Field Density Tests of Compacted Soils Method D-6938
Project: Proposed Residence - Lot 67, Creek'side A Date: August 31, 2018
Address: 8620 Cobblestone Drive, Fort Pierce
Area Tested: Building Pad
Material Type: Brown Sand with Traces of Shell
Client: D.R. Horton, Inc.
Address: 1430 Culver Drive NE IN
Palm Bay, FL 32907 �
Order #: 18DR778
Permit #: ' &. rz_
Tech: BK
Compaction Req.:
Proctor Method:
95%
ASTM D-1557
Test
#
TEST LOCATION
I
ob e
Depth
Elev.
Moist
%
Dry
Density
PCF
Proctor
Value
PCF
Optimum
Moisture
%
Compaction
Pass
1
Center of Building Pad
121'
FL
9.4
106.3
108.0
11.6
98.4%
Yes
2 ISW
Corner of Building Pad
12"
FL
6.7
106.7
108.0
11.6
98.8%
Yes
3
NE Corner of Building Pad
12"
FL
6.6
106.1
108.0
11.6
98.2%
'Yes
4
I
5
I
6
I
7
I
8
I
9
10
11
I
12
I
13
14
Remarks: See Reverse Side (Page 2 of 2) for Additional Information for Disclaimer
This is a Compaction Test only on;the top 12" of the pad and is not a verification bf Soil, 5WarinGjCapacity.
Legend for Elevation: ,
PR = Proofroll 1,2,3 = 1st, 2nd, 3rd Lift Submitted by:
SL = Springline FL = Final Lift Kzith LeBI'anc, P.E. '-
SG = Subgrade BG = Below Grade 1 Federal Engineering A Testing,: Inc.
BC = Basecourse BOF = Bottom of Footing Florida Reg. ado: 59394
TOP = Top of Pipe FG = Finished Grade Certificate, ouf,a5ihorization #5471
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property,of,clients, and authorization fcr,-publication of statements,
conclusions or extracts from or regarding our reports is reserved pending our written approval. A density test determlrias'the.degree of ccmpactiof of the tested layer of material
only. A density does not replace a soil bearing capacity determination. These'density tests do not certify the underlying soil materiels 6eicw th.O'.posed structure. The results
do not preclude or guarantee that future settlement and cracking will not occur. A soil boring test is required to certify thai ihb9underiying soils will supportthe proposed structure
without settlement. If no soil borings have been performed to verify the underlying soils, we recommend that soil borings be,perfonnbd to evaluate the suitability of the underlying
soil to support the proposed structure. After laying dormant for a period of 90 days or after heavy rain/storms, retesting must be perforined'on'this work.
PAGE 1 of 2
J f
Compacted 'Soils Metlio'd"D=6938 Disclaimer
Pursuant to your request, Federal Engineering & Testing, Inc. (FET) has performed a compaction test at the referenced
project on the reverse side. The purpose of our test,was to determine the degree of compaction of the tested layer of
material only. In no way shall a compaction test replace a soil bearing capacity determination. A soil boring test must be
performed by the client prior to construction to verify subsoil .conditions. Our scope of services only included testing the top
12" of added fill material. FET was not contracted to perform -supervision of the building pad preparation. This testing of the
added fill material does not include an analysis of the. underlying soil materials to determine if they are capable of supporting
the proposed structure without settlement. This density compaction test does not warranty any underlying soil materials or
conditions below the tested top 12 inches of material. If no soil borings have been performed in the location of the proposed
structure, we recommend performing soil borings below all foundation areas of the proposed structure to verify the underlying
soil conditions.
Environmental analysis of the soil materials is not part of the scope of services. If environmental analysis of the soils is
required, we can provide a proposal for performing an environmental analysis of the soil materials. The scope of services is
for determination of the degree of compaction of'the tested layer;of material only. No other analysis is implied or warranted.
Job project specifications were not available at the time the work was performed. Determination of the pass/fail compaction
results are based on current common industry requirements of 95% of the ASTM D-1557 standard for building foundations
and 98% of the AASHTO T-180 standard for paved areas such as roadways and parking lots. If different specifications are
required, Federal Engineering & Testing, Inc. shall be notified.
Our findings are relative to the date and areas of our site work and should not be relied upon to represent conditions on other
areas or dates. Any subsequent site disturbances due to water erosion, rain waters, construction activities, excavations,
overgrown, vegetation, traffic and other disturbances will void this test and the site must be re -compacted and re -tested prior
to construction.
As a mutual protection to clients, the public and ourselves, all reports are submitted are the confidential property of clients
and authorization for use, publication of statements, conclusions or extracts from or regarding our reports is reserved
pending written approval.
It has been a pleasure working with you and we look forward to doing so in the near future.
16
• ,- �'•-° .. yr
Page 2 of 2
a
RECEivea"Phone 954-784-2941
800-848-1919
ederal SEt g. � Department
art Fax 954 784 7875
L 4 8 TESTING INC. perrtt►tttn C:ke county www.fed-eng.com
250 SW 13th Ave Pompano Beach, FL 33069 St Lucie County
Field Density Tests of Compacted Solis Method D-6938
Project: Proposed Residence Lot 67, Creekside Date: August 31, 2018
Address: 8620 Cobblestone Drive, Fort Pierce, FL ! Order #: 18DR778
Area Tested: Building Pad
Material Type: Brown Sand with Traces of Shell
Client: D.R. Horton, Inc.
Address: 1430 Culver Drive NE
Palm Bay, FL 32907
Permit #: 1W - D 7 KZ
Tech: BK
Proctor Method:
P�
95%
ASTM D-1557
Test
#
TEST LOCATION
Probe
Depth
'
Elev.
Moist
%
Dry
Density
PCF
Proctor
Value
PCF
Optimum
Moisture
/o
Compaction
Pass
1
Center of Building Pad
12"
FL
9.4
106.3
108.0
11.6
98.4%
Yes
2
SW Comer of Building Pad
1211
I
iFL
6.7
106.7
108.0
11.6
98.8%
Yes
3
NE Comer of Building Pad
12"
i
FL
6.6
106.1
108.0
11.6
98.2%
Yes
4
i
5
6
i
7
8
9
10
11
12
13
�tt61l6r
14
r
Remarks: See Reverse Side (Page 2 of 2) for Additional Information for Disclaimer
This Is a Compaction Test only on the top 12" of the pad and is not a verification of Soil art p
Legend for Elevation:
PR = Proofroil 1.2.3 =1st, 2nd, 3rd Lift Submitted by:
SL = Springline FL = Final Lift Keith LeBlanc, P.E.'H
SG = Subgrade BG = Below Grade Federal Engineering.&�Teatil'�fr��'��C'
BC = Basecourse BOF = Bottom of Footing Florida Reg. No. 59394.,°/����, 0,®�
TOP = Top of Pipe FG = Finished Grade Certificate of Authorizatiorf'5{p�7�lr
As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and authorization for publication of'statements,
conclusions or extracts from or regarding our reports Is reserved pending our written approval. A density test determines the degree of compaction of the tested layer of material
only. A density does not replace a soil bearing capacity determination. These density tests do not certify the underlying soil materials below the proposed structure. The results
do not preclude or guarantee that future settlement and cracking will not occur. A soil boring test is required to certify that the underlying soils will support the proposed structure
without settlement. if no soil borings have been performed to verify the underlying soils, we recommend that soil borings be performed to evaluate the suitability of the underlying
soil to support the proposed structure. After laying dormant for a period of 90 days or after heavy rain/storms, retesting must be performed on this work.
PAGE 1 of 2