Commissioning Report
for
Saint Lucie County International Airport
3000 Curtis King Blvd.
Fort Pierce, FL. 34946
Table of Contents
#20061
Date: 6/12/2020
1. Commissioning Group Certification
2. Executive Summary
3. Commissioning Plan
A. Appendix "A"— Pre-Commissioning Check Lists
B. Appendix "B"— Functional Performance Tests
C. BAS Systems - Site Observation screen captures
4. Daily Logs
5. Sign-In Sheets
6. T&B report
OCI ENGINEERING
Commissioning Group
Certification
Project:
#20061
The data presented in this report are the results obtained from the building commissioning process
in accordance with AABC ACG Commissioning Guideline and ASHRAE standard 202-2018
Fundamental Commissioning Requirements.Any variances from design are noted within this report.
Submitted &Certified by
AABC ACG Certified Commissioning Group: OCI Engineering, LLC
AABC ACG Certified Commissioning Authority: William A. Munns
Reg. No. 514-1170 Signature - z
I 9V
Date June 12, 2020
`►, a--C
.�.
A
'���•1110
OCI ENGINEERING
L011100'r
Commissioning Report
SLC International Airport Remediation
3000 Curtis King Blvd.
Ft. Pierce, FL. 34946
#20061
Executive Summary
06-12-2020
Scope of the Commissioning Program
OCI Engineering was hired by Saint Lucie County, to provide commissioning services. The intent
of the commissioning program was to help ensure that all commissioned systems were designed,
installed and tested in accordance with the contract documents and the owner's requirements,
and that all systems were fully functional when turned over to the owner by the contractor. Also,
the program was intended to help ensure that the owner's maintenance personnel were fully
trained in the operation and maintenance of the systems at completion of the project. The general
contractor and all mechanical, electrical, controls and T&B subcontractors were members of the
commissioning team and participated in the commissioning process.
Commissioning activities for the project began March-09-2020 when the commissioning
specifications and a commissioning plan were prepared for incorporation into the construction
documents. Field visits were made to verify that the installation was in accordance with the plans
and specifications and to hold commissioning meetings. Pre-commissioning check lists were
prepared by OCI and completed by the contractors prior to the start of functional performance
testing on June-08-2020. Commissioning of the mechanical systems was essentially finished on
June-08-2020 with the punch list items addressed. OCI prepared a commissioning report of
systems for the owner.
Systems
Commissioning was provided for one new dedicated AAON outside air unit, 3 existing EF's, new
ductwork, and the updated building automation system.
Orlando -Ft. Pierce -West Palm Beach -Miami -Ft. Myers Tampa Washington DC
Baltimore -Norfolk -Dallas - San Francisco
600 S. Orlando Avenue, Suite 100,Maitland,FL 32751
Phone: 407-332-5110 Fax: 407-332-7704 www.oc1associates.com
Commissioning Methodology
On this project, the commissioning process started when OCI developed pre-commissioning
checklists for each piece of equipment which were then completed by the responsible contractor
during startup. In many cases the checklists served as the startup forms. Once completed, the
forms were spot checked against the installed equipment for accuracy. The check lists were
intended to help the contractor document his startup activities and to bring some rigor and
methodology to the startup process. All checklists were signed by the subcontractor's field
personnel.
Once the checklists were complete, the functional performance testing started using forms and
procedures developed specifically for the project based on the engineer's drawings, sequences of
operation and the approved control shop drawings and submittals. The equipment and controls
were checked for full and proper operation. The actual test procedures and results can be found
on the completed forms in the body of the report. Functional performance testing was carried out
by OCI in conjunction with the responsible sub-contractors. The test and balance report was
validated through random sampling of the readings in the final test and balance report. After the
completion of the functional testing, the owner's operating staff was trained in the proper
operation and maintenance of all systems related to this project.
A random sampling of the calibration of control system analog inputs was conducted during the
functional performance testing. All temperature sensors were calibrated. All thermostat control
ranges and the high and low limit settings specified by the owner were programmed.
Commissioning Results
In general, the commissioning of the new air conditioning and heating systems, has resulted in
systems that are fully functional in accordance with the contract documents (see resolution in
daily log attached). The mechanical and controls contractors have corrected the deficiencies
uncovered during commissioning process.
Outstanding Issues
At the completion of the functional testing program on June-08-2020 with exception as noted in
the final FPT and daily log, all the systems were operating as specified and in accordance with
the intent of the drawings and specifications.
Orlando -Ft.Pierce -West Palm Beach-Miami -Ft.Myers—Tampa—Washington DC
Baltimore-Norfolk-Dallas- San Francisco
600 S. Orlando Avenue, Suite 100,Maitland, FL 32751
Phone: 407-332-5110 Fax: 407-332-7704 www.ociassociates.com
Commissioning Plan
SLC International Airport Remediation
3000 Curtis King Blvd.
Ft. Pierce, FL. 34946
March 18, 2020
Prepared for:
Saint Lucie County
3000 Curtis King Blvd.
Ft. Pierce, FL. 34946
OCI ENGINEERING
Performed by:
OCI Engineering, LLC
#20061
Summary
The Commissioning Plan is developed in draft form for the specific project during the
design phase and is updated during construction. The plan provides direction for the
commissioning tasks during construction. The plan focuses on providing support for the
specifications and forms for the application of the commissioning process.
Table of Contents
1.0 Overview.................................................................................................. 1
1.1 Abbreviations................................................................................. 1
1.2 Purpose of the Commissioning Plan ............................................ 2
1.3 Commissioning Scope................................................................... 2
1.4 Commissioning Flow Chart............................................................ 3
1.5 Commissioned Systems................................................................ 4
1.6 Appendix A— Pre-Commissioning Checklist................................. 5
1.7 Appendix B — Functional Performance Tests............................... 5
2.0 General Building Information................................................................. 6
3.0 Construction/ Cx Team Data................................................................. 7
4.0 Roles and Responsibilities..................................................................... 8
4.1 Commissioning Team.................................................................... 9
4.2 Responsibilities.............................................................................. 9
5.0 Commissioning Process ...................................................................... 11
5.1 LEED Requirements.................................................................... 11
5.2 Miscellaneous Management Protocols........................................ 12
5.3 Submittals and Documentations.................................................. 12
5.4 Special Submittals, Notifications and Clarifications..................... 12
5.5 Pre-functional Tests..................................................................... 13
5.6 Start-up .................................................................................. 13
5.7 TAB Plan ................................................................................. 14
5.8 Controls Check Out Plan............................................................. 14
5.9 Development of Functional Test and Verification Procedures..... 14
5.9.1 Overview.......................................................................... 14
5.9.2 Scope of Testing.............................................................. 15
5.9.3 Development Process...................................................... 15
5.10 Execution of Functional Testing Procedures............................... 15
5.10.1 Overview and Process..................................................... 15
5.10.2 Deficiencies and Retesting .............................................. 15
5.11 Operating and Maintenance Manuals.......................................... 16
5.12 Training of Owner's Personnel .................................................... 16
5.12.1 Overall Plan ..................................................................... 16
5.13 Warranty Period ......................................................................... 16
5.14 Final Commissioning Report ....................................................... 17
5.15 Schedule .................................................................................... 18
i
1. OVERVIEW
1.1 Abbreviations
The following are common abbreviations and definitions used in this document.
A/E Design architects/engineers
CxP Commissioning authority
CC Controls contractor
CM Construction manager
Cx Commissioning
Cx Plan Commissioning plan document
EC Electrical contractor
FT Functional performance test
GC General contractor
MC Mechanical contractor
PM Owner's project manager
PC Pre-functional checklist
Subs Subcontractors to general
TAB Test and balance contractor
Trade Representative: Person who competently represents the work force
engaged by the contractor for the individual trade
named. This person shall be completely familiar with
the work performed for this contract at all levels of
detail of his trade and with coordination to other
trades.
Participate: Attend commissioning events, provide technical
expertise or knowledge, equipment, measurements
and observation needed or requested by the
commissioning authority or owner. Provide follow-up
analysis, equipment data, design data, or other trade
or professional service needed in response to
commissioning events.
Verify: To positively determine that the measured or
observed quantity satisfies all required criteria. Simply
performing the test, measurement or observation does
not constitute"verification". The test result must also
pass all contract criteria. Tests, which fail, must be
repeated at no additional cost to the owner after repairs
or adjustments are made, until full verification
is achieved.
1
1.2 Purpose of the Commissioning Plan
The purpose of the construction phase commissioning plan is:
To provide direction for team members participating in the commissioning process
during construction, particularly providing resolution for issues and providing
details that cannot be, or were not, fully developed during design, such as
scheduling, participation of various parties of this project, actual lines of reporting
and approvals, coordination, etc.
