HomeMy WebLinkAboutShur-GardHUForceHTunderlayTech
Mule-Hide Products Co., Inc. Page 1 of 3 PDS 09-1501
Product Data Sheet
Shur-Gard MU Force HT
DESCRIPTION Feb 2021
Shur-Gard MU Force HT is fiberglass reinforced SBS polymer modified,
high-temperature underlayment with a unique slip-resistant film surface for
use under metal roofing materials. Approved to perform up to 250°F, this
product provides additional protection in high temperature applications.
Conforms to ASTM D1970.
BASIC USES
• Specifically designed as an underlayment for high temperature applications.
• Approved for use under metal panels and mechanically attached tile.
TYPICAL PHYSICAL PROPERTIES
Physical Properties and Typical Performance
Physical Property ASTM Testing Method Typical Results
Maximum load MD/CD min D2523 / D1970 ≥ 25 lbf/in
Elongation at break D2523 / D1970 ≥ 10%
Adhesion to plywood, min @ 40°F D903 / 1970 ≥ 2.0 lbf/ft
Adhesion to plywood, min @ 75°F D903 / D1970 ≥ 12.0 lbf/ft
Low temperature flexibility, max D1970 Pass
Moisture Vapor Permeance E96 ≤ 0.1 U.S. perms
Sealability Around Nail D1970/ D7349 Pass
Waterproof Integrity of Lap Seam D1970/ D7349 Pass
PACKAGING
28 rolls per pallet, roll size is 39 3/8” x 66’
Weight: 68 lbs per roll (nominal)
Coverage: 200 SF per roll
Thickness: 60 mils
FEATURES AND BENEFITS
• Unique “textured” slip resistant surface – greater feeling of safety and security while walking.
• Exceptional SBS rubberized adhesive backing – unique modified bitumen formulation with wide
temperature installation range and great nail/screw seal ability.
• Highly pliable fiberglass mat reinforcement – conforms easily to valleys, corners and angles.
• 180-day UV exposure – longer dry-in time and greater protection from temporary exposure.
• Florida Building Code, Miami-Dade County, and Texas Department of Insurance approvals are pending.
STORAGE & HANDLING
Shur-Gard MU Force HT membranes should be stored in their factory applied packaging. It is recommended
that self-adhered products be stored inside a dry, protected warehouse at a temperature not exceeding 110°F.
Mule-Hide recommends a maximum of 2 levels of stacking of all self-adhered products while in protected
storage as stacking higher may damage the material.
Mule-Hide Products Co., Inc. Page 2 of 3 PDS 09-1501
Product Data Sheet Shur-Gard MU Force HT
APPLICATION TEMPERATURES
Apply only when material interface temperatures are 40°F and rising. Lower temperatures will result in lower
tack and reduced adhesion. If low temperatures are present during installation, product may be back nailed to
hold sheet in position during installation. As temperatures rise, adhesive will activate and bond with substrate
and seams.
APPLICATION
PREPARATION:
• Ensure the deck is dry, smooth and without voids or unsupported areas. Remove any existing nails,
fasteners or staples. All decayed, rotting, rusted or broken materials must be removed and replaced
before installing roof underlayments.
• Deck must be in sound condition, stable and secured to sound framing with the correct fasteners, clips
and spacing as per local building codes and or roofing manufacturers’ published specifications.
• If using new OSB sheathing or plywood, a gap should be left between sheets to allow for expansion
and contraction of new sheathing and prevent bulging and ridges from forming. Spacing should be
approximately 1/8" at end joints and 3/16" at side joints; however, verify with roof covering
manufacturer’s specifications.
• To help alleviate expansion and contraction of new OSB or plywood, allow the material to be pre-
conditioned prior to installation. Always ensure adequate roof and attic ventilation when applying
waterproofing membranes.
• Priming is not required for clean and dry roof decks made of wood. Concrete and masonry deck
surfaces require priming with Mule-Hide 121 Asphalt Primer.
INSTALLATION:
• Always follow local buildings codes for your specific region. Apply Shur-Gard MU Force HT
horizontally starting at the bottom edge of the roof with surface material side up. Roll out materials
onto existing roof deck and cut sheet to a suitable, workable length prior to placement.
• Align sheet with the lower edge of the roof (at the rake or side edge of roof) with the sheet extending
over 1/4". Applications may require tacking of nails along upper edge of membrane to hold in place.
• Standing above the sheet on the roof deck, remove top half of release film from the sheet and apply
firm even pressure from the center to the outer edges.
• Remove the release film from the remaining half of the sheet applying firm even pressure.
• Install working up the slope of the roof, ensuring a minimum overlap of 3" on side laps and 6" on end
laps. Where back nailing is required, be sure that all nails are covered by the overlapping next sheet.
• Immediately after installation, roll entire membrane surface, first rolling side to side across the
membrane then roll end to end. Be sure to roll end laps and side laps to ensure bonding of adhesive.
• Roller weight shall be a minimum of 70 lbs. for low slopes and approximately 28 lbs. for steep slopes.
VENTILATION:
• This product is designed to be an air, water and vapor barrier and will retard the flow of moisture vapors
when applied over the entire roof deck.
• In this application, ensure the roof and attic are properly vented. Lack of ventilation can result in
presence of moisture and deck deterioration and/or mold.
• Always consult a design professional to address potential moisture entrapment and condensation
issues.
• This can be in the form of ridge vents, solar / power vents, continuous ceiling vapor barriers or other
ventilation products. Proper ventilation will help alleviate these concerns. In hot and arid climates, heat
build-up can result in drying, cracking and premature aging of roofing materials and therefore venting
is also required.
Mule-Hide Products Co., Inc. Page 3 of 3 PDS 09-1501
Product Data Sheet Shur-Gard MU Force HT
PROTECTION & SAFETY
Mule-Hide maintains Safety Data Sheets on all of its non-exempt products. Safety Data Sheets contain health and
safety information for your development of appropriate product handling procedures to protect your employees
and customers. Mule-Hide Safety Data Sheets should be read and understood by all of your supervisory
personnel and employees before using Mule-Hide products in your facilities.
ADDIT IONAL INFORMATION
The information given on this PDS is subject to change without notice. Always check the Mule-Hide website at
www.mulehide.com for the latest information, changes and updates or contact Mule-Hide Products Co., Inc. at
800-786-1492.
DISCLAIMER
The statements provided concerning the material shown are intended as a guide for material usage and are believed to be true and accurate
at the time of printing. No statement made by anyone may supersede this information, except when done in writing by Mule-Hide Products
Co., Inc. Since the manner of use is beyond our control, Mule-Hide does not authorize anyone to make any warranty of merchantability or
fitness for any particular purpose or any other warranty, guarantee or representation, expressed or implied, concerning this material. This
product may be eligible for a Mule-Hide warranty, please check the Mule-Hide website at www.mulehide.com or contact Mule-Hide directly at
800-786-1492 for details. Buyer and user accept the product under these conditions and assume the risk of any failure, any injury person or
property (including that of the user), loss or liability resulting from the handling, storage or use of the product whether or not it is handled,
stored or used in accordance with the directions or specifications. Mule-Hide must be notified in writing of any claims and be given the
opportunity to inspect the alleged failure before repairs are made.