HomeMy WebLinkAboutLetter; FPL ProcessingFPL
Company
MKS Construction
461 Sw Lairo Ave
Port St Lucie, FL 34953
R& 7466 LeQen s Dr
Dear Leah:
Florida Power & Light
1050 Se Brandon Circle
Port St. Lucie, FL 34952
FDEC 16 2020
ST. Lucie County, Permitting
Thank you for contacting FPL early in your planning
process. This will help you to achieve your desired
schedule for your project. At the present time FPL has
sufficient capacity to provide electric service to your
property.
Please fill out the Notification of New Construction form
enclosed with this letter. This information is critical for us
to be able to initiate the design process of your project & will
help us to provide you with the best service in accordance
with applicable rates, rules and regulations. Once we have
received the new construction form, you will be contacted to
schedule a pre -design meeting..
We will also need from you:
1. Site plan
2. Utility plans, showing the water, sewer, drainage,
paving & landscape plans.
3. Electrical plans, showing electrical riser diagram and
panel schedules.
4. Time frame of when permanent electric power is
needed.
5. If a transformer is required, then a design wol lid be
required
If the customer chooses to go underground and the service
requires an underground transformer then a design job will
be created. After FPL has designed an electrical layout for
your project and before the job can be scheduled for
construction, FPL will need:
1. A recorded 10-foot-wide easement for FPL's
underground cable route and padmount transformer
location. We will send you FPUs easement form and
easement instruction letter.
2. A signed Underground Facilities Installation
Agreement form. We will send you this.
3. There is a choice for residential to have someone
install FPUs conduit to FPUs specifications and
required minimum depth. We will send you a Conduit
Installation Spec sheet.
4. Payment for any FPL construction charges that may
apply for this project. We will send you an invoice for
this if required.
Finally, the design time -frame for FPL can take anywhere
from three to five months after all required information is
received from you and any necessary additional information
is received in a timely manner. The scheduling and
construction time -frame will be based on the scope of the
design.
You may also visit www.fpl.com/partner/builders for more
information. Please contact me if you have any questions
about your project and I look forward to developing a good
working relationship with you.
Sincerely,
Melanie Wildrick
Service Planner
Treasure Coast Distribution
772-337-7024
an FPL Group Company