This plan does not provide a detailed explanation of required testing procedures. The
detailed testing requirements and procedures are found in the specifications sections
230800.
1.3 Commissioning Scope
Commissioning is a systematic process of achieving, verifying and documenting that the
performance of the facility and its various systems meets the design intent and functional
and operational needs of the owner and occupants. This includes the specific training of
the facility personnel involved in the operation and maintenance of the building's
equipment and facilities. There are numerous checks for each stage of the building
commissioning process which ensures that set procedures are followed. This approach to
constructing a building, along with the necessary training of facility personnel, serves as a
thorough quality assurance program for building construction, and the building
construction industry.
Commissioning during the construction of this project is intended to achieve the following
specific objectives:
• Ensure that equipment and systems being commissioned are installed properly
and receive adequate operational checkout by installing contractors.
• Verify and document proper performance of equipment and systems.
• Ensure that O&M documentation is complete.
• Ensure that the owner's operating personnel are adequately trained.
2
1.4 Commissioning Flow Chart—For Fundamental Commissioning Requirements
The following chart illustrates the overall status of the commissioning process for the project.
Gray - Not included in scope
Project Start OPR Workshop
Cx Plan Verification Sheets Functional Performance
Design Phase Development 101 Development Test Forms Development
Design Review Design Review
Comments
Start Collection of Submittal&O&M Data
Documentation for Sheets
Tech Transfer
On-Site Progress Construction Phase Progress Reporting
Construction Observations Issues
Phase
Cx Construction Coordination&Updating
Meetings Issue Updating&
Resolution
Daily Log
Test&Balance TAB Testing Review TAB Reports
Coordination
Field Testing Component Verification Functional Performance
Testing
Training
Observation
Systems Manuals
Draft Cx Report
Tech Transfer O&M Manuals Review Project Warranty Letters Record Drawings Review
Turnover Phase
-� Review
Final Cx Report Submittal&Data Sheets Specifications Cx Testing Reports
Seasonal or Updated Issue Status
Deferred Testing
Warranty Follow-up 3
Inspections
1.5 Commissioned Systems
The following systems are being commissioned in this project. All general references to
equipment in this document refer only to equipment that is to be commissioned.
HVAC System (and all integral equipment controls)
• Roof top units (existing)
• Air handler (existing)
• Dedicated Outside Air unit
• Electric duct heater
• Exhaust fans (existing)
• Ductwork, Duct pressure testing
• Testing, adjusting and balancing work
• Facility management and control system (controlled devices, control loops, and
system integration)
4
1.6 Appendix A— Pre-Commissioning Checklists
Dedicated outside air unit
Condensing Unit
Air Handling Unit (existing)
Rooftop Units (existing)
Exhaust Fans (existing)
Electric Duct Heater
Ductwork
Automatic Controls
1.7 Appendix B— Functional Performance Tests
Dedicated Outside Air unit
Rooftop units (existing)
Air Handling unit (existing)
Electric Duct Heater
Exhaust fans (existing)
Automatic Controls
5
2.0 General Building Information
Project: SLC International Airport Remediation
Location: Ft. Pierce, Florida
Total Square Footage: 6963
Buildings: Airport Terminal
Project Schedule
Design Complete: 3/3018
Construction Complete: 4/30/2020
Project Budget: $250,000
Description: Retrofit to the HVAC system including the dedicated outside air unit,
AHU, RTU's, ductwork, exhaust flow and building automation control
system
6
3.0 Construction/Cx Team Data (primary parties)
Team Member Company& Contact Names Office, Cell, Email
Owner O: 772-834-9097
Saint Lucie County C:
2300 Virginia Ave. Scotty Beaulieu
Email: beaulieus@stlucieco.org
Fort Pierce, FL. 34982
Architect O:
C:
Email:
Commissioning Authority O: (407)332-5110
OCI Engineering C: (407)808-9782
600 S. Orlando Ave, Ste. 100 Art Munns
Maitland, FL 32751 Email: amunns@ociengineering.com
Electrical Designer/Eng. O:407-380-0400
Salas O'Brien Kyle Cartier C:
3501 Quardrangle Blvd., Suite 100
Orlando, FL. 32817 Email: Email:kyle.cartier@salasobrien.com
Mechanical Designer/Eng. O:407-380-0400
Salas O'Brien C:
3501 Quardrangle Blvd., Suite 100 Kyle Cartier
Email:kyle.cartier@salasobrien.com
Orlando, FL. 32817
General Contractor O: 772-370-4024
Crist Construction Jim Crist C:
4365 Gator Trace Lane
Fort Pierce, FL. 34982 Email:jimcrst@yahoo.com
Mechanical Contractor : 772-461-8711
Grimes C:
Jim Grimes
3054 N. US HWY 1
Fort Pierce, FL. 34946 Email:jimgrimesjr@aol.com
Electrical Contractor O:
C:
Email:
Plumbing Contractor O:
C:
Email:
TAB Contractor O: 772-216-7632
Omega Air Services, LLC C:
126 Wisteria Ave. Hugh Grimes
Fort Pierce, FI. 34982 Email: omegamaniac532002@yahoo.com
Controls Contractor O: 954-802-8631
Siemens Tom Bolko C:
2969 SW 42"d Avenue
Email:Thomas.bolko@siemens.com
Palm City, FL. 34990
7
4.0 Roles and Responsibilities
The CxP was hired by the owner directly. In general, the CxP coordinates the commissioning
activities and reports to the program manager and owner. The CxP's responsibilities, along with
all other contractors' commissioning responsibilities are detailed in the specifications. The
specifications will take precedence over this Cx plan. All members work together to fulfill their
contracted responsibilities and meet the objectives of the contract documents. For coordination
purposes, the commissioning scope involving all parties is outlined here.
1. Document systems design intent (A/E)
2. Inspect and confirm that equipment and systems have been properly installed in
accordance with the contract documents and manufacturer's written installation
instructions (CxP and contractor).
3. Inspect and confirm that equipment has been placed into operation with manufacturer's
oversight and approval and in accordance with contract requirements. (CxP and
contractor).
4. Identify, document and report all deficiencies of the work versus contract specifications and
performance requirements, for tracking and correction (CxP and contractor).
5. Monitor and enforce accessibility of all work areas and pieces of equipment.
(contractor).
6. Assemble contractor as-built drawings (contractor).
7. Assemble operation, installation and maintenance instructions and submittal data
(contractor).
8. Inspect and confirm the performance of each piece of equipment and each system
(CxP and contractor), as described in contract.
9. Validate the test and balance report. (contractor, CxP)
10. Train owner's personnel in the proper operation of each piece of equipment and
each system (contractor, CxP and A/E).
11. Document warranty start and end dates (contractor).
12. Prepare final commissioning report. (CxP)
8
4.1 Commissioning Team
The commissioning team will consist of all members needed to execute the approved
commissioning program. Minimum membership shall include:
1. Commissioning Authority (CxP)
2. Owner's Mechanical Engineer
3. Owner's Maintenance Representative
4. Contractor's Trade Representative
5. Mechanical Trade Representative
6. TAB Contractor
7. FMCS Contractor
8. Engineers of Record
The contractor's personnel shall be made available to execute all aspects of the
commissioning program until the owner accepts results.
4.2 Responsibilities
Owner:
1. Assign engineering and maintenance personnel and schedule them to participate in the
various meetings, training sessions and inspections.
Commissioning Authority:
1. Review all commissioning requirements and intent of the contract documents and all
related testing, verification and quality control procedures.
2. Coordinate the pre-commissioning and final commissioning schedules and activities.
3. Make periodic visits to the site, as necessary to witness equipment and system
installations.
4. Schedule a pre-commissioning coordination meeting at some convenient location and at a
time suitable to the contractor and engineers of record. In attendance are the respective
representatives of the GC, CM, CxP, PM, A/E and the mechanical, controls, and TAB
subs. This pre-commissioning meeting will be for reviewing the complete commissioning
program, the flow of documents, establishing tentative schedules for maintenance
orientation and inspections, O&M submittals, training sessions,job completion, system
start-up and testing. At the meeting commissioning parties are introduced, the
commissioning process is reviewed, and management and reporting lines are determined.
The Cx plan is reviewed and process questions are addressed. Also covered are the
general list of each party's responsibilities.
5. Attend selected planning and job-site meetings to remain informed on construction progress
and to update parties involved in commissioning. The CM and GC provide the CxP with
information regarding substitutions, change orders and any architect's supplemental
instructions that may affect commissioning equipment, systems or the commissioning
schedule. Later during construction, the CxP, through the PM, as required, will schedule
necessary meetings between various commissioning team parties.
