HomeMy WebLinkAboutReport Of GeothechnicalENGINEERING & TESTING, INC.
Phone: (866) 781-6889.Faa: (866).784-8550
www.floridaenginceringandtcsting.com
250 S.W.13'h Avenue
Pompano Beach, FL 3W9
REPORT OF
GEOTECHNICAL EXPLORATION
FOR:
Rick Friedrich
140 Blue Grotto Drive
Fort Pierce, Florida
PREPARED FOR:
Proposed Two Story Residence
260 Marina Drive ,
Fort Pierce, Florida
PREPARED BY:
Florida Engineering & Testing, Inc.
250 S.W.13*h Avenue
Pompano Beach, Florida 33069
(954) 781-6889
ON:
January 3, 2017 File Copy
Qrcdtity �.�QA ✓lsstrrance
4
TABLE OF CONTENTS
I.) DISCLAEWER
II.) COVER. LETTER
• SOIL STRATA$
• WATER LEVELS .
• FOUNDATION RECOA01ENDATIONS
M-) STANDARD (DYNAMIC CONE) PENETRATION LOGS).
IV.) FIELD SKETCH
V.) MAP 'OF SUBJECT SITE
VI.) GENERAL NOTES
• KEY CLASSIFICATIONS & SYMBOLS
VII.) MUTATIONS OF LIABILITY
DISCLAIMER
Our report findings are based on. present onsite soil conditions encountered. It is imperative that you
read our reports in their entirety and follow all recommendations as listed. Failure to follow our
recommendations, may result in delays and additional costs due to permitting agencies (Building
Department, etc.) withholding a Certificate of Occupancy for your proposed structure(s).
All recommendations shall be followed in order to receive a final certification, which may include but
not be limited to density testing per lift of fill material, demucking verifications, piling inspections. In
addition, these reports are for foundation analysis only and shall not be used for excavating, backfilling,
or pricing estimates.
Please schedule us at least 24 hours in advance for all tests and inspections. If you choose to use
another engineering firm for further testing and inspections, it is your responsibility to ensure that they
provide you with the proper certification in writing, as outlined in our report.
January 3, 2017
Rick Friedrich .
140 BIue Grotto Drive
Fort Pierce, Florida
RE:* SUBSOIL INVESTIGATION
Proposed Two Story Residence
260 Marina Drive
Fort Pierce, Florida
Dear Sir or Madam;
ENGINEERING & TESTING, INC.
Phone: (866) 781-6889 •Fax:. (866) 784-8550
www.floridaengineeringandtesting.com
2.50 S.W.13a` Avenue
Pompano Beach, FL 33069
Job Order No.:16-3934
Pursuant to your request, Florida Engineering & Testing, Inc., has completed a subsoil investigation on
December 23, 2016, at the above referenced site. The purpose of our investigation was to verify
subsoil conditions relative to the proposed structure(s) .foundation preparation and design. Our
recommendations are based on the assumption that the proposed structure(s) are as follows: two story
residence (approximately 3,000 square feet).
A total of two (2) SPT borings were performed according to ASTM D-1586 down to depth of thirty to
thirty-five feet (30' 35') (BEGL) below existing ground level (see attached field sketch for locations).
Based on our soil borings, the soil profile varies across the subject site (see attached SPT Test Boring
Report(s) for details).
Groundwater table elevation was measured immediately at the completion of the boring(s) and was
found -at depths ranging from six feet eight inches to six feet ten inches (6'8" to 6'10") BEGL..
Fluctuation in water levels should be anticipated due to surface runoff, tidal influences, seasonal
variations, varying ground elevation, construction dewatering and pumping activities in the area. Site
contractor must familiarize themselves with site conditions in the event groundwater controls and
dewatering is needed. The contractor shall make sure that groundwater levels on adjacent properties
are not affected by the contractors dewatering activities. Specialty groundwater contractors shall be
consulted for all work below the groundwater level.
Quality �,,3��/✓lesrsrance
Page 2
January 3, 2017 Job Order No. 16-3934
Rick Friedrich FILORXX3A
Proposed Two Story Residence
260 Marina Drive, Fort Pierce,.Florida:
The boring log(s) attached present(s) a detailed description of the soils encountered at the test
location(s). The soil stratification shown on. the boring log(s) is based on the examination of the
recovered soil samples and interpretation of the driller's field log(s). It indicates only the approximate
boundaries between soil types. The actual transitions. between adjacent soil types may be gradual.
Based on our understanding of the proposed structure and the information obtained from our field
boring log(s); we recommend the following procedures for foundation preparation:
1) Strip the entire construction areas plus five feet (5) past the outer perimeter of the structure of
topsoil and ground vegetation (when encountered) down to clean granular material.
