HomeMy WebLinkAboutWS-LOT-51 ENERGY CALC-4Project Name:
Owner:
Builder Name:
Permit Office:
Jurisdiction:
ST. LUCIE COUNTY
K. HOVNANIANWATERSTONE LOT-51
Street:
City, State, Zip:FT. PIERCE , FL , 34951
ARMINA PL. LOT-51, BLOCK-3
Permit Number:
Design Location:FL, Fort Pierce CHECKAIR BARRIER CRITERIA
A continuous air barrier shall be installed in the building envelope.
The exterior thermal envelope contains a continuous air barrier.
Breaks or joints in the air barrier shall be sealed.
The air barrier in any dropped ceiling/soffit shall be aligned with
the insulation and any gaps in the air barrier shall be sealed.
Access openings, drop down stairs or knee wall doors to
unconditioned attic spaces shall be sealed.
The junction of the foundation and sill plate shall be sealed.
The junction of the top plate and the top of exterior walls shall be
sealed.
Knee walls shall be sealed.
The space between window/door jambs and framing, and
skylights and framing shall be sealed.
Rim joists shall include the air barrier.
The air barrier shall be installed at any exposed edge of
insulation.
Exposed earth in unvented crawl spaces shall be covered with
a Class I vapor retarder with overlapping joints taped.
Duct shafts, utility penetrations, and flue shafts opening to
exterior or unconditioned space shall be sealed.
Narrow cavities
Shafts, penetrations
Crawl space walls
Floors
(including
above-garage
and cantilevered
floors)
Rim joists
Windows, skylights
Walls
Ceiling/attic
General
COMPONENT
Garage separation
Recessed lighting
Plumbing and wiring
S h o w e r / t u b
HVAC register boots HVAC register boots that penetrate building thermal envelope shall
be sealed to the sub-floor or drywall.
The air barrier shall be installed behind electrical or communication
boxes or air-sealed boxes shall be installed.
The air barrier installed at exterior walls adjacent to showers and
tubs shall separate them from the showers and tubs.
Batt insulation shall be cut neatly to fit around wiring
and plumbing in exterior walls, or insulation that on
installation readily conforms to available space shall
extend behind piping and wiring.
Recessed light fixtures installed in the building thermal envelope
shall be sealed to the drywall.
Air sealing shall be provided between the garage and conditioned spaces.
When required to be sealed, concealed fire sprinklers shall only be
sealed in a manner that is recommended by the manufacturer.
Caulking or other adhesive sealants shall not be used to fill voids
between fire sprinkler cover plates and walls or ceilings.
C o n c e a l e d
Electrical/phone box on
exterior walls
Batts in narrow cavities shall be cut to fit, or narrow
cavities shall be filled by insulation that on
installation readily conforms to the available cavity
spaces.
TABLE 402.4.1.1
AIR BARRIER AND INSULATION INSPECTION COMPONENT CRITERIA
INSULATION INSTALLATION CRITERIA
EnergyGauge® USA 6.0.02 (Rev. 1) - FlaRes2017 FBC 6th Edition (2017) Compliant Software8/7/2020 2:32 PM Page 1 of 1
Air-permeable insulation shall
not be used as a sealing material.
The insulation in any dropped ceiling/soffit
shall be aligned with the air barrier.
Cavities within corners and headers of frame walls
shall be insulated by completely filling the cavity
with a material having a thermal resistance of R-3
per inch minimum.
Exterior thermal envelope insulation for framed
walls shall be installed in substantial contact and
continuous alignment with the air barrier.
Rim joists shall be insulated.
Floor framing cavity insulation shall be installed to
maintain permanent contact with the underside of
subfloor decking, or floor framing cavity insulation
shall be permitted to be in contact with the top side
of sheathing, or continuous insulation installed on
the underside of floor framing and extends from the
bottom to the top of all perimeter floor framing
members.
and doors
on exterior wall
requirements
Recessed light fixtures installed in the building
thermal envelope shall be air tight and IC rated.
sprinklers
Where provided instead of floor insulation, insulation
shall be permanently attached to the crawlspace
Exterior walls adjacent to showers and tubs shall
be insulated.
2017 - AIR BARRIER AND INSULATION INSPECTION COMPONENT CRITERIA
a. In addition, inspection of log walls shall be in accordance with the provisions of ICC-400.