9
6. Schedule HVAC systems training for maintenance personnel prior to final
commissioning of the above systems.
7. Receive and review operation and maintenance (O&M) manuals as submitted by the
contractor and approved by the engineer of record.
8. Schedule the owner training sessions.
9. Upon receipt of the approved test and balance report, plan and schedule the test and
balance report validation with the TAB contractor.
10. Upon receipt of notification from the contractor that the systems have been started, and
that the systems and equipment is functioning as designed and specified, schedule the
functional performance tests. These demonstrations will be conducted by the contractor
and the controls trade representatives and witnessed by the CxP and other appropriate
designees.
11. Prepare final commissioning report and submit to owner. Schedule final review with owner.
Present all documentation and turn over signed acceptance of the system by the owner and
CxP to the contractor.
Engineers of record:
1. Prepare basis of design and system description documentation.
2. Verify adequate maintenance accessibility for each piece of equipment in actual
installation. Periodic inspections are part of the engineer of record's construction
administration duties.
3. Attend and participate in maintenance training sessions.
4. Review and approve all shop drawings.
5. Receive and review O&M Manuals as submitted by the contractor. Insert sections on system
description.
6. Issue field reports noting deficiencies requiring correction to the CxP.
Contractor:
1. Ensure full cooperation in the commissioning program.
2. Ensure cooperation and participation of specialty sub-trade representatives, as required.
3. Ensure participation of major equipment manufacturers and their representatives,
as required.
4. Prepare operation, maintenance and installation manual submission, training sessions,
equipment operation and job completion verification for use by CxP.
5. Conduct training sessions and conduct maintenance orientation and inspection
sessions.
10
6. Update contractor as-built drawings and review with CxP.
7. Gather O&M data on all equipment and assemble in binders. Submit to engineer of record
prior to the distribution completion stage.
8. Conduct and schedule representatives to participate in the training sessions as
scheduled up by CxP.
9. Provide written certification that the work has been completed in accordance with the plans
and specifications and that they are functioning as designed. Submit completed pre-
functional checklist forms to CxP prior to the final verification.
10. At the completion of the controls and energy management systems start- up and
adjustment work, demonstrate to CxP the performance of the facilities management and
control systems.
11. Demonstrate the performance of each piece of equipment to CxP. Schedule the contractor
representatives as may apply to demonstrate the performance of the equipment and
systems.
12. Provide personnel and equipment as required to validate the TAB work.
13. Turn over set of contractor as-built drawings to CxP for review prior to incorporation into
the record drawings.
5.0 Commissioning Process
This section details the commissioning process by commissioning task or activity.
5.1 LEED Requirements (NOT REQUIRED)
For this project, "LEED for new construction" addressed building Cx in 1 place, EA prerequisite 1.
The scope of services for Cx should be based on the owner's project requirements. The following
table outlines the team members primarily responsible to perform each Cx requirement.
Table 5-1 LEED related Cx team members' responsibilities
Task Responsibilities
Designate Cx Authority (CxP) Architect
Document Owner's Project Requirements (OPR) Architect, CxP
Develop Basis of Design Design Team
Incorporate Cx requirements into construction documents CxP, Design Team
Conduct Cx design review to mid-construction documents CxP
Develop and implement a Cx plan CxP
Review contractor submittals applicable to systems being submitted N/A
Verify the installation and performance of commissioned systems CxP
Develop a systems manual for the commissioned systems N/A
Verify that the requirements for training are completed Project team, CxP
Complete a summary Cx report CxP
Review building operations within 10 months after substantial completion N/A
11
5.2 Miscellaneous Management Protocols
The following protocols will be used on this project.
Issue Protocol
For requests for The CxP goes first to the PM and the GC.
information (RFI) or formal
documentation requests:
For minor or verbal The CxP goes directly to the informed party.
information and
clarification:
For notifying contractors of The CxP documents deficiencies through the PM, but may discuss
deficiencies: deficiency issues with contractors prior to notifying the PM.
For scheduling functional The CxP works with the PM and GC to develop schedules.
tests or training:
For scheduling The CxP selects the date and schedules through the GC.
commissioning meetings:
For making a request for The CxP has no authority to issue change orders.
significant changes:
For making small changes The CxP may make small sequences of operations changes to
in specified sequences of improve efficiency or control or to correct deficiencies, through the
operations: responsible contractor, but shall review the change with the A/E,
document the change and provide all changes of specified
sequences to the PM and A/E.
Subcontractors disagreeing Try and resolve with the CxP first. Then work through GC who will
with requests or work with CxP directly or through the PM to resolve the situation.
interpretations by the CxP
shall:
5.3 Submittals and Documentation
The CxP provides all subs responsible for commissioned equipment with commissioning
documentation requirements for their respective equipment and systems. This data
request typically coincides with the normal A/E submittal process. At minimum, this
equipment data includes installation and start-up procedures, approved shop drawings,
O&M data, performance data and control drawings.
5.4 Special Submittals, Notifications and Clarifications
The subs, GC or A/E notify the CxP of any new design intent or operating parameter changes,
added control strategies and sequences of operation, or other change order that may affect
commissioned systems. The controls contractor provides the CxP a full points list with details
requested by the CxP. Thirty (30) days prior to performing any required tests, cleaning or
12
flushing the subs provide the CxP full details of the procedures. As the phases of the TAB are
completed, the draft TAB report is provided to the CxP with full explanations of approach,
methods, results, data table legends, etc. The final TAB report is provided to the CxP upon
completion. These submittals to the CxP do not constitute compliance for submittals for the
O&M manuals. The CxP may request additional design narrative from the A/E and from the
controls contractor depending on how complete the documentation was which was provided
with the bid documents. The CxP may submit written RFIs to contractors through the PM, or
address them directly for clarifications, as needed.
5.5 Pre-functional Checklists
The word pre-functional refers to before functional testing. Pre-functional checklists (PC) are
important to ensure that the equipment and systems are hooked up and operational and that
functional performance testing may proceed without unnecessary delays. Each piece of
equipment receives full pre-functional checkout by the contractor. No sampling strategies are
used. In general, the pre-functional testing for a given system, must be successfully completed
prior to formal functional performance testing of equipment or sub-systems of the given system.
Pre-functional checklists are primarily static inspections and procedures to prepare the equipment
or system for initial operation (e.g., oil levels checked, fan belt tension, labels affixed, gauges in
place, sensor calibration, etc.). However, some pre-functional checklist items entail simple
testing of the function of a component, a piece of equipment or system (such as measuring the
voltage imbalance on a three-phase pump motor of a chiller system). Pre-functional checklists
augment and are combined with the manufacturer's start-up checklist.
Contractors typically already perform some, if not all, of the pre-functional checklist items the
commissioning authority will recommend. However, few contractors document in writing the
execution of these checklist items. This project requires that the procedures be documented in
writing by the installing technician. The CxP does not witness all the pre-functional checklist
verification, except for testing of larger or more critical pieces of equipment and some spot-
checking.
5.6 Start-up
The CxP assists the commissioning team members responsible for start-up in developing detailed
start-up plans for all equipment. All start-up plans are to be approved by the CxP.
Four weeks prior to start-up, the subs and vendors schedule start-up and initial checkout with the
PM, GC and CxP. The start-up and initial checkout are directed and executed by the sub or
vendor. The CxP, and PM if necessary, observe, at minimum, the procedures for each piece of
primary equipment, unless there are multiple units, when a sampling strategy is used. For
components of equipment, (e.g., VAV boxes), the CxP observes a sampling of the pre-functional
and start-up procedures.
To document the process of start-up and checkout, the site technician performing the line item
task initials and dates each paragraph of procedures in the "start-up plan" and checks off items on
the pre-functional and manufacturer field checkout sheets, as they are completed. Only
individuals having direct knowledge of a line item being completed shall check or initial the forms.
The subs and vendors execute the checklists and tests and submit a signed copy of the
completed start-up and pre-functional tests and checklists to the CxP. The CxP may review pre-
13
functional checklists in progress, as necessary.
The subs clearly list any outstanding items of the initial start-up and pre-functional procedures that
were not completed successfully at the bottom of the procedures form or on an attached sheet.
The procedures form and deficiencies are provided to the CxP within two days of test completion.
The CxP works with the subs and vendors to correct and retest deficiencies or uncompleted items,
involving the PM and others as necessary. The installing subs or vendors correct all areas that are
deficient or incomplete according to the checklists and tests.
