Progress Inspection Report #17
Permit #SLC 2102-0371
Project Name: Barclay Beach Club Progress Report thru 9-10-21
Project Address: 2800 SR-A1A, Hutchinson Island Inspection Visits: 9-9-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: Unit 405, 505, and Penthouse 4 repairs, 04 stack edge stucco
applications, 07 stack texture prep
INSPECTOR'S REPORT
Keystone Engineering visited the site on 9-9-21 and had several conversations with the
construction team by telephone throughout the week.
The construction crew installed interior barricades and removed sliding glass doors on the Unit
505 balcony. New excavations were completed for Units 405 and 505 and workers
detailed the existing reinforcement. The crew also excavated a new edge repair on the
Penthouse 4 balcony, cast backs are in progress for these units.
Stucco applications are in progress for edge repairs on the 04 stack. Workers are prepping the
floors of the 07 stack for waterproofing and texture applications.
A1
�/
��•' �CENSF'•�
. No. •k
A : S'O� OF
ao
o �
Y//" 's/O NAL "`a
I �
c
'J
fi
View of surface repairs in progress under sliding glass doors on the Unit 505 balcony
r�
�i
\ t
View of additional surface repairs in progress under sliding glass doors on the Unit 505 balcony
i
4 �"11•
r
/r
,y_- x� _�, � i .eye• .J /''
t
View of surface repairs in progress under a door on the Unit 405\balcony
NW,
Y
Additional view of surface repairs in progress under doors on the Unit 405 balcony
J
windowView of a surface repair tunneled under the on the Unit 40
r
View of additional surface repairs in progress under doors on the Unit 405 balcony
I
1 17 l
View of the stucco applications in progress on the 04 stack
. South
KEYSTONE Beach,. .
. .
ENGINEERING &� : : :
�r
CONSULTING, IN('.
Progress Inspection Report #18
Permit #SLC 2102-0371
Project Name: Barclay Beach Club Progress Report thru 9-17-21
Project Address: 2800 SR-A1A, Hutchinson Island Inspection Visits: 9-17-21
Prime Contractor: Blue Coast Construction
Superintendent: Rafael Rodriguez
Activities in-progress: 04 stack handrail removal and shutter track reinstallations, Unit 205, 305,
405, and PH5 excavations and cast backs.
INSPECTOR'S REPORT
Keystone Engineering visited the site on 9-17-21 and had several conversations with the
construction team by telephone throughout the week.
Handrail removal and shutter track reinstallations are in progress on the 04 stack. Workers
removed all the handrails and are excavating any remaining metal from the cored in
posts. Shutter tracks were reinstalled on the ceilings, floor tracks will be reinstalled later
when the floor is ready.
New excavations were completed on the Unit 203, 305, and Penthouse 5 balconies. Workers
adjusted a swing stage in order to access a spalled edge on the Penthouse 5 balcony.
The crew detailed the existing reinforcement, installed forms, and cast backs were
completed. Workers are grinding the floors, applying stucco, and power washing the 07
stack to prep for the waterproofing and knockdown textures.
if No. *068 ': .
STXTE 4F
r w
0P:
����✓/��s�O NA l��?G\\\\�\`\\
sO/Mil1111110\\
s
t
� 1
f
IL
View of a surface repair in progress on the Unit 205 balcony
View of an additional surface repair inView of an additional surface repair in progress on the Unit 205 balconyon the Unit 205 balcony
Y View of a full depth and surface repairs in progress on the Unit 205 balcony
s
View of an edge repair in progress on the Unit 305 balcony
I
1
}
{
t '
View of surface repair in progress on the Unit 305 balcony
':f`,
F � �
t
q
7
!n'
tl�ti Y'
View of the Unit 404 column repair cast back
� �• . : �' a .. •,. ..•sue,##� `
je
E \
y
View of the handrail removal in progress on the Unit 404 balcony
1
View of the ceiling shutter track reinstalled on the Unit 404 balcony
r
ti
tt
r
View of the handrail removal in progress on the Unit 304 balcony
a
t
View of the stucco applications in progress for the large edge repair cast back on the Unit Penthouse 5 balcony
r.
�I l
S
i
View of a worker power washing the 07 stack windows
i
-- s
View of the form installation View of the form installation progress for cast backs on the 05 stack cast backs on the 05 stack