HomeMy WebLinkAbout21-139B - Bryn Mawr Condos 2021 - Bldg B - Rep 2 - 12.16.21M L Engineering Inc.
Consulting Engineers
Threshold Inspector
2030 37th Avenue
Vero Beach, Florida 32960
Phone: (772) 569-1257
Fax: (772) 569-4041
www.mlengineeringinc.com
Project No. 21-139B Report No. 2
Project Manager:
Building Official:
Contractor:
File
Mr. Gene Ross – Elliott Merrill Community Mgmt.
SLC Building Department
Mr. Chris Arias – Daniello & Associates, Inc.
Page 1 of 2
THRESHOLD INSPECTION REPORT
BRYN MAWR CONDOMINIUMS CONCRETE REPAIRS 2021 – BLDG. B
5059 N. HWY A1A, FORT PIERCE, FL 34949
SLC BLDG. DEPT. PERMIT NUMBER: 2106-0406
PROJECT NAME: Bryn Mawr Condominiums Concrete
Repairs 2021 – Bldg. B DATE: December 16, 2021
CLIENT: Elliott Merrill Community Management LOCATION: Fort Pierce, FL
CONTRACTOR: Daniello & Associates, Inc. PROJECT MGR: Mr. Chris Arias
INSPECTED BY: Todd Rhoten WEATHER: Sunny
WORK INSPECTED:
Concrete pre-pour at the common walkways – 5th, 6th, 7th, and 8th floors.
OBSERVATIONS:
• Loose concrete has been chipped and removed at all floors as indicated in permit drawings.
• Reinforcing was exposed and found to be in serviceable condition with minor corrosion.
• Reinforcing bars have been cleaned and painted with the approved corrosion inhibitor.
RECOMMENDATIONS:
• Concrete placement is approved for all common walkway surface and column spalls.
______________________________ _________________________________
Michael Lue, P.E. Todd Rhoten
M L Engineering Inc.
Consulting Engineers
Threshold Inspector
2030 37th Avenue
Vero Beach, Florida 32960
Phone: (772) 569-1257
Fax: (772) 569-4041
www.mlengineeringinc.com
Project No. 21-139B Report No. 2
Project Manager:
Building Official:
Contractor:
File
Mr. Gene Ross – Elliott Merrill Community Mgmt.
SLC Building Department
Mr. Chris Arias – Daniello & Associates, Inc.
Page 2 of 2
Pic 1 – Unit 505
Column spall repair
Pic 2 – Unit 703
Surface spall repair
Pic 3 – Unit 803
Surface spall repair