Progress Inspection Report #24
Permit #SLC 2102-0371
Project Name: Barclay Beach Club Progress Report thru 10-29-21
Project Address: 2800 SR-Al A, Hutchinson Island Inspection Visits: 10-29-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: Stack 08 demo, 01 stack swing stage installation and marks for repair, 04
stack waterproofing, 05 stack paint, and 04 stack shutter removal
INSPECTOR'S REPORT
Keystone Engineering visited the site on 10-29-21 and had several conversations with the
construction team by telephone throughout the week.
This week the construction crew installed a swing stage above the 01 stack, initial marks for
repair were completed for obvious damage. Workers applied protective netting on the 01
balcony stack, where floor coating and shutter track removal are in progress. Flood
testing, surface profiling, and waterproofing applications were completed on the 04 stack
where the crew is now prepping for knockdown textures. The walls and ceilings were
painted on the 05 stack, workers are now prepping the surfaces for waterproofing
applications.
The crew also installed a swing stage above the east windows on the 04 stack where shutter
removal is in progress to prepare for new window installations. The contractor plans to
remove 1 or 2 windows at a time while repairing any concrete damage in the frames
before installations.
�4�;i;;Y111311f1111/�j
:
* # No. 5*0068 •i �'
STATE O
• F
% to. w�
g •. p R.�O;. �w s
F •'•••••....••� � �.t
'� 0
�ONA� `
``�`1
Il!!11
k
1
View of two ceiling spalls marked for repair on the Penthouse 1 balcony
A Ili
r Y.,
.:.1
l
I
r
View of an edge spall marked for repair on the Penthouse 1 balcony
View of a crack in the drip edge marked for repair on the Unit 1001 ceiling
r *MI T
r
t
View of corroded reinforcement exposed above a sliding glass door after a spall was pulled from the ceiling on
the Unit 901 balcony
g6
i-
i
i
View of an edge spall marked for repair on the Unit 901 ceiling
View of surface spalls marked for repair on the Unit 501 balcony
View of the shutter removal in progress on the east 04 stack windows
South25 Brevard
KEYSTONE • . : -. .
'm �7 • • •
r� ENGINEERING & i • iii
1 CONSI TTING, INC.
� f
Progress Inspection Report #25
�--�� Permit #SLC 2102-0371
Project Name: Barclay Beach Club Progress Report thru 11-5-21
Project Address: 2800 SR-Al A, Hutchinson Island Inspection Visits: 10-29-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: 04 stack shear window removal, 01/08 stack handrail removal, 04/05
stack waterproofing and textures
INSPECTOR'S REPORT
Keystone Engineering visited the site on 11-5-21 and had several conversations with the
construction team by telephone throughout the week.
This week the construction crew installed interior barricades inside Units 1004, 904, 804, and
Penthouse 3 to prepare for shear window removal. Workers removed the shear windows
from Penthouse 3, 1004, and 904 which has revealed severe corrosion of the
reinforcement and concrete spalling. Spalling was observed inside on the Unit 904
ceiling and in the slab edges in between several windows on the 04 stack. New
excavations will begin next week to repair the concrete before new windows are
installed.
Workers removed the handrails from the 01 and 08 stacks, where coating removal and initial
excavations are in progress. Knockdown textures were completed on the 04 stack
balconies and waterproofing applications were completed on the 05 stack. Workers are
now prepping the 05 stack surfaces for knockdown textures.
