Field Density Tests of Compacted Soils Method D-6938
Proposed Residence Lot 119, Creekside Date: November 24, 2017
Order #: 17-DR-1158
Area Tested: Building Pad IPermit #:
Material Type: Brown Sand with Traces of Rock Tech: SL
3105 Yellowstone Circle, Fort Pierce, FL 34945
Client: D.R.. Horton, Inc.
Address: 1430 Culver Drive NE Compaction Req.:
Palm Bay, FL 32907 Proctor Method:
I
95%
ASTM D-1557
Test
#
TEST LOCATION !
Probe
Depth
Elev.
Moist
%
Dry
Density
PCF
Proctor
Value
PCF
Optimum
Moisture
%
Compaction
Pass
1
Center of Pad
12"
FL
10.8
106.9
112.0
10.0
95.4%
Yes
2
SW Corner of Pad
12"
FL
9.3
107.3
112.0
10.0
95.8%
Yes
3
NE Corner of Pad
12"
FL
9.7
106.6
112.0
10.0
' 95.2%
Yes
4
I
5
I
6
I
7
8
9
I
10
11
�
12
13
14
Remarks: See Reverse Side (Page 2 of 2) for Additional Information for Disclaimer
This is a Compaction Test only on the top 12" of the pad and is not a verification.of, Soil Bearing Capacity.
Legend for Elevation: c i
PR = Proofroll 1,2,3 = 1st, 2nd, 3rd Lift Submitted by:, Q
SL = Springline FL = Final Lift Keith LeBlaric�P.E:.
SG = Subgrade BG =Below Grade Federal Engiopering4 Testing, Inc.
BC = Basecourse BOF = Bottom of Footing Florida<Reg. No. 59394
TOP =Top of Pipe FG =Finished Grade Certfirate of Authorization #5471
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidertial.property of`clients, and authodzatioi; for publication of statements,
conclusions or extracts from or regarding our reports is deserved pending our written approval. A density test determines the degree of compaction of the tested layer of
material only. A density does not replace a soil bearing capacity determination. These density tests do'not certify the urdeflyiag soil nteterials below the proposed structure.
The results do not preclude or guarantee that future settlement and cracking will not occur. A soil boring,tesi'is;required-to"cerift,:i at;4he underlying soils will support the
proposed structure without settlement. If no soil borings have been performed to verify the underlying soils,; we i2comrnend_61 soil 'borings be performed to evaluate the
suitability of the underlying soil to support the proposed structure. After laying dormant for a period of 90 days o� aPiev hoavy,rain/storms, retesting -must be performed on this
work.
PAGE 1 of 2
Compacted Soils Method D-6938 Disclaimer
Pursuant to your request, Federal Engineering & Testing, Inc. (FET) has performed a compaction test at the referenced
project on the reverse side. The purpose of our test was to determine the degree of compaction of the tested layer of
material only. In no way shall a compaction test replace a soil bearing capacity determination. A soil boring test must be
performed by the client prior to construction to verify subsoil conditions. Our scope of services only included testing the top
12" of added fill material. FET was not contracted to perform supervision of the building pad preparation. This testing of
the added fill material does not include an analysis of the underlying soil materials to determine if they are capable of
supporting the proposed structure without settlement. This density compaction test does not warranty any underlying soil
materials or conditions below the tested top 12 inches of material. If no soil borings have been performed in the location of
the proposed structure, we recommend performing soil borings below all foundation areas of the proposed structure to
verify the underlying soil conditions.
Environmental analysis of the soil materials is not part of the scope of services. If environmental analysis of the soils is
required, we can provide a proposal for performing an environmental analysis of the soil materials. The scope of services is
for determination of the degree of compaction of the tested layer of material only. No other analysis is implied or warranted.
Job project specifications were not available at the time the work was performed. Determination of the pass/fail compaction
results are based on current common industry requirements of 95% of the ASTM D-1557 standard for building foundations
and 98% of the AASHTO T-180 standard for paved areas such as roadways and parking lots. If different specifications are
required, Federal Engineering & Testing, Inc. shall be notified.