2) Saturate and compact all construction areas with a vibratory roller to a minimum of 95% of the
A.S.T.M. D-1557 modified proctor method. Make a minimum of ten (10) passes with the
roller iii each direction.
3) Backfill construction areas to proper elevation if needed using a clean granular material placed
in lifts not to exceed twelve inches (12") in thickness and compacted as per item 2.
4) Care should be taken when using vibration in case of existing structures in the vicinity of the
construction area. If vibration cannot be used for compaction, static compaction may be
applied. However, in this case, the compacted' layers should not exceed six inches (6") in
thickness.
5) All construction fill material shall be clean granular soil; free of organics or other deleterious
material, and shall contain no more than twelve (12) percent fines passing a U.S. Standard No.
200 sieve (0.075mm).
6) Representative samples of the on -site and proposed fill material should be collected and tested
to determine the classification and compaction characteristics.
7) Verify. all densification procedures by taking an adequate number of field density tests in each
layer of compacted material and bottom of footing excavations. This must be scheduled
immediately after Tamp and Spray and/or Compaction but before steel placement. If
steel is already in -place, it must be removed from all areas to be, tested prior to
performing densities.
8) All Geotechnical work shall be performed under the supervision of a Geotechnical Engineer or
his representative.
9) After the installation of any plumbing and electrical piping; we recommend that the disturbed
areasbe recompacted and additional density tests be performed to verify proper compaction of
the disturbed areas.
Provided the above foundation recommendations are achieved and verified; it is our opinion that
the proposed structure can be designed for a shallow foundation system with a permissible soil
bearing pressure not to exceed 2,500 P.S.F. Bearing capacity certification requires satisfactory
completion and verification of all the above foundation recommendations.
(7)
Page 3 .
January 3, 2017 Job, Order No. 16-3934
Rick Friedrich
Proposed Two Story Residence
260 Marina Drive, Fort Pierce, Florida:
E 0 - IN ,
T7t
We recommend a minimum width of 16 inches for continuous footings and 30 inches for individual
footings, even though the soil bearing pressure may not be fully developed in all cases. We
recommend that the bottom of footings be at least 12 inches below the lowest adjacent finished grade.
It is our, opinion that the floor slab system may be constructed as a slab on grade. We recommend that
a vapor barrier be placed between the soil and concrete. We also recommend that the reinforcing steel
mesh be placed at the approximate center of the slab for tensile support. -
It was estimated that upon proper completion, long-term total settlements .should be on the order of
less than one inch. Differential settlements should be approximately one-half of the total settlement.
Provisions shall be made by the architect, engineer of record. and contractor to address differential
settlements when tying in new to existing structures. Mixing of different foundation types shall not be
used unless provided with expansion joints to address differential settlement. If applicable, the seawall
structure should be inspected to verify the structural integrity and prevent undermining due to the
piling installation or excavation operations.
Regardless of the thoroughness of a Geotechnical exploration there is always a possibility that
conditions may be different from those of the test location(s); therefore Florida Engineering & Testing,
Inc., does not guarantee any subsoil condition surrounding the bore test hole(s). For a more accurate
portrayal of subsurface conditions, the site contractor should perform test pits. The discovery of any
site or subsurface conditions during construction which substantially deviate from the information in
our subsoil investigation should be reported to us immediately for our evaluation. In accepting this
report the client understands that all data from this soil boring report is intended for foundation
analysis only and is not to be used for excavating, backfilling, or pricing estimates. The site contractor
must familiarize themselves with thejob site conditions prior to bidding.
As mutual protection to clients, the public, and ourselves, all reports are submitted as the confidential
property of clients, and authorization for publication of statements, conclusions, or extracts from or
regarding our reports is reserved pending our written approval. All work must be conducted under the
supervision of our Geotechnical engineer. All work shall be, conducted in compliance with the Florida
Building Code FBC and OSHA workers protection rules and all applicable Federal, State, County and
City rules and Regulations. '
Florida Engineering & Testing, Inc., appreciates the opportunity �to4 be 1of service to you at this phase of
your project. If you have any questions or comments, please'give„us A,call. We would be pleased to
help any way -'we can. It has been a pleasure working rward to doing so in the near
future.
�r s �rls?f}K,
Sincerely, '
Mark A. Mesiano, P.F,: `'r r' `
Florida Engineering 8c' Testing, Inc.
