Loading...
HomeMy WebLinkAboutSt. Lucie Airport Cx Report COMMISSIONING v �ENGINEERING Commissioning Report for Saint Lucie County International Airport 3000 Curtis King Blvd. Fort Pierce, FL. 34946 Table of Contents #20061 Date: 6/12/2020 1. Commissioning Group Certification 2. Executive Summary 3. Commissioning Plan A. Appendix "A"— Pre-Commissioning Check Lists B. Appendix "B"— Functional Performance Tests C. BAS Systems - Site Observation screen captures 4. Daily Logs 5. Sign-In Sheets 6. T&B report OCI ENGINEERING Commissioning Group Certification Project: #20061 The data presented in this report are the results obtained from the building commissioning process in accordance with AABC ACG Commissioning Guideline and ASHRAE standard 202-2018 Fundamental Commissioning Requirements.Any variances from design are noted within this report. Submitted &Certified by AABC ACG Certified Commissioning Group: OCI Engineering, LLC AABC ACG Certified Commissioning Authority: William A. Munns Reg. No. 514-1170 Signature - z I 9V Date June 12, 2020 `►, a--C .�. A '���•1110 OCI ENGINEERING L011100'r Commissioning Report SLC International Airport Remediation 3000 Curtis King Blvd. Ft. Pierce, FL. 34946 #20061 Executive Summary 06-12-2020 Scope of the Commissioning Program OCI Engineering was hired by Saint Lucie County, to provide commissioning services. The intent of the commissioning program was to help ensure that all commissioned systems were designed, installed and tested in accordance with the contract documents and the owner's requirements, and that all systems were fully functional when turned over to the owner by the contractor. Also, the program was intended to help ensure that the owner's maintenance personnel were fully trained in the operation and maintenance of the systems at completion of the project. The general contractor and all mechanical, electrical, controls and T&B subcontractors were members of the commissioning team and participated in the commissioning process. Commissioning activities for the project began March-09-2020 when the commissioning specifications and a commissioning plan were prepared for incorporation into the construction documents. Field visits were made to verify that the installation was in accordance with the plans and specifications and to hold commissioning meetings. Pre-commissioning check lists were prepared by OCI and completed by the contractors prior to the start of functional performance testing on June-08-2020. Commissioning of the mechanical systems was essentially finished on June-08-2020 with the punch list items addressed. OCI prepared a commissioning report of systems for the owner. Systems Commissioning was provided for one new dedicated AAON outside air unit, 3 existing EF's, new ductwork, and the updated building automation system. Orlando -Ft. Pierce -West Palm Beach -Miami -Ft. Myers Tampa Washington DC Baltimore -Norfolk -Dallas - San Francisco 600 S. Orlando Avenue, Suite 100,Maitland,FL 32751 Phone: 407-332-5110 Fax: 407-332-7704 www.oc1associates.com Commissioning Methodology On this project, the commissioning process started when OCI developed pre-commissioning checklists for each piece of equipment which were then completed by the responsible contractor during startup. In many cases the checklists served as the startup forms. Once completed, the forms were spot checked against the installed equipment for accuracy. The check lists were intended to help the contractor document his startup activities and to bring some rigor and methodology to the startup process. All checklists were signed by the subcontractor's field personnel. Once the checklists were complete, the functional performance testing started using forms and procedures developed specifically for the project based on the engineer's drawings, sequences of operation and the approved control shop drawings and submittals. The equipment and controls were checked for full and proper operation. The actual test procedures and results can be found on the completed forms in the body of the report. Functional performance testing was carried out by OCI in conjunction with the responsible sub-contractors. The test and balance report was validated through random sampling of the readings in the final test and balance report. After the completion of the functional testing, the owner's operating staff was trained in the proper operation and maintenance of all systems related to this project. A random sampling of the calibration of control system analog inputs was conducted during the functional performance testing. All temperature sensors were calibrated. All thermostat control ranges and the high and low limit settings specified by the owner were programmed. Commissioning Results In general, the commissioning of the new air conditioning and heating systems, has resulted in systems that are fully functional in accordance with the contract documents (see resolution in daily log attached). The mechanical and controls contractors have corrected the deficiencies uncovered during commissioning process. Outstanding Issues At the completion of the functional testing program on June-08-2020 with exception as noted in the final FPT and daily log, all the systems were operating as specified and in accordance with the intent of the drawings and specifications. Orlando -Ft.Pierce -West Palm Beach-Miami -Ft.Myers—Tampa—Washington DC Baltimore-Norfolk-Dallas- San Francisco 600 S. Orlando Avenue, Suite 100,Maitland, FL 32751 Phone: 407-332-5110 Fax: 407-332-7704 www.ociassociates.com Commissioning Plan SLC International Airport Remediation 3000 Curtis King Blvd. Ft. Pierce, FL. 34946 March 18, 2020 Prepared for: Saint Lucie County 3000 Curtis King Blvd. Ft. Pierce, FL. 34946 OCI ENGINEERING Performed by: OCI Engineering, LLC #20061 Summary The Commissioning Plan is developed in draft form for the specific project during the design phase and is updated during construction. The plan provides direction for the commissioning tasks during construction. The plan focuses on providing support for the specifications and forms for the application of the commissioning process. Table of Contents 1.0 Overview.................................................................................................. 1 1.1 Abbreviations................................................................................. 1 1.2 Purpose of the Commissioning Plan ............................................ 2 1.3 Commissioning Scope................................................................... 2 1.4 Commissioning Flow Chart............................................................ 3 1.5 Commissioned Systems................................................................ 4 1.6 Appendix A— Pre-Commissioning Checklist................................. 5 1.7 Appendix B — Functional Performance Tests............................... 5 2.0 General Building Information................................................................. 6 3.0 Construction/ Cx Team Data................................................................. 7 4.0 Roles and Responsibilities..................................................................... 8 4.1 Commissioning Team.................................................................... 9 4.2 Responsibilities.............................................................................. 9 5.0 Commissioning Process ...................................................................... 11 5.1 LEED Requirements.................................................................... 11 5.2 Miscellaneous Management Protocols........................................ 12 5.3 Submittals and Documentations.................................................. 12 5.4 Special Submittals, Notifications and Clarifications..................... 12 5.5 Pre-functional Tests..................................................................... 13 5.6 Start-up .................................................................................. 13 5.7 TAB Plan ................................................................................. 14 5.8 Controls Check Out Plan............................................................. 14 5.9 Development of Functional Test and Verification Procedures..... 14 5.9.1 Overview.......................................................................... 14 5.9.2 Scope of Testing.............................................................. 15 5.9.3 Development Process...................................................... 15 5.10 Execution of Functional Testing Procedures............................... 15 5.10.1 Overview and Process..................................................... 