Our findings are relative to the date and areas of our site work and should not be relied upon to represent conditions on
other areas or dates. Any subsequent site disturbances due to water erosion, rain waters, construction activities,
excavations, overgrown, vegetation, traffic and other disturbances will void this test and the site must be re -compacted and
re -tested prior to construction.
As a mutual protection to clients, the public and ourselves, all reports are submitted are the confidential property of clients
and authorization for use, publication of statements, conclusions or extracts, from or regarding our reports is reserved
pending written approval.
It has been a pleasure working with you and we look forward to doing so in the near future.
Page 2 of 2
L Phone 954-784-2941
,t., 800-848-1919 Jederl-
Fax 954-784-7875
& TESTING INC. www.fed-eng.com
250 SW 13th Ave Pompano Beach, FL 33069
Field Density Tests of Compacted Soils Method D-6938
Project: Proposed Residence Lot 119,-Creekside Date: November 24, 2017
Address: 3105 Yellowstone Circle, Fort, Pierce; FL 34945 Order #: 17-DR-1158
Area Tested: l§uii n6'Pad I I Permit .
Material Type: Brown Sand with Traceslof Rock Tech: SL
Client: D.R.. Horton,, Inc.
Address: 1430 Culver Drive NE, Compaction Req.: 956/0
Palm Bay, FL 32907 Proctor Method: ASTM D-1557
Test
#
TEST LOCATION
Probe
De th
p
Elev.
Moist
%
Dry
Density
PCF
Proctor
Value
PCF
Optimum
Moisture
%
Compaction
Pass
1
Center of Pad
12",
FL
10.8
106.9
112.0
1 10.0.
95.4%
Yes
2
JSW Corner of Pad
12"
FL
9.3
107.3
112.0
10.0
95.8%
Yes,
3
NE Corner of Pad
12"
FL
9.7
106.6
112.0
10.0
95.2%
Yes
4
5
6
7
8
9
10
11
f
12
13
14
Remarks: See Reverse Side (Page 2 of 2) for Additional Information for Disclaimer
This is a Compaction Test only on;the top IT'of the pad and is not a verification of Soil F3earing Capacity.
Legend for Elevation:
PR = Proofroll 1,2,3 = 1st, 2nd, 3rd Lift Submitted by:
SL = Springline FL = Final Lift Keith LeBlanc, P.E.`
SG = Subgrade BG = Below Grade 'Federal Engineering Tesfing,-inc.
BC = Basecourse BOF = Bottom of Footing Florida Reg. Na.59394
TOP = Top of Pipe FG = Finished Grade Certificate of AiAhorization #►547'
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and authorization for.+pubGcation of statements,
conclusions or extracts from or regarding our reports is reserved pending our written approval. A density test deiennines the degree of.compae'orof the tested layer of
material only. A density does not replace a soil bearing capacity determination. These density tests do not certify the underlying•,soll materials h�l .-Jie proposed structure.
The results do not preclude or guarantee that future settlement and cracking will not occur. A soil boring test is requlreit-to certify thaf'the,underi" ing soils will support the
proposed structure without settlement. If no soil borings have been performed to verify the underlying soils, we recommend that soil borings-bs performed to evaluate the
suitability of the underlying soil to support the proposed structure. After laying dormant for a period of 90 days or after heavy raln%storms;. retesting must be performed on this
work.
