
Resolution 2013-167
Page 7
Date 8/28/2013
St Lucie County
Certificate of Capacity
Certificate No. 2918
This document certifies that concurrency will be met and that adequate public facility
capacity exists to maintain the standards for levels of service as adopted in the St
Lucie County Comprehensive Plan for:
1. Type of development Major Site Plan
Number of units 0 Number of square feet 1232835
2. Property legal description & Tax ID no.
230234100010008,230231200200007,230232100100002,230234200010001,230233100010007
N Rock Rd, .5 mi north of Orange Ave
St. Lucie Commerce Center
3. Approval: Building
Resolution No. 2013-167 Letter
4. Subject to the following conditions for concurrency:
See Res 2013-167 and Development Agreement
Owner's name
Lucie Rock, LLC
Address
P.O. Box 279
Biscayne Bay FL 33149
6. Certificate Expiration Date 9/3/2015
This Certificate of Capacity is transferable only to subsequent owners of the same
parcel, and is subject to the same terms, conditions and expiration date listed herein.
The expiration date can be extended only under the same terms and conditions as the
underlying development orderissued with this certificate, or for subsequent
development order(s) issued for the same property, use and size as described herein.
Signed ~ Date: 9/17/2013
Planning and Development Services Director
St Lucie County, Florida
Tuesday, September 17, 2013 Page 1 of 2