HomeMy WebLinkAbout20-202 Ocean Harbor N - Bldg E - Rep 3 - 03.19.21 DSignedM L Engineering Inc.
Consulting Engineers
Threshold Inspector
2030 37th Avenue
Vero Beach, Florida 32960
Phone: (772) 569-1257
Fax: (772) 569-4041
www.mlengineeringinc.com
Project No. 20-202 Report No. 3
Project Manager:
Building Official:
Contractor:
File
Mr. Gene Ross – Elliott Merrill Community Mgmt.
St. Lucie County Bldg. Dept.
Mr. Robert Stark – Structure-Con
Mr. Khris McConnel – Structure Con
Page 1 of 3
THRESHOLD INSPECTION REPORT
OCEAN HARBOR NORTH CONDOMINIUMS – BLDG. E CONCRETE REPAIRS
5167 N. HWY. A1A, FT. PIERCE, FL 34949
SLC BUILDING PERMIT NUMBER: 2009-0182
PROJECT NAME: Ocean Harbor N. Condos – Bldg. E
Concrete Repairs DATE: March 19, 2021
CLIENT: Elliott Merrill Community Management LOCATION: Ft. Pierce, FL
CONTRACTOR: Structure-Con PROJECT MGR: Mr. Khris McConnell
INSPECTED BY: Todd Rhoten WEATHER: Sunny
WORK INSPECTED:
Units 108/208 & 408/508
OBSERVATIONS:
Shoring is in place as specified in the permit drawings.
Unit 108/208
• (10) additional cables at the northwest edge are scheduled to be locked off, as recommended in our previous
report.
• The screen enclosure has been removed from the west facing balcony edge at Unit 108 ceiling.
• Loose concrete was removed from the west edge and cable anchors appear to be in serviceable condition.
Unit 408/508
• (13) post tension cables have been cut and new cables were spliced at the north edge.
• Form boards are in place for first pour, leaving approximately 12” between pour and lock off plates.
• (2) new #4 bursting bars were placed behind PT anchor plates and doweled and lapped with existing.
RECCOMMENDATIONS:
Unit 108/208
• Clean & coat existing anchors and all exposed reinforcing bars along west edge.
Unit 408/508
• Allow proper curing time for the first concrete pour prior to re-tensioning the cables.
______________________________ _________________________________
Michael Lue, P.E. Todd Rhoten
M L Engineering Inc.
Consulting Engineers
Threshold Inspector
2030 37th Avenue
Vero Beach, Florida 32960
Phone: (772) 569-1257
Fax: (772) 569-4041
www.mlengineeringinc.com
Project No. 20-202 Report No. 3
Project Manager:
Building Official:
Contractor:
File
Mr. Gene Ross – Elliott Merrill Community Mgmt.
St. Lucie County Bldg. Dept.
Mr. Robert Stark – Structure-Con
Mr. Khris McConnel – Structure Con
Page 2 of 3
Pic 1
Unit 108/208
Northwest elevation
Pic 2
Unit 108/208
Cables at west elevation
Pic 3
Unit 408/508
Cables spliced & forms in place
M L Engineering Inc.
Consulting Engineers
Threshold Inspector
2030 37th Avenue
Vero Beach, Florida 32960
Phone: (772) 569-1257
Fax: (772) 569-4041
www.mlengineeringinc.com
Project No. 20-202 Report No. 3
Project Manager:
Building Official:
Contractor:
File
Mr. Gene Ross – Elliott Merrill Community Mgmt.
St. Lucie County Bldg. Dept.
Mr. Robert Stark – Structure-Con
Mr. Khris McConnel – Structure Con
Page 3 of 3
Pic 4
Unit 408/508
Cables spliced & forms in place
Pic 5
Unit 408/508
Post tension cable anchor plate and bursting bars