RESOLUTION 2026-106
File No. MJSP-2506-000139
A RESOLUTION OF THE BOARD OF COUNTY
COMMISSIONERS OF ST. LUCIE COUNTY GRANTING A
MAJOR SITE PLAN TO DEVELOP A 319 SINGLE-FAMILY
DETACHED UNIT SUBDIVISION FOR A PROJECT TO BE
KNOWN AS SERENOA WITHIN THE PUD (PLANNED UNIT
DEVELOPMENT) ZONING DISTRICT ON +/-114.85 ACRES OF
PROPERTY LOCATED SOUTH OF ANGLE ROAD AND EAST
OF FLORIDA'S TURNPIKE IN UNINCORPORATED ST. LUCIE
COUNTY, FLORIDA.
WHEREAS, the Board of County Commissioners of St. Lucie County, Florida, based on the
testimony and evidence, including but not limited to findings in the staff report and traffic
analysis review, has made the following determinations:
1. Cotleur & Hearing, on behalf of property owners Gustavo Tellez and Lilia C. Fandino,
presented a Major Site Plan application to develop a 319-unit detached single-family
subdivision, along with drainage and utility infrastructure, amenities, preserve, and
buffers within the PUD(Planned Unit Development) Zoning District for a project known
as the Serenoa PUD, bounded by Florida's Turnpike on the west, Angle Rd on the
north, Old FFA Rd. on the east, and Canal No. 43 on the south, in unincorporated St.
Lucie County, Florida, as legally described in Part "B" and depicted on the attached
map as Exhibit "A".
2. On May 6, 2025, the Board of County Commissioners granted the PUD Rezoning &
Preliminary PUD Plan approval, with conditions, via Resolution 2025-108, for the subject
parcels.
3. On June 2, 2026, this Board held a public meeting on this petition.
4. The Development Review Committee has reviewed the Major Site Plan for the project
and found it meets the technical requirements of the St. Lucie County Land
Development Code and has satisfied the standards of review set forth in Section
11.02.07, Standards for Site Plan Review, and Section 11.02.05. B. of the St. Lucie
County Land Development Code.
5. Planning Staff has performed a detailed analysis of the project and determined it to
be consistent with the St. Lucie County Land Development Code and Comprehensive
Plan. The analysis is found in the Planning and Development Services Department
memorandum titled Serenoa (FKA NVR Ryan Homes) PUD Final Site Plan — MJSP-
25-6-000139, dated May 27, 2026.
6. All reasonable steps have been taken to minimize any adverse effect of the proposed
conditional use on the immediate vicinity through site design, landscaping, and
screening.
7. The proposed Major Site Plan, with conditions therein, will not have an undue adverse
effect on adjacent property, the character of the neighborhood, traffic conditions,
parking, utility facilities, or other matters affecting the public health, safety, and
Resolution No. 2026-106
File No.: MJSP-2506-000139
Page 2
general welfare.
8. The proposed project will be constructed, arranged, and operated so as not to
interfere with the development and use of neighboring property, in accordance with
applicable district regulations.
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of St.
Lucie County, Florida:
A. Pursuant to Section 11.02.04 of the St. Lucie County Land Development Code, the
Site Plan is hereby approved as shown on the drawing prepared by Cotleur & Hearing,
dated August 11, 2023 with revision date of June 2, 2026, for the property described
in Part "B" below, subject to the following conditions:
1) Prior to commencement of development, including, but not limited to; clearing,
filling, excavation, grading, or planting of vegetation, as defined in LDC 2.00.00.,
the following shall occur:
a. a Vegetation Removal Permit or Exemption shall be issued by the
Environmental Resources Department per LDC 6.00.03; and
b. the developer shall provide an executed Conservation Easement over the
onsite preserve area, along with the approved Preserve Area Monitoring
and Management Plan (PAMMP), with an attached affidavit and cashier's
check (payable to the Clerk of the Court for recording fees) to the County
Attorney.
C. The applicant shall also provide a georeferenced GIS shapefile or CAD file
of the conservation easement boundaries to St. Lucie County.
d. Listed species surveys shall be updated as necessary per individual
species -specific requirements or written correspondence stating any
potential impacts have been resolved from the appropriate state and
federal agency. If any listed species impacts are found to be present as a
result of these updated surveys, appropriate mitigative measures per state
and federal agency requirements shall be provided prior to initiation of any
clearing activities.
e. An Environmental Resource Permit (ERP) from South Florida Water
Management District (SFWMD) shall be provided to verify the limits of the
wetlands. Should the limits of the wetland substantially deviate from the
environmental consultant's delineation, a new Wetland Waiver application
shall be submitted in accordance with Comprehensive Plan Policy 6.1.14.4.
2) Prior to issuance of a Certificate of Occupancy, all Category I listed invasive plants
shall be eradicated from the site.
3) Prior to the 60th certificate of occupancy, of Phase 2 (western pod), a multi -use
path between the eastern and western pods across Arterial A shall be constructed.
Prior to the final certifications for Phase 1 close-out, 60% of the linear park
improvements shall be completed.
4) The Amenity Plan for common areas shall be submitted to, reviewed by, and
require approval by the Planning & Development Services Director prior to
issuance of the first residential Certificate of Occupancy. At least one Amenity
Parcel and associated features, planned to serve the entire development, shall be
Resolution No. 2026-106
File No.: MJSP-2506-000139
Page 3
completed or adequate security posted prior to the issuance of building permits of
more than 40% of the approved 128 units.
5) Lot and spatial differentiation standards shall include the requirement that at least
one of every five consecutive lots shall have a front fagade positioned (plane
variation) at least five feet forward or behind the adjacent setback line. Minimum
driveway depth remains 22 feet.
6) Prior to issuance of building permits for residential units, the Applicant shall
integrate alternative home planting plans, to reduce visual monotony between lots.
7) Proposed pet waste stations may be relocated (except for at the Preserve
entrances and amenity centers) to provide for more strategic locations that serve
more homes, to be located in common areas including drainage easements. At
least two additional pet waste stations shall be provided to the Plan (currently 14)
prior to the final residential Certificate of Occupancy.
8) In accordance with the Site Plan, the developer(s), successors in interest, or
assigns shall:
a. be required to improve Angle Road from the project's access point to the
nearest road, in accordance with the limits on the plans;
b. Improve Old FFA Rd., from Angle Road to the southern property line,
concurrent with development of this community or provide payment -in -lieu
(proportionate share contribution for the project's frontage);
C. provide for a secondary connection to Old FFA Rd., sited to ensure
compliance with the County' s minimum access design and separation
standards, within 365 days of such time that Old FFA Rd. is paved and
connects to the County's Road system to the south; and
d. install and maintain the Turnpike and Arterial A buffers which are to utilize
the planting arrangement detailed in the Typical Buffer Enhancement
Exhibit and shall cover the entire width and depth of buffers. These buffers
shall be planted at the time the adjacent development infrastructure is
installed and shall achieve the closed forest effect and 90% opacity within
two years, with general utilization of this enhanced planting set along the
northwest property line of the west pod to help to buffer the existing Angle
Rd. single-family residence to the west.
9) The dedication shall be accompanied by a maintenance and access agreement for
Arterial A between the County and the Developer.
10) Prior to issuance of the first Certificate of Occupancy, the applicant, property owner,
developer, successors, or assigns, shall convey to St. Lucie County, in a manner
or form acceptable to the County Attorney, 35' of right-of-way along Angle Road
and 160' feet of right-of-way for Arterial A. Based on the Applicant's commitment,
the Developer/Applicant shall forego impact fee credits for the Arterial A land
donation.
11) A minimum six-foot wide sidewalk shall be provided along each phase frontage of
Angle Road, and Phase 2 frontage on Old FFA. The Board of County
Commissioners may authorize the applicant to pay a Fee -in -Lieu of construction
of the sidewalk. Should an access point to Old FFA be achieved by the project
Resolution No. 2026-106
File No.: MJSP-2506-000139
Page 4
during Phase 2 development, a sidewalk shall be installed (not paid -in -lieu) from
this access point to Old FFA north to Angle Road along this portion of frontage.
Prior to issuance of the Site Development Permit, the final cross section(s),
including the canal and adjacent property as applicable to this extension shall be
depicted.
12) A Road Improvement Agreement and appropriate bond will be required for all
permanent improvements within the Right -of -Way.
13) A Site Development Permit is required prior to performing site improvement
activities.
14) For plat approval prior to completion of required improvements, a Subdivision
Improvement Agreement and appropriate bonding is required.
15) A Revocable License agreement or other method acceptable to the Public Works
Director and County Attorney will be required for the proposed utilities crossing the
future Arterial A Right -of -Way.
16) The stormwater runoff from the public right of way splitting the site is noted to be
collected within the onsite stormwater system. An easement would be required
over the stormwater system allowing the County the right, but not the obligation to
access the system for emergency repairs/maintenance.
B. Legal_Des
cri tion:
PARCEL 1:
A PARCEL OF LAND LYING IN THE NE 1 /4 OF SECTION 4, TOWNSHIP 35
SOUTH, RANGE 39 EAST, ST. LUCIE COUNTY, FLORIDA: MORE
PARTICULARLY DESCRIBED AS FOLLOWS:
COMMENCING AT THE NW CORNER OF THE NE 1/4 OF SECTION 4, TWP 35
S, RANGE 39 E, ST. LUCIE COUNTY, FLORIDA; THENCE S01001'58" EAST
ALONG THE WEST LINE OF THE SAID NE 1 /4, 250.06 FEET TO ITS
INTERSECTION WITH THE SOUTH RIGHT-OF-WAY LINE OFA COUNTY ROAD,
DESIGNATED AS ANGLE WEST ROAD, SAID POINT BEING THE POINT OF
BEGINNING; THENCE CONTINUE S01'01'58" E ALONG THE WEST LINE OF
SAID NE 1 /4 593.61 FEET MORE OR LESS TO ITS INTERSECTION WITH THE
NE'LY RIGHT-OF-WAY LINE OF THE FLORIDA SUNSHINE STATE PARKWAY;
THENCE SOUTH 42046'35" E. ALONG THE SAID NE'LY RIGHT-OF-WAY LINE,
2695.19 FEET MORE OR LESS TO ITS INTERSECTION WITH THE N'LY RIGHT-
OF-WAY LINE OF THE NORTH ST. LUCIE RIVER DRAINAGE DISTRICT CANAL
NO. 43; THENCE S89°57'13"E ALONG THE SAID N'LY RIGHT-OF-WAY LINE,
166.35 FEET TO A POINT THAT LIES 726.38 FEET WESTERLY OF, AS
MEASURED AT A RIGHT ANGLE TO, THE EAST LINE OF THE SAID NE 1/4 OF
SECTION 4; THENCE N02002'43"W ALONG A LINE THAT LIES PARALLEL TO
AND 726.38 FEET WESTERLY OF, AS MEASURED AT A RIGHT ANGLE TO, THE
SAID EAST LINE OF THE NE 1/4 OF SECTION 4, 2565.09 FEET MORE OR LESS
TO A POINT IN THE SOUTH RIGHT-OF-WAY LINE OF SAID ANGLE WEST
ROAD; THENCE N89044'46"W ALONG THE SAID SOUTH RIGHT-OF-WAY LINE,
1915.93 FEET MORE OR LESS TO A POINT OF BEGINNING
Resolution No. 2026-106
File No.: MJSP-2506-000139
Page 5
PARCEL 2:
THE EAST 726.38 FEET OF THE NORTHEAST 1/4, LYING SOUTH OF ANGLE
ROAD WEST RIGHT-OF-WAY AND NORTH OF CANAL 43 RIGHT-OF-WAY,
LESS THE EAST 40 FEET, SECTION 4, TOWNSHIP 35 SOUTH, RANGE 39
EAST, ST LUCIE COUNTY, FLORIDA
PARCEL CONTAINS 113.85 ACRES, MORE OR LESS.
Parcel ID Numbers: 2304-112-0001-000-0 & 2304-111-0002-000-4
C. This Major Site Plan for the Serenoa PUD shall expire within 24 months of the
effective date of this order unless a building permit is issued, or an extension is
granted in accordance with the provision of Land Development Code Section
11.02.06.
