HomeMy WebLinkAbout19-1008 SLCPW Sitework PermitST. LUCIE I"J �; !E'
September 28, 2020
Arenamax, LLC
3501 Industrial 27th Street
Ft. Pierce, FL 34946
Attention: Mr. Richard Greenfield
Subject: Site Development Permit
Arenamax
Ref: PDS Order 2020-033, MNSP-1202025666
The Construction Plans signed and sealed September 9, 2020, are accepted for
construction of the site improvements as proposed.
Construction of site improvements is conditioned on the following:
1. Prior to commencement of any construction of site improvements or access, the
FOR shall coordinate a pre -construction meeting including the St. Lucie County
Public Works representatives, Robert Krip, 772-519-0440, KripR(-,stlucieco.org
and Nick Linehan, 772-408-7595, LinehanN@stlucieco.org.
2. A set of plans stamped as accepted by the County, together with all other
applicable permits shall be on site at all times during construction.
3. Prior to commencement of work, all other agency permits must be obtained and
followed. The more stringent condition of common or conflicting conditions shall
be met. Discrepancies within the plans shall be appropriately addressed and
does not relieve the contractor of his obligation to construct according to local,
state and federal rules and regulations.
4. Site inspections shall be coordinated as established at the Pre -Construction
meeting. Inspections shall be performed at a minimum for the following stages:
A. Pre -pour for the building slab, confirm site grading protection
B. Pre -sod for SW installation confirmation
C. Final after FOR Certification
5. Any proposed changes to the permitted stamped plans must be approved by
the County prior to initiating any change in construction. This includes material
changes such as pavement type, type of drainage pipe, etc.
6. Any structure shown or not shown on the plans (such as walls, gates, signs,
columns, etc.) requiring a building permit, such permit shall be obtained prior to
initiating construction on such structures. This permit does not authorize the
construction of above ground structures.
Board of County
Commissioners
Cathy Townsend
DISTRICT 5
Chair
Chris Dzadovsky
DISTRICT I
Vice -Chair
Sean Mitchell
DISTRICT 2
Linda Bartz
DISTRICT 3
Frannie Hutchinson
DISTRICT 4
Administration
Howard Tipton
COUNTY
ADMINISTRATOR
Dan McIntyre
COUNTY ATTORNEY
PUBLIC WORKS DEPARTMENT
y hgysd@stlucieco.org
1 2300 Virginia Avenue I Fort Pierce, FL 34982 (772) 462 - 1491im
" (772) 462 - 1428 0 (772) 462 - 1707 Qwww.stlucieco.gov
Mr. Richard Greenfield
Arenamax, LLC
September 28, 2020
Pg 2of2
7. The permittee is responsible for administering the construction contract in accordance with this
permit. If the permittee fails to comply with any part of this permit or any other permit issued for
this project by any regulatory authority, the County may at its sole discretion, cause to cease
construction activities on the site until said permit condition is complied with. A Cease and Desist
Order will be issued by the County Administrator or his designee, and served in an appropriate
manner to the permittee or the permittee's agent. Under no circumstances shall work proceed
when a Cease and Desist Order has been issued until said Order has been withdrawn in writing
by the County. If a Cease and Desist Order is issued, the County, at its sole discretion, may take
other action against the permittee and the permittee's agent(s) for the project.
8. Activities approved by this permit shall be conducted in a manner which does not cause pollution
or allow pollution to exit the site. The permittee is solely responsible for preventing pollution
caused by dewatering water and/or stormwater runoff from the construction site or work area. In
addition to taking its own actions and remedies against the permittee for a permit violation, the
County may report each violation to the South Florida Water Management District, Florida
Department of Environmental Protection, Water Control District (or other Florida Statute Chapter
298 Drainage District, as appropriate), County Code Enforcement, and other pertinent regulatory
or enforcement agencies. No construction work shall begin until the pollution control and
treatment system have been constructed in accordance with approved permits and plans.
9. A copy of the Stormwater Pollution Prevention Plan (SWPPP) must be available on site during
construction. Any necessary change to the SWPPP shall be agreed upon with the County prior to
implementing such change.
10. An `Illicit Discharge Sign' shall be obtained, installed and remain posted continuously during
construction activities. The sign may be obtained from the County Public Works Department at the
pre -construction meeting or by separate arrangement's.
11. An As -Built survey is required along the EOR's certification upon request for a final inspection of
the site and access improvements. A published benchmark utilized for site elevations shall be
referenced for use by other parties, including but not limited to the County.
This permit shall expire as conditioned by the Development Order. Please do not hesitate to contact me
at (772) 462-1491 if you have any questions.
Sincerely,
David Hays, P , CFM
Sr. Project Engineer
cc: Patrick Dayan, PE
Bethany Grubbs
Robert Krip
Lindsay Lankford