Loading...
HomeMy WebLinkAbout20-202 Ocean Harbor N - Bldg E - Rep 4 - 03.25.21 DSignedM L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37th Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772) 569-4041 www.mlengineeringinc.com Project No. 20-202 Report No. 4 Project Manager: Building Official: Contractor: File Mr. Gene Ross – Elliott Merrill Community Mgmt. St. Lucie County Bldg. Dept. Mr. Robert Stark – Structure-Con Mr. Khris McConnel – Structure Con Page 1 of 3 THRESHOLD INSPECTION REPORT OCEAN HARBOR NORTH CONDOMINIUMS – BLDG. E CONCRETE REPAIRS 5167 N. HWY. A1A, FT. PIERCE, FL 34949 SLC BUILDING PERMIT NUMBER: 2009-0182 PROJECT NAME: Ocean Harbor N. Condos – Bldg. E Concrete Repairs DATE: March 25, 2021 CLIENT: Elliott Merrill Community Management LOCATION: Ft. Pierce, FL CONTRACTOR: Structure-Con PROJECT MGR: Mr. Khris McConnell INSPECTED BY: Todd Rhoten WEATHER: Sunny WORK INSPECTED: Units 108/208 & 408/508 OBSERVATIONS: Shoring is in place as specified in the permit drawings. Unit 108/208 • (10) Post tension (PT) cables have been locked off at the north elevation. • Loose concrete has been chipped and removed around the cables. • Existing bursting bars at slab edge are corroded and require replacing. • Longitudinal reinforcing bars have minor corrosion and require power tool cleaning and coating. Unit 408/508 • Lock off plates have been removed from (8) PT cables and have been re-stressed. • Wedge anchors have been placed at the re-stressed cable ends and cables cut flush with slab. • Due to the proximity of the cables, the re-stressing will be done in two phases. The remaining (5) cables will be re-stressed next week. • The secondary concrete pour at the lock off is complete. RECOMMENDATIONS: Unit 108/208 • Replace the bursting bars at the slab edge, dowel and lap with existing. • Provide 45-degree bursting bars laps at the corner. • The first pour shall include column type sections between PT cables for additional support during re-stressing. ______________________________ _________________________________ Michael Lue, P.E. Todd Rhoten M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37th Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772) 569-4041 www.mlengineeringinc.com Project No. 20-202 Report No. 4 Project Manager: Building Official: Contractor: File Mr. Gene Ross – Elliott Merrill Community Mgmt. St. Lucie County Bldg. Dept. Mr. Robert Stark – Structure-Con Mr. Khris McConnel – Structure Con Page 2 of 3 Pic 1 Unit 108/208 (10) PT cables locked off and concrete repair in progress Pic 2 Unit 108/208 PT cable lock off plates Pic 3 Unit 408/508 Secondary pour at re-stressed cables complete (5) Remaining cables to be re-stressed M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37th Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772) 569-4041 www.mlengineeringinc.com Project No. 20-202 Report No. 4 Project Manager: Building Official: Contractor: File Mr. Gene Ross – Elliott Merrill Community Mgmt. St. Lucie County Bldg. Dept. Mr. Robert Stark – Structure-Con Mr. Khris McConnel – Structure Con Page 3 of 3 Pic 4 Unit 408/508 Re-stressed PT cable ends. Pic 5 Unit 408/508 Re-stressed PT cable ends.