PAGE 1 of 2
Compacted Soils Method ®-6936 Disclaimer
Pursuant to your request, Federal Engineering & Testing, Inc. (FET) has performed a 'compaction test at the -referenced
project on the reverse side. The purpose of our test was to determine the degree of compaction of the tested layer of
material only. In no way shall a compaction test replace a soil bearing capacity determination. A soil boring test must be
performed by the client prior to construction to verify subsoil conditions. Our scope of services only included testing the top
12" of added fill material. FET was not contracted to perform supervision of the building pad preparation. This testing of
the added fill material does not include an analysis of the underlying soil materials to determine if they are capable of
supporting the proposed structure without settlement. This density compaction test does not warranty any underlying soil
materials or conditions below the tested top 12 inches of material. If no soil borings have been -performed in the location of
the proposed structure, we recommend performing soil borings below all foundation areas of the proposed structure to
verify the underlying soil conditions.
Environmental analysis of the soil materials is not part of the scope of services. If environmental analysis of the soils is
required, we can provide a proposal for performing an environmental analysis of the soil materials. The scope of services is
for determination of the degree of compaction of the tested layer of material only. No other analysis is implied or warranted.
Job project specifications were not available at the time the work was performed. Determination of the pass/fail compaction
results are based on current common industry requirements of 95% of the ASTM D-1557 standard for building foundations
and 98% of the AASHTO T-180 standard for paved areas such as roadways and parking lots. If different specifications are
required, Federal Engineering & Testing, Inc. shall be notified.
Our findings are relative to the date and areas of our site work and should not be relied upon to represent conditions on
other areas or dates. Any subsequent site disturbances due to water erosion, rain waters, construction activities,
excavations, overgrown, vegetation, traffic and other disturbances wi►I void this test and the site must be re -compacted and
re -tested prior to construction.
As a mutual protection to clients, the public and ourselves, all reports are submitted are the confidential property of clients
and authorization for use, publication of statements, conclusions or extracts from or. regarding our reports is reserved
pending written approval.
It has been a pleasure working with you and we look forward to doing so in the near future.
Page 2 of 2
ail
DEC 0 � 2017
Phone 954-784-2941
ederal
L4
1919
PEt;�^a7i7TjFaG
954-784-7875
Fax 954-784-7875
& TESTING INC.
St. Lucie County, FL
www.fed-eng.com
250 SW13th Ave Pompano Beach, FL 33059
Field Density Tests of Compacted Soils Method D-6938
Project: Proposed Residence . Lot! 119, Creekside
Date:
November 24, 2017
Address: 3105 Yellowstone Circle, Fort Pierce, FL 34945
Order #:
17-DR-1158
Area Tested: Building Pad
Permit #:
Material Type: Brown Sand with Traces of Rock
I
Tech:
SL
Client: D.R. Horton, Inc.
Address: 1430 Culver Drive NE
Compaction Req.:
95%
Palm Bay, FL 32907
I
Proctor Method:
ASTM D-1557
Test
#
TEST LOCATION
Probe
Depth
p
Elev.
Moist
%
Dry
Density
PCF
Proctor
Value
PCF
Optimum
Moisture
%
Compaction
Pass
1
I
Center of Pad
12"
FL
10.8
106.9
112.0
10.0
95.4%
Yes
2
SW Corner of Pad
12"
FL
9.3
107.3
1 112.0
10.0
95.8%
Yes
3
NE Corner of Pad ;
12"
FL
9.7
106.6
112.0
10.0
95.2%
Yes
4
5
I
6
7
8
9
10
11
12
13
14
Remarks: See Reverse Side (Page 2 of
This is a Compaction Test of
Legend for Elevation:
PR = Proofroll 1,2,3 = 1st, 2nd, 3rd Lift
St. = Springline FL = Final Lift
Additional Information for Disclaimer
the top 12" of the pad and is not a verification of S-i8e 'f, ao
Submitted by:
SG = Subgrade BG = Below Grade Federal Engine$W 8,Test%r,,►1ftYr' Zee `
BC = Basecourse BOF = Bottom of Footing i Florida Reg. No @►; �'�' o
TOP =Top of Pipe FG =Finished Grade Certificate of Autt�" �•```
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and autho o ants,
conclusions or extracts from or regarding our reports is reserved pending our written approval. A density test determines the degree of r� ¢f t�tl�1 layer of
material only. A density does not replace a soil bearing capacity determination. These density tests do not certify the underlying soil materials badW $�8,brbposed structure.