5.7 TAB Plan
The TAB contractor submits the outline of the TAB plan and approach to the CxP and the
controls contractor eight weeks prior to starting the TAB. Included in the approach, is an
explanation of the intended use of the building control system. The CxP reviews the plan and
approach for understanding and coordination issues and may comment but does not approve
changes. The controls contractor reviews the feasibility of using the building control system for
assistance in the TAB work. The TAB submits weekly written reports of discrepancies, contract
interpretation requests and lists of completed tests to the CxP and PM. This facilitates quicker
resolution of problems and will result in a more complete TAB before functional testing begins.
TAB work will not begin until the control system has been pre-functionally tested and selective
functional tests have been performed and approved by the CxP.
5.8 Controls Check Out Plan
The controls contractor develops and submits a written step-by-step plan to the CxP, which
describes the process, they intend to follow in checking out the control system and the forms on
which they will document the process. The controls contractor will also meet with the TAB
contractor prior to the start of TAB and review the TAB plan to determine the capabilities of the
control system for use in TAB. The controls contractor will provide the TAB with any necessary
unique instruments for setting terminal unit boxes and instruct TAB in their use (hand-held control
system interface for use around the building during TAB, etc.). The controls contractor shall also
provide a technician qualified to operate the controls to assist the TAB contractor in performing
TAB.
All CxP required controls pre-functional checklists, calibrations, start-up and selected functional
tests of the system shall be completed and approved by the CxP prior to TAB. The controls
contractor shall execute the tests and trend logs assigned to them and remain on site for
assistance for mechanical system functional tests.
5.9 Development of Functional Test and Verification Procedures
5.9.1 Overview
Functional testing is the dynamic testing of systems (rather than just components) under full
operation (e.g., the chiller pump is tested interactively with the chiller functions to see if the pump
ramps up and down to maintain the differential pressure set point). Systems are tested under
various modes, such as during low cooling or heating loads, high loads, component failures,
unoccupied, varying outside air temperatures,fire alarm, power failure, etc. The systems are run
through all the control system's sequences of operation and components are verified to be
responding as the sequences state. The commissioning authority develops the functional test
procedures in a sequential written form, coordinates, oversees and documents the actual testing,
which is usually performed by the installing contractor or vendor.
14
5.9.2 Scope of Testing
A detailed description of the functional and pre-functional testing procedures and process will be
developed for this project by the CxP for each piece of commissioned equipment.
5.9.3 Development Process
Before test procedures are written, the CxP obtains all requested documentation and a current list
of change orders affecting equipment or systems, including an updated points list, control
sequences and set points. The CxP develops specific test procedures to verify proper operation of
each piece of equipment and system. The CxP obtains clarification, as needed, from contractors
and the A/E regarding sequences and operation to develop these tests. Prior to execution, the
CxP provides a copy of the primary equipment tests to the installing sub (via the GC)who reviews
the tests for feasibility, safety, warranty and equipment protection. Blank copies of the procedures
are input into the O&M manuals for later use by operations staff.
Functional testing and verification may be achieved by manual testing (persons manipulate the
equipment and observe performance)or by monitoring the performance and analyzing the
results using the control system's trend log capabilities or by stand- alone data loggers. The CxP
uses judgment where needed to determine which method is most appropriate.
5.10 Execution of Functional Testing Procedures
5.10.1 Overview and Process
The CxP schedules functional tests through the PM, GC and affected subs. For any given
system, prior to performing functional testing, the CxP waits until the pre-functional checklist has
been submitted with the necessary signatures, confirming that the system is ready for functional
testing. The CxP oversees, witnesses and documents the functional testing of all equipment and
systems according to the specifications and the Cx plan. The subs execute the tests. The control
system is tested before it is used to verify performance of other components or systems. The air
balancing and water balancing is completed before functional testing of air-related or water-
related equipment or systems. Testing proceeds from components to subsystems to systems
and finally to interlocks and connections between systems.
5.10.2 Deficiencies and Retesting
The CxP documents the results of the test. Corrections of minor deficiencies identified are
made during the tests at the discretion of the CxP. The CxP records the results of
the test on the procedure or test form. Deficiencies or non-conformance issues are noted and
reported to the PM on the Commissioning Corrective Action Report(Daily Log). Subs correct
deficiencies, notify the CxP and return the form certifying correction. The CxP schedules retesting
through the PM. Decisions regarding deficiencies and corrections are made at as low a level as
possible, preferably between CxP or PM and the sub. For areas in dispute, final authority, besides
the owner's, resides with the A/E. The CxP recommends acceptance of each test to the PM. The
PM gives final approval on each test.
15
5.11 Operating and Maintenance Manuals
The CxP reviews the O&M manuals and documentation for systems that were commissioned
to verify compliance with the specifications. The CxP recommends approval and acceptance
of these sections of the O&M manuals to the PM. The CxP also reviews each equipment
warranty and verifies that all requirements to keep the warranty valid are clearly stated.
Initial preparation shall be the responsibility of the HVAC and electrical trade
representative as per contract bid document.
5.12 Training of Owner's Personnel
The owner's maintenance personnel shall be given comprehensive training in the understanding of
the systems and the operation and maintenance of each major piece of equipment. The CxP, in
cooperation with the contractor, schedules the training, which shall start with classroom sessions
followed by hands on training on each piece of equipment. Hands on training shall include start-
up, operation in all modes possible, shut-down and any emergency procedures.
The contractor or his representative, shall conduct and video tape all sessions and shall add to
each session any special information relating to the details of installation of the equipment as it
might impact the operation and maintenance.
5.12.1 Overall Plan
After reviewing the specifications, and after interviewing facility staff, if necessary, the owner
and CxP fill out a table listing all the equipment for which training or orientation will be provided
listing, among other things, the type and number of trainees, rigor of training desired by the
owner, the primary responsible subcontractor, the trainer's company and columns for tracking
training agendas. The commissioning authority provides this form to the contractor for
reference.
The contractor will prepare a training agenda describing the subjects covered, duration of each
subject and the methods that will be used in the training, along with the name and qualifications
of the trainer(s)for submission to the owner and CxP. The owner and CxP review the agenda;
make comments; approve the training subject to the comments; and submit back to the
contractor. The contractor provides the approved agenda to the trainer to use during the
training. The trainer provides a copy of the agenda to each trainee.
5.13 Warranty Period
During the warranty period, seasonal testing and other deferred testing required is completed
according to the specifications. The CxP coordinates this activity. Tests are executed, and
deficiencies corrected by the appropriate subs, witnessed by facilities staff and the CxP. Any final
adjustments to the O&M manuals and record drawings due to the testing are made. In addition,
the CxP will return to the project approximately 10 months into the 12-month warranty period.
During this visit(s)the CxP will review with facility staff the current building operation and the
condition of outstanding issues related to the original and seasonal commissioning. The CxP will
also interview facility staff and identify problems or concerns they have operating the building as
originally intended.
16
The CxP will make suggestions for improvements and for recording these changes in the O&M
manuals. The CxP will identify areas that may come under warranty or under the original
construction contract. The CxP will also assist facility staff in developing reports and documents
and requests for services to remedy outstanding problems.
5.14 Final Commissioning Report
A final summary report by the CxP will be provided to the PM. The report shall include an
executive summary, list of participants and roles, brief building description, overview of
commissioning and testing scope and a general description of testing and verification methods.
For each piece of commissioned equipment, the report should contain the disposition of the
commissioning authority regarding the adequacy of the equipment, documentation and training
meeting the contract documents. All outstanding non-compliance items shall be specifically listed.
Each non-compliance issue shall be referenced to the specific functional test, inspection, trend
log, etc. where the deficiency is documented. The functional performance and efficiency section
for each piece of equipment shall include a brief description of the verification method used
(manual testing, BAS trend logs, data loggers, etc.) and include observations and conclusions
from the testing.
The final commissioning report shall be submitted. The report shall contain as a minimum the
following information:
• Cover sheet with following information:
• Date
• Project and address
• Architect
• Engineer
• General contractor
• SCA (name, address, e-mail, fax & phone number)
• Final updated commissioning plan
• Name, address, phone, fax, e-mail for commissioning team members
• Completed copies of all commissioning forms
• Copies of Cx related RFI's, meeting minutes, contractor certification, reports, and
code authority inspections.
• Copies of inspection and construction observation reports
• Copy of equipment and system certification forms with listing of equipment and
systems commissioned.
• Copies of completed component test forms
17
5.15 Schedule
The initial commissioning schedule is summarized in the table below.