15 5.10.2 Deficiencies and Retesting .............................................. 15 5.11 Operating and Maintenance Manuals.......................................... 16 5.12 Training of Owner's Personnel .................................................... 16 5.12.1 Overall Plan ..................................................................... 16 5.13 Warranty Period ......................................................................... 16 5.14 Final Commissioning Report ....................................................... 17 5.15 Schedule .................................................................................... 18 i 1. OVERVIEW 1.1 Abbreviations The following are common abbreviations and definitions used in this document. A/E Design architects/engineers CxP Commissioning authority CC Controls contractor CM Construction manager Cx Commissioning Cx Plan Commissioning plan document EC Electrical contractor FT Functional performance test GC General contractor MC Mechanical contractor PM Owner's project manager PC Pre-functional checklist Subs Subcontractors to general TAB Test and balance contractor Trade Representative: Person who competently represents the work force engaged by the contractor for the individual trade named. This person shall be completely familiar with the work performed for this contract at all levels of detail of his trade and with coordination to other trades. Participate: Attend commissioning events, provide technical expertise or knowledge, equipment, measurements and observation needed or requested by the commissioning authority or owner. Provide follow-up analysis, equipment data, design data, or other trade or professional service needed in response to commissioning events. Verify: To positively determine that the measured or observed quantity satisfies all required criteria. Simply performing the test, measurement or observation does not constitute"verification". The test result must also pass all contract criteria. Tests, which fail, must be repeated at no additional cost to the owner after repairs or adjustments are made, until full verification is achieved. 1 1.2 Purpose of the Commissioning Plan The purpose of the construction phase commissioning plan is: To provide direction for team members participating in the commissioning process during construction, particularly providing resolution for issues and providing details that cannot be, or were not, fully developed during design, such as scheduling, participation of various parties of this project, actual lines of reporting and approvals, coordination, etc. This plan does not provide a detailed explanation of required testing procedures. The detailed testing requirements and procedures are found in the specifications sections 230800. 1.3 Commissioning Scope Commissioning is a systematic process of achieving, verifying and documenting that the performance of the facility and its various systems meets the design intent and functional and operational needs of the owner and occupants. This includes the specific training of the facility personnel involved in the operation and maintenance of the building's equipment and facilities. There are numerous checks for each stage of the building commissioning process which ensures that set procedures are followed. This approach to constructing a building, along with the necessary training of facility personnel, serves as a thorough quality assurance program for building construction, and the building construction industry. Commissioning during the construction of this project is intended to achieve the following specific objectives: • Ensure that equipment and systems being commissioned are installed properly and receive adequate operational checkout by installing contractors. • Verify and document proper performance of equipment and systems. • Ensure that O&M documentation is complete. • Ensure that the owner's operating personnel are adequately trained. 2 1.4 Commissioning Flow Chart—For Fundamental Commissioning Requirements The following chart illustrates the overall status of the commissioning process for the project. Gray - Not included in scope Project Start OPR Workshop Cx Plan Verification Sheets Functional Performance Design Phase Development 101 Development Test Forms Development Design Review Design Review Comments Start Collection of Submittal&O&M Data Documentation for Sheets Tech Transfer On-Site Progress Construction Phase Progress Reporting Construction Observations Issues Phase Cx Construction Coordination&Updating Meetings Issue Updating& Resolution Daily Log Test&Balance TAB Testing Review TAB Reports Coordination Field Testing Component Verification Functional Performance Testing Training Observation Systems Manuals Draft Cx Report Tech Transfer O&M Manuals Review Project Warranty Letters Record Drawings Review Turnover Phase -� Review Final Cx Report Submittal&Data Sheets Specifications Cx Testing Reports Seasonal or Updated Issue Status Deferred Testing Warranty Follow-up 3 Inspections 1.5 Commissioned Systems The following systems are being commissioned in this project. All general references to equipment in this document refer only to equipment that is to be commissioned. HVAC System (and all integral equipment controls) • Roof top units (existing) • Air handler (existing) • Dedicated Outside Air unit • Electric duct heater • Exhaust fans (existing) • Ductwork, Duct pressure testing • Testing, adjusting and balancing work • Facility management and control system (controlled devices, control loops, and system integration) 4 1.6 Appendix A— Pre-Commissioning Checklists Dedicated outside air unit Condensing Unit Air Handling Unit (existing) Rooftop Units (existing) Exhaust Fans (existing) Electric Duct Heater Ductwork Automatic Controls 1.7 Appendix B— Functional Performance Tests Dedicated Outside Air unit Rooftop units (existing) Air Handling unit (existing) Electric Duct Heater Exhaust fans (existing) Automatic Controls 5 2.0 General Building Information Project: SLC International Airport Remediation Location: Ft. Pierce, Florida Total Square Footage: 6963 Buildings: Airport Terminal Project Schedule Design Complete: 3/3018 Construction Complete: 4/30/2020 Project Budget: $250,000 Description: Retrofit to the HVAC system including the dedicated outside air unit, AHU, RTU's, ductwork, exhaust flow and building automation control system 6 3.0 Construction/Cx Team Data (primary parties) Team Member Company& Contact Names Office, Cell, Email Owner O: 772-834-9097 Saint Lucie County C: 2300 Virginia Ave. Scotty Beaulieu Email: beaulieus@stlucieco.org Fort Pierce, FL. 34982 Architect O: C: Email: Commissioning Authority O: (407)332-5110 OCI Engineering C: (407)808-9782 600 S. Orlando Ave, Ste. 100 Art Munns Maitland, FL 32751 Email: amunns@ociengineering.com Electrical Designer/Eng. O:407-380-0400 Salas O'Brien Kyle Cartier C: 3501 Quardrangle Blvd., Suite 100 Orlando, FL. 32817 Email: Email:kyle.cartier@salasobrien.com Mechanical Designer/Eng. O:407-380-0400 Salas O'Brien C: 3501 Quardrangle Blvd., Suite 100 Kyle Cartier Email:kyle.cartier@salasobrien.com Orlando, FL. 32817 General Contractor O: 772-370-4024 Crist Construction Jim Crist C: 4365 Gator Trace Lane Fort Pierce, FL. 34982 Email:jimcrst@yahoo.com Mechanical Contractor : 772-461-8711 Grimes C: Jim Grimes 3054 N. US HWY 1 Fort Pierce, FL. 34946 Email:jimgrimesjr@aol.com Electrical Contractor O: C: Email: Plumbing Contractor O: C: Email: TAB Contractor O: 772-216-7632 Omega Air Services, LLC C: 126 Wisteria Ave. Hugh Grimes Fort Pierce, FI. 34982 Email: omegamaniac532002@yahoo.com Controls Contractor O: 954-802-8631 Siemens Tom Bolko C: 2969 SW 42"d Avenue Email:Thomas.bolko@siemens.com Palm City, FL. 34990 7 4.0 Roles and Responsibilities The CxP was hired by the owner directly. In general, the CxP coordinates the commissioning activities and reports to the program manager and owner. The CxP's responsibilities, along with all other contractors' commissioning responsibilities are detailed in the specifications. The specifications will take precedence over this Cx plan. All members work together to fulfill their contracted responsibilities and meet the objectives of the contract documents. For coordination purposes, the commissioning scope involving all parties is outlined here. 1. Document systems design intent (A/E) 2. Inspect and confirm that equipment and systems have been properly installed in accordance with the contract documents and manufacturer's written installation instructions (CxP and contractor). 3. Inspect and confirm that equipment has been placed into operation with manufacturer's oversight and approval and in accordance with contract requirements. (CxP and contractor). 