CITY OF PORT ST. LUCIE
UTILITY SYSTEMS DEPARTMENT
900 S.E. Ogden Lane
Port St. Lucie, FL 34983
I
GUIDELINE FOR ESTIMI TING NEW COMMERCIAL PR03ECT FEES
THIS FORM IS NOT AN APPLICATION FOR SERVICE
Inquiries regarding applications for service, or other questions regarding ser-
vice for existing or new comlmercial accounts should be directed to the Com-
mercial Development unit of Ithe Utility Engineering Division at the City of Port
St. Lucie Utility Systems. You may visit our office at 900 S.E. Ogden Lane, or
call (772) 873-6400.
DEFINITIONS
ERC - Equivalent Residential Connection. (1 ERC equals 250 gallons per day)
ERC Determination Table - Is a guideline adopted by City Council for deter-
mining the ERC value for commercial developments. If a development is not
listed on this guideline, the I ERC value is determined by a fixture unit method.
Fixture Unit Method - Fixture Units are based and listed in the Standard
Plumbing Code.
I
Water & Sewer Connection Charges — Charges are calculated per ERC.
PROCESSING FEES: A $250.00 processing fee is required for all commercial
service or development applications.
INSPECTION & PLAN REVIEW FEES: Fees are dependent upon total ERCs
i
WATER SERVICE:
Water Plant Capacity Fee: $885.00 per ERC
$885.00 x ERCs = $
Water Line Capital Fee: $500.00 per ERC
$500.00 x ERCs = $
- 1 -
10-27-'06 15:43 FROM -AM ENGINEERING 772-461-8880 T-289 P003/005 F-699
7
A. M. ENGINEERING AND TESTING,
3-5042b.MUSTRTA1; 33I SmB-f,.
.3.4946
F0kT.,PMRPPj FLORIDA
LocAL OFFIcE: (772) 461 -7508 FAX (772) 461-8880
MOISTURE - DENSITY RELATIONSHIP OF SOIL
er 27-�006
Client: &t'idget t, o�Iloru _6&66 Project No.:
'10 4
Project: oleander Warehouse
Conttad6r:'- Cli6f."
SAMPU bAlrk
Date'Sampled:
Octobei 1.3 ' -2oo6
Sampled'by. - :--R, Afik6
'
Location:
composite
Oevation- Base
Description:
Gray fine sand, little rock nodules
MPISTW DENSITY CURVE
1TEST &M wocowry^"
126
124
122
120+
4
6 8 10
Moisture, %
12,
AASHTOX 190
Technician:.
1V1. Barkley
Test Method .,
Preparation:
Dry
Hammer:
Mechanical
lHammer Face:
Sector
RESULTS
Dry Deas#y* .. .- - I
I ... 125.5,pcf
_
1 0ELt' " Moisture oisture ContContent*'70%
1
*Tkrrtaiiuiurftd6n ity is ie0Mdt60.V1b.k ft. hfidb6tiftwifirrioistore to
P
the neamst 0.1 % for infannation only. AASHTO calls for these to be
reported to the nearest whole number.
V
Distribution: Reviewed by:
Client -1 A M. EWINEERJNG AND TESTING, INC.
Paul C. Martin, P.R.
PM/ah Florida Registration No. 65051
Describe in general terms the proposed project,, system, or activity.
The subject project entails the construction of a 9,616 sq. ft. office building on 1.074 acres
-eit Port St. Lucie $ems:- /
of assoc«�t'eGQ ,
�GtUe-YAeo'
If there have been any re -application me ings, including at the project site, with regulatory staff,
please list the date(s), to tion(s), and nameo of key staff and project representatives.
Please identify by numbs any
denied for projects at the loc (ion
Agency Date
names, addresses and
(excluding applicant). P
lines. Attach additional s
1.
MSSW/Wetland resource/ERP/ACOE Permits pending, issued or
and a related enforcement actions.
Type,6f Application
codes of property i
attach a plan view
s if necessary.
3. 4.
ction Taken
proposed to occur in, on or over wetlands
ation to use state owned submerged lands
ental Resource Permit. Please provide the
hose property directly adjoins the project
the owner's names and adjoining property
10-27-'06 15:42 FROM -AM ENGINEERING 772-461-8880 T-289 P002/005 F-699
A. M. ENGINEERING AND TESTING, INC.
3 504 INDUSTRIAL 33'D STREET
FT. PIERCE, FLoRIDA 34946
LdCALOPPiCE: � (772) 461=7508 ` FAj :=(712) 461-8886
DENSITY OF SOIL IN PLACE
Client: Budget Copt tructiok
Contractor: Client .
Site: Oleander Warehouse
Subgrade
Report Date:' 10/27/06
Technician: R, Ankrom
Test
No.
Date
Tested
Location
Eleva-
tion "
(ft)
Field
Test Results
proctor
Max
Dry
Density
e
Com action
'Pass/
Fail
HCP
H2O
%
' Dry ..,-
Density
c
Pe6be
Depth
in
In.
place
'Min'
Req'd
10545
10/23/06
Map_ i_;c 6ation;1
Sub, de
60+1
12
118.5 .
. 98+
,9$
P
10546
,� 2
��
60+
.
12
I1$.5 V
9$+
98
p
IOS47
._.��... ,
��
=60+
...
; ,.,_.,..
12 ��
. 118.5
98+.
98
P
10548
a
:: „
6U+
12
118:5
98+'
98 __...
P
Remarks:
• The field density tests were performed in general compliance with ASTM D 2922, Density of Soