MASTER POOLS GUILD MEMBERWW.MA
WSTERPOOLSGUILD:COM
CONCRETE'
8880 GLADES CUT OFF RD DPORT SAINT OLSNIE,FL34986 :(772)
878-7752 RECEMAR 2 ST. Lucie Counmitting,
DELUXE POOL FOR TERMANINI
Building the
world's finest pools
FEBRUARY 1ST"; 2020
STANDARD STRUCTUAL ENGINEERING PLANS & SPECIFICATIONS ALL CONSTRUCTION PERMITS AS REQUIRED BY LOCAL MUNICIPALITY
POOL PERMIT QUALIFIED BY OWNERS ART ALLEN AND TRAMS LEONARD
SPOOL DIMENSIONS,12'X32'
EXCAVATE & HAUL EXCESS SOIL ON DAY OF EXCAVATION (Min. 9' acom for excavation)
GRAVEL ROCK BASE FOUNDATION, FOR ENTIRE POOL SHELL, STEEL REINFORCING THROUGHOUT STRUCTURE
GUNITE CONCRETE SHELL TO EXCEED LOCAL BUILDING CODES
6" GUNITE WALLS & 8" GUNITE FLOORS
V SHALLOW END DEPTH TO 4.5' DEEP END DEPTH
LIFETIME STRUCTURAL WARRANTY
ONE SET OF ENLARGED GUNITE STEPS WITH TILED EDGE AS PER PLAN
GUNITE CONCRETE SWIMOUT LEDGE WITH CAP TILE TRIM
SCHEDULE 40 NON -CORROSIVE PVC PLUMBING THROUGHOUT
BACKFILL OF CONCRETE SHELL AND PLUMBING LINES
SEPARATE INDEPENDENT CERTIFIED COMPACTION REPORT
(2) 2" MAIN DRAINS WITH 3" TRUNK LINES, AND APPROVED MAIN DRAIN FRAMES AND GRATES PER V.G.B. ASMEIANS1112.19.8.2007
HYDROSTATIC UPLIFT VALVE WITH UNDER -DRAIN STUB OUT FOR FUTURE DRAINAGE
AUTOMATIC WIDE MOUTH SKIMMER ENCASED IN GUNITE BEAM
THREE 2" PLUMBING RETURN LINES
COMPLETE HOOK-UP OF PLUMBING LINES FROM FILTER TO POOL
PRESSURE TESTALL PLUMBING LINES
III MULTI COLOR L E 0 UNDERWATER POOL LIGHTS IN POOL
6" BAND OF GLASS OR CERAMIC WATERLINE TILE (Wide Standard selection)
DELUXE JANDY BRAND CARTRIDGE. FILTER CS200 40.000 GALLON FILTRATION MEDIA WITH 3 YEAR PARTS AND LABOR WARRANTY
DELUXE JANDY BRAND 2.7HP VARIABLE SPEED PUMP WITH 3 YEAR PARTS AND LABOR WARRANTY FOR FILTRATION
IN LINE CHLORINATOR
CONCRETE PAD FOR POOL EQUIPMENT
ALL ELECTRIC HOOK-UP INCLUDING TIMER, JUNCTION BOX AND SUB PANEL
"GEM"DELUXE AGGREGATE POOL PLASTER FINISH (standard Colons)
DELUXE MAINTENANCE KIT INCLUDING: VACUUM HEAD, HOSE & TELE-POLE, BRUSH,
LEAF SKIMMER AND TEST. KIT
PRE -FILTER SYSTEM TO PURIFY INITIAL START-UP WATER
COMPLETE INITIAL CHEMICAL START-UP SERVICE, OPERATING INSTRUCTIONS AND
MAINTENANCE MANUAL
DECO DRAIN
CHILD BARRIER FENCE
ALL NECESSARY INSPECTIONS REQUIRED BY MUNICIPALITY
STATE SALES AND FEDERAL TAXES
GENERAL LWBILITYAND WORKMAN'S COMPENSATION INSURANCE
CONSTRUCTION PROPERTY DAMAGE & NEGLIGENCE INSURANCE
UP TO 3 PALLETS OF SOD REPLACED
SCREEN ENCLOSURE
• TOTAL .... $47,288.00
• INCLUDES ALL PERMIT FEES AND SALES TAX
• 842 WEEKS FOR PERMITISCHEDULING
• 8-10 WEEKS CONSTRUCTION
i