HomeMy WebLinkAboutPDS-20-008 - Faux Effects (fka Gem Electric/Harpetco) - 2700 Industrial Avenue 2PDS 2020-008
File No. SPMj-10201925619
AN ORDER GRANTING APPROVAL FOR A MINOR
ADJUSTMENT TO MAJOR SITE PLAN KNOWN AS FAUX
EFFECTS (FKA GEM ELECTRIC/HARPETCO) FOR A
PROPERTY LOCATED AT 2700 INDUSTRIAL AVENUE 2, FORT
PIERCE, FL
WHEREAS, the St. Lucie County Planning and Development Services Director has reviewed the
application for Minor Adjustment to a Major Site Plan submitted by MBV Engineering, Inc. on behalf
of Faux Effects, and the comments made by the St. Lucie County Development Review Committee
on this application and has made the following determinations:
1. MBV Engineering, Inc. filed an application on behalf of Faux Effects for a Minor Adjustment
to the Major Site Plan known as Faux Effects, for the purpose of constructing two internal
tenant lease spaces and additional parking and vehicular use areas to support new tenants.
2. On February 26, 1985, the Board of County Commissioners approved Resolution 85-39,
granting Major Site Plan approval for the construction of a 40,000 sq. ft. electric goods
manufacturing facility previously known as Harpetco, on approximately 4.86 acres of land
as described in Part B, within the IL (Industrial Light) Zoning District.
3. On May 10, 1988, the Board of County Commissioners approved Resolution 88-118,
granting a Minor Adjustment to the Major Site Plan for a 30,000 sq. ft. expansion for the
facility to be known as Gem Electric (FKA Harpetco).
4. The St. Lucie County Development Review Committee has reviewed the proposed Minor
Adjustment to the Major Site Plan and found it to meet the technical requirements of the
St. Lucie County Land Development Code, and to be consistent with the St. Lucie County
Comprehensive Plan, and to have satisfied the standards of review set forth in Section
11.02.07, Standards for Site Plan Review, subject to the conditions set forth in Part "A" of
this Order.
5. The proposed project will not have an undue adverse effect on adjacent property, the
character of the neighborhood, traffic conditions, parking, utility facilities, or other matters
affecting the public health, safety, and general welfare.
6. All reasonable steps have been taken to minimize any adverse effect of the proposed
project on the immediate vicinity through building design, site design, landscaping, and
screening.
7. The proposed project will be constructed, arranged, and operated so as not to interfere
with the development and use of neighboring property, in accordance with applicable
district regulations.
I
8. The proposed project is to be served by the Fort Pierce Utilities Authority water and
wastewater services.
JOSEPH E. SMITH, CLERK OF THE CIRCUIT COURT
SAINT LUCIE COUNTY
Page 1 FILE # 4688364 03/17/2020 08:34:15 AM PDS No. 2020-008
OR BOOK 4396 PAGE 2563 - 2568 Doc Type: ORD File No.: SPMn-10201925619
RECORDING: $52.50
9. Planning Staff has performed detailed analysis of the project and determined it to be
consistent with Sections 11.02.04(C) Minor Adjustment to Major Site Plan and 11.02.07.,
Standards for Site Plan Review, of the St. Lucie County Land Development Code. The
analysis is found in the Staff Report for the Faux Effects Minor Adjustment to the Major Site
Plan, dated March 6, 2020.
10. A Certificate of Capacity Exemption has been issued for this development, a copy of which
is attached to this order in Exhibit "C", as required under Chapter V, St. Lucie County Land
Development Code.
NOW, THEREFORE, BE IT ORDERED:
A. Pursuant to Section 11.02.04 of the St. Lucie County Land Development Code, the Minor
Adjustment to the Faux Effects Major Site Plan is hereby approved as shown on the site
plan drawings prepared by MBV Engineering, Inc. dated August 5, 2019, and date stamped
received by the St. Lucie County Planning and Development Services Department on
January 22, 2020, as depicted in Exhibit "A" subject to the following conditions:
Prior to issuance of a Certificate of Occupancy, all Category I listed invasive plant
species shall be eradicated from the site, pursuant to Land Development Code Section
7.09.05.
B. The property on which this Minor Adjustment to Major Site Plan, as depicted in Exhibit "B"
is being granted is described as follows:
LEGAL DESCRIPTION:
Lot 9, 10, 11, and 12, Block 5, Airport Industrial Park Unit One, according to the map or
Plat thereof as recorded in Plat Book 12, Page(s) 40, Public Records of St. Lucie County,
Florida.
PARCEL ID No.: 1429-501-0073-000-0
C. The approvals granted by this administrative order shall expire twenty-four (24) months
from the effective date, unless a Building Permit is obtained or an extension is granted in
accordance with the provisions of Section 11.02.06 of the St. Lucie County Land
Development Code.
