HomeMy WebLinkAbout17-012RESOLUTION NO. 17-012
A RESOLUTION OF THE ST. LUCIE COUNTY BOARD OF COUNTY
COMMISSIONERS RELATING TO THE CONSTRUCTION AND
FUNDING OF POTABLE WATER AND FIRE PROTECTION
IMPROVEMENTS BENEFITTING REAL PROPERTY LOCATED WITHIN
THE PARKLAND MSBU; SUPPLEMENTING COUNTY RESOLUTION
NOS. 2015-172 AND 2015-188; REDUCING THE AMOUNT OF THE
SPECIAL ASSESSMENT IMPOSED AGAINST THE PARCELS
COMPRISING THE PARKLAND MSBU IN LIGHT OF LOWER THAN
ESTIMATED CONSTRUCTION COSTS; AUTHORIZING PARTIAL
REFUNDS FOR ASSESSMENTS WHICH WERE PREPAID IN FULL;
APPROVING AND FINALIZING THE ASSESSMENT ROLL; AND
PROVIDING AN EFFECTIVE DATE.
BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF ST. LUCIE COUNTY
AS FOLLOWS:
SECTION 1. AUTHORITY. This Resolution of the St. Lucie County Board of
County Commissioners (the "Board") is adopted pursuant to the provisions of Article IV of
Chapter 40 of the County Code of Ordinances (as successor to Chapter 1-13.6 thereof) (the
"Assessment Ordinance"), sections 125.66, 197.3632, and 197.3635, Florida Statutes, and other
applicable provisions of law, and County Resolution Nos. 2015-172 and 2015-188 (collectively,
the "Initial Resolutions").
SECTION 2. DEFINITIONS. All capitalized terms in this Resolution shall have
the meanings defined in the Assessment Ordinance and the Initial Resolutions.
SECTION 3. FINDINGS. It is hereby ascertained, determined and declared
that:
(A) The Initial Resolutions described the potable water and fire protection
improvements comprising the Project, provided for the funding thereof through Assessments
and the method of assessing the cost of such improvements against the real property located
I
within the Parkland MSBU benefited by the Project, and approved the preliminary Assessment
Roll.
(B) The amount of the Assessments imposed against Assessed Property was based
on construction cost estimates developed at the time the Initial Resolutions were adopted.
(C) Construction of the Project is now complete and the actual costs associated with
the Project are known. The final cost of the Project is less than the preliminary estimates used
to develop the Assessments and Assessment Roll.
(D) Section 5(E) of Resolution No. 2015-188 provides that the Assessment imposed
against each Parcel may be reduced upon completion of the Project based upon lower than
expected construction costs, and that such reduction shall be established by supplemental
resolution of the Board.
(E) This Resolution is adopted for purposes of reducing the Assessment imposed
against the Parcels comprising the Parkland MSBU to reflect the actual cost of the Project,
approving and finalizing the Assessment Rall for the Project, and authorizing a partial refund
for the owners of Assessed Property who prepaid the Assessment based on the higher cost
estimate.
SECTION 4. ASSESSMENT REDUCTION. In light of the lower than estimated
construction costs for the Project and related interest savings, the Board hereby determines as
follows:
(A) The total amount of the Assessment imposed against each ERC included on the
Assessment Rall shall be reduced by $582.13, such that the annual installment of the
Assessment collected from each ERC shall be reduced from $636.40 to $578.60 beginning with
2
the installment to be collected in November, 2017 and thereafter for the remainder of the
Assessment term.
(B) Sixteen of the ERCs were prepaid in full by the owners of Assessed Property on
or prior to December 30, 2015, as authorized by Section 7 of Resolution No, 2015-188. The
Assessment Coordinator is authorized to process a partial refund for the prepaid ERCs in the
amount of $1,031.83 each. Such partial refund shall be paid to the current owner of the
Assessed Property for which prepayment was made.
SECTION 6. APPROVAL OF ASSESSMENT ROLL.
(A) The Assessment Roll has been updated to reflect the reduced Assessments as
provided for herein and is now finalized. The updated Assessment Roll, a copy of which is on
file in the office of the County Engineer and incorporated herein by reference, is hereby
approved. The Assessment Coordinator is authorized and directed to certify the updated
Assessment Roll to the Tax Collector for collection pursuant to the Uniform Assessment
Collection Act, and to take such actions as may be necessary or desirable in furtherance
thereof.
(B) The updated Assessment Roll shall be retained by the Assessment Coordinator
and shall be available for public inspection.
SECTION 7. RATIFICATION AND CONFIRMATION OF INITIAL RESOLUTION
AND PRIOR ACTIONS.
(A) As supplemented herein, the Initial Resolutions are hereby ratified and
confirmed.
3
(B) Any and all prior actions of the Board and County staff associated with the
imposition of Assessments to fund the Project are hereby approved, ratified and confirmed in
their entirety.
[Remainder of Page Intentionally Left Blank]
4
SECTION S. EFFECTIVE DATE. This Resolution shall take effect immediately upon its
passage and adoption.
AFTER MOTION AND SECOND, the vote on this Resolution was as follows:
Chairman Chris Dzadovsky
AYE
Vice Chairman Tod Mowery
AYE
Commissioner Linda Bartz
AYE
Commissioner Frannie Hutchinson
ABSENT
Commissioner Cathy Townsend
AYE
PASSED AND DULY ADOPTED this 24th day of January, 2017.
ATTEST:
Deputy Clerk
5
BOARD OF COUNTY COMMISSIONERS
ST. LUCIE COUNTY, FLORIDA
By: _ 2"..e
Chairmdn
APPROVED AS TO FORM AND
CORRECTNESS:
County