Progress Inspection Report #24 NOV 12 2021
Permit #SLC 2102-0371
St.Lucie County
Permitting
Project Name: Barclay Beach Club Progress Report thru 10-29-21
Project Address: 2800 SR-A1A, Hutchinson Island Inspection Visits: 10-29-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: Stack 08 demo, 01 stack swing stage installation and marks for repair, 04
stack waterproofing, 05 stack paint, and 04 stack shutter removal
INSPECTOR'S REPORT
Keystone Engineering visited the site on 10-29-21 and had several conversations with the
construction team by telephone throughout the week.
This week the construction crew installed a swing stage above the 01 stack, initial marks for
repair were completed for obvious damage. Workers applied protective netting on the 01
balcony stack, where floor coating and shutter track removal are in progress. Flood
testing, surface profiling, and waterproofing applications were completed on the 04 stack
where the crew is now prepping for knockdown textures. The walls and ceilings were
painted on the 05 stack, workers are now prepping the surfaces for waterproofing
applications.
The crew also installed a swing stage above the east windows on the 04 stack where shutter
removal is in progress to prepare for new window installations. The contractor plans to
remove 1 or 2 windows at a time while repairing any concrete damage in the frames
before installations.
E.
No.60965
STATE OF
ij F toR10 .•'�`•
/011 S/ONA1 �?\\
!I
View of two ceiling spalls marked for repair on the Penthouse 1 balcony
J
r
View of an edge spall marked for repair on the Penthouse 1 balcony
Y
View of a crack in the drip edge marked for repair on the Unit 1001 ceiling
•i_.,
r
View of corroded reinforcement exposed above a sliding glass door after a spall was pulled from the ceiling on
the Unit 901 balcony
View of an edge spall marked for repair on the Unit 901 ceiling
y
View of surface spalls marked for repair on the Unit 501 balcony
.t
r
{ I✓
View of the shutter removal in progress on the east 04 stack windows
' 25 South • ,
• '•KEYSTONE Beach, FL 32931
Phone: • •
ENGINEERING
CONSULTING, INC.
Progress Inspection Report #25 NOV 12 2021
Permit #SLC 2102-0371 St.Lucie County
Permitting
Project Name: Barclay Beach Club Progress Report thru 11-5-21
Project Address: 2800 SR-A1A, Hutchinson Island Inspection Visits: 10-29-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: 04 stack shear window removal, 01/08 stack handrail removal, 04/05
stack waterproofing and textures
INSPECTOR'S REPORT
Keystone Engineering visited the site on 11-5-21 and had several conversations with the
construction team by telephone throughout the week.
This week the construction crew installed interior barricades inside Units 1004, 904, 804, and
Penthouse 3 to prepare for shear window removal. Workers removed the shear windows
from Penthouse 3, 1004, and 904 which has revealed severe corrosion of the
reinforcement and concrete spalling. Spalling was observed inside on the Unit 904
ceiling and in the slab edges in between several windows on the 04 stack. New
excavations will begin next week to repair the concrete before new windows are
installed.
Workers removed the handrails from the 01 and 08 stacks, where coating removal and initial
excavations are in progress. Knockdown textures were completed on the 04 stack
balconies and waterproofing applications were completed on the 05 stack. Workers are
now prepping the 05 stack surfaces for knockdown textures.
E. F� i
i
* �
No.60965 :
-- .0
-A 1, STATE OF ;
F -!.�40R10p:•
ONAL ��
1111 .,
11
lilt
li l t
11
ll ,
rt 11
View of the handrails removed from the 08 stack
4'
View of the handrails removed from the 01 stack
T
1
f
View of the shutter removal completed and window removal in progress on the 04 stack
r�
View of corroded reinforcement and spalling in the Penthouse 3 floor after the shear window was removed
i rt1 1
r
i
i
View of the interior barricade installed for the Penthouse 3 window ~
• S _
View of the corroded reinforcement and soalling observed on the ceiling of Unit 904
Additional view of the corroded reinforcement and spalling observed on the ceiling of Unit 904
• a' � r 1j� �..
x..
.w
View of corroded reinforcement and spalline observed between the Unit 904 and 804 shear windows
r ?�
View of concrete spalling in between the Unit 704 and 604 shear windows
I.
I
View of concrete spalling in between the Unit 404 and 304 shear windows
South25 i • Avenue,
KEYSTONE cocoa
Be . . : •
ENGINEERING & : ::
CONSULTING, INC.
