HomeMy WebLinkAboutRichardson Roofing Permit PackageSection A (General Information)
Master Permit No. Process No.
Contractors Name: ____________________________________ License # _______________________________
Job Address
ROOF CATEGORY
Low Slope Mechanically Fastened Tile Mortar/Adhesive Set Tiles
Asphaltic Shingles Metal Panel/Shingles Wood Shingles/Shakes
Prescriptive BUR-RAS 150
ROOF ROOF TYPE
New roof Repair Maintenance Reroofing
ROOF SYSTEM INFORMATION
Recovering
Low Slope Roof Area (SF) ________ Steep Sloped Roof Area (SF) _________________
Section B (Roof Plan)
Total (SF) _______
Sketch Roof Plan: Illustrate all levels and sections, roof drains, scuppers, overflow scuppers and overflow drains.
Include dimensions of sections and levels, clearly identify dimensions of elevated pressure zones and location of parapets.
DuraVerde J&N Roofing and Construction CCC1332515
7507 Salerno Rd, Fort Pierce, FL 34951
X
X
X
204 2445 2649
Product Approval No.:________________________
Design Wind Pressures, From RAS 128 Or Calculations:
Zone 1': ___ Zone 1: _____ Zone 2: ____Zone 3: _____
Max. Design Pressure, from the specific product approval
system: ______________________________________
Deck:
Type:___________________________________
Gauge Thickness: _________________________
Slope: __________________________________
Anchor/Base Sheet & No. df Ply(s): _______________
Anchor/Base Sheet Fastener/Bonding Material:
___________________________________________
Insulation Base Layer: _________________________
Base Insultation Size and Thickness: _____________
Base Insulation Fastener/Bonding Material:
___________________________________________
Top Insulation Layer: __________________________
Top Insulation Size and Thickness: _______________
Top Insulation Fastener/Bonding Material:
___________________________________________
Base Sheet(s) & No. of Ply(s): ___________________
Base Sheet Fastener/Bonding Material:
___________________________________________
Ply Sheet(s)' & No. of Ply(s): ____________________
Ply Sheet Fastener/Bonding Material:
___________________________________________
Top Ply: _________________________________
Top Ply Fastener/Bonding Material:
Surfacing: ___________________________________
Fastener Spacing for Anchor/Base Sheet Attachment:
Zone 1':" oc @ Lap, # Rows
Zone 1:" oc @ Lap, # Rows
Zone 2:" oc @ Lap, # Rows
Zone 3:" oc @ Lap, # Rows
Number of Fasteners Per Insulation Board:
Zone 1':Zone 1:Zone 2:Zone 3:
Illustrate Components Noted and Details as Applicable:
Woodblocking, Gutter, Edge Termination, Stripping,
Flashing, Continuous Cleat, Cant Strip, Base Flashing,
Counterflashing, Coping, Etc.
Indicate: Mean Roof Height, Parapet Height, Height of Base
Flashing, Component Material, Material' Thickness, Fastener
Type, Fastener Spacing or Submit Manufacturers Details that
Comply with RAS 1 11 and Chapter 16.
FT.
FT.
Parapet
Height
Mean
Roof
Height
wood
0/12
Section C (Low Slope Roof)
Fill in specific roof assembly components and identify
manufacturer
(If a component is not used, identify as "NA")
System Manufacturer: ________
20-0414.16
N/A
1
E(5) -97.5
Self-Adhered
-98 -124 -163-71.8
Tri-Built SA Cap
Self-Adhered
Beacon Sales Acquisition - Tri-Built
Section D (Steep Slope Roof System)
Roof System Manufacturer:
Notice of Acceptance Number:
Minimum Design Wind Pressures, If Applicable (From RAS 127 or Calculations):
Zone 1:Zone 2e:Zone 2n:Zone 2r:Zone 3e:Zone 3r:
IKO Dynasty
19-1112.02
3
4" Aluminum
IKO Dynasty - Laminate Asphalt Shingles
1-1/4 RS Nails 4"o/c @ laps & 2 rows 12"o/c
3/4" Plywood
OC Tri-Gran Ice and Water
11.5
97 97 142 142 142 169_____