HomeMy WebLinkAboutPDS-20-052 - Maverick Boat CompanyPDS ORDER 2020-052
File No.: SPMn-2202025685
AN ORDER GRANTING A MINOR ADJUSTMENT TO THE MAJOR SITE
PLAN FOR THE PROJECT KNOWN AS MAVERICK BOAT COMPANY
FOR PROPERTY LOCATED AT 4551 ST. LUCIE BOULEVARD
WHEREAS, the St. Lucie County Planning and Development Services Director has reviewed the
request for a Minor Adjustment to the Major Site Plan for the project known as Maverick Boat
Company, the recommendation of the Development Review Committee, and has made the
following determinations:
Jim Leffew, of Maverick Boat Group Inc., and representative, Scott McGuire, P.E., of KMA
Engineering & Surveying, LLC, filed an application requesting a Minor Adjustment to the
Major Site Plan to amend the parking lot configuration for the existing boat manufacturing
facility and phased build -out. This parking lot modification, titled Phase 1 B, seeks to add
130 parking spaces within a new Phase 1 B, providing 282 total parking spaces in Phase 1,
with 378 parking spaces provided at build -out. The subject 36.33-acre property is located
at 4551 St. Lucie Boulevard, Fort Pierce, within the IL (Industrial, Light) Zoning District.
2. On May 16, 2017, the Board of County Commissioners approved Resolution 2017-112,
granting Major Site Plan Approval for the construction of a 252,500 sq. ft. (280,400 sq. ft.
inclusive of covered areas) boat manufacturing facility, to be constructed in four (4) phases
on approximately 36.33 acres of land as described in Part B, within the IL (Industrial Light)
Zoning District, located at 4551 St. Lucie Boulevard.
3. On September 24, 2018, the Planning and Development Services Director granted
approval of PDS 18-056 for a Minor Adjustment to the Major Site Plan to amend the
parking configuration and access driveways to loading areas, reduce surplus (non -
required) parking spaces, and correct minor errors within the site area data table.
4. The Development Review Committee reviewed the proposed Site Plan for the project and
found it meets the technical requirements of the St. Lucie County Land Development Code
and has satisfied the standards of review set forth in Section 11.02.07, Standards for Site
Plan Review, of the St. Lucie County Land Development Code.
Planning Staff has performed a detailed analysis of the project and determined it to be
consistent with the St. Lucie County Land Development Code and Comprehensive Plan.
The analysis is located in the Planning and Development Services Department
memorandum titled Maverick Boat Company— Phase 1 B — MinorAdjustment to the Major
Site Plan (SPMn-2202025685), dated August 6, 2020.
6. The proposed project will not have an undue adverse effect on adjacent property, the
character of the neighborhood, traffic conditions, parking, utility facilities, or other matters
affecting the public health, safety, and general welfare.
JOSEPH E. SMITH, CLERK OF THE CIRCUIT COURT
SPMn-2202025685 SAINT LUCIE COUNTY
PDS 2020-052 FILE # 4746916 08/27/2020 09:13:38 AM
Page 1 of 6 OR BOOK 4467 PAGE 920 - 925 Doc Type: ORD
RECORDING: $52.50
7. All reasonable steps have been taken to minimize any adverse effects of the proposed
project on the immediate vicinity through building design, site design, landscaping, and
screening.
NOW, THEREFORE, BE IT ORDERED BY THE PLANNING AND DEVELOPMENT SERVICES
DIRECTOR OF ST. LUCIE COUNTY, FLORIDA:
A. Pursuant to Section 11.02.04 and 11.02.07 of the St. Lucie County Land Development Code,
the Minor Adjustment to the Major Site Plan is hereby approved as shown on the Site Plan
drawings prepared by KMA Engineering & Surveying, LLC, revised through June 8, 2020, and
date stamped by the Planning & Development Services Department on June 10, 2020, subject
to the following conditions:
Planning and Development Service Department, Planning Division
1) Prior to a Certificate of Occupancy for Phase II development as depicted on the Site Plan,
the applicant shall install the ingress turn lanes (an eastbound right -turn lane and a
westbound left -turn lane) within the right-of-way at the intersection of St. Lucie Boulevard
and Hammond Road and modify the east driveway to provide exclusive left and right turn
egress lanes in order to decrease the amount of internal queuing during the peak hours.
2) All boat manufacturing activities shall occur within an enclosed structure.
Environmental Resources Department
3) Within 90 days of this Minor Adjustment approval, all Category I listed invasive species shall
be eradicated from the site and landscaping shall be installed consistent with the Site Plan
dated March 19, 2020 and approved by the Environmental Resources Department.
4) Prior to beginning site work, a vegetation permit application will be required to be submitted.
Public Works Department, Water Quality Division
5) Prior to the issuance of a Building Permit for Phase 11 improvements as depicted on the Site
Plan, off -site construction (engineering) plans shall be submitted to the Water Quality
Division for review and approval.