4. Identify, document and report all deficiencies of the work versus contract specifications and performance requirements, for tracking and correction (CxP and contractor). 5. Monitor and enforce accessibility of all work areas and pieces of equipment. (contractor). 6. Assemble contractor as-built drawings (contractor). 7. Assemble operation, installation and maintenance instructions and submittal data (contractor). 8. Inspect and confirm the performance of each piece of equipment and each system (CxP and contractor), as described in contract. 9. Validate the test and balance report. (contractor, CxP) 10. Train owner's personnel in the proper operation of each piece of equipment and each system (contractor, CxP and A/E). 11. Document warranty start and end dates (contractor). 12. Prepare final commissioning report. (CxP) 8 4.1 Commissioning Team The commissioning team will consist of all members needed to execute the approved commissioning program. Minimum membership shall include: 1. Commissioning Authority (CxP) 2. Owner's Mechanical Engineer 3. Owner's Maintenance Representative 4. Contractor's Trade Representative 5. Mechanical Trade Representative 6. TAB Contractor 7. FMCS Contractor 8. Engineers of Record The contractor's personnel shall be made available to execute all aspects of the commissioning program until the owner accepts results. 4.2 Responsibilities Owner: 1. Assign engineering and maintenance personnel and schedule them to participate in the various meetings, training sessions and inspections. Commissioning Authority: 1. Review all commissioning requirements and intent of the contract documents and all related testing, verification and quality control procedures. 2. Coordinate the pre-commissioning and final commissioning schedules and activities. 3. Make periodic visits to the site, as necessary to witness equipment and system installations. 4. Schedule a pre-commissioning coordination meeting at some convenient location and at a time suitable to the contractor and engineers of record. In attendance are the respective representatives of the GC, CM, CxP, PM, A/E and the mechanical, controls, and TAB subs. This pre-commissioning meeting will be for reviewing the complete commissioning program, the flow of documents, establishing tentative schedules for maintenance orientation and inspections, O&M submittals, training sessions,job completion, system start-up and testing. At the meeting commissioning parties are introduced, the commissioning process is reviewed, and management and reporting lines are determined. The Cx plan is reviewed and process questions are addressed. Also covered are the general list of each party's responsibilities. 5. Attend selected planning and job-site meetings to remain informed on construction progress and to update parties involved in commissioning. The CM and GC provide the CxP with information regarding substitutions, change orders and any architect's supplemental instructions that may affect commissioning equipment, systems or the commissioning schedule. Later during construction, the CxP, through the PM, as required, will schedule necessary meetings between various commissioning team parties. 9 6. Schedule HVAC systems training for maintenance personnel prior to final commissioning of the above systems. 7. Receive and review operation and maintenance (O&M) manuals as submitted by the contractor and approved by the engineer of record. 8. Schedule the owner training sessions. 9. Upon receipt of the approved test and balance report, plan and schedule the test and balance report validation with the TAB contractor. 10. Upon receipt of notification from the contractor that the systems have been started, and that the systems and equipment is functioning as designed and specified, schedule the functional performance tests. These demonstrations will be conducted by the contractor and the controls trade representatives and witnessed by the CxP and other appropriate designees. 11. Prepare final commissioning report and submit to owner. Schedule final review with owner. Present all documentation and turn over signed acceptance of the system by the owner and CxP to the contractor. Engineers of record: 1. Prepare basis of design and system description documentation. 2. Verify adequate maintenance accessibility for each piece of equipment in actual installation. Periodic inspections are part of the engineer of record's construction administration duties. 3. Attend and participate in maintenance training sessions. 4. Review and approve all shop drawings. 5. Receive and review O&M Manuals as submitted by the contractor. Insert sections on system description. 6. Issue field reports noting deficiencies requiring correction to the CxP. Contractor: 1. Ensure full cooperation in the commissioning program. 2. Ensure cooperation and participation of specialty sub-trade representatives, as required. 3. Ensure participation of major equipment manufacturers and their representatives, as required. 4. Prepare operation, maintenance and installation manual submission, training sessions, equipment operation and job completion verification for use by CxP. 5. Conduct training sessions and conduct maintenance orientation and inspection sessions. 10 6. Update contractor as-built drawings and review with CxP. 7. Gather O&M data on all equipment and assemble in binders. Submit to engineer of record prior to the distribution completion stage. 8. Conduct and schedule representatives to participate in the training sessions as scheduled up by CxP. 9. Provide written certification that the work has been completed in accordance with the plans and specifications and that they are functioning as designed. Submit completed pre- functional checklist forms to CxP prior to the final verification. 10. At the completion of the controls and energy management systems start- up and adjustment work, demonstrate to CxP the performance of the facilities management and control systems. 11. Demonstrate the performance of each piece of equipment to CxP. Schedule the contractor representatives as may apply to demonstrate the performance of the equipment and systems. 12. Provide personnel and equipment as required to validate the TAB work. 13. Turn over set of contractor as-built drawings to CxP for review prior to incorporation into the record drawings. 5.0 Commissioning Process This section details the commissioning process by commissioning task or activity. 5.1 LEED Requirements (NOT REQUIRED) For this project, "LEED for new construction" addressed building Cx in 1 place, EA prerequisite 1. The scope of services for Cx should be based on the owner's project requirements. The following table outlines the team members primarily responsible to perform each Cx requirement. Table 5-1 LEED related Cx team members' responsibilities Task Responsibilities Designate Cx Authority (CxP) Architect Document Owner's Project Requirements (OPR) Architect, CxP Develop Basis of Design Design Team Incorporate Cx requirements into construction documents CxP, Design Team Conduct Cx design review to mid-construction documents CxP Develop and implement a Cx plan CxP Review contractor submittals applicable to systems being submitted N/A Verify the installation and performance of commissioned systems CxP Develop a systems manual for the commissioned systems N/A Verify that the requirements for training are completed Project team, CxP Complete a summary Cx report CxP Review building operations within 10 months after substantial completion N/A 11 5.2 Miscellaneous Management Protocols The following protocols will be used on this project. Issue Protocol For requests for The CxP goes first to the PM and the GC. information (RFI) or formal documentation requests: For minor or verbal The CxP goes directly to the informed party. information and clarification: For notifying contractors of The CxP documents deficiencies through the PM, but may discuss deficiencies: deficiency issues with contractors prior to notifying the PM. For scheduling functional The CxP works with the PM and GC to develop schedules. tests or training: For scheduling The CxP selects the date and schedules through the GC. commissioning meetings: For making a request for The CxP has no authority to issue change orders. significant changes: For making small changes The CxP may make small sequences of operations changes to in specified sequences of improve efficiency or control or to correct deficiencies, through the operations: responsible contractor, but shall review the change with the A/E, document the change and provide all changes of specified sequences to the PM and A/E. Subcontractors disagreeing Try and resolve with the CxP first. Then work through GC who will with requests or work with CxP directly or through the PM to resolve the situation. interpretations by the CxP shall: 5.3 Submittals and Documentation The CxP provides all subs responsible for commissioned equipment with commissioning documentation requirements for their respective equipment and systems. This data request typically coincides with the normal A/E submittal process. At minimum, this equipment data includes installation and start-up procedures, approved shop drawings, O&M data, performance data and control drawings. 