HomeMy WebLinkAboutAvalon - KSM - Soil Report LOT 7 (12.31.19)Headquarters:
11345 U.S. Highway 1
Sebastian, FL. 32958
Orlando:
723 Progress Way
Sanford, FL. 32771
If CA t I ENGINEERING
JLXIJAVL AND TESTING
Mailing:
P.O. Box 78-1377
Sebastian, FL. 32978
Phone: 772-589-0712
C.A. # 5693
KSMengineering.net
December 31, 2019
Matt Basaraba
Ocean Estates Drive [[C
9508 Windy Ridge Rd.
Windermere, FL 34786
Re: Lot 7, Avalon Beach
North Hutchinson Island
Fort Pierce, Florida
KSM Project#: 195257-b
Dear Mr. Basaraba:
As requested, KSM Engineering & Testing has performed a subsurface investigation at the
referenced site. Presentation of the data gathered during the investigation, together with
our geotechnical related opinions, are included in this report.
A. Site Description:
At the time of drilling, the site was fairly flat and cleared.
B. Project Description:
A single-family residence is planned to be constructed on the site. Loads from the
structure will be transferred to the ground by conventional shallow footings. We estimate
the maximum loads will be less than 2,500 pounds per linear foot along the wall
foundation.
Some additional site fill will be required to reach the desired grades.
Proudly Serving Florida since 1990
Headquarters:
11345 U.S. Highway 1
Sebastian, FL. 32958
Orlando:
723 Progress Way
Sanford, FL. 32771
IV CV1k I ENGINEERING
JL%OJLVL AND TESTING
Mailing:
P.O. Box 78-1377
Sebastian, FL. 32978
Phone: 772-589-0712
C.A. # 5693
KSMengineering.net
Lot 7, Avalon Beach -2- December 31, 2019
Fort Pierce, Florida
C. The scope of our study consisted of the following:
1. Performed Standard Penetration Test Borings in the proposed construction area to
estimate the subsoil relative density.
2. Measured the groundwater level at each boring.
3. Evaluated the existing soil conditions with respect to the proposed construction and
provided recommendations for site preparation and foundation design.
4. Prepared this report to document our findings.
D. Site Investigation:
The site investigation program consisted of performing two (2) Standard Penetration Test
borings (SPT), in the proposed construction area. The SPT borings were terminated at
depths of 10 to 14 feet below grade. The locations of the borings are indicated on the
attached boring logs.
The SPT borings were completed in accordance with procedures described in ASTM D-
1586. A standard 1.5 inch ID., 2 inch O.D. split-spoon sampler is driven into the soil by
successive blows of a 140 pound hammer freely falling 30 inches. The number of blows
required to drive the sampler 1 foot, after seating 6 in., is designated the Penetration
Resistance, or "N' value. At regular intervals the sampler is extracted from the ground and
opened to allow visual examination and classification of the retained soil sample. Also, the
groundwater table was allowed to stabilize and the depth of the groundwater elevation
recorded from existing grade.
The records of the soils encountered, the penetration resistances and groundwater level
are shown on the attached logs.
Proudly Serving Florida since 1990
Headquarters:
11345 U.S. Highway 1
Sebastian, FL. 32958
Orlando:
723 Progress Way
Sanford, FL. 32771
IV C4 t I ENGINEERING
A%1JAVA AND TESTING
Mailing:
P.O. Box 78-1377
Sebastian, FL 32978
Phone: 772-589-0712
C.A. # 5693
KSMengineering.net
Lot 7, Avalon Beach -3- December 31, 2019
Fort Pierce, Florida
E. Engineering Evaluation and Conclusions:
Based on the information obtained from this site investigation, we are pleased to offer the
following evaluation:
The boring logs indicate the subsurface soils consist mostly of fine-grained sand and
slightly silty sand. Shell fragments were also found in the borings. "N" values recorded
during the boring operation indicate the soil density is generally medium dense. Please
refer to the soil boring logs for specific information relative to the soil description.
Based on the existing soil conditions, the proposed structure can be supported on a
shallow foundation system provided that the site is properly prepared.
The following sections provide recommendations for the site preparation and foundation
design.
F. Site Preparation:
The proposed building area and areas to be paved, plus a minimum margin of five feet
beyond the proposed construction shall be stripped and grubbed of surface debris,
including vegetation, roots and organic matter. The building area should be graded level
and proofrolled. Any soft yielding areas shall be excavated and replaced with clean
compacted fill. Sufficient passes should be made during compaction operations to
produce a density no less than 95 percent of its modified dry Proctor value (ASTM D 1557)
to a depth of two feet.
After the exposed surface has been proofrolled, the building and pavement areas may be
filled to the desired grades. The fill material shall consist of clean granular sand containing
less than 10% material passing the U.S. Standard No. 200 mesh sieve. Place structural fill
in loose layers of 12 inches in thickness and compact each lift to at least 95 percent of its
modified dry Proctor value. We do not recommend heavy vibratory equipment on this site
due to the proximity to the neighboring structures.
After excavating for the footings, the disturbed footing subgrade should be recompacted to
95 percent (minimum) of its modified dry Proctor value. This can be best achieved by
making several passes with a relatively light-weight walk-behind vibratory sled or roller.
Proudly Serving Florida since 1990
Headquarters:
11345 U.S. Highway 1
Sebastian, FL. 32958
Orlando:
723 Progress Way
Sanford, FL. 32771
IV 0 Ik I ENGINEERING
1%.1J.IVL AND TESTING
Mailing:
P.O. Box 78-1377
Sebastian, FL. 32978
Phone: 772-589-0712
C.A. # 5693
KSMengineering.net
Lot 7, Avalon Beach -4- December 31, 2019
Fort Pierce, Florida
G. Foundation:
Provided that our recommendations for site preparation are followed, the proposed
structure may be supported on conventional concrete, steel reinforced footings designed
for an allowable soil bearing pressure of 2,500 pounds per square foot, or less.