Initial Commissioning Schedule Summary
Task/Activity Estimated Start Estimated End Date
Date
Initial scoping meeting and final plan
Submittals obtained and reviewed
Begin construction site visits/inspections
Pre-functional forms developed and distributed
Start-up and initial checkout plans
Start-up and initial checkout executed
TAB reports obtained and reviewed
Functional performance tests
O&M documentation review and verification
Final commissioning forms executed
Training and training verification
Final commissioning report
18
SLC International Airport Remediation
3000 Curtis King Blvd.
Ft. Pierce, FL. 34946
Commissioning of Mechanical Systems
Appendix A
Pre-Commissioning Check Lists
/ SLC Airport Remediation
OCI ENGINEERING #20061
L000or
DOAS 1
Pre-Commissioning Check List
Tag Model#
DOAS-1 R N A-0 1 1 -C-0-2-D J A J A-0 0 0 0 0
MFGR Serial#
AAON 201909-BNCZ16133
Documentation Checked By(Initial)
OCI Contractor
a• Cut sheets, approved shop drawings TS
b• Performance data TS
c• O&M manuals TS
d• Installation and startup manual and plan TS
e. IStartup report TS
Installation
a• Vibration isolation devices installed and released TS
b. Inspection and access doors are operable and sealed TS
c• Casing undamaged TS
d. Insulation undamaged TS
e• lCondensate drainage is unobstructed TS
f. Fan adjusted and clear of any obstructions NA
9. Any damage to coil fins has been repaired NA
h. Manufacturer's required maintenance clearance provided TS
I• Labels installed TS
j. Instrumentation installed TS
k• Concrete housekeeping pad(s)in place as required NA
I. All mounting brackets properly installed TS
M. Clean up completed TS
/ SLC Airport Remediation
OCI ENGINEERING #20061
Duct Mounted Electric Heater(AAON)
Pre-Commissioning Check List
No Duct Heater
Tag Model#
EDH-1
MFGR Serial#
Documentation Checked By(Initial)
OCI Contractor
a• Cut sheets,approved shop drawings
b. Performance data
G. O&M manuals
d. Installation and startup manual and plan
e• Startup report
Installation
a• Supports installed per specifications
b. Access doors are operable and sealed
C. Casing undamaged
d. Verify correct direction installation
e. Associated equip.
f• Elements are adjusted and clear of any obstructions
g. Any damage to elements has been repaired
h• Manufacturer's required maintenance clearance provided
i. Labels installed
j• Instrumentation installed
k• All mounting brackets and sleeves are properly installed
l• Clean up completed
Electrical
a• Power available to unit disconnect
b. Power available to unit control panel
C. Control system interlocks functional
d. Verify that power disconnect is located within sight of the unit
e. Unit KW / Number of stages
f• Power available to electric heating coil
g• Input voltage V. / Ph.
Controls
a• Iverify proper location and installation
b• JAII sensors calibrated
Notes:
Z ) SLC Airport Remediation
OCI ENGINEERING #ZOOGZ
LOOOOOr
Ductwork Installation Pre-Commissioning Check List
Tag:
Documentation Checked By(Initial)
OCI Contractor
a. Ductwork leak test complete(report attached) TS
b• As-built shop drawings submitted TS
Installation
a• Ductwork complete TS
b. Turning vanes installed TS
c• Fire dampers, smoke dampers, and access doors installed (as required) TS
d. Duct sealant installed as specified TS
e• IDuctwork insulated as required TS
f. Duct liner properly installed (If applicable) NA
g. Verify open/closed status of dampers, linkage connected TS
h. Verify smoke dampers operation NA
i• Flexible connectors installed as specified TS
1• ISeismic bracing installed as required NA
Notes:
/ SLC Airport Remediation
OCI ENGINEERING #20061
LOOOOF
Automatic Controls Pre-Commissioning Check List
Tag
Siemens
Documentation Checked By(Initial)
OCI Contractor
a. Approved controls submittal with complete sequences of operation for each piece of
equipment and single line diagrams of all control strategies,parameters,and settings
b. Full descriptive points list
c. Installation manual provided
d. I Start-up sheets for each piece of equipment provided
e. As-built shop drawings, manufacturer's cut-sheets,and calibration report submitted
f. JO&M manuals submitted
Installation
a. Layout and location of control panels matches drawings
b. Equipment/panel labels affixed
c. Wiring labeled inside panels(to controlled components)
d. Control wiring and tubing labeled at all terminations, splices,and junctions
e. IShielded wiring used on electronic sensors
f. Battery back up in place and operable
9. lGraphic interfaces installed and mapped to control points
Controls installed,fully functional,tested,and calibrated for all equipment listed:
a. Dedicated OA Unit
b. Exhaust Fans
C. Air flow monitoring stations
d. Temperature sensors
e. I Damper actuators
f. BAS control modules
9•
h.
j•
k.
Notes:
St. Lucie International Airport
St. Lucie, Florida
Commissioning of Mechanical Systems
Appendix B
#20061
Functional Performance Test
j ST. Lucie international Airport
OCI ENGINEERING $k20061
LOOOO"F
FUNCTIONAL TEST
DX Air Handling Unit
DOAS-1
1. Participants
Sean Willis
Art Munns
David Dickson
Party filling out form and witnessing testing. Sean Willis
Date of test. 6/8/2020
2. Prerequisite Checklist
The following have been started up and startup reports and pre-functional checklists submitted and
approved ready for functional testing:
0 AHU unit
0 All control system functions for this and all interlocking systems are programmed and operable per contract
documents.
0 David Dickson 6/8/2020
Controls Contactor Signature or Verbal Date
0 Test and balance (TAB) completed and approved for the airflow system.
❑ These functional test procedures reviewed and approved by installing contractor.
❑ Review the FMCS software control program(s)for this equipment. Parameters, set points and logic sequences
appear to follow the specified written sequences.
Parameter Owner Specified or Final
Reasonable Value Value
Supply Air set point 70°F 74°F
OA flow set point(CFM) 1400 1400
Supply fan static pressure set point 0.50 n/a
Building static pressure set point N/A n/a
Occupied cooling set point °F 74°F
Occupied heating set point °F 74°F
Occupied dehum set point average (SPACE) 50% R.H. 55% R.H.
/ ST. Lucie international Airport
OCI ENGINEERING #20061
DOAS-1/CU-1 Location Initial Instrument Final Required Pass
Sensor& Location OK FMCS Measured FMCS OffsetYIN
Value Value Value
OA temp Y 83.6°F 85°F 83.6°F Y
Precooling temp n/a °F °F °F n/a
Cooling Coil temp Y 64.6°F 63°F 64.6°F Y
Reheat temp Y 74°F 74°F 74°F Y
OA CFM Y 1332 1332 Y
Supply fan discharge temp I Y 74°F 74°F 74°F Y
Device Calibration Checks The actuators or devices listed below checked for calibration.
Device or Actuator& Location FMCS Reading Site Observation as Log #
YIN
OA damper position 1. Closed Y
2. Full open Y
Supply fan 1. On Y
2. Off Y
DX PreCooling 1. On Y
2. Off Y
DX ReHeat 1. On Y
2. Off Y
Condenser Unit CU-1 (AHU-1) 1. On Y
2. Off Y
Trending Points Verification
Point Name Notes as Log #
YIN
OA Temp Y
Precooling Temp n/a
Cooling Coil temp Y
Reheat temp Y
OA CFM Y
Suppl air temp. Y
Unit Status Y
OA damper position n/a
Test DOAS-1/CU-1 Test Procedure Expected Response as Log #
YIN
1 Unoccupied Off Mode:
Put unit schedule in unoccupied mode. Supply fan OFF Y
Observe the unit in OFF condition. OA damper CLOSED Y
DX Heat- OFF Y
Compressors - OFF Y
/ ST. Lucie international Airport
OCI ENGINEERING #20061
1
Test D0AS-1/CU-1 Test Procedure Expected Response as Log #
2 Occupied Cooling Start/Ventilation:
Place the unit in the occupied mode through
the DDC system. Supply fan ON
OA damper modulate OPEN to maintain
minimum air flow set point of 1400 CFM
Verify set point was determined and OA flow
station calibrated by T&B contractor
Condensing units stage ON and stage UP to
maintain set point
DX heat shall stage to maintain 63.3°F
supply air temp. (M3.2) (74°F ACTUAL)
3 Discharge Air Temperature Control:
override the supply air temperature set point Compressors shall stage ON to maintain
5°F UP active discharge air temp set point
override the supply air temperature set point Compressors shall stage OFF to maintain
YF DOWN active discharge air temp set point
4 Economizer Mode (If applicable)
override the OUTSIDE air temperature set Compressors shall stage OFF and fan shall
point 50°F continue to run to maintain set point
Reset override(s)
5 Fan Capacity Control: (If applicable)
override Static Pressure Set point(5) inwc UP VFD shall increase and fan shall ramp up to
maintain SP set point n/a
SP set point we n/a
Actual SP we n/a
Reset override(s)
j ST. Lucie international Airport
ENGINEERINGOC� #20061
Test DOAS-1ICU-1 Test Procedure Expected Response YEN Log #
6 Miscellaneous Alarms & Safeties:
FIRE ALARM MODE: Fan should shut down, and an alarm shall
Fire alarm is hard-wired independent to shut be registered in the BAS
down supply fan upon actuation.