5.4 Special Submittals, Notifications and Clarifications The subs, GC or A/E notify the CxP of any new design intent or operating parameter changes, added control strategies and sequences of operation, or other change order that may affect commissioned systems. The controls contractor provides the CxP a full points list with details requested by the CxP. Thirty (30) days prior to performing any required tests, cleaning or 12 flushing the subs provide the CxP full details of the procedures. As the phases of the TAB are completed, the draft TAB report is provided to the CxP with full explanations of approach, methods, results, data table legends, etc. The final TAB report is provided to the CxP upon completion. These submittals to the CxP do not constitute compliance for submittals for the O&M manuals. The CxP may request additional design narrative from the A/E and from the controls contractor depending on how complete the documentation was which was provided with the bid documents. The CxP may submit written RFIs to contractors through the PM, or address them directly for clarifications, as needed. 5.5 Pre-functional Checklists The word pre-functional refers to before functional testing. Pre-functional checklists (PC) are important to ensure that the equipment and systems are hooked up and operational and that functional performance testing may proceed without unnecessary delays. Each piece of equipment receives full pre-functional checkout by the contractor. No sampling strategies are used. In general, the pre-functional testing for a given system, must be successfully completed prior to formal functional performance testing of equipment or sub-systems of the given system. Pre-functional checklists are primarily static inspections and procedures to prepare the equipment or system for initial operation (e.g., oil levels checked, fan belt tension, labels affixed, gauges in place, sensor calibration, etc.). However, some pre-functional checklist items entail simple testing of the function of a component, a piece of equipment or system (such as measuring the voltage imbalance on a three-phase pump motor of a chiller system). Pre-functional checklists augment and are combined with the manufacturer's start-up checklist. Contractors typically already perform some, if not all, of the pre-functional checklist items the commissioning authority will recommend. However, few contractors document in writing the execution of these checklist items. This project requires that the procedures be documented in writing by the installing technician. The CxP does not witness all the pre-functional checklist verification, except for testing of larger or more critical pieces of equipment and some spot- checking. 5.6 Start-up The CxP assists the commissioning team members responsible for start-up in developing detailed start-up plans for all equipment. All start-up plans are to be approved by the CxP. Four weeks prior to start-up, the subs and vendors schedule start-up and initial checkout with the PM, GC and CxP. The start-up and initial checkout are directed and executed by the sub or vendor. The CxP, and PM if necessary, observe, at minimum, the procedures for each piece of primary equipment, unless there are multiple units, when a sampling strategy is used. For components of equipment, (e.g., VAV boxes), the CxP observes a sampling of the pre-functional and start-up procedures. To document the process of start-up and checkout, the site technician performing the line item task initials and dates each paragraph of procedures in the "start-up plan" and checks off items on the pre-functional and manufacturer field checkout sheets, as they are completed. Only individuals having direct knowledge of a line item being completed shall check or initial the forms. The subs and vendors execute the checklists and tests and submit a signed copy of the completed start-up and pre-functional tests and checklists to the CxP. The CxP may review pre- 13 functional checklists in progress, as necessary. The subs clearly list any outstanding items of the initial start-up and pre-functional procedures that were not completed successfully at the bottom of the procedures form or on an attached sheet. The procedures form and deficiencies are provided to the CxP within two days of test completion. The CxP works with the subs and vendors to correct and retest deficiencies or uncompleted items, involving the PM and others as necessary. The installing subs or vendors correct all areas that are deficient or incomplete according to the checklists and tests. 5.7 TAB Plan The TAB contractor submits the outline of the TAB plan and approach to the CxP and the controls contractor eight weeks prior to starting the TAB. Included in the approach, is an explanation of the intended use of the building control system. The CxP reviews the plan and approach for understanding and coordination issues and may comment but does not approve changes. The controls contractor reviews the feasibility of using the building control system for assistance in the TAB work. The TAB submits weekly written reports of discrepancies, contract interpretation requests and lists of completed tests to the CxP and PM. This facilitates quicker resolution of problems and will result in a more complete TAB before functional testing begins. TAB work will not begin until the control system has been pre-functionally tested and selective functional tests have been performed and approved by the CxP. 5.8 Controls Check Out Plan The controls contractor develops and submits a written step-by-step plan to the CxP, which describes the process, they intend to follow in checking out the control system and the forms on which they will document the process. The controls contractor will also meet with the TAB contractor prior to the start of TAB and review the TAB plan to determine the capabilities of the control system for use in TAB. The controls contractor will provide the TAB with any necessary unique instruments for setting terminal unit boxes and instruct TAB in their use (hand-held control system interface for use around the building during TAB, etc.). The controls contractor shall also provide a technician qualified to operate the controls to assist the TAB contractor in performing TAB. All CxP required controls pre-functional checklists, calibrations, start-up and selected functional tests of the system shall be completed and approved by the CxP prior to TAB. The controls contractor shall execute the tests and trend logs assigned to them and remain on site for assistance for mechanical system functional tests. 5.9 Development of Functional Test and Verification Procedures 5.9.1 Overview Functional testing is the dynamic testing of systems (rather than just components) under full operation (e.g., the chiller pump is tested interactively with the chiller functions to see if the pump ramps up and down to maintain the differential pressure set point). Systems are tested under various modes, such as during low cooling or heating loads, high loads, component failures, unoccupied, varying outside air temperatures,fire alarm, power failure, etc. The systems are run through all the control system's sequences of operation and components are verified to be responding as the sequences state. The commissioning authority develops the functional test procedures in a sequential written form, coordinates, oversees and documents the actual testing, which is usually performed by the installing contractor or vendor. 14 5.9.2 Scope of Testing A detailed description of the functional and pre-functional testing procedures and process will be developed for this project by the CxP for each piece of commissioned equipment. 