7/1
�`��yiti�►�edt �
:`� •• • •• C
EN
. 50088
.A STLTE OF
ar
r
v,
�o 4 O R A!
trn
i
Jill °.
lilt
f Jill
lilt
AW
View of the handrails removed from the 08 stack
f ` 4
Y'l
1,
View of the handrails removed from the 01 stack
I
View of the shutter removal completed and window removal in progress on the 04 stack
� � 7
06,
s
View of corroded reinforcement and spalling in the Penthouse 3 floor after the shear window was removed
1
I
1
View of the interior barricade installed for the Penthouse 3 window ~
.r
View of the corroded reinforcement and spalling observed on the ceiling of Unit 904
Nk
.� t
+ i
F
i
Additional view of the corroded reinforcement and spalling observed on the ceiling of Unit 904
.►
n
'
i
View of corroded reinforcement and spalling observed between the Unit 904 and 804 shear windows
�.. ,..
w
View of concrete spalling in between the Unit 704 and 604 shear windows
I '
View of concrete spalling in between the Unit 404 and 304 shear windows
South25 BreN,ard Avenue,
KEYSTONE • • •i
• • •
N� ENGINEERING & - : : :
CONSULTING, INC.
Progress Inspection Report #26
a
Permit #SLC 2102-0371
roject Adilffile: Barclay Beach Club Progress Report thru 11-12-21
-Project Address: 2800 SR-Al A, Hutchinson Island Inspection Visits: 11-8, 11-12-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: 08 stack coating removal and marks for repair, 04 stack shear window
barricades and initial excavations
INSPECTOR'S REPORT
Keystone Engineering visited the site on 11-8, 11-12-21, and had several conversations with the
construction team by telephone throughout the week.
This week the construction crew finished removing the floor coatings on the 08 stack, coating
removal is still in progress on the 01 stack. The 08 balconies were re-inspected and
marked for repairs, initial excavations are in progress to expose the reinforcement under
spalling near doors. Workers installed interior barricades by the shear windows inside
Units 504, 604, 704, 1005, and Penthouse 4 to prepare for window removal later on.
Initial excavations are in progress to repair concrete slabs under removed windows from
last week.
`�O� S P .
No. 50068
,o S1` TE OF
�0 �•'•�4 O R 110• �v
ii1/i, Fy,�� ••...... �d� `INC
r
'1�;ili�����b ;li• ,.11
t
,r
r
View of edge spalls observed on the Penthouse 1 balconv
ZY/Of
�No
\,1 S t� ! !� r !i rF ...
:a{, ,0 :111IIII1��1/1
If jig
View of corroded reinforcement exposed after the core-mounted handrails were removed on the Unit 1008
balconv
View of the floor coatings removed and marks for repair on the Unit 808 balcony
I'
I
View of the floor coatings removed on the Unit 708 balcony
'1 r
J
i
View of an edge spall marked for repair on the Unit 608 balcony
I
.r�r.
+ f
a
View of the floor coatings removed and marks for repair on the Unit 608 balcony
s
4 `• y
f
Ns
y
View of surface spalls marked for repair next to a door on the Unit 508 balcony
yJ h
1,44
! 7 f A
' «�� ,�t yid•:.y` 4 '
Z.
View of severely corroded reinforcement and spalling observed next to another door on the Unit 508 balcony
F
11V ,
f
i
AM
/ 1
View of floor coatings removed and marks for repair on the Unit 408 balcony
View of corroded reinforcement exposed by a core-mounted handrail post on the Unit 308 balcony
fr 1 �•
1
View of the floor coatings removed on the Unit 208 balcony
25 South Brevard Avenue,
KEYSTONE cocoa Beach, FL 32931
Vroject
• • •
ENGINEERING &CONSULTING, INC.
co
Progress Inspection Report #27
Permit #SLC 2102-0371
Name: Barclay Beach Club Progress Report thru 11-19-21
Project Address: 2800 SR-A1A, Hutchinson Island Inspection Visits: 11-19-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: 01 stack coating removal and marks for repair, 08 stack initial
excavations, 05/04 stack paint and shutter track reinstallations, Unit 904, 1004, and PH3
window repairs
INSPECTOR'S REPORT
Keystone Engineering visited the site on 11-19-21 and had several conversations with the
construction team by telephone throughout the week.
