Loading...
HomeMy WebLinkAboutNettles Pile log-Signed 587 W. Eau Gallie Blvd. Suite 201 Melbourne FL 32935 ph. 321-600-0672 email: mike@mkstructural.com March 10, 2020 RE: Pile Inspection and Log for: 163 Nettles Blvd., Jensen Beach Install date: March 3, 2020 For your information, during the pile installation at the above referenced property, each pile was documented for proper type and size of steel placement, correct grout mix, the number of strokes indicating volume and any abnormalities that may have occurred during installation. Each pile was checked by “counting the strokes method” as documented in several literature including “Inspector Guide to the Auger Cast-in-Place Piles” published by the Auger Cast-In- Place Pile Committee of the” The Deep Pile Institute”. The approved drawings specified a 14” diameter auger cast pile drilled 30’. Piles 1, 2 and 6 were installed with steel cages consistent with the approved plans. The remaining piles were reinforced with a single #7 bar. The concrete pump used, a Transcrete BV75 was calibrated on site and determined to produce 0.7 cuft / stroke. A digital stroke counter was provided on the pump. The drilling equipment was fitted with gauges that were used to monitor the grouting pressure at the tip of the auger. These were monitored to insure a positive head was maintained throughout the grouting of each pile. Attached is a detailed record of the pile volumes pumped into each pile. The lowest yield for any pile was 140% which is consistent with the recommendations and meets the job requirements as set forth in the structural drawings. Based on this information, it is my professional opinion, the piles constructed for the referenced project were installed in accordance with industry standards and as specified according to the construction drawings to the best of my knowledge. The pile documentation and location plan are attached. Please feel free to contact me if you have any questions. Thank you, Michael A. Kalajian Michael A. Kalajian, P.E. PE. No. 60133 mike@mkstructural.com P1 P9 P8 P7 P6 P5 P4 P3 P2 P13 14 P12 P11 P10 14” diameter piles installed 30’ from grade. Theoretical Volume: 32.1 Cuft Theoretical strokes (.7 cu ft/stroke) 46 Pile Strokes grout factor 1 54 1.17 2 56 1.23 3 58 1.26 4 57 1.24 5 62 1.35 6 58 1.26 7 55 1.2 8 62 1.35 9 56 1.23 10 57 1.24 11 58 1.26 12 64 1.4 13 57 1.24 14 58 1.28 Piles 1, 2 and 6 were installed with steel cages consistent with the approved plans. The remaining piles were reinforced with a single #7 bar.