B. The property on which this Minor Adjustment to the Major Site Plan is being granted is
described as follows:
LEGAL DESCRIPTION:
The northwest 1 /3, of the northeast 1 /3 of Section 31, Township 34 south, Range 40
east, LESS the north 98 feet lying in St. Lucie County, Florida.
Parcel Identification Number: 1431-120-0000-000-6
SPMn-2202025685
PDS 2020-052
Page 2 of 6
Address: 4551 St. Lucie Boulevard, Fort Pierce, FL 34946
C. This Minor Adjustment to the Major Site Plan for Maverick Boat Group, Inc. shall expire
within twenty-four (24) months of the effective date of this Order, unless a building permit is
issued or an extension is granted in accordance with Section 11.02.06, St. Lucie County
Land Development Code.
D. The developer is advised as part of this Minor Adjustment to the Major Site Plan approval
for Maverick Boat Group, Inc., including any successors in interest, the developer shall
obtain all applicable development permits and construction authorizations from the
appropriate State and Federal and local regulatory agencies including, but not limited to,
the United States Army Corps of Engineers, the Florida Department of Environmental
Protection, and South Florida Water Management District, and the St. Lucie County
Environmental Resources Public Works and Building Departments prior to the
commencement of any development activities on the property described in Part B.
Issuance of this approval by the County does not in any way create any rights on the part
of the developer to obtain a permit from a State or Federal agency and does not create any
liability on the part of the County for issuance of this permit if the developer fails to obtain
requisite approvals or fulfill the obligations imposed by a State or Federal agency or
undertake actions that may result in a violation of State or Federal law.
E. A copy of this Order shall be attached to the Site Plan drawings described in Part A, which
then shall be placed on file with the St. Lucie County Planning and Development Services
Department and mailed to the developer and agent of record as identified on the Site Plan
application.
F. The conditions set forth in Part A are an integral non -severable part of the Minor
Adjustment to the Major Site Plan approval granted by this Order. If any condition set forth
in Part A is determined to be invalid or unenforceable for any reason and the developer
declines to comply voluntarily with that condition, the Site Plan approval granted by this
Order shall become null and void.
G. A Certificate of Capacity Exemption, a copy of which is attached hereto as Exhibit B and
made a part hereof the Order, was granted by the Planning and Development Services
Department Director, which shall remain valid for the period of Site Plan approval.
H. This Order shall be recorded in the Public Records of St. Lucie County.
SPMn-2202025685
PDS 2020-052
Page 3 of 6
This ORDER effective the day of August 2020.
SPMn-2202025685
PDS 2020-052
PLANNING AND DEVELOPMENT SERVICES
ST. LWCIE GOUNTY,t FLORIDA
I.1yo
Isonj AICP, Director
APPROVED AS TO"FORM
AND CORR TNESS:
BY
County Attorney
Page 4 of 6
SPMn-2202025685
PDS 2020-052
EXHIBIT "A"
Amended Site Plan
Page 5 of 6
EXHIBIT "B"
Certificate of Capacity Exemption
tit I.ucle ( ounl%
( rrhficulc 1►f ( upltcit% t %aim ►lun)
Date x , ' Certificate No -
This document certifies that concurrency will be met and that adequate public facility
capacity elfish to maintain the standards lot levels of service as adopted in the St
Lucia County Comprehensive Plan for
t type of develot"nent
Number of units Number of %quart feet
2 Property legal description 6 Tax ID no
J Approval Suildinq Resolution No Letter
4. As part of the devolopmont
5 On property owned by
Jm► 1.01c'A
45SI %I 1_ew►a Il.ti;rtiarJ
Fort Pillrco 11 14%16
is too by panted • CarUhute 00 Capeaslr iaesa/MMI ettett),ng rt. Pa 1011tt++ng (.1.0pWIS) of Ilia yl 1 ut io (.oia+rr
1 anti Ue,wiorw itni Code S o) 0llA) LJ to3w(ell S 0) 0119i2 S 0) 02(903 S 03 OIr9N
S 01 00" V wwo)(RiG S 0) WIAI S 0) 041A)2 S 03 041A0
S 03 041111I1 163'"S)I S 01 "813 S 03 0419A
G. Certificate Expiration Date
This Certificate of Capacity is traneferable only to subsequent owners of the some
parcel, and Is subject to the same Terms. conditions and expiration date listed herein
The expiration date can be extended only under the same terms and conditions as the
underlying developryietil ordetissued with this cerllficale, or for subsequent
devolopmInt tt►derls) Issued for ilia sarnt property, use and site as described herein
�rcncd ' ' i fay � _ IMr: R+Lin0:U
planning aPd Development ServkM DUrctor
St Lt Comty, Florida
SPMn-2202025685
PDS 2020-052
Page 6 of 6