D. The developer, including any successors in interest, is advised as part of this Minor
Adjustment approval for Faux Effects, all applicable development permits and construction
authorizations shall be obtained from the appropriate State and Federal and Local
regulatory agencies including, but not limited to, the United States Army Corps of
Engineers, the Florida Department of Environmental Protection, and South Florida Water
Management District, and the St. Lucie County Environmental Resources, Public Works,
and Building Departments prior to the commencement of any development activities on the
property described in Part B. Issuance of this permit by the County does not in any way
create any rights on the part of the developer to obtain a permit from a state or federal
agency and does not create any liability on the part of the County for issuance of this permit
if the developer fails to obtain requisite approvals or fulfill the obligations imposed by a state
or federal agency or undertake actions that may result in a violation of state or federal law.
E. This Order shall become effective upon the date of approval indicated below. Should the
Page 2 PDS No. 2020-008
File No.: SPMn-10201925619
property owner, developer or authorized agent wish to appeal any condition described in
Part A above, all such appeals must be filed in writing with the County Administrator within
30 days of the rendering of this Order, as described in Section 11.02.04(B), St. Lucie
County Land Development Code. Should an appeal to this Order be filed, no permitting
reviews or further administrative action shall take place on the processing of this
development project until the appeal is resolved.
F. A copy of this Order shall be attached to the site plan drawings described in Part A, which
plan shall be placed on file with the St. Lucie County Planning and Development Services
Department and mailed to the developer and agent of record as identified on the site plan
application.
G. The conditions set forth in Part A are an integral non -severable part of the site plan approval
granted by this Order. If any condition set forth is Part "A" is determined to be invalid or
unenforceable for any reason and the developer declines to comply voluntarily with that
condition, the site plan approval granted by this order shall become null and void.
H. This order shall be recorded in the Public Records of St. Lucie County.
�
I1 t
ORDER effective the l M " day of N` 2020.
PLANNING & DEVELOPMENT SERVICES DIRECTOR
ST. I,LICIE COUNTY, FLORIDA
Olsorf, AICP
APPROVED AS\TO FORM
AND CORREC—NESS:
BY
County Attorney
Page 3
PDS No. 2020-008
File No.: SPMn-10201925619
EXHIBIT A
(Location
M
G 2
Subject)to
-
Parcel
C,__:_-
- - — StiLuc
ie. IlBlvd �, ,— .1
IC
-71
A—i.-._
N
Page 4 PDS No. 2020-008
File No.: SPMn-10201925619
EXHIBIT B
(Approved Site Plan)
ASWM
Is
Mqd 3115
E Go
I
Page 5 PIDS No. 2020-008
File No.: SPMn-10201925619
EXHIBIT C
(Certificate of Capacity Exemption)
St Lucie County
Certificate of Capacity Exemption
Date 312f2020 Certificate No, 6385
This document certifies that concurraency will be met and that adequate public facility
capacity exists to maintain the -standards for Levels of service as adopted 1n the St
Lucie County Comprehensive Plan for:
1. Type of development !Mincer Adiustnient to Major Site Plan
Number of units Number of square feet 70,017
2. Property regal description & Tax ID no.
1429-501-0073-000-0
2700 Industrial Avenue 2, Fort Picrcc 1=L
Faux Effects (FICA Gent Elcc(ric I Hatpelco)
3. Approval: Building
4. As part of the development:
S. On property yawned by
Raymond 5andor
115 McKee Lane
Vero Beach FL 32960
Airport Industrial. Park
Resolution No. PDS 2020-002 Letter
ie hereby granted a Certitica0e of Capacity Exemption according to the following Chepter(si of the St. Lucie County
Land Development Code; ❑ S,03.02(A) ❑ 5.e3.02(BI1 El 5.03.02(11I2 ❑ 5.03.02(B)3 ❑ 0.03.02(B)4
5.03.02(B)5 ❑ 5.03.02(B)6 ® 5.03.04(A) El 6.0104(A)2 ID 6.03.04(A)3
UR 5.03.04(B)i ❑ 6.03."03)2 CJ 6.e3.04(8)3 ❑ 6.03.04(B)4
S, Certificate Expiration Date
This Certificate of Capacity is transferable only to subsequent owners of the same
parcel, and is subject to the same terms, conditions and expiration date listed herein.
The expiration date can be extended only under the same terms and conditions as the
underiyl g develop ent orderissued with this certificate, or for subsequent
develomentJ'lardekA issued for the some prop", use and size as described herein.
Signed V 31412020
lannTaoDevelopment Services Director
St Lucnty, Florida
Page 6 PDS No. 2020-008
File No.: SPMn-10201925619