A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF
ST. LUCIE COUNTY FOR A CONDITIONAL USE PERMIT TO
DEVELOP A FOUR (4) STORY SELF-STORAGE BUILDING WITH
OFFICE SPACE TOTALING 124,200 SQUARE FEET WITHIN THE
KINGSGATE CENTER PLANNED NON-RESIDENTIAL DEVELOPMENT
(PNRD) FOR PROPERTY LOCATED IN ST. LUCIE COUNTY, FLORIDA.
WHEREAS, the Board of County Commissioners of St. Lucie County, Florida, based on
the testimony and evidence, including but not limited to findings in the staff report and
traffic analysis review, has made the following determinations:
1. PSC Storage Holdings, LLC presented a petition for a Conditional Use Permit to
allow for the development of a four (4) story self-storage building with office
space totaling 124,200 square feet. The site will include eight (8) vehicular
parking spaces, a vehicular portico over the loading zone, and improved
landscaping within the Kingsgate Center Planned Non-Residential Development
(PNRD). The property is located on the southwest corner of Orange Avenue and
Kings Highway on Lot three (3) of Kingsgate Center, as legally described in
Paragraph "B" and depicted on the attached map as Exhibit "A".
2. On December 14, 2023, the St. Lucie County Planning and Zoning Commission
held a public hearing on the petition after publishing notice in the St. Lucie News
Tribune at least 10 days prior to the hearing, installing a sign on the property and
notifying by mail all owners of property within five hundred (500) feet of the
subject property, and recommended that the Board of County
Commissioners approve request for a Conditional Use Permit.
3. On January 9, 2024, this Board held a public hearing on the petition, after
publishing notice in the St. Lucie News Tribune at least 10 days prior to the
hearing, installing a sign on the property and notifying by mail all owners of
property within 500 feet of the subject property, at which all interested persons
were given an opportunity to be heard.
4. All reasonable steps have been taken to minimize any adverse effect of the
proposed Conditional Use on the immediate vicinity through site design,
landscaping screening.
5. The proposed Conditional Use, with conditions therein, will not have an undue
adverse effect on adjacent property, the character of the neighborhood, traffic
conditions, parking, utility facilities, or other matters affecting the public health,
safety and general welfare.
MICHELLE R.MILLER,CLERK OF THE CIRCUIT COURT
SAINT LUCIE COUNTY
FILE# 5302248 02/21/2024 08:13.18 AM Resolution No. 2024-041
OR BOOK 5109 PAGE 1469-1475 Doc Type:RESO File No. CU-2310-000063
RECORDING: $61.00 Page 1
6. A Certificate of Capacity, a copy of which is attached hereto as Exhibit "C", was
granted by the Planning and Development Services Director.
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of St.
Lucie County, Florida:
A. Pursuant to Section 11.07.00 of the St. Lucie County Land Development Code,
the Conditional Use Permit for the project to be known as Kingsgate Center Self-
Storage Facility, as shown on the drawings for the project prepared by Newlines
Land Consultants, dated May 22, 2023, is hereby approved, for the subject
property described in Paragraph B, subject to the following conditions:
1. Prior to associated building permit issuance, the wall signs or ground sign
shall require review and approval by the Planning Division for compliance with
the LDC Section 7.10.24.G Signs and Lighting Standards.
2. Prior to commencement of development, including, but not limited to clearing,
filling, excavation, grading, or planting of vegetation, as defined in LDC
2.00.00, a 100% gopher tortoise survey conducted by a state certified gopher
tortoise agent per Florida Fish and Wildlife Conservation Commission (FWC)
protocol shall be provided.
3. Prior to issuance of a Certificate of Occupancy, all Category I listed invasive
plants shall be eradicated from the site.
4. Prior to the issuance of a Certificate of Occupancy, the County will seek
resurfacing of the existing roadway (north of the subject site) to address the
disrepair in the roadway.
5. The applicant, property owner, developer, successors, or assigns shall be
responsible for contributing wayfinding signage and park benches within
implementation of the Kingsgate Center Park, as identified on the site plan.
6. A Site Development Permit is required prior to performing site improvement
activities. The Site Development Permit application can be found on the
County's website under the Public Works Department link. In accordance with
the permit and Land Development Regulations, the applicant shall retain the
FOR for site inspections and final certification.
B. The property on which this Conditional Use Permit is being granted is described
as follows:
Legal Description:
LOT 3, KINGSGATE CENTER, ACCORDING TO THE PLAT THEREOF, AS
RECORDED IN PLAT BOOK 99, PAGE 24, OF THE PUBLIC RECORDS OF ST.
LUCIE COUNTY, FLORIDA.
Resolution No. 2024-041
File No. CU-2310-000063
Page 2
Location: Southwest corner of Orange Avenue and Kings Highway (Kingsgate
Center Lot 3).
Parcel Identification No.: 2311-801-0004-000-8
C. The approvals and authorizations granted by this Resolution are for the purpose
to construct and operate a self-storage facility within St. Lucie County, and are
not assigned to any other party or institution. Should the petitioners choose or
decide to assign this operation to another entity or individual, a Minor Adjustment
to the Conditional Use Permit shall be required.