FAN HIGH STATIC ALARM: override fan Fan should shut down, and an alarm shall
speed above 2"we static pressure. be registered in the BAS
LOW OA FLOW ALARM: Override OA total
flow to 1200 (1100 PER Bob) @30 min An alarm shall be registered in the BAS
FAN FAILURE: With breaker to fan shut
OFF, initiate AHU to START An alarm shall be registered in the BAS
OUTSIDE AIR DAMPER ALARM: Disable
outside air damper to the CLOSED position An alarm shall be registered in the BAS
when in occupied mode.
VFD FAILURE: (If possible) An alarm is registered in the BAS
Reset override(s)
END OF TEST
Notes: DISCONNECT SHOULD HAVE A PERMANENT LABEL.
j ST. Lucie international Airport
OCI ENGINEERING $$20061
LOOOOF
FUNCTIONAL TEST
Exhaust Fans
1. Participants
Party filling out form and witnessing testing. Sean Willis
Date of Test 6/8/2020
2. Prerequisite Checklist
The following have been started up and startup reports and prefunctional checklists submitted and approved
0 Exhaust fan
El All control system functions for this and all interlocking systems are programmed and operable per
contract documents.
6/8/2020
Controls Contractor Signature or Verbal Date
El Test and balance (TAB) completed and approved.
❑ All A/E punch list items for this equipment corrected.
❑ Review the FMCS software control program(s)for this equipment.
ST. Lucie international Airport
#20061
FUNCTIONAL TEST
EXHAUST FAN EF-1
1. Functional Testing Record
Test Test Procedure Expected Response YEN Log #
1 Observe the unit in OFF condition. Backdraft damper closed. (if applicable)
Disconnect functions properly.(if
Fan is off and stopped completely Y
2 Observe the unit in ON condition. Fan rotation correct. Y
No excessive noise or vibration. Y
Backdraft damper open.(if applicable)
3 Describe fan controls and interlocks:
ON/OFF Control -
Test all specified interlocks by starting and Fan starts and stops under control from
stopping lead equipment and verifying fan specified controller
start/stop
Interlock
AHU-NA(FANS ARE TIED TO SCHEDULE
Miscellaneous Alarms & Safeties:
In occupied mode fail EF-1 An alarm shall be registered in the BAS
Reset sequence
END OF TEST
Notes:
ST. Lucie international Airport
#20061
FUNCTIONAL TEST
EXHAUST FAN EF-2
1. Functional Testing Record
Test Test Procedure Expected Response YEN Log #
1 Observe the unit in OFF condition. Backdraft damper closed. (if applicable)
Disconnect functions properly.(if
Fan is off and stopped completely Y
2 Observe the unit in ON condition. Fan rotation correct. Y
No excessive noise or vibration. Y
Backdraft damper open.(if applicable)
3 Describe fan controls and interlocks:
ON/OFF Control -
Test all specified interlocks by starting and Fan starts and stops under control from
stopping lead equipment and verifying fan specified controller
start/stop
Interlock
AHU-NA(FANS ARE TIED TO SCHEDULE
Miscellaneous Alarms & Safeties:
In occupied mode fail EF-2 An alarm shall be registered in the BAS
Reset sequence
END OF TEST
Notes:
ST. Lucie international Airport
#20061
FUNCTIONAL TEST
EXHAUST FAN EF-3
1. Functional Testing Record
Test Test Procedure Expected Response YEN Log #
1 Observe the unit in OFF condition. Backdraft damper closed. (if applicable)
Disconnect functions properly.(if
Fan is off and stopped completely Y
2 Observe the unit in ON condition. Fan rotation correct. Y
No excessive noise or vibration. Y
Backdraft damper open.(if applicable)
3 Describe fan controls and interlocks:
ON/OFF Control -
Test all specified interlocks by starting and Fan starts and stops under control from
stopping lead equipment and verifying fan specified controller
start/stop
Interlock
AHU-NA(FANS ARE TIED TO SCHEDULE
Miscellaneous Alarms & Safeties:
In occupied mode fail EF-3 An alarm shall be registered in the BAS
Reset sequence
END OF TEST
Notes:
ST. Lucie international Airport
OCI ENGINEERING #20061
LO***v
Zone Sensor Calibration Verification
Room Instrument Measured Value Wall Sensor Value
LOBBY 73.71'52RH 72.81'55RH
PASSENGER WAITING ROOM 74F 54RH 72.1F 53RH
RECEPTION AREA 72.51'59RH 71.71'57RH
Notes:
/ ..� ST. Lucie international Airport
OCI ENGINEERING #20061
LOO**'F
MAU-1 System Overview
PF
St Lucie Air Port
MAU1
�- AAflN BACNET CDM MUNICATED VALUES
AIRPORT '® '®
SA TEMP 74.10 OA TEMP 87.90
COILTEMP 45.80 CA 1h9 TEMP 77.10 TO RESET ALARMS COMMAND ALARM RESET ON
AHWE CA DP TEMP 7240 0OPER.THE ALARM RESET POINT WILL QUICKLY
TURN ON AND THEN OFF AGAIN.
OA HUMID 60.10 IF ALARM CCU IPION5 ARE CLEAR
ALARMS WILL RESET IF THEY ARE NOT THE
SUCPRESS 152.0 a ALARM WILL COME BACK IN S MINUTES.
HEAP PRESS 355.W COMP TEMP 148.80
OtiV -U. OO Utiti�
OA H U SA
�G v
MAW START STOP • ;�
NORMAL �•
ON
/ I ST. Lucie international Airport
OCI ENGINEERING #20061
LOO**'F
AHU-1 System Overview
TOD TRG ULL THU TOD IRL,
St Lucie Air Port �ON UN ON
AHME o
4 10 SLCIA.DAIE.PPCL.RPT r r
r I'
..IRPORT 77,10 DEG F
YY f YY
sLaMaui T
I H fSFlh
u
.Y , L.gffl ®n 67,22 DEG F
r
nna
'OA l X$10, SA
COOL STAGE 8I r r SUPPLY FAN SIS
ON r ON
rr• r
SLA.EF1 SLA.EF2 SLA.EF3 PA TEMP OA HUMIDITY
JI..A h1AU1 S$$ EX FAN SS ER FAN SS EX FAN SS 94.76 DEG F 67.74 PCT
Y r r Y ..L• 1_S7A�.STL3[ ON ON
ON
♦; • s I Alarm Status
�• Y e :Y
/ ..� ST. Lucie international Airport
OCI ENGINEERING #20061
v
RTU-1 System Overview
RFtIER ROOF TOP PACKAGE UNIT SLCdA.dx1€.PLOT
�,IRPORT
Outsida Air
7 +
SAT
�M
00o n
B S$NFO Tf]C *SuAppN
Return 1 r ON
Air -
CSLA
OMP STS
ON1 1 •l Y
I
i 1 �
BArrrFTTRo,u rAT0R
1 1 •
PCT
RI TM
. 11
Murtfdty
OFF
' 1: 72,10
[j Graphics•[SLA.RTLI.Oi] T€vrpalatrrte
Z-I I ST. Lucie international Airport
OCI ENGINEERING #20061
LOO**'F
RTU-2 System Overview
CARRIER ROOF TOP PACKAGE UNIT
iilTrg
AIRPORT �.
Outside Air
L_01
T Supply
r
Retur I 1 4
Air `v-
caraPsis
' ON
BACNETTRANSLATGR +rNm1 1 r • `a'
43.63 PC
r eAll,
H umldkty
RH TRG
OFF
l+ 1 +
TeFrwrature
Commissioning Log
SLC International Airport
#20061
No Date Discipline Associated Issue Description Resp Resolution/Follow-up Res Date Status
Equipment Discipline
1 6/8/20 Controls BAS No low outside airflow alarm Siemens Alarm added during Cx @1100CFM after 30 6/8/20 CLOSED
min, per Bob with SLC. OCI-SW 06-08-20
2 6/8/20 Mech. AAON Unit Disconnect does not have a permanent label Grimes 6/8/20
CU-1 mounting hardware is rusting
3 6/8/20 Mech. CU-1 Grimes 6/8/20
1
Commissioning Log
OCI EN�M'
SLC International Airport
#20061
Condenser unit fan connections are exposed
above grilles. St. Lucie County to comment.