The results do not preclude or guarantee that future settlement and cracking will not occur. A soil boring test is required to certify that the underlying soils will supportthe
proposed structure without settlement. if no soil borings have tieen performed to verify the underlying soils, we recommend that soil borings be performed to evaluate the
suitability of the underlying soil to support the proposed structure. After laying dormant for a period of 90 days or after heavy rain/storms, retesting must be performed on this
work.
Keith
PAGE 1 of 2
Compacted. Soils Method. D-6938 Disclaimer
Pursuant to your request, Federal Engineering. & Testing, Inc. (FET) has performed a compactiontest at the. referenced
project on the reverse side: The purpose of our test was to determine the degree of compaction of -the -tested .layer of
material only. In no way shall a compaction test replace a soil bearing capacity determination. A soil boring test -must be
performed by the client prior to construction to verify subsoil. conditions. Our scope of services only included testing -the top
12" of added fill material. FET was not: contracted to perform supervision of the building pad: preparation. This testing of
the added fill material does not include an analysis of the underlying soil materials to, determine if they are capable .of
supporting :the proposed structure without settlement. This density compaction test does not warranty any underlying soil
materials or conditions below the tested top 12 inches of material. If no soil borings have .been performed in :the location of
the proposed structure,, we recommend performing soil .borings below all foundation areas of the proposed structure to
verify the underlying soil conditions.
Environmental analysis of the soil materials is not part of the scope of services. If environmental analysis of the soils is
required., we can provide a proposal for performing;an environmental analysis of the soil materials. The scope of services is
for determination of the degree of compaction of the tested layer of material only. No other analysis is implied.or warranted.
Job project specifications were not available at the time the work was. performed. Determination of the-pass/fail compaction
results are based on current common industry requirements of 95%:of the ASTM D-1557 standard for buildingfoundations
and 98% of the AASHTO T-180 standard for paved areas such as roadways and parking lots. If different specifications are
required, Federal Engineering & Testing, Inc. shall be -notified.
Our findings are relative to the date and areas of our site work and should not berelied upon to represent conditions on
other areas or dates. Any subsequent site disturbances due to water erosion, rain waters, construction activities,
excavations, overgrown, vegetation, traffic and other disturbances will void this test and -the site must be re -compacted and
re -tested prior -to construction.
As a mutual protection to clients, the public and ourselves,all reports are submitted are the. confidential property of clients
and authorization for use, publication of _statements, conclusions or.ektracts from or regarding our.reports is reserved
pending written approval.
It has been a pleasure working with you and we look forward to doing so in the near future:
Page 2 of-2
eder"''I'
& TESTING INC.
250 SW 13th Ave Pompano Beach, FL 33069
Field Densit
Project: Proposed Residence Lc
Address: 3105'Yell6wst6 e'Circle, Fort
Area Tested: . '.Building -Pad
Material Type: Brown Sand with Traces
Phone 954-784-2941
800-848-1919
Fax 954-784-7875
www.fed-eng.com
Tests of Compacted Soils Method'D-6938
119;•Creekside Date: November 24, 2017
'ierce,'FL 34945 Order #: 17-DR-1158
Permit #:
f Rock . Tech: SL
Client: D.R. Horton, Inc.
Address: 1430 Culver Drive NE ! Compaction Req.: 95.%
Palm Bay, FL 32907 Proctor Method: ASTM D-1557
Test
#
TEST LOCATION
Probe
Depth
p
Elev.
Moist
%
' Dry
Density
PCF
Proctor
Value
PCF
;.Optimum
Moisture
% ..
Compaction
Pass
1
Center of Pad
12"
FL
10.8
106.01.
, 1.12.0
10.0 ,
95.4%
Yes
2
i
SW Corner of Pad
12"
FL
9.3.