This week the construction crew finished painting the floors on the 05 balcony stack, shutter
track reinstallations are now in progress on the 04 and 05 stacks. Workers removed all
the floor coatings on the 01 stack and the balconies were re-inspected and marked for
repairs, initial excavations are now in progress. The crew excavated spalled concrete
under the shear windows for Units 904, 1004, and Penthouse 3. Workers are detailing
the existing reinforcement and installing forms to prep for cast backs.
ss� �`.�S P 0�C%
°r• �GENS •••.� s
F :
.. •
No, 50W
* 7•
a
MTE of r w
OR \
/111t1111111111
I i 7
• � w
" {
•�i
Y
I
View of the floor coatings removed and marks for repair on the Unit 1001 balconv
:a
1�
View of the floor coatings removed on the Unit 901 balconv
TTl"m
1 ri. T} i1 Y it.i RC4,5 / J ,Y�l 72• ifj�i�`I•I,l! � i'I, '/
011
.1i�. ••f`ffi` P•jflf:�L';jf;ll',f.�! '�f' l!" ,..
16
t'
.,.�" �' a ,�. � /{K9} yy�. p{�{�(. �♦F• t:
' q} M 'may. ♦J yic.1 .. _
bw
Pli
1}:: •j' ,k u, .i5 9-
View of an edge spall caused by water intrusion through the core-mounted handrail post on the Unit 901
balcony
w�sr,
l
1
View of the floor coatings removed on the Unit 801 balcony
i
F
o �
1
_ . 11
View of an edge spall marked for repair on the Unit 801 balcony
r•
View of the floor coatings removed on the Unit 701 balcony
l `
a
View of corroded reinforcement exposed through a spall on the Unit 701 balcony
9
View of the floor coatings removed from the Unit 601 balcony
�k.
1 J.
r�
3
d
View of corroded reinforcement exposed after the handrail post was removed on the Unit 601 balcony
View of the floor coatings removed and marks for repair on the Unit 501 balcony
y !
{ 0
T 1
r
7
View of the floor coating removed on the Unit 401 balcony
e
View of several surface saalls marked for of several surface marked for repair on the Unit 401 balconvon the Unit 401 balconv
View of the floor coatings removed on the Unit 201 balcony
21,
`
View of an edge repair in progress under the Unit 804 shear window
View of an edge repair in progress under the Unit 904 shear window
South25 i • '
TA KEYSTONE Cocoa Beach, FL 32931
� • • •
ENGINEERING & : : :
CONSULTING, INC.
CP
_ v
Progress Inspection Report #28
A.
Permit #SLC 2102-0371
s
Project Name: Barclay Beach Club Progress Report thru 11-26-21
Project Address: 2800 SR-Al A, Hutchinson Island Inspection Visits: 11-22-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: 04 and 05 shutter track reinstallations, 01/08 stack initial excavations,
shear window edge repairs
INSPECTOR'S REPORT
Keystone Engineering visited the site on 11-22-21 and had several conversations with the
construction team by telephone throughout the week.
Work was short this week due to a holiday, no work was active on Thursday and Friday. The
construction crew finished reinstalling the shutter tracks on the 04 and 05 balcony
stacks. Workers cast back the edge repairs under the shear windows in progress last
week on the 04 stack. After all the shutters were removed on the 05 stack the crew
applied foam to existing cracks from the spalling under the windows, slabs were
inspected and marked for repairs. Initial excavations are still in progress on the 01 and
08 stacks, when the damaged areas are exposed the reinforcement under sliding glass
doors will be inspected.
\e``�1�llitill l /
* f No. 5M8
4 i STITE OF
4 pr� w ;
V/// `4I O N A L r4`11``���
�/II1NIItf111��
�� i�t 4
s
View of edge spallin
g marked for repair und
er the Penthouse 4 window
t .
Y
View of edge spalling marked for repair under the Unit 1005 window
i
aN
View of edge spalling marked for repair under the Unit 905 window
r
View of additional soallinit marked for repair under the Unit 905 window
� f
S
1
View of edge spalling marked for repair under the Unit 805 window
View of edge spalling marked for repair under the Unit 605 window