D. The approvals and authorizations granted by this Resolution shall expire on
January 9, 2025, unless a Building Permit is obtained, or Certificate of Zoning
Compliance issued for the use described in Part A above, or an extension has
been granted in accordance with Section 11.07.05 F., St. Lucie County Land
Development Code.
E. The petitioner is advised as part of this Conditional Use Permit approval, the
petitioner shall obtain all applicable site plan approval, development permits and
construction authorizations from the appropriate state and federal and local
regulatory agencies including, but not limited to, the United States Army Corps of
Engineers, the Florida Department of Environmental Protection, and South
Florida Water Management District, and the St. Lucie County Environmental
Resources, Public Works and Building Departments prior to the commencement
of any development activities on the property described in Paragraph B.
Issuance of this permit by the County does not in any way create any rights on
the part of the petitioner to obtain a permit from a state or federal agency and
does not create any liability on the part of the County for issuance of this permit if
the petitioner fails to obtain requisite approvals or fulfill the obligations imposed
by a state or federal agency or undertake actions that may result in a violation of
state or federal law.
F. The conditions set forth in Part A are an integral non severable part of the
Conditional Use Permit approval granted by this Resolution. If any condition set
forth in Part A is determined to be invalid or unenforceable for any reason and
the Petitioner declines to comply voluntarily with the condition, the Conditional
Use Permit approval granted by this resolution becomes null and void.
G. A copy of this Resolution shall be attached to the Conditional Use Permit Site
Plan drawings depicted in Exhibit "B" and placed on file with the Planning and
Development Services Department.
H. This Order shall become effective upon the date indicated below. An appeal from
the Board of County Commissioners' action may be processed within thirty (30)
days in accordance with Section 11.11.02.F, of the St. Lucie County Land
Development Code.
Resolution No. 2024-041
File No. CU-2310-000063
Page 3
I. This Resolution shall be recorded in the Public Records.
After motion and second, the vote on this Resolution was as follows:
Cathy Townsend, Chair AYE
Chris Dzadovsky, Vice-Chair AYE
Larry Leet, Commissioner AYE
Linda Bartz, Commissioner AYE
Jamie Fowler, Commissioner AYE
PASSED AND DULY ADOPTED this 9th day of January, 2024.
BOARD OF COUNTY COMMISSIONERS
ST. LUCIE COUNTY, FLOIRDA
BY
HAIR
ATTEST: APPROVED AS TO FORM
AND ORRECTN :
_1`1.GLQ' 0' / QMM/S BY
DEPUTY CLE' ' �
AZ 0 COUNTY A T RNEY
o
%� cn
`GC4F couw r•*�O
Resolution No. 2024-041
File No. CU-2310-000063
Page 4
Exhibit "A"
(Location Map)
\ . ,
Kingsgate Center
Self-Storage
Aillill,
Location
,
( ) ,
JN
W'A&
Resolution No. 2024-041
File No. CU-2310-000063
Page 5
Exhibit "B"
(Site Plan)
ii
i' :i '1
•
I1`
rill \i pp JDO
co
.71
:0.:,.. tit
'► I .!' r !\ n .N O
u l
I
Ii
►• 131 taowc zorE 1v c R!1� . .'''.+ '*fie`-, iI:I
ip
411
A , . .� um�t
a I f I
1--; I
ki
t 1
11 a 6 :1
;I ;
i age l' I $. .o
i . I
Ili ! ! 1s"n `W"' L dam,--i
I .
£ L Idle _
rifle
rm.- ,, ... .,..: 7. ,
Ij
E
E u9 , I :io;,eill I-1 1
1 '
Resolution No. 2024-041
File No. CU-2310-000063
Page 6
Exhibit "C"
(Certificate of Capacity)
St Luck County
Certificate of Capacity
Date 2'�t '[i)I Certificate No. 0,3
This document certifies that concurrency will be met and that adequate public Facility
capacity exists to maintain the standards for levels of service as adopted in the St
Lucie County Comprehensive Plan for:
1.Type of development Conditional Use Permit
Number of units a Number of square feet 124,200
2. Property legal description& Tax ID no.
2311-801-0004-000.8
SW corner of Orange Ave&Kinr.1 i t
Kingsgate Center Self-Storage Kingsgate Center Lot 3
3.Approval: Building Resolution No. 2024-041 Letter
4. Subject to the following conditions for concurrency:
Outlined in Resolution No.2024-041
Owner's name
NC Storage holdings,LLC
Address
1111 Benefield Blvd.Suite 100
Millersville MI) 21108
6. Certificate Expiration Date 1/9/2025
This Certificate of Capacity is transferable only to subsequent owners of the same
parcel,and is subject to the same terms, conditions and expiration date listed herein.
The expiration date can be extended only under the same terms and conditions as the
underlying development orderissued with this certificate,or for subsequent
development or ler(s su for the same property, use and size as described herein.
Signed \ Date:2/9/2024
Planning and Development Services Director
St Lucie County, Florida
Friday.February 9,2024 Pier to 1
Resolution No. 2024-041