4 6/8/20 SLC CU-1 SLC
2
Commissioning Log
OCI E�ERlly
SLC International Airport
#20061
General housekeeping and clean up of
construction debris.
5 6/8/20 GC Mech Room GC
Ductwork should have a mastic finish
6 6/8/20 Mech. Ductwork Grimes 6/8/20
7,
T-
3
j Commissioning Log
OCI ENGINEERING SLC International Airport
k000lr #20061
Flexible conduit should have straps to
ductwork
7 6/8/20 Electrical Conduit
6d
8
4
Date: 06-08-2020 SLC International Airport bldg remediation
Time: 09:O0am #20061
Art Munns OCI Engineering 407-808-9782 amunns@ociengineering.com
Sean Willis OCI Engineering 407-721-4411 swillis@ociengineering.com
Brian Masters Saint Lucie County 407-808-9782 mastersb@stlucieco.org
David Dickson Siemens 954-329-6109
Terrell Selph Grimes 777-979-4193
Hugh Grimes Omega T&B 777-216-7632
Luis Vega AAON
1
SALASO' BRIEN 3501 Quadrangle Blvd., Suite 100
Orlando, Florida 32817
expect a difference 407.380.0400 1 www.salasobrien.com
April 21, 2020
SHOP DRAWING REVIEW COMMENTS
Reference: St. Lucie County Airport Forensic Analysis
Salas O'Brien Florida #15072
Subject: Final Test and Balance Report Submittal
Reviewed By: Kyle J. Cartier, P.E.
Engineer's review is for general conformance with the design concept and contract documents.Markings or comments
shall not be construed as relieving the Contractor from compliance with the project plans and specifications, nor
departures therefrom. The Contractor remains responsible for details and accuracy, compliance with the Contract
Documents and intent,for confirming and correcting all quantities and dimensions,for selecting appropriate fabrication
processes,for techniques of assembly,and for performance of work in a safe manner.
OVERALL DISPOSITION: Revise and Resubmit
1. Verify the recorded values for AHU-1. The summation of the outside air (1,852 CFM) and
return air (4,665 CFM) exceed the supply air from the unit (total of outside and return is
6,517 CFM, recorded supply is 5,341 CFM). The summation of the return air from the AHU-
1 table is 2,808 CFM, which is not consistent with the value recorded in the AHU-1 data
sheet (4,665 CFM).
2. It is noted that the final total supply air for RTU-1 is considerably lower than design (73%).
3. There is a difference of 356 CFM between the recorded RTU-2 supply air (1,986 CFM) and
return air(1,630 CFM). This implies that the outside air damper on RTU-2 is not completely
closed. Ensure the outside air damper on RTU-2 is completely closed and sealed and re-
measure to ensure the supply and return airflow values are the essentially the same.
4. It appears exhaust fans EF-1, EF-2 and EF-3 have not been rebalanced to their respective
new airflows as required by sheet M1.1, Plan Reference Notes 14, 13 and 15
respectively. Rebalance exhaust fans to values indicated, record and re-submit for review.
5. The Outside Air Unit test data is missing the entering and leaving dry bulb and wet bulb
air temperatures across the unit heat pipe coils. Measure and record these values and
include in the test report for evaluation. Refer to sheet M4.1, Grade Mounted Package
100% Outside Air Unit Schedule for indicated values across the pre-cooling and reheat
coils.
6. Confirm the 52 degree off-coil temperature indicated in the Outside Air Unit report form
is the temperature leaving the DX cooling coil prior to entering the heat pipe reheat coil.
7. Measure and record the total unit amp draw and voltage at design conditions. It appears
the recorded values for amps and voltage are for the evaporator fan only. Refer to sheet
M4.1, Grade Mounted Package 100% Outside Air Unit Schedule for unit design MCA value.
Shop Drawing Review Comments
Page 2 of 2
8. Rebalance total airflow from the Outside Air Unit to within 10% of the total design (1,540
CFM maximum) as opposed to the 1,852 CFM recorded.
END OF DOCUMENT
OMEGA AIR SERVICES LLC
DBA OMEGA TEST AND BALANCE
NNNA CERTIFIED INDEPENDENT TES TAND BALANCE COMPA N Y---
126 WISTERIA AVENUE, FORT PIERCE, FLORIDA 34982
CELL (772)216-7632
TABB CERTIFICATION NO. BB032001C
www.omegaairserviceslic.com
omegamaniac532002@yahoo.com
TESTING, ADJUSTING, AND BALANCING REPORT
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
FORT PIERCE, FLORIDA
MECHANICAL ENGINEER:
SIMS WILKERSON CARTIER ENGINEERING INC.
12124 HIGH TECH AVENUE, SUITE 200
ORLANDO, FL 32817
MECHANICAL CONTRACTOR:
GRIMES HEATING & AIR CONDITIONING
3054 NORTH US HWY. ONE
FORT PIERCE, FLORIDA 34946
4-9-20
--ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES—
HUGH GRIMES
TABB TECHNICIAN
B610"12610T SEPTEMBER 30,�1
TESTING,ADJUSTING AND BALANCING BUREAU
HVAC EXPERTISE "THE PROFESSIONAL'S CHOICE"'
OMEGA AIR SERVICES LLC
DBA OMEGA TEST AND BALANCE
NNNA CERTIFIED INDEPENDENT TES TAND BALANCE COMPA N Y---
126 WISTERIA AVENUE, FORT PIERCE, FLORIDA 34982
CELL (772)216-7632
TABB CERTIFICATION NO. BB032001C/BB032002S/BB1032610T
www.omegaairserviceslic.com
omegamaniac532002@vahoo.com
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
TEST AND BALANCE INSTRUMENTS
SHORTRIDGE SERIES 8400 FLOWHOOD W/ADM860 AIR DATA MULTIMETER
RANGE: 0 TO 61 IN H.G
ACCURACY: 0.05% FS
CALIBRATION DATE: SEPTEMBER 8, 2019
CHECK-IT DIGITAL PSYCHROMETER—MODEL #622
RANGE: 350 TO 2050 F, 5% TO 100% RH
ACCURACY: ±20 ±1 DIGIT t30/o
CALIBRATION DATE: AUGUST 8, 2018
SHORTRIDGE ADT446 TEMPROBE
RANGE: -200 TO 1800 F
ACCURACY: t 0.50 FROM 320 TO 1580 F
CALIBRATION DATE: AUGUST 8, 2018
FLUKE 322 CLAMP METER
HUGH A. GRIMES,
CERTIFIED T.A.B.B. CONTRACTOR/SUPERVISOR/TECHNICIAN
--ALL WORK PERFORMED IN ACCORDANCE WITH TABS STANDARDSAND PROCEDURES—
AM
g rr
HUGH GRIMES
TABB TECHNICIAN
B61032610T SEPTEMBER 30.2020 A 1.
�W#kl
-_ TESTING,ADJUSTING AND BALANCING BUREAU
HVAC EXPERT[Sf 'THE PROFESSIONALS CHOICE""`
_.-\ CartYFv"
L^ 4ry
HUGH GRIMES
TABB TECHNICIAN
B107 610T S PT M6 R 30,2021
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
AIR HANDLING UNIT
UNIT AHU-1
MAKE CARRIER
MODEL 40RUAA16
SERIAL 1112UO9486
SHEAVE 7 X 1
BELTS 1/A46
FILTERS 1"
MOTOR
MAKE IFR GE156
HP I RPM 3.711750
VIPHIHZ 208-23013160
FLAISF 10.611.15
SHEAVE 3 3/4 X 1
CL 17
HEAT 2.76 KW ELECTRIC
EVAPORATOR DESIGN I ACTUAL
SA CFM 575015341
OA CFM 140011852**
RA CFM 5225I4665
EXT. SP NA 1.84
DISC. SP NA 1.67
SUCT. SP NA 1-.17
OAT DB/WB NA 88.1/80.1
RAT DB/WB NA 72.3/61.8
LAT DB/WB NA 54.1/53.6
FAN RPM NA I NA
VOLTS 2081210 AVG.
AMPS 10.618.6 AVG.