With the foundation properly designed and the site properly prepared, we anticipate total
settlements less than 3/4 of an inch and differential settlement of less than 1/4 of an inch.
The majority of the settlement should occur during construction.
H. Floor Slabs:
A conventional slab-on-grade can be used in the "at grade" portion of the building. We
recommend the disturbed subgrade below the floor slab be re-compacted to 95 percent of
the modified Proctor maximum dry density (ASTM D 1557) prior to placement of the
concrete. An estimated modulus of subgrade reaction of 150 pounds per cubic inch (pci)
can be used for design of the slab-on-grade. We recommend that control joints be
incorporated in the slab at frequent intervals to control shrinkage cracks.
A moisture barrier is recommended beneath the floor slab to prevent moisture migration
from the underlying soil resulting in dampness of the slab.
Proudly Serving Florida since 1990
9
Headquarters:
11345 U.S. Highway 1
Sebastian, FL. 32958
Orlando:
723 Progress Way
Sanford, FL. 32771
T/ 0 Ik I ENGINEERING
11J.IV& AND TESTING
Mailing:
P.O. Box 78-1377
Sebastian, FL. 32978
Phone: 772-589-0712
C.A. # 5693
KSMengineering.net
Lot 7, Avalon Beach -5- December 31, 2019
Fort Pierce, Florida
I. Closure:
This report has been prepared in accordance with generally accepted soil and foundation
engineering practices based on the results of the test borings and the assumed loading
conditions. No warranties, either expressed or implied, are intended or made. This report
does not reflect any variations which may occur between the borings. If variations appear
evident during the course of construction, it would be necessary to re-evaluate the
recommendations of this project.
Environmental conditions, wetland delineation, water quality, and municipal requirements
are not a part of this report.
We are pleased to be of assistance to you on this phase of your project. When we may be
of furtF psN,1tp1. you or should you have any questions, please feel free to contact us.
' : L
J.
JEK/jt
E-mail to: matt@gelcorp.net
Proudly Serving Florida since 1990
GEOTECH BH PLOTS - GINT STD US LAB GDT - 12/31/19 13O6 - \\KSM-SERVER\KSM FILES\19 DOGS BORING NUMBER B-I
PAGE 1 OF 1
KSM Engineering & Testing
K AS714' P.O. Box 78-1377
Sebastian, FL 32978
Tel: (772)-589-0712
Fax: (772)-589-6469
NOTES See Attached Location Plan AFTER DRILLING
LOGGED BY CH/SH/BB CHECKED BY JEK AT END OF DRILLING
Bottom of borehole at 14.0 feet.
A SPT N VALUE A
20 40 60 80 (-)
0-0 MATERIAL DESCRIPTION
PL MC LL
I 0 I
20 40 60 80
El FINES CONTENT (%) 0
20 40 60 80
I
Lu
0
Brown Sand with Traces of Roots
Light Brown Sand with Traces of Shell Fragments
Brown Sand with Traces of Clay
Gray Sand, Slightly Silty
'7 .
17
SS
SS
SS
SS x 3-3-4
(7)
5-6-9
(15)
9-11-13
(24)
12-13-14
(27)
14-15-16
(31)
17-19-20
(39)
21-25-22
(47)
x
x
x
SS
SS
SS
GEOTECH BH PLOTS - GINT STD US LABGOT - 12/31/191306- \\KSM-SERVER\KSM FILES\19 DOCS (KSM-SERVER)\195257-8 GP. BORING NUMBER B-2
PAGE 1 OF 1
KSM Engineering & Testing
KA5714 P.O. Box 78-1377
Sebastian, FL 32978
Tel: (772)-589-0712
Fax: (772)-589-6469
HOLE SIZE inches GROUND ELEVATION
GROUND WATER LEVELS:
AT TIME OF DRILLING 6.25 ft
DATE STARTED 12/30/19 COMPLETED 12/30/19
DRILLING CONTRACTOR
DRILLING METHOD Split Spoon Sample
LOGGED BY CH/SH/BB CHECKED BY JEK AT END OF DRILLING
NOTES See Attached Location Plan AFTER DRILLING
CLIENT Ocean Estates Drive LLC PROJECT NAME Lot 7, Avalon Beach
PROJECT NUMBER 195257-b PROJECT LOCATION N. Hutchinson Island, Fort Pierce, Florida
Bottom of borehole at 10.0 feet.
SS
SS
Gray Sand, Slightly Silty
A SPT N VALUE A
20 40 60 80
PL MC LL
I I I
20 40 60 80
O FINES CONTENT (%) 0
20 40 60 80
WE
>0
0
W
Brown Sand with Traces of Roots
Light Brown Sand with Traces of Shell
Brown Sand with Traces of Clay
X SS
5
10
X SS
X SS
17
C-)
MATERIAL DESCRIPTION
0
13-12-14
(26)
14-15-15
(30)
8-10-12
(22)
5-7-8
(15)
3-4-5
(9)
.'-.--- -w
PROJECT: Lot 7, Avalon Beach, North Hutchinson Island, Fort Pierce, Florida
SHEET 1 OF
PERMIT #:
PROJECT #: 195257-b
TI C4 IL £ ENGINEERING
L_qJq AND TESTI N G
DRAWN BY: C.V.
DESIGNED BY: J.K.
DATE: 20200103
SCALE: NONE