In-Place Density Test Report
Client:D.R. HORTON, INC. EAST FLORIDA DIVISION UES Technician:Johnnie Smith
1430 Culver Drive, NE
Palm Bay, FL 32907
Date Tested:01/12/2021
Project:CMT CREEKSIDE
Various Locations,Vero Beach, County, FL 32967
Type of Test:
Area Tested:3213 Trinity, Lot 69, Foundation Pad Field:ASTM D-6938 Nuclear Gauge Method
Material:Fill Laboratory:ASTM D1557 Modified Proctor
Reference Datum:0 = Top of Final Grade
The tests below meet the 95% minimum compaction requirement.
Test
No.Location of Test Range
Maximum
Density
(pcf)
Optimum
Moisture
(%)
Field Dry
Density
(pcf)
Field
Moisture
(%)
Soil
Compaction
(%)
Pass
or
Fail
1 W section 0-1 ft 118.6 10.8 118.2 10.7 100 Pass
2 E section 0-1 ft 118.6 10.8 118.4 10.6 100 Pass
3 Center section 0-1 ft 118.6 10.8 118.7 10.9 100 Pass
Remarks:1-2’ HCP=50+, > 95 % Compaction, PASS. HCP tests are empirically correlated to the relative density of the soil.
Permit # 2002-0063
Reviewed By
GFA International, Inc
FBPE Registry No.4930
Thomas Dominic Montano
Branch Manager
STATE OF FLORIDA
Professional Engineer No. 84146
This item has been digitally signed and sealed by Thomas Dominic
Montano on the date adjacent to the seal. Printed copies of this
document are not considered signed and sealed and the signature
must be verified on any electronic copies.
To establish a mutual protection to Universal's clients, the Public and ourselves, all reports are submitted as confidential property of our clients and
authorization for publication of statements, conclusions or extracts from or regarding Universal's reports is reserved pending our written approval.
Page 1