HomeMy WebLinkAboutSITE SURVEY PERFORMED 1/5
BARuN CORP
December 22,2021
RE: CERTIFICATION LETTER
Project Address: CEDRIC ALLWOOD RESIDENCE
48 SILVER OAK DRIVE
PORT ST. LUCIE, FL 34952
Design Criteria:
Applicable Codes=2020 FLBC/FLEBC 7th Edition,2020 FLRC 7th Edition,2018 IEBC/IBC/IRC,ASCE 7-16 and 2018 NDS
Risk Category= II
Wind Speed= 158 mph, Exposure Category C, Partially/Fully Enclosed Method
Ground Snow Load=0 psf
Roof 1-3:2 x 4 @ 24"OC, Roof DL= 12 psf, Roof LL/SL=20 psf(Non-PV), Roof LL/SL=0 psf(PV)
To Whom It May Concern,
A job site survey of the existing framing system of the address indicated above was performed .All structural evaluation is based on the
site inspection observations and the design criteria listed above.
Existing roof structural framing has been reviewed for additional loading due to installation of PV Solar System on the roof.The
structural review applies to the sections of roof that is directly supporting the solar PV system.
Based on this evaluation, I certify that the alteration to the existing structure by installation of the PV system,with blocking upgrades in
Roof 3(Hip), meets the prescriptive compliance requirements of the applicable existing building and/or new building provisions
adopted/referenced above.
Additionally,the PV module assembly including attachment hardware has been reviewed to be in accordance with the manufacturer's
specifications and to meet and/or exceed the requirements set forth by the referenced codes.
FL
10 YUR!q��'%
N, c E N SF .�O
* N�o.�8^626 *y�_�}Q Digitally signed by
• � ��I SL Yurianto Yurianto
Sincerely, DN:cn=Yurianto Yurianto
c=US o=Unaffliated
v A01410D00000176B
Yuri Yurianto,S.E., P.E. '� r u �t� o 07CBF250000A7A2
�O�• STATE E O F Reason:I am the author
•,•/C P, ,••' of this document
Location
` ` Date:
1 15 08 0012-22
By Yuri at 11:14:53 AM, 1212212021
This item has been electronically signed and sealed by
Yurianto Yurianto,SE,PE.on the date and/or time
stamp shown using a digital signature. Printed copies
of this document are not considered signed and sealed
and the signature must be verified by a 3rd Party
Certificate Authority on any electronic copy.
Barun Corp I Design and Engineering 1610.202.4506 1 chrisk@barun-corp.com www.barun-corp.com
2/5
BARUN CORP lumlor 94
CEDRIC ALLWOOD RESIDENCE,48 SILVER OAK DRIVE, PORT ST. LUCIE, FL 34952
MOUNTING •N (BASED ON IMPACT
ROOF ROOF PITCH (deg.) RESULT
Roof 1-3 18' OK
STANDOFF . •DWARE EVAULATION FOR WIND UPLIFT
ROOF UPLIFT DCR
Roof 1-3 76.3%
Barun Corp I Design and Engineering 1610.202.4506 1 chrisk@barun-corp.com I www.barun-corp.com
3/5
LOAD CALCULATION
BPR"MRMPE
Roof 1-3
CEDRIC ALLWOOD RESIDENCE,48 SILVER OAK DRIVE,PORT ST.LUCIE,FL 34952
PV SYSTEM DEAD LOAD
PV module weight 2.5 psf
Hardware assembly weight 0.5 psf
PV-DL 3.00 psf
ROOF DEAD LOAD
Existing Roofing Material Comp Roof 3 layers 7.5 psf
Underlayment 0.5 psf
Plywood Sheathing 1.5 psf
Framing Weight 2 x 4 @ 24 in.O.C. 0.73 psf
Vaulted ceiling No 0 psf
Miscellaneous 1.5 psf
Total Roof Dead Load R-DL 11.73 psf
REDUCED • • • • EXPRESSION
Roof Live Load Lo 20.0 psf
Member Tributary Area At <200 sf
Roof 1-3 Pitch 4/12 or 18'
Trubutary Area Reduction Rl 1
Slope Roof Reduction Rz 1
Reduced Roof Live Load Lr=Lo(RI)(R2) 20.00 psf
SNOW LOAD
Ground Snow Load pg 0
Effective Roof Slope 18'
Snow Importance Factor IS 1.0
Snow Exposure Factor Ce 1.0
Snow Thermal Factor Cf 1.1
Minimum Flat Roof Snow Load Pf-min 0
Flat Roof Snow Load Pf 0.00
iIIIMIIIIIIIIR SLOPED ROOF SNOW LOAD ON ROOF (All other surfaces)
Roof Slope Factor Cs-roof 1.00
Ps-roof 0.00
SLOPED ROOF SNOW LOAD ON PV PANEL (Unobstructed slippery surface
Roof Slope Factor Cs_P 0.87
Ps-Pv 0.00
Barun Corp I Design and Engineering 1610.202.4506 1 chrisk@barun-corp.com I www.barun-corp.com
4/5
■ IMPACT
ARON B MRPCE ■
Roof 1-3
CEDRIC ALLWOOD RESIDENCE,48 SILVER OAK DRIVE,PORT ST.LUCIE,FL 34952
Roof Dead Load(DL)= 11.73 14.73 psf
Roof Live Load(Lr)= 20.00 0.00 psf
Roof Snow Load(SL)= 0.00 0.00 psf
I EXISTING WITH PV PANEL
(DL+Lr)/Cd= 25.38 16.37 psf
(DL+SL)/Cd= 10.20 12.81 psf
Maximum Gravity Load= 25.38 16.37 psf
Load Increase(%)_ -35.53% OK
IEBC Provision: 2018
The requirements of section 806.2 of 2018 IEBC are met and the structure is permitted to remain unaltered.