107.3
112.0
10.0 - ,
95.8%
Yes
3
NE Corner of Pad I
12"
FL
9.7
106.6
112.0
10.0
95.2%
Yes
4
5
6
8
9
.
10
11
i
•
� trii
12
13
I
14
! .
KemarKS: See Reverse Side (Page 2 of 2) forjAdditional Information for Disclaimer
This is a Compaction Test only on 'the top 12" of the pad and is not a verificatioei ofS iCBearing Capacity.
Legend for Elevation: f �
PR = Proofroll 1,2,3 = 1st, 2nd, 3rd Lift Submitted by:
SL = Springline FL = Final Lift _. Keith LeBlanc, P.E.
N Z'!
SG = Subgrade BG = Below Grade Federal Ettgiree[irtg;& Testing '; -Inc.
BC = Basecourse BOF = Bottom of Footing Florida Reg. t6. 59394 -
TOP = Top of Pipe FG = Finished Grade Certificate -of, cktithorization #5471
Asa mutual protection to clients, the public and ourselves, all reports are submitted as the confidential proliert`y.of clients, and authorization for publication of statements,
conclusions or extracts from or regarding our reports is reserved pending our written approval. A density teat determines, the degree of,corri�sation of the tested layer of
material only. A density does not replace a soil bearing capacity determination. These density tests do not certify tiig Underlying soil_ r6ateriais-"6elf
ro d st t py
The results do not preclude or guarantee that future settlement and cracking will not occur. A soil boring test is Fegi;ireii rertiiy th t ihe-underHs • suppo
proposed structure without settlement. If no soil borings have been performed to verify the underlying soils, we recom,mendjtllefi s�11 borings be d eval a th
suitability of the underlying soil to support the proposed structure. After laying dormant for a period of 90 days or after heavy raiiif t- 's,• retesting e n TIM
work.
PAGE 1 of 2
Compacted Soils Method ®-6938 Disclaimer
Pursuant to your request, Federal Engineering & Testing, Inc. (FET) has performed a compaction test at the referenced
project on the reverse side. The purpose of our test was to determine the degree of compaction of the tested layer of
material only. -In no way shall a compaction test replace a soil bearing capacity determination. A soil boring test must be
performed by the client prior to construction to verify subsoil conditions. Our scope of services only included testing the top
12" of added fill material. FET was not contracted to perform supervision of the building pad preparation. This testing of
the added fill material does not include an analysis of the underlying soil materials to determine if they are capable of
supporting the proposed structure without settlement. This density compaction test does not warranty any underlying soil
materials or conditions below the tested top 12 inches of material. If no soil borings have been performed in the location of
the proposed, structure, we recommend performing soil borings below all foundation areas of the proposed structure to
verify the underlying soil conditions.
Environmental analysis of the soil materials is not part of the scope of services. If environmental analysis of the soils is
required, we can provide a proposal for performing, an environmental analysis of the soil materials. The scope of services is
for determination of the degree of compaction of the tested layer of material only. No other analysis is implied or warranted.
Job project specifications were not available at the time the work was performed. Determination of the pass/fail compaction
results are based on current common industry requirements of.95% of the ASTM D-1557 standard for building foundations
and 98% of the AASHTO T-180 standard for paved areas such as roadways and parking lots. If different specifications are
required, Federal Engineering & Testing, Inc. shall.be notified.
Our findings are relative to the date and areas of. our site work and should not be relied upon to represent conditions on
other areas or dates. Any subsequent site disturbances due to water erosion, rain waters, construction activities,
excavations, overgrown, vegetation, traffic and other disturbances will void this test and the site must be re -compacted and
re -tested prior to construction.
As a mutual protection to clients, the public and ourselves, all reports are submitted are the confidential property of clients
and authorization for use, publication of statements, conclusions or extracts from or regarding our reports is reserved
pending written approval.
It has been a pleasure working with you and we look forward to doing so in the near future.
Page 2 of 2