Florida Reg: No. 49202'
Certificate of Authorization No. 6923
SPT Test Borm` a Report
Client: Rick Friedrich. Hole No: B-1
Project: Proposed Two Story Residence Date: 12/23/16
Address: 260 Marina Drive Fort Pierce, Florida
Location: See Attached Field Sketch
I
Penetration 'IN" Value
01' 41 Dark Grayish Brown
Slightly Silty Fine Sand
�an�nui�i�uin�ii�
�ouA6.1
!ie��m�nmas
B rown Fine Sand
��wn7nrinnm�n
- 10' Brown Fine Sand with
Traces of Cemented Sands
�m■unni�nrm■n
Grayish Brown Fine Sand
�OIIIIAI►11AlIAlll■
�oni�u!�memWn
Fi-re Sand
�oiN!�eirynvnan
7
Fine Sand with Some S bell
Fragments
�011�lilIIIIIIIIINII�I
�AWII�IIIAIII�IIi
Cemented Sand
�manmrmnn�nnn�
�A�YIII
IYIIIIIIIBIII
�0n�aimoienmvn
�■NYINIIIIIMIIIII
Water Level: 618" BEGL
As a mutual protection to clients, the public and ourselves, all
reports are submitted as the confidential property of clients,
and authorization for publication of statements, conclusions or
Mark A. Mesiano, P.E. ,
extracts from or regarding our reports is reserved pending our r > J
written approval. Florida Engineering &,ilesting, Inc.
A =Auger/Straight Rod Florida,Reg. No: ,4820%2'.�l'',_'
Ref =Refusal Certificate of Authorization No. 6923
BEGL = Below Existing Ground Level
0 = Weight of Hammer
U
SPT Test Boring Report
Client: Rick Friedrich Hole No • B-2
Project: Proposed Two Story Residence Date: 12/23/16
Address: 260 Marina Drive Fort Pierce, Florida
Location: See Attached Field Sketch
Soil Descriptions
Penetration "N" Value
0' - 4' Light Brown Fine Sand with
�lANIIIIIIIIYIIIYIYII
Trace of Shell Fragments
�ain��uwi�u�un
'41- 61 Grayish Brown Slightly Silty'
Fine Sand
��Al1i�I�111A1A1111
��IIIIIIIIIIIIAYIIIIIAI
Grayish Brown Fine Sand
15'- 20' Grayish Brown Silty Fine
lSand
�mI�IIIIRIIAIII�INI
doll
�I�1�1�1111
�mum�s�rdrn�np
Water Level: 6'10" BEGL `' •' c; y 5° E.�
As a mutual :protection to clients, the public and ourselves, all
reports are submitted as the confidential property of clients, Mark A. Mesiano, Y.E. `
and authorization for publication of statements, conclusions or
extracts from or regarding our reports is reserved pending our Florida,Engineering.& Testing, Inc.
t. it:.
written approval. Florida Reg. No. 1 2, 02-
A = Augei /Straight Rod Certificate of Authorization No. 6923
Ref = Refusal
BEGL =.Below Existing Ground Level
0 = Weight of Hammer
�4G ! rrt^c. Or
LOT 13
OCCUPIED
RRC
La
CORAL COVE
156 ncl r rn r,+, 0 r
� oc°c�u1Fa
e
C
CO
N
a' B-2 R:
7" _h_
7025"�IFIR
(NO5D) ,
20' ASPHALY Ra40WAY
Lj bing maps
260 Marina Dr, Fort Pierce, FL 34949
FL
GENERAL NOTES
• Soil boring(s) on unmarked vacant property or existing structure(s) to be demolished should be
considered preliminary with farther boring(s) to be performed after building pad(s) are staked out:
• As a mutual protection ' to clients, the public and ourselves, . all reports are. submitted as the
confidential property of clients, and authorization for publication of statements, conclusions or
extracts from or regarding our reports is reserved pending our written approval.
• It is not our field inspector's responsibility to supervise, schedule, or stop any phase of the project.
His/her responsibility is limited by the duties stated in the contract.
• It is the client's responsibility to provide adequate safety for the site and personnel.
KEY CLASSIFICATIONS & SYMBOLS
Correlation of Penetration Resistance
Particle Size
with Relative Density and Consistency
Boulder
> 12in
Cobble
3 -12in
Dynamic Cone
Standard
Gravel
4.76mm - 3in
Penetrometer
Penetration
Relative
Sand
0.074mm - 4.76mm
(Penetrometer
mer
Dens i
Silt
0.005mm - 0.074mm
Resistance)
Blows)Clay
< O.00Smm
0 - 10
0 - 3
Very Loose
10 - 25
3- 8
Loose
Sands 25 - 45
8 -15
Firm
Modifiers
45 - 75
15 - 25
Very Firm
75 -120
25 - 40
Dense
0 - 5%
Slightly Silty/Clayey
> 120
> 40
Very Dense
5 - 30%
Silty/Clayey
30 - 50%
Very Silty/Clayey
0 - 6
0 - 2
Very Soft
0 - 2%
Very Slight Trace
Silts 6 - 15
2- 5 .