Progress Inspection Report #22 RECEIVED
Permit #SLC 2102-0371 NOV 12 2021
L.:,:io Qpurtty
Project Name: Barclay Beach Club Progress Report thru 404I5-21
Project Address: 2800 SR-Al A, Hutchinson Island Inspection Visits: 10-15-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: 06 and 07 stack painting and shutter track reinstallations, 05 stack new
excavations, 04 stack cast backs and stucco applications
INSPECTOR'S REPORT
Keystone Engineering visited the site on 10-15-21 and had several conversations with the
construction team by telephone throughout the week.
This week new excavations were completed on the 05 stack to address the new concrete
spalling found on the edge of the balconies after the handrails were removed. A pre-pour
inspection was completed on Friday, steel prep and form installations are in progress to
prep for cast backs.
Painting is finishing up on the 06 and 07 stacks, where the construction crew applied the final
floor coatings on the balconies. Floor shutter tracks are being reinstalled on the 06 stack,
reinstallations will soon begin on the 07 stack as well. Workers cast back the new edge
repairs on the east side of the 04 stack, where stucco applications are in progress.
No.601985
STATE F
0
Ile
d� w1
y2[
t"
`Y
• •• •. ••Mrs •1 1 •.
t.
a
Aft
�, .F
F-
�fA
ash ri
�t r -. � JY7l4T a1�4 yuA.
! ail�•. t ,j f T a ; >N�'a "t
rv..r__l
� ` I
TU.0
r
e. J t< rt +t i j ✓�.3 t'.� ,i "�'rM 2*�`?t y � x �a
- y..'- � ,� inn `7�,� � �. 7k �4f °'^C✓'��'c��{b �t r � i +n
21,
jdsf �ki2�y,'�, '^
t
I I
I �/
J
View of a new edge repair in progress on the Penthouse 4 balcon71
1
View of a new edge repair in progress on the Unit 1005 balcony
ry
is
�.\ .S 1 `9• L .
71
ny�
View of a new edgeproltress on the Unit 605 balconv
View of a new edge repair in Projuess on the Unit 305 balcon
M�
1
7
+r �
A 4 ,
44 t 1 'y1
View of a new edge repair in progress on the Unit 205 balcony
South25 : • •
KEYSTONE i i
• • •
ENGINEERING 98 �
CONSULTING, INC.
Progress Inspection Report #23
Permit #SLC 2102-0371
Project Name: Barclay Beach Club Progress Report thru 10-22-21
v
Project Address: 2800 SR-A1A, Hutchinson Island �ECEiFr�pection Visits: 10-21-21
QV 12 2021
Prime Contractor: Blue Coast Construction St.t.un;e 9ownty
Superintendent: Rafael Rodriguez Permitting
Activities in-progress: 07 stack shutter reinstallations, 06/07 stack floor coatings, 04 stack
waterproofing, and 08 stack mobilization
INSPECTOR'S REPORT
Keystone Engineering visited the site on 10-15-21 and had several conversations with the
construction team by telephone throughout the week.
This week the construction crew finished applying the 2,d layer of floor coatings on the 06 and
07 balcony stacks. Waterproofing applications are in progress on the 04 stack, and
workers are cleaning,the 05 stack balconies to prep for waterproofing. Floor shutter track
reinstallations are also in progress for the 07 stack.
The crew installed a swing stage over the 08 stack, initial marks for repair were completed on
Thursday. Floor coating removal is in progress, after coatings are removed balconies will
be re-inspected and marked. Next week the crew will install a swing stage on the 01
stack where marks for repair will continue.
rr�lltl�lllil�,
\\�
M0
No.60965
STAT F
O�
CO IOP•" '�
/2111S _..
AL
� Pill!.,
w
View of an edge spall marked for repair on the Penthouse 6 balconv
View of a surface spall marked for repair on the Unit 1008 balconv
}
b
1
I
f
'f
View of marks for repair on the Unit 908 balcony
h.
M
.f
View of corroded reinforcement exposed on the edge of the Unit 708 ceiling
S
f'
-All
View a spall marked for repair on the edge of the Unit 708 ceiling
'WE
►'M ��
t
..i� - ,
r
View of a surface spall marked for repair on the Unit 608 balcony
e
s
View of marks for repair on the Unit 408 balcony
View of marks for repair on the Unit 208 balcony
mlul
View of the swing stage installed above the 08 stack