HomeMy WebLinkAboutLetter; Tankless Water Heater InstallationNovember 6th, 2020
John Jacobs Construction Inc.
4701 Oleander Avenue
Ft. Pierce, FL 34982
Project Location: 356 Midway Rd, Fort Pierce
RE: Tankless Water Heater Installation
Florida Power & Light Company
Dear: John Jacobs
Thank you for contacting FPL about the installation of your Tankless Water Heater at 356 E
Midway Rd, Fort Pierce. Florida Power & Light has no objections to the installations of the 8KW
Rheem. RTex-08 Tankless water heater at the 356 Midway Rd project. The current Transformer is
loaded at 36.89KVA, with the addition of the 8KW water heater the new load at Peak will be
45.78KVA which is under the 50KVA rated TX that is currently feeding the property. In addition,
the current load being used on the building is 16.2 KWD and with the additional load of 8KW it will
bring the total to 24.2KWD with an Amperage of 112.02 that will be on the Conductor which falls
within the rating. Voltage Drop and Flicker calculation is good as well and falls within range. If
additional loading is added to the building there can be instances where the Voltage and Flicker can
fall below the acceptable range and will be the customers responsibility to pay for the upgrades of
the facilities. If you have any additional question, please let rose know.
if you should require additional information, please contact me at 772-337.7058.
sincerely,
osley Gonzalez
Engineering Lead