Soft
2 = 5%
Slight Trace
& 15 - 30
5 -10
Firm
5 -10%
Trace
30 - 45
10 -15
Stiff
10 -15%
Little
Clay 45- 90
15 - 30
Very Stiff
15 - 30%
Some
90 -150
30 - 50
Hard
> 30%
with
Rock Hardness Description
Soft Rock core crumbles when handled.
Medium Can break core with your hands.
Moderately Hard Thin edges of rock core can be broken with fingers.
Hard Thin edges of rock core cannot be broken with fingers.
Very Hard Rock core rings when struck with a hammer.
FLO . A
LIMITATIONS OF LLABILITY
WARRANTY .
We warrant that the services performed by. Florida
Engineering and Testing, Inc., are conducted in a .manner
consistent with the level . of skill and care ordinarily
exercised by members of the profession currently practicing
under similar conditions. No'other warranties, expressed, or
implied, are made.. While the services of Florida
Engineering & Testing, Inc., are an integral -and valuable
part of the design and construction process, We do not
warrant, guarantee, or insure the quality or completeness of
services or satisfactory performance provided. by other
members of the construction process and/or the construction
plans and specifications which we have not prepared, nor the
ultimate performance of building site materials.
As mutual protection to clients, the public and ourselves, all
reports are submitted as the confidential property of clients,
and authorization for.publication of statements, conclusions
or extracts from or regarding our reports is reserved pending
our written approval.
SUBSURFACE EXPLORATION
Subsurface exploration is normally accomplished by test
borings. The soil boring log includes sampling information,
description of the materials recovered, approximate depths
of boundaries between soil and rock strata and groundwater
data. The log represents conditions specifically at the
location and time the boring was made. The boundaries
between different,, soil strata are indicated at specific depths;
however, these depths are in fact approximate and dependent
upon the frequency of sampling. The transitions between
soil stratum are often gradual. 'Water level readings are
made at the time the boring. was performed and can change
with time, precipitation, canal levels, local well drawdown,
and other factors.
Regardless of the thoroughness of a Geotechnical
exploration there is always a possibility that conditions may-
be different from those of the test. locations; therefore
Florida Engineering & Testing, Inc., does not guarantee any
subsoil condition surrounding the bore test holes. For a
more accurate portrayal of subsurface conditions, the site
contractor should perform tests pits. If different conditions
are encountered, Florida Engineering & Testing, Inc., shall
be notified to review the findings and make -any
recommendations as needed.
LABORATORY AND FIELD TESTS
Tests are performed in accordance with . specific ASTM
Standards unless otherwise indicated. All criteria included
in a given ASTM Standard are not always required and
performed. Each test report indicates the measurements and
determinations actually made.
ANALYSIS AND RECOMMENDATIONS
The Geotechnical report is prepared primarily to aid in the
design of site work and structural foundations. Although the
information , in the, report is expected .to be sufficient for
these purposes, it' is not intended to determine the cost of
construction or to stand alone as construction specifications.
In accepting this report the client understands that all data
from the soil boring is intended for foundation analysis only
and is not to be used for excavating, backfilling or pricing
estimates. The site contractor must familiarize themselves
with the job site conditions.
Reportrecommendations are based primarily on ' data from
test borings made at the locations shown on the test boring
reports. Soil variations may exist between borings and may
not become evident until construction. If variations are then
noted, Florida Engineering & Testing, Inc., should be.
contacted so that field conditions can , be examined and
recommendations .revised if necessary.
The Geotechnical report states our understanding as to,, -the
location, dimensions, and structural features proposed of the
site. Any significant changes in the nature, design, or
location of the site improvements must be communicated to
Florida Engineering & Testing, Inc„'so that the Geotechnical
analysis, conclusions, and recommendations can be
appropriately adjusted.
CONSTRUCTION OBSERVATIONS
Construction observation and testing is an important element
of Geotechnical services. The Geotechnical Engineer's Field
Representative (Field Rep.) is the "owner's representative"
observing the work of the contractor, performing tests, and.
reporting, data from such tests and observations. The
Geotechnical Engineer's Field Representative does not direct
the contractor's construction means, methods, operations, or
personnel. The Field Rep. does not interfere with the
relationship between the owner and the contractor, and
except as an observer, does not become a substitute owner
on site. The Field Rep. is only collecting data for our
Engineer to review.
The Field Rep. is responsible for his/her safety only, but has
no responsibility for the safety of other personnel and/or the
general public at the site. If the Field Rep. does not feel that
the site is offering a safe environment for him/her, the Field
Rep. will stop his/her observation/ testing until he/she deems
the site is safe. The Field Rep. is an important member of a
team whose responsibility is to observe the test and work
being done and report to the owner whether that work is
being carried out in general conformance with the plans and
specifications.