D. The developer is advised as part of this Major Site Plan approval that the property
owner(s), developer, etc. including any successors in interest, shall obtain all
applicable development permits and construction authorizations from the
appropriate State and Federal and local regulatory agencies including, but not
limited to, the United States Army Corps of Engineers, the Florida Department of
Environmental Protection, Florida Department of Transportation, South Florida
Water Management District, and the St. Lucie County Environmental Resources,
Public Works, and Building Departments prior to the commencement of any
development activities on the property described in Part A. Issuance of this permit
by the County does not in any way create any rights on the part of the developer to
obtain a permit from a state or federal agency and does not create any liability on
the part of the County for issuance of this permit if the developer fails to obtain
requisite approvals or fulfill the obligations imposed by a state or federal agency or
undertake actions that may result in a violation of state or federal law.
E. The conditions set forth in Part "A" are an integral non -severable part of the Site Plan
approval granted by this Resolution. If any condition set forth in Part "A" is
determined to be invalid or unenforceable for any reason and the developer declines
to comply voluntarily with that condition, the Site Plan approval granted by this
Resolution shall become null and void.
F. A Concurrency Certificate, signed by the Planning & Development Services
Directory on May 28, 2026, is attached as Exhibit C and made a part of the
Resolution.
G. A recorded copy of this Resolution shall be attached to the site plan drawings
described in Part A, which plan shall be placed on file with the St. Lucie County
Planning & Development Services Department Director.
H. This Order shall become effective upon the date indicated below. An appeal of the
Board of County Commissioners' action may be processed within thirty (30) days in
accordance with Section 11.11.02.F, of the St. Lucie County Land Development
Code.
This Resolution shall be recorded in the Public Records of St. Lucie County.
Resolution No. 2026-106
File No.: MJSP-2506-000139
Page 6
After the motion and second, the vote on this resolution was as follows:
Jamie Fowler, Chair AYE
Larry Leet, Vice -Chair AYE
James Clasby, Commissioner AYE
Erin Lowry, Commissioner AYE
Cathy Townsend, Commissioner AYE
PASSED AND DULY ADOPTED this 2"d day of June, 2026.
GOMM/Ss�'O
o
ATTEST. v ®�
IPA
0
Deputy Clerk
BOARD OF COUNTY COMMISSIONERS ST
LUCIE COUNTY, FL ORIDA
CHAIR
APPROVED AS TO FORM AND
CORRECTNESS:
County Attorney
Resolution No. 2026-106
File No.: MJSP-2506-000139
Page 7
Exhibit "A"
Location Map
Resolution No. 2U2G-10G
File Nu:W0GP-25D6-O0O13Q
Page
Eohibd"B"
Site Plan
Exhibit "C"
Concurrency Certificate
St Lucie County
Certificate of Capacity
Date 5r28/2026
Resolution No. 2026-106
File No.: MJSP-2506-000139
Page 9
Certificate No. 3385
This document certifies that concurrency will be met and that adequate public facility
capacity exists to maintain the standards for levels of service as adopted in the St
Lucie County Comprehensive Plan for:
1. Type of development Final Major Site Plan
Number of units 319 Number of square feet
2. Property legal description & Tax ID no.
2304-112-0001-000-0 & 2304-111-0002-000-4
S. of Angle Rd. & East of Turnpike
Serena (PKA NVR-Ryan Iforns) Serena
3. Approval: Building Resolution No. 2026-106 Letter
4. Subject to the following conditions for concurrency:
See Resolution
owner's name
Gustavo Tellez and Lilia C. Fandino
Address
101 Crandon Blvd, Apt 117
Key Biscayne FL 33458
S. Certificate Expiration Date 6i2d2028
This Certificate of Capacity is transferable only to subsequent owners of the same
parcel, and is subject to the same terms, conditions and expiration date listed herein.
The expiration date can be extended only under the same terms and conditions as the
underlying development orderissued with this certificate, or for subsequent
development orders issued for the same property, use and size as described herein.
Signed Date: 5/28/2026