5.9.3 Development Process Before test procedures are written, the CxP obtains all requested documentation and a current list of change orders affecting equipment or systems, including an updated points list, control sequences and set points. The CxP develops specific test procedures to verify proper operation of each piece of equipment and system. The CxP obtains clarification, as needed, from contractors and the A/E regarding sequences and operation to develop these tests. Prior to execution, the CxP provides a copy of the primary equipment tests to the installing sub (via the GC)who reviews the tests for feasibility, safety, warranty and equipment protection. Blank copies of the procedures are input into the O&M manuals for later use by operations staff. Functional testing and verification may be achieved by manual testing (persons manipulate the equipment and observe performance)or by monitoring the performance and analyzing the results using the control system's trend log capabilities or by stand- alone data loggers. The CxP uses judgment where needed to determine which method is most appropriate. 5.10 Execution of Functional Testing Procedures 5.10.1 Overview and Process The CxP schedules functional tests through the PM, GC and affected subs. For any given system, prior to performing functional testing, the CxP waits until the pre-functional checklist has been submitted with the necessary signatures, confirming that the system is ready for functional testing. The CxP oversees, witnesses and documents the functional testing of all equipment and systems according to the specifications and the Cx plan. The subs execute the tests. The control system is tested before it is used to verify performance of other components or systems. The air balancing and water balancing is completed before functional testing of air-related or water- related equipment or systems. Testing proceeds from components to subsystems to systems and finally to interlocks and connections between systems. 5.10.2 Deficiencies and Retesting The CxP documents the results of the test. Corrections of minor deficiencies identified are made during the tests at the discretion of the CxP. The CxP records the results of the test on the procedure or test form. Deficiencies or non-conformance issues are noted and reported to the PM on the Commissioning Corrective Action Report(Daily Log). Subs correct deficiencies, notify the CxP and return the form certifying correction. The CxP schedules retesting through the PM. Decisions regarding deficiencies and corrections are made at as low a level as possible, preferably between CxP or PM and the sub. For areas in dispute, final authority, besides the owner's, resides with the A/E. The CxP recommends acceptance of each test to the PM. The PM gives final approval on each test. 15 5.11 Operating and Maintenance Manuals The CxP reviews the O&M manuals and documentation for systems that were commissioned to verify compliance with the specifications. The CxP recommends approval and acceptance of these sections of the O&M manuals to the PM. The CxP also reviews each equipment warranty and verifies that all requirements to keep the warranty valid are clearly stated. Initial preparation shall be the responsibility of the HVAC and electrical trade representative as per contract bid document. 5.12 Training of Owner's Personnel The owner's maintenance personnel shall be given comprehensive training in the understanding of the systems and the operation and maintenance of each major piece of equipment. The CxP, in cooperation with the contractor, schedules the training, which shall start with classroom sessions followed by hands on training on each piece of equipment. Hands on training shall include start- up, operation in all modes possible, shut-down and any emergency procedures. The contractor or his representative, shall conduct and video tape all sessions and shall add to each session any special information relating to the details of installation of the equipment as it might impact the operation and maintenance. 5.12.1 Overall Plan After reviewing the specifications, and after interviewing facility staff, if necessary, the owner and CxP fill out a table listing all the equipment for which training or orientation will be provided listing, among other things, the type and number of trainees, rigor of training desired by the owner, the primary responsible subcontractor, the trainer's company and columns for tracking training agendas. The commissioning authority provides this form to the contractor for reference. The contractor will prepare a training agenda describing the subjects covered, duration of each subject and the methods that will be used in the training, along with the name and qualifications of the trainer(s)for submission to the owner and CxP. The owner and CxP review the agenda; make comments; approve the training subject to the comments; and submit back to the contractor. The contractor provides the approved agenda to the trainer to use during the training. The trainer provides a copy of the agenda to each trainee. 5.13 Warranty Period During the warranty period, seasonal testing and other deferred testing required is completed according to the specifications. The CxP coordinates this activity. Tests are executed, and deficiencies corrected by the appropriate subs, witnessed by facilities staff and the CxP. Any final adjustments to the O&M manuals and record drawings due to the testing are made. In addition, the CxP will return to the project approximately 10 months into the 12-month warranty period. During this visit(s)the CxP will review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal commissioning. The CxP will also interview facility staff and identify problems or concerns they have operating the building as originally intended. 16 The CxP will make suggestions for improvements and for recording these changes in the O&M manuals. The CxP will identify areas that may come under warranty or under the original construction contract. The CxP will also assist facility staff in developing reports and documents and requests for services to remedy outstanding problems. 5.14 Final Commissioning Report A final summary report by the CxP will be provided to the PM. The report shall include an executive summary, list of participants and roles, brief building description, overview of commissioning and testing scope and a general description of testing and verification methods. For each piece of commissioned equipment, the report should contain the disposition of the commissioning authority regarding the adequacy of the equipment, documentation and training meeting the contract documents. All outstanding non-compliance items shall be specifically listed. Each non-compliance issue shall be referenced to the specific functional test, inspection, trend log, etc. where the deficiency is documented. The functional performance and efficiency section for each piece of equipment shall include a brief description of the verification method used (manual testing, BAS trend logs, data loggers, etc.) and include observations and conclusions from the testing. The final commissioning report shall be submitted. The report shall contain as a minimum the following information: • Cover sheet with following information: • Date • Project and address • Architect • Engineer • General contractor • SCA (name, address, e-mail, fax & phone number) • Final updated commissioning plan • Name, address, phone, fax, e-mail for commissioning team members • Completed copies of all commissioning forms • Copies of Cx related RFI's, meeting minutes, contractor certification, reports, and code authority inspections. • Copies of inspection and construction observation reports • Copy of equipment and system certification forms with listing of equipment and systems commissioned. • Copies of completed component test forms 17 5.15 Schedule The initial commissioning schedule is summarized in the table below. Initial Commissioning Schedule Summary Task/Activity Estimated Start Estimated End Date Date Initial scoping meeting and final plan Submittals obtained and reviewed Begin construction site visits/inspections Pre-functional forms developed and distributed Start-up and initial checkout plans Start-up and initial checkout executed TAB reports obtained and reviewed Functional performance tests O&M documentation review and verification Final commissioning forms executed Training and training verification Final commissioning report 18 SLC International Airport Remediation 3000 Curtis King Blvd. Ft. Pierce, FL. 34946 Commissioning of Mechanical Systems Appendix A Pre-Commissioning Check Lists / SLC Airport Remediation OCI ENGINEERING #20061 L000or DOAS 1 Pre-Commissioning Check List Tag Model# DOAS-1 R N A-0 1 1 -C-0-2-D J A J A-0 0 0 0 0 MFGR Serial# AAON 201909-BNCZ16133 Documentation Checked By(Initial) OCI Contractor a• Cut sheets, approved shop drawings TS b• Performance data TS c• O&M manuals TS d• Installation and startup manual and plan TS e. IStartup report TS