Barun Corp I Design and Engineering 1610.202.4506 1 chrisk@barun-corp.com I www.barun-corp.com
5/5
M WIND CALCULATION
BARON CORP
Roof 1-3
CEDRIC ALLWOOD RESIDENCE,48 SILVER OAK DRIVE,PORT ST.LUCIE,FL 34952
SITE INFORMATION
Ultimate Wind Speed(mph)= 158 Roof Pitch(deg.)= 18°
Risk Category: II Roof Type: Hip
Exposure Category: C Kd= 0.85
Mean Roof Height(ft)= 15 Kzt= 1
Solar Array Dead Load(psf)= 3.00 Kz= 0.85
qh=0.00256*Kz*Kzt*Kd*Ke*VZ= 46.11
a(ft)= 3.00
Array Edge Factor(yE)= 1.50
Solar Array Pressure Eq.Factor(ya)= 0.60
Hardware Type: SFM INFINITY MICRORAIL WITH UNIRAC SFM INFINITY RAIL-LESS
Allowable Load(lb)= 982.50 Ibs,S.Pine 2.5"Embedment
Max.X-Spacing(ft)(Zone 1) 4.00 Effective Wind Area(ft2)
Max.Y-Spacing(ft)(Zone 1) 3.30 13.20
Max.X-Spacing(ft)(Zone 2r) 4.00 Effective Wind Area(ft)
Max.Y-Spacing(ft)(Zone 2r) 3.30 13.20
Max.X-Spacing(ft)(Zone 2e&3) 4.00 Effective Wind Area(ft)
Max.Y-Spacing(ft)(Zone 2e&3) 3.30 13.20
ROOFZONE GCp(-)UPLIFT UPLIFT PRESSURE(psf) PULLOUTFORCE
1 -1.30 -30.66 404.70
2r -1.75 -41.86 552.61
2e&3 -2.35 -56.81 749.83
*Wind calculation is based on ASCE 7-16,29.4-C&C,LC#7:0.61)+0.6W used.
-0 10 100 -0 10 100
•3.8 = 1 13.8
3 •3 ICI d
•32 32
-3.0 40
� .2.8 a .2.s 6 ® 3
C] .2.6 2.6 CJ •2.6- _Z____T_
[7 2.4 2.4 �? -24 4-4 i
.29 -9-0 .W -2.0
.i4 - 3 -i 4 + ' 1
L2 -1 1.2 1-31 0 p IQ QI (D I�
a a
4 ' 4642
W .2
e'
40A � +03 +p.9" w ouel e 3 Q 3
o.a +08 - +07 a I PLAN
fl0 fi ID 20 50 200 5oot0c0
t too r t0 20 50 too 200 50a1000
W (09)0 (461 M" ww) (00 W 0 (46)N CK (4657(9P91
Effective Wind Area,R 2(m2) Hffective Wind Area,ft 2(In 2)
FIGURE 30.3-2E Components and Cladding [h<60 ft(h<18.3 m)]: External Pressure Coefficients, (GC,),for Enclosed and Partially
Enclosed Buildings-Hip Roofs,7°<9<20°(Roof)
Barun Corp I Design and Engineering 1610.202.4506 1 chrisk@barun-corp.com I www.barun-corp.com
[Ey HIP TRUSS
TOPCHORD
(E)PLYWOOD
SHEATHING
t
INSTALLATION NOTES:
• CUT AND ADD (N)2x4 (or 2x6) BLOCKING AS
SHOWN IN S1.
FASTEN (N)2x BLOCKING TO (E) HIP TRUSS TOP
fE1 JACK TRUSS
(N)VERTICAL2x4or2x69LOCK CHORD USING SIMPSON A34 CLIP ON EACH SIDE.
TOPCHORD . INSTALL BLOCKING AT ALL LOCATIONS THAT REQUIRE
(N)SIMPSONA34CLIP A PV SYSTEM MOUNT/LAG.
AT EACH END OF THE SLACK
51 BLOCKING UPGRADE
NTS