COMPRESSOR
MAKE
MODEL
SERIAL
VIPHIHZ
RLA
LO PRESSURE
HI PRESSURE
REFRIGERANT
FANIHPIRPM
VIPHIHZ
CC HEAT AMPS
REMARKS:MTR. PULLEY FULLYCLOSED. ** SEE NOTES ON OUTSIDE AIR UNIT.
ALL WORK PERFORMED IN ACCORDANCE WITH TABB STANDARDS AND PROCEDURES
1
vrea
cCa�6 "cS�
m
HUGH GRIMES
TABB TECHNICIAN
BB10"22670T SEPTEMBER 30 2021.
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
AIR OUTLETS
AHU-1
SUPPLY
ADDRESS OUTLET TYPE DESIGN PRE. FINAL
NUMBER CFM CFM CFM
101 1 SW 900 822 861
106 2 SW 900 702 737
121 3 SW 900 808 827
117 4 SW 900 803 878
NA 5 CD 100 82 96
111 6 CD 150 130 139
110 7 CD 100 72 90
106 8 CD 150 66 113
103 9 CD 125 100 112
107 10 CD 175 143 147
107 11 CD 175 146 159
108 12 CD 175 140 160
112 13 CD 75 54 77
115 14 CD 175 144 151
116 15 CD 275 218 301
116 16 CD 275 232 292
109 17 CD 75 78 81
102 18 CD 125 123 131
5750 4863 5352
REMARKS: NOTE REVISED FUTURE OUTSIDE AIR SETPOINTS COULD
EFFECT THE FINAL NUMBERS
ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDSAND PROCEDURES
1
vrea
cCa�6 "cS�
m
HUGH GRIMES
TABB TECHNICIAN
BB10"22670T SEPTEMBER 30 2021.
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
AIR OUTLETS
AHU-1
RETURN
ADDRESS OUTLET TYPE DESIGN PRE. FINAL
NUMBER CFM CFM CFM
116 1 RG -600 -549 357
116 2 RG -600 -536 348
115 3 RG -175 -155 99
108 4 RG -175 -159 104
107 5 RG -350 -313 203
101 6 RG -750 -659 428
101 7 RG -750 -655 425
101 8 RG -750 -680 442
104 9 RG -750 -686 445
106 10 RG -325 -273 177
-5225 -4665 2808
REMARKS:NOTE LOWER RETURN VALUES ARE MEASURED WITH
OUTSIDE AIR UNIT PRODUCING WHAT IS REPORTED
ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES
1
�' .. sn►ar 4m
HUGH GRIMES
TABB TECHNICIAN
BB1032670T SEPTEMBER 30,2021
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
AIR OUTLETS
RTU-1
SUPPLY
ADDRESS OUTLET TYPE DESIGN PRE. FINAL
NUMBER CFM CFM CFM
117A 1 CD 250 145 187*
117A 2 CD 250 151 190*
117A 3 CD 250 149 169*
117A 4 CD 250 156 189*
117A 5 CD 250 138 182*
117A 6 CD 250 137 177*
1500 876 1094
REMARKS: ---RTU-1 NOT ACCESSIBLE FOR TESTING.
---EAT @ 74.3
---LAT @ 57.5
NOTE;EXISTING EQUIPMENT UNIT HAS VARIABLE MOTOR DRIVE
Test and Balance has no access to these systems. SEE PRELIMINARY
REPORT
ALL WORKPERFORMED INACCORDANCE WITH TABB STANDARDSAND PROCEDURES
1
vrea
cCa�6 "cS
m
HUGH GRIMES
TABB TECHNICIAN
BB10"22670T SEPTEMBER 30 2021.
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
AIR OUTLETS
RTU-1
RETURN
ADDRESS OUTLET TYPE DESIGN PRE. FINAL
NUMBER CFM CFM CFM
117A 1 RG -725 -561 561
117A 2 RG -725 -516 516
-1450 -1077 1077
REMARKS:
ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES
1
vrea
cCa�6 "cS�
m
HUGH GRIMES
TABB TECHNICIAN
BB10"22670T SEPTEMBER"I0;2021.
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
AIR OUTLETS
RTU-2
SUPPLY
ADDRESS OUTLET TYPE DESIGN PRE. FINAL
NUMBER CFM CFM CFM
124 1 CD 175 87 137
124 2 CD 175 70 133
ATOS 3 CD 150 50 97
126 4 CD 175 51 131
124 5 CD 175 66 99
124 6 CD 175 108 139
102 7 CD 175 168 171
102 8 CD 125 78 114
119 9 CD 125 71 109
120 10 CD 125 68 113
123 11 SW 225 239 217
123 12 SW 225 256 216
123 13 SW 225 269 211
126 14 CD 125 38 96
2000 1619 1986
REMARKS: ---RTU-2 NOT ACESSIBLE FOR TESTING.
---EAT @ 73.7
---LAT @ 55.1
ALL WORK PERFORMED INACCORDANCE WITH TA BB STANDARDS AND PROCEDURES
1
vrea
cCa�6 "cS
m
HUGH GRIMES
TABB TECHNICIAN
BB10"22670T SEPTEMBER 30 2021.
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
AIR OUTLETS
RTU-2
RETURN
ADDRESS OUTLET TYPE DESIGN PRE. FINAL
NUMBER CFM CFM CFM
124 1 RG -575 -265 561
124 2 RG -575 -208 548
102 3 RG -550 -406 523
-1700 -879 1630
REMARKS:
ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES
1
�' .. sn►ar 4m
HUGH GRIMES
TABB TECHNICIAN
BB1032670T SEPTEMBER 30,-,21
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
AIR OUTLETS
EF-1
EXHAUST
ADDRESS OUTLET TYPE DESIGN PRE. FINAL
NUMBER CFM CFM CFM
10S 1 EG -200 -137 137
103 2 EG -7S -61 61
-27S -198 198
REMARKS:
ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES
1
�' .. sn►ar 4m
HUGH GRIMES
TABB TECHNICIAN
BB1032670T SEPTEMBER 30,-,21
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
AIR OUTLETS
EF-2
EXHAUST
ADDRESS OUTLET TYPE DESIGN PRE. FINAL
NUMBER CFM CFM CFM
102 1 EG -75 -74 74
NA 2 EG -100 -113 113
NA 3 EG -100 -67 67
-275 -254 254
REMARKS:
ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES
1
vrea
cCa�6 "cS�
m
HUGH GRIMES
TABB TECHNICIAN
BB10"22670T SEPTEMBER 30 2021.
ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL
PRELIMINARY READINGS
AIR OUTLETS
EF-3
EXHAUST
ADDRESS OUTLET TYPE DESIGN PRE. FINAL
NUMBER CFM CFM CFM
118 1 EG -75 * 41
119 2 EG -100 -75 70
120 3 EG -125 -130 123
119 4 EG -100 -144 131
120 5 EG -125 -89 80
-525 -438 445
REMARKS: ---*NO ACCESS
ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES
L^ 4ry
HUGH GRIMES
TABB TECHNICIAN
B10t 610T C PT M6 R 30,2021
OUTSIDE AIR UNIT
REMARKS: ST.LUCIE AIRPORT
UNIT O\A
MAKE AAON
MODEL RNA 011
SERIAL 201909
SHEAVE DD
BELTS DD
FILTERS NA
MOTOR
MAKE I FR NA
HPIRPM 1\NA
VIPHIHZ 230\3\60
FLAISF 4.2
SHEAVE DD
CL DD
HEAT NA
EVAPORATOR DESIGN I ACTUAL DESIGN ACTUAL DESIGN ACTUAL
SA CFM 1400I1852
OA CFM 1400I1852
RA CFM INA I I
EXT. SP INA I I
DISC. SP INA I I
SUCT. SP INA I I
OAT DB/WB 95\85I84.6\77.8 I I
EAT DB/WB 95\85I84.6\77.8 I I
LAT DB/WB 52.3I 52.2/52@COIL* I I
FAN RPM NAINA NAINA NAINA
VOLTS 2301210 AVG. I I
AMPS NA 12.1 AVG. I I
COMPRESSOR 1 1 1
MAKE
MODEL PLEASE NOTE WE DO NOT
SERIAL TEST THE REFRIGERANT
VIPHIHZ SIDE
RLA
LO PRESSURE
HI PRESSURE
REFRIGERANT
FANIHPIRPM
VIPHIHZ
CC HEAT AMPS
NOTE:LAT @a D15CGARGE=68 160.1 DURING TESTING 5ETPOINT5 BY OTHERS
Unit alarm/shut down if drive setting below 35 Hertz
Building pressure f,019
ALL WORKPERFORMED INACCORDANCE WITH TABB 5TANDARD5AND PROCEDURES