Installation a• Vibration isolation devices installed and released TS b. Inspection and access doors are operable and sealed TS c• Casing undamaged TS d. Insulation undamaged TS e• lCondensate drainage is unobstructed TS f. Fan adjusted and clear of any obstructions NA 9. Any damage to coil fins has been repaired NA h. Manufacturer's required maintenance clearance provided TS I• Labels installed TS j. Instrumentation installed TS k• Concrete housekeeping pad(s)in place as required NA I. All mounting brackets properly installed TS M. Clean up completed TS / SLC Airport Remediation OCI ENGINEERING #20061 Duct Mounted Electric Heater(AAON) Pre-Commissioning Check List No Duct Heater Tag Model# EDH-1 MFGR Serial# Documentation Checked By(Initial) OCI Contractor a• Cut sheets,approved shop drawings b. Performance data G. O&M manuals d. Installation and startup manual and plan e• Startup report Installation a• Supports installed per specifications b. Access doors are operable and sealed C. Casing undamaged d. Verify correct direction installation e. Associated equip. f• Elements are adjusted and clear of any obstructions g. Any damage to elements has been repaired h• Manufacturer's required maintenance clearance provided i. Labels installed j• Instrumentation installed k• All mounting brackets and sleeves are properly installed l• Clean up completed Electrical a• Power available to unit disconnect b. Power available to unit control panel C. Control system interlocks functional d. Verify that power disconnect is located within sight of the unit e. Unit KW / Number of stages f• Power available to electric heating coil g• Input voltage V. / Ph. Controls a• Iverify proper location and installation b• JAII sensors calibrated Notes: Z­ ) SLC Airport Remediation OCI ENGINEERING #ZOOGZ LOOOOOr Ductwork Installation Pre-Commissioning Check List Tag: Documentation Checked By(Initial) OCI Contractor a. Ductwork leak test complete(report attached) TS b• As-built shop drawings submitted TS Installation a• Ductwork complete TS b. Turning vanes installed TS c• Fire dampers, smoke dampers, and access doors installed (as required) TS d. Duct sealant installed as specified TS e• IDuctwork insulated as required TS f. Duct liner properly installed (If applicable) NA g. Verify open/closed status of dampers, linkage connected TS h. Verify smoke dampers operation NA i• Flexible connectors installed as specified TS 1• ISeismic bracing installed as required NA Notes: / SLC Airport Remediation OCI ENGINEERING #20061 LOOOOF Automatic Controls Pre-Commissioning Check List Tag Siemens Documentation Checked By(Initial) OCI Contractor a. Approved controls submittal with complete sequences of operation for each piece of equipment and single line diagrams of all control strategies,parameters,and settings b. Full descriptive points list c. Installation manual provided d. I Start-up sheets for each piece of equipment provided e. As-built shop drawings, manufacturer's cut-sheets,and calibration report submitted f. JO&M manuals submitted Installation a. Layout and location of control panels matches drawings b. Equipment/panel labels affixed c. Wiring labeled inside panels(to controlled components) d. Control wiring and tubing labeled at all terminations, splices,and junctions e. IShielded wiring used on electronic sensors f. Battery back up in place and operable 9. lGraphic interfaces installed and mapped to control points Controls installed,fully functional,tested,and calibrated for all equipment listed: a. Dedicated OA Unit b. Exhaust Fans C. Air flow monitoring stations d. Temperature sensors e. I Damper actuators f. BAS control modules 9• h. j• k. Notes: St. Lucie International Airport St. Lucie, Florida Commissioning of Mechanical Systems Appendix B #20061 Functional Performance Test j ST. Lucie international Airport OCI ENGINEERING $k20061 LOOOO"F FUNCTIONAL TEST DX Air Handling Unit DOAS-1 1. Participants Sean Willis Art Munns David Dickson Party filling out form and witnessing testing. Sean Willis Date of test. 6/8/2020 2. Prerequisite Checklist The following have been started up and startup reports and pre-functional checklists submitted and approved ready for functional testing: 0 AHU unit 0 All control system functions for this and all interlocking systems are programmed and operable per contract documents. 0 David Dickson 6/8/2020 Controls Contactor Signature or Verbal Date 0 Test and balance (TAB) completed and approved for the airflow system. ❑ These functional test procedures reviewed and approved by installing contractor. ❑ Review the FMCS software control program(s)for this equipment. Parameters, set points and logic sequences appear to follow the specified written sequences. Parameter Owner Specified or Final Reasonable Value Value Supply Air set point 70°F 74°F OA flow set point(CFM) 1400 1400 Supply fan static pressure set point 0.50 n/a Building static pressure set point N/A n/a Occupied cooling set point °F 74°F Occupied heating set point °F 74°F Occupied dehum set point average (SPACE) 50% R.H. 55% R.H. / ST. Lucie international Airport OCI ENGINEERING #20061 DOAS-1/CU-1 Location Initial Instrument Final Required Pass Sensor& Location OK FMCS Measured FMCS OffsetYIN Value Value Value OA temp Y 83.6°F 85°F 83.6°F Y Precooling temp n/a °F °F °F n/a Cooling Coil temp Y 64.6°F 63°F 64.6°F Y Reheat temp Y 74°F 74°F 74°F Y OA CFM Y 1332 1332 Y Supply fan discharge temp I Y 74°F 74°F 74°F Y Device Calibration Checks The actuators or devices listed below checked for calibration. Device or Actuator& Location FMCS Reading Site Observation as Log # YIN OA damper position 1. Closed Y 2. Full open Y Supply fan 1. On Y 2. Off Y DX PreCooling 1. On Y 2. Off Y DX ReHeat 1. On Y 2. Off Y Condenser Unit CU-1 (AHU-1) 1. On Y 2. Off Y Trending Points Verification Point Name Notes as Log # YIN OA Temp Y Precooling Temp n/a Cooling Coil temp Y Reheat temp Y OA CFM Y Suppl air temp. Y Unit Status Y OA damper position n/a Test DOAS-1/CU-1 Test Procedure Expected Response as Log # YIN 1 Unoccupied Off Mode: Put unit schedule in unoccupied mode. Supply fan OFF Y Observe the unit in OFF condition. OA damper CLOSED Y DX Heat- OFF Y Compressors - OFF Y / ST. Lucie international Airport OCI ENGINEERING #20061 1 Test D0AS-1/CU-1 Test Procedure Expected Response as Log # 2 Occupied Cooling Start/Ventilation: Place the unit in the occupied mode through the DDC system. Supply fan ON OA damper modulate OPEN to maintain minimum air flow set point of 1400 CFM Verify set point was determined and OA flow station calibrated by T&B contractor Condensing units stage ON and stage UP to maintain set point DX heat shall stage to maintain 63.3°F supply air temp. (M3.2) (74°F ACTUAL) 3 Discharge Air Temperature Control: override the supply air temperature set point Compressors shall stage ON to maintain 5°F UP active discharge air temp set point override the supply air temperature set point Compressors shall stage OFF to maintain YF DOWN active discharge air temp set point 4 Economizer Mode (If applicable) override the OUTSIDE air temperature set Compressors shall stage OFF and fan shall point 50°F continue to run to maintain set point Reset override(s) 5 Fan Capacity Control: (If applicable) override Static Pressure Set point(5) inwc UP VFD shall increase and fan shall ramp up to maintain SP set point n/a SP set point we n/a Actual SP we n/a Reset override(s) j ST. Lucie international Airport ENGINEERINGOC� #20061 Test DOAS-1ICU-1 Test Procedure Expected Response YEN Log # 6 Miscellaneous Alarms & Safeties: FIRE ALARM MODE: Fan should shut down, and an alarm shall Fire alarm is hard-wired independent to shut be registered in the BAS down supply fan upon actuation. FAN HIGH STATIC ALARM: override fan Fan should shut down, and an alarm shall speed above 2"we static pressure. be registered in the BAS LOW OA FLOW ALARM: Override OA total flow to 1200 (1100 PER Bob) @30 min An alarm shall be registered in the BAS FAN FAILURE: With breaker to fan shut OFF, initiate AHU to START An alarm shall be registered in the BAS OUTSIDE AIR DAMPER ALARM: Disable outside air damper to the CLOSED position An alarm shall be registered in the BAS when in occupied mode. VFD FAILURE: (If possible) An alarm is registered in the BAS Reset override(s) END OF TEST Notes: DISCONNECT SHOULD HAVE A PERMANENT LABEL. j ST. Lucie international Airport OCI ENGINEERING $$20061 LOOOOF FUNCTIONAL TEST Exhaust Fans 1. Participants Party filling out form and witnessing testing. Sean Willis Date of Test 6/8/2020 2. Prerequisite Checklist The following have been started up and startup reports and prefunctional checklists submitted and approved 0 Exhaust fan El All control system functions for this and all interlocking systems are programmed and operable per contract documents. 6/8/2020 Controls Contractor Signature or Verbal Date El Test and balance (TAB) completed and approved. ❑ All A/E punch list items for this equipment corrected. ❑ Review the FMCS software control program(s)for this equipment. ST. Lucie international Airport #20061 FUNCTIONAL TEST EXHAUST FAN EF-1 1. Functional Testing Record Test Test Procedure Expected Response YEN Log # 1 Observe the unit in OFF condition. Backdraft damper closed. (if applicable) Disconnect functions properly.(if Fan is off and stopped completely Y 2 Observe the unit in ON condition. Fan rotation correct. Y No excessive noise or vibration. Y Backdraft damper open.(if applicable) 3 Describe fan controls and interlocks: ON/OFF Control - Test all specified interlocks by starting and Fan starts and stops under control from stopping lead equipment and verifying fan specified controller start/stop Interlock AHU-NA(FANS ARE TIED TO SCHEDULE Miscellaneous Alarms & Safeties: In occupied mode fail EF-1 An alarm shall be registered in the BAS Reset sequence END OF TEST Notes: ST. Lucie international Airport #20061 FUNCTIONAL TEST EXHAUST FAN EF-2 1. Functional Testing Record Test Test Procedure Expected Response YEN Log # 1 Observe the unit in OFF condition. Backdraft damper closed. (if applicable) Disconnect functions properly.(if Fan is off and stopped completely Y 2 Observe the unit in ON condition. Fan rotation correct. Y No excessive noise or vibration. Y Backdraft damper open.(if applicable) 3 Describe fan controls and interlocks: ON/OFF Control - Test all specified interlocks by starting and Fan starts and stops under control from stopping lead equipment and verifying fan specified controller start/stop Interlock AHU-NA(FANS ARE TIED TO SCHEDULE Miscellaneous Alarms & Safeties: In occupied mode fail EF-2 An alarm shall be registered in the BAS Reset sequence END OF TEST Notes: ST. Lucie international Airport #20061 FUNCTIONAL TEST EXHAUST FAN EF-3 1. Functional Testing Record Test Test Procedure Expected Response YEN Log # 1 Observe the unit in OFF condition. Backdraft damper closed. (if applicable) Disconnect functions properly.(if Fan is off and stopped completely Y 2 Observe the unit in ON condition. Fan rotation correct. Y No excessive noise or vibration. Y Backdraft damper open.(if applicable) 3 Describe fan controls and interlocks: ON/OFF Control - Test all specified interlocks by starting and Fan starts and stops under control from stopping lead equipment and verifying fan specified controller start/stop Interlock AHU-NA(FANS ARE TIED TO SCHEDULE Miscellaneous Alarms & Safeties: In occupied mode fail EF-3 An alarm shall be registered in the BAS Reset sequence END OF TEST Notes: ST. Lucie international Airport OCI ENGINEERING #20061 LO***v Zone Sensor Calibration Verification Room Instrument Measured Value Wall Sensor Value LOBBY 73.71'52RH 72.81'55RH PASSENGER WAITING ROOM 74F 54RH 72.1F 53RH RECEPTION AREA 72.51'59RH 71.71'57RH Notes: / ..� ST. Lucie international Airport OCI ENGINEERING #20061 LOO**'F MAU-1 System Overview PF St Lucie Air Port MAU1 �- AAflN BACNET CDM MUNICATED VALUES AIRPORT '® '® SA TEMP 74.10 OA TEMP 87.90 COILTEMP 45.80 CA 1h9 TEMP 77.10 TO RESET ALARMS COMMAND ALARM RESET ON AHWE CA DP TEMP 7240 0OPER.THE ALARM RESET POINT WILL QUICKLY TURN ON AND THEN OFF AGAIN. OA HUMID 60.10 IF ALARM CCU IPION5 ARE CLEAR ALARMS WILL RESET IF THEY ARE NOT THE SUCPRESS 152.0 a ALARM WILL COME BACK IN S MINUTES. HEAP PRESS 355.W COMP TEMP 148.80 OtiV -U. OO Utiti� OA H U SA �G v MAW START STOP • ;� NORMAL �• ON / I ST. Lucie international Airport OCI ENGINEERING #20061 LOO**'F AHU-1 System Overview TOD TRG ULL THU TOD IRL, St Lucie Air Port �ON UN ON AHME o 4 10 SLCIA.DAIE.PPCL.RPT r r r I' ..IRPORT 77,10 DEG F YY f YY sLaMaui T I H fSFlh u .Y , L.gffl ®n 67,22 DEG F r nna 'OA l X$10, SA COOL STAGE 8I r r SUPPLY FAN SIS ON r ON rr• r SLA.EF1 SLA.EF2 SLA.EF3 PA TEMP OA HUMIDITY JI..A h1AU1 S$$ EX FAN SS ER FAN SS EX FAN SS 94.76 DEG F 67.74 PCT Y r r Y ..L• 1_S7A�.STL3[ ON ON ON ♦; • s I Alarm Status �• Y e :Y / ..� ST. Lucie international Airport OCI ENGINEERING #20061 v RTU-1 System Overview RFtIER ROOF TOP PACKAGE UNIT SLCdA.dx1€.PLOT �,IRPORT Outsida Air 7 + SAT �M 00o n B S$NFO Tf]C *SuAppN Return 1 r ON Air - CSLA OMP STS ON1 1 •l Y I i 1 � BArrrFTTRo,u rAT0R 1 1 • PCT RI TM . 11 Murtfdty OFF ' 1: 72,10 [j Graphics•[SLA.RTLI.Oi] T€vrpalatrrte Z-I I ST. Lucie international Airport OCI ENGINEERING #20061 LOO**'F RTU-2 System Overview CARRIER ROOF TOP PACKAGE UNIT iilTrg AIRPORT �. Outside Air L_01 T Supply r Retur I 1 4 Air `v- caraPsis ' ON BACNETTRANSLATGR +rNm1 1 r • `a' 43.63 PC r eAll, H umldkty RH TRG OFF l+ 1 + TeFrwrature Commissioning Log SLC International Airport #20061 No Date Discipline Associated Issue Description Resp Resolution/Follow-up Res Date Status Equipment Discipline 1 6/8/20 Controls BAS No low outside airflow alarm Siemens Alarm added during Cx @1100CFM after 30 6/8/20 CLOSED min, per Bob with SLC. OCI-SW 06-08-20 2 6/8/20 Mech. AAON Unit Disconnect does not have a permanent label Grimes 6/8/20 CU-1 mounting hardware is rusting 3 6/8/20 Mech. CU-1 Grimes 6/8/20 1 Commissioning Log OCI EN�M' SLC International Airport #20061 Condenser unit fan connections are exposed above grilles. St. Lucie County to comment. 4 6/8/20 SLC CU-1 SLC 2 Commissioning Log OCI E�ERlly SLC International Airport #20061 General housekeeping and clean up of construction debris. 5 6/8/20 GC Mech Room GC Ductwork should have a mastic finish 6 6/8/20 Mech. Ductwork Grimes 6/8/20 7, T- 3 j Commissioning Log OCI ENGINEERING SLC International Airport k000lr #20061 Flexible conduit should have straps to ductwork 7 6/8/20 Electrical Conduit 6d 8 4 Date: 06-08-2020 SLC International Airport bldg remediation Time: 09:O0am #20061 Art Munns OCI Engineering 407-808-9782 amunns@ociengineering.com Sean Willis OCI Engineering 407-721-4411 swillis@ociengineering.com Brian Masters Saint Lucie County 407-808-9782 mastersb@stlucieco.org David Dickson Siemens 954-329-6109 Terrell Selph Grimes 777-979-4193 Hugh Grimes Omega T&B 777-216-7632 Luis Vega AAON 1 SALASO' BRIEN 3501 Quadrangle Blvd., Suite 100 Orlando, Florida 32817 expect a difference 407.380.0400 1 www.salasobrien.com April 21, 2020 SHOP DRAWING REVIEW COMMENTS Reference: St. Lucie County Airport Forensic Analysis Salas O'Brien Florida #15072 Subject: Final Test and Balance Report Submittal Reviewed By: Kyle J. Cartier, P.E. Engineer's review is for general conformance with the design concept and contract documents.Markings or comments shall not be construed as relieving the Contractor from compliance with the project plans and specifications, nor departures therefrom. The Contractor remains responsible for details and accuracy, compliance with the Contract Documents and intent,for confirming and correcting all quantities and dimensions,for selecting appropriate fabrication processes,for techniques of assembly,and for performance of work in a safe manner. OVERALL DISPOSITION: Revise and Resubmit 1. Verify the recorded values for AHU-1. The summation of the outside air (1,852 CFM) and return air (4,665 CFM) exceed the supply air from the unit (total of outside and return is 6,517 CFM, recorded supply is 5,341 CFM). The summation of the return air from the AHU- 1 table is 2,808 CFM, which is not consistent with the value recorded in the AHU-1 data sheet (4,665 CFM). 2. It is noted that the final total supply air for RTU-1 is considerably lower than design (73%). 3. There is a difference of 356 CFM between the recorded RTU-2 supply air (1,986 CFM) and return air(1,630 CFM). This implies that the outside air damper on RTU-2 is not completely closed. Ensure the outside air damper on RTU-2 is completely closed and sealed and re- measure to ensure the supply and return airflow values are the essentially the same. 4. It appears exhaust fans EF-1, EF-2 and EF-3 have not been rebalanced to their respective new airflows as required by sheet M1.1, Plan Reference Notes 14, 13 and 15 respectively. Rebalance exhaust fans to values indicated, record and re-submit for review. 5. The Outside Air Unit test data is missing the entering and leaving dry bulb and wet bulb air temperatures across the unit heat pipe coils. Measure and record these values and include in the test report for evaluation. Refer to sheet M4.1, Grade Mounted Package 100% Outside Air Unit Schedule for indicated values across the pre-cooling and reheat coils. 6. Confirm the 52 degree off-coil temperature indicated in the Outside Air Unit report form is the temperature leaving the DX cooling coil prior to entering the heat pipe reheat coil. 7. Measure and record the total unit amp draw and voltage at design conditions. It appears the recorded values for amps and voltage are for the evaporator fan only. Refer to sheet M4.1, Grade Mounted Package 100% Outside Air Unit Schedule for unit design MCA value. Shop Drawing Review Comments Page 2 of 2 8. Rebalance total airflow from the Outside Air Unit to within 10% of the total design (1,540 CFM maximum) as opposed to the 1,852 CFM recorded. END OF DOCUMENT OMEGA AIR SERVICES LLC DBA OMEGA TEST AND BALANCE NNNA CERTIFIED INDEPENDENT TES TAND BALANCE COMPA N Y--- 126 WISTERIA AVENUE, FORT PIERCE, FLORIDA 34982 CELL (772)216-7632 TABB CERTIFICATION NO. BB032001C www.omegaairserviceslic.com omegamaniac532002@yahoo.com TESTING, ADJUSTING, AND BALANCING REPORT ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS FORT PIERCE, FLORIDA MECHANICAL ENGINEER: SIMS WILKERSON CARTIER ENGINEERING INC. 12124 HIGH TECH AVENUE, SUITE 200 ORLANDO, FL 32817 MECHANICAL CONTRACTOR: GRIMES HEATING & AIR CONDITIONING 3054 NORTH US HWY. ONE FORT PIERCE, FLORIDA 34946 4-9-20 --ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES— HUGH GRIMES TABB TECHNICIAN B610"12610T SEPTEMBER 30,�1 TESTING,ADJUSTING AND BALANCING BUREAU HVAC EXPERTISE "THE PROFESSIONAL'S CHOICE"' OMEGA AIR SERVICES LLC DBA OMEGA TEST AND BALANCE NNNA CERTIFIED INDEPENDENT TES TAND BALANCE COMPA N Y--- 126 WISTERIA AVENUE, FORT PIERCE, FLORIDA 34982 CELL (772)216-7632 TABB CERTIFICATION NO. BB032001C/BB032002S/BB1032610T www.omegaairserviceslic.com omegamaniac532002@vahoo.com ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL TEST AND BALANCE INSTRUMENTS SHORTRIDGE SERIES 8400 FLOWHOOD W/ADM860 AIR DATA MULTIMETER RANGE: 0 TO 61 IN H.G ACCURACY: 0.05% FS CALIBRATION DATE: SEPTEMBER 8, 2019 CHECK-IT DIGITAL PSYCHROMETER—MODEL #622 RANGE: 350 TO 2050 F, 5% TO 100% RH ACCURACY: ±20 ±1 DIGIT t30/o CALIBRATION DATE: AUGUST 8, 2018 SHORTRIDGE ADT446 TEMPROBE RANGE: -200 TO 1800 F ACCURACY: t 0.50 FROM 320 TO 1580 F CALIBRATION DATE: AUGUST 8, 2018 FLUKE 322 CLAMP METER HUGH A. GRIMES, CERTIFIED T.A.B.B. CONTRACTOR/SUPERVISOR/TECHNICIAN --ALL WORK PERFORMED IN ACCORDANCE WITH TABS STANDARDSAND PROCEDURES— AM g rr HUGH GRIMES TABB TECHNICIAN B61032610T SEPTEMBER 30.2020 A 1. �W#kl -_ TESTING,ADJUSTING AND BALANCING BUREAU HVAC EXPERT[Sf 'THE PROFESSIONALS CHOICE""` _.-\ CartYFv" L^ 4ry HUGH GRIMES TABB TECHNICIAN B107 610T S PT M6 R 30,2021 ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL AIR HANDLING UNIT UNIT AHU-1 MAKE CARRIER MODEL 40RUAA16 SERIAL 1112UO9486 SHEAVE 7 X 1 BELTS 1/A46 FILTERS 1" MOTOR MAKE IFR GE156 HP I RPM 3.711750 VIPHIHZ 208-23013160 FLAISF 10.611.15 SHEAVE 3 3/4 X 1 CL 17 HEAT 2.76 KW ELECTRIC EVAPORATOR DESIGN I ACTUAL SA CFM 575015341 OA CFM 140011852** RA CFM 5225I4665 EXT. SP NA 1.84 DISC. SP NA 1.67 SUCT. SP NA 1-.17 OAT DB/WB NA 88.1/80.1 RAT DB/WB NA 72.3/61.8 LAT DB/WB NA 54.1/53.6 FAN RPM NA I NA VOLTS 2081210 AVG. AMPS 10.618.6 AVG. COMPRESSOR MAKE MODEL SERIAL VIPHIHZ RLA LO PRESSURE HI PRESSURE REFRIGERANT FANIHPIRPM VIPHIHZ CC HEAT AMPS REMARKS:MTR. PULLEY FULLYCLOSED. ** SEE NOTES ON OUTSIDE AIR UNIT. ALL WORK PERFORMED IN ACCORDANCE WITH TABB STANDARDS AND PROCEDURES 1 vrea cCa�6 "cS� m HUGH GRIMES TABB TECHNICIAN BB10"22670T SEPTEMBER 30 2021. ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS AIR OUTLETS AHU-1 SUPPLY ADDRESS OUTLET TYPE DESIGN PRE. FINAL NUMBER CFM CFM CFM 101 1 SW 900 822 861 106 2 SW 900 702 737 121 3 SW 900 808 827 117 4 SW 900 803 878 NA 5 CD 100 82 96 111 6 CD 150 130 139 110 7 CD 100 72 90 106 8 CD 150 66 113 103 9 CD 125 100 112 107 10 CD 175 143 147 107 11 CD 175 146 159 108 12 CD 175 140 160 112 13 CD 75 54 77 115 14 CD 175 144 151 116 15 CD 275 218 301 116 16 CD 275 232 292 109 17 CD 75 78 81 102 18 CD 125 123 131 5750 4863 5352 REMARKS: NOTE REVISED FUTURE OUTSIDE AIR SETPOINTS COULD EFFECT THE FINAL NUMBERS ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDSAND PROCEDURES 1 vrea cCa�6 "cS� m HUGH GRIMES TABB TECHNICIAN BB10"22670T SEPTEMBER 30 2021. ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS AIR OUTLETS AHU-1 RETURN ADDRESS OUTLET TYPE DESIGN PRE. FINAL NUMBER CFM CFM CFM 116 1 RG -600 -549 357 116 2 RG -600 -536 348 115 3 RG -175 -155 99 108 4 RG -175 -159 104 107 5 RG -350 -313 203 101 6 RG -750 -659 428 101 7 RG -750 -655 425 101 8 RG -750 -680 442 104 9 RG -750 -686 445 106 10 RG -325 -273 177 -5225 -4665 2808 REMARKS:NOTE LOWER RETURN VALUES ARE MEASURED WITH OUTSIDE AIR UNIT PRODUCING WHAT IS REPORTED ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES 1 �' .. sn►ar 4m HUGH GRIMES TABB TECHNICIAN BB1032670T SEPTEMBER 30,2021 ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS AIR OUTLETS RTU-1 SUPPLY ADDRESS OUTLET TYPE DESIGN PRE. FINAL NUMBER CFM CFM CFM 117A 1 CD 250 145 187* 117A 2 CD 250 151 190* 117A 3 CD 250 149 169* 117A 4 CD 250 156 189* 117A 5 CD 250 138 182* 117A 6 CD 250 137 177* 1500 876 1094 REMARKS: ---RTU-1 NOT ACCESSIBLE FOR TESTING. ---EAT @ 74.3 ---LAT @ 57.5 NOTE;EXISTING EQUIPMENT UNIT HAS VARIABLE MOTOR DRIVE Test and Balance has no access to these systems. SEE PRELIMINARY REPORT ALL WORKPERFORMED INACCORDANCE WITH TABB STANDARDSAND PROCEDURES 1 vrea cCa�6 "cS m HUGH GRIMES TABB TECHNICIAN BB10"22670T SEPTEMBER 30 2021. ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS AIR OUTLETS RTU-1 RETURN ADDRESS OUTLET TYPE DESIGN PRE. FINAL NUMBER CFM CFM CFM 117A 1 RG -725 -561 561 117A 2 RG -725 -516 516 -1450 -1077 1077 REMARKS: ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES 1 vrea cCa�6 "cS� m HUGH GRIMES TABB TECHNICIAN BB10"22670T SEPTEMBER"I0;2021. ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS AIR OUTLETS RTU-2 SUPPLY ADDRESS OUTLET TYPE DESIGN PRE. FINAL NUMBER CFM CFM CFM 124 1 CD 175 87 137 124 2 CD 175 70 133 ATOS 3 CD 150 50 97 126 4 CD 175 51 131 124 5 CD 175 66 99 124 6 CD 175 108 139 102 7 CD 175 168 171 102 8 CD 125 78 114 119 9 CD 125 71 109 120 10 CD 125 68 113 123 11 SW 225 239 217 123 12 SW 225 256 216 123 13 SW 225 269 211 126 14 CD 125 38 96 2000 1619 1986 REMARKS: ---RTU-2 NOT ACESSIBLE FOR TESTING. ---EAT @ 73.7 ---LAT @ 55.1 ALL WORK PERFORMED INACCORDANCE WITH TA BB STANDARDS AND PROCEDURES 1 vrea cCa�6 "cS m HUGH GRIMES TABB TECHNICIAN BB10"22670T SEPTEMBER 30 2021. ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS AIR OUTLETS RTU-2 RETURN ADDRESS OUTLET TYPE DESIGN PRE. FINAL NUMBER CFM CFM CFM 124 1 RG -575 -265 561 124 2 RG -575 -208 548 102 3 RG -550 -406 523 -1700 -879 1630 REMARKS: ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES 1 �' .. sn►ar 4m HUGH GRIMES TABB TECHNICIAN BB1032670T SEPTEMBER 30,-,21 ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS AIR OUTLETS EF-1 EXHAUST ADDRESS OUTLET TYPE DESIGN PRE. FINAL NUMBER CFM CFM CFM 10S 1 EG -200 -137 137 103 2 EG -7S -61 61 -27S -198 198 REMARKS: ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES 1 �' .. sn►ar 4m HUGH GRIMES TABB TECHNICIAN BB1032670T SEPTEMBER 30,-,21 ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS AIR OUTLETS EF-2 EXHAUST ADDRESS OUTLET TYPE DESIGN PRE. FINAL NUMBER CFM CFM CFM 102 1 EG -75 -74 74 NA 2 EG -100 -113 113 NA 3 EG -100 -67 67 -275 -254 254 REMARKS: ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES 1 vrea cCa�6 "cS� m HUGH GRIMES TABB TECHNICIAN BB10"22670T SEPTEMBER 30 2021. ST. LUCIE COUNTY INTERNATIONAL AIRPORT TERMINAL PRELIMINARY READINGS AIR OUTLETS EF-3 EXHAUST ADDRESS OUTLET TYPE DESIGN PRE. FINAL NUMBER CFM CFM CFM 118 1 EG -75 * 41 119 2 EG -100 -75 70 120 3 EG -125 -130 123 119 4 EG -100 -144 131 120 5 EG -125 -89 80 -525 -438 445 REMARKS: ---*NO ACCESS ALL WORK PERFORMED INACCORDANCE WITH TABB STANDARDS AND PROCEDURES L^ 4ry HUGH GRIMES TABB TECHNICIAN B10t 610T C PT M6 R 30,2021 OUTSIDE AIR UNIT REMARKS: ST.LUCIE AIRPORT UNIT O\A MAKE AAON MODEL RNA 011 SERIAL 201909 SHEAVE DD BELTS DD FILTERS NA MOTOR MAKE I FR NA HPIRPM 1\NA VIPHIHZ 230\3\60 FLAISF 4.2 SHEAVE DD CL DD HEAT NA EVAPORATOR DESIGN I ACTUAL DESIGN ACTUAL DESIGN ACTUAL SA CFM 1400I1852 OA CFM 1400I1852 RA CFM INA I I EXT. SP INA I I DISC. SP INA I I SUCT. SP INA I I OAT DB/WB 95\85I84.6\77.8 I I EAT DB/WB 95\85I84.6\77.8 I I LAT DB/WB 52.3I 52.2/52@COIL* I I FAN RPM NAINA NAINA NAINA VOLTS 2301210 AVG. I I AMPS NA 12.1 AVG. I I COMPRESSOR 1 1 1 MAKE MODEL PLEASE NOTE WE DO NOT SERIAL TEST THE REFRIGERANT VIPHIHZ SIDE RLA LO PRESSURE HI PRESSURE REFRIGERANT FANIHPIRPM VIPHIHZ CC HEAT AMPS NOTE:LAT @a D15CGARGE=68 160.1 DURING TESTING 5ETPOINT5 BY OTHERS Unit alarm/shut down if drive setting below 35 Hertz Building pressure f,019 ALL WORKPERFORMED INACCORDANCE WITH TABB 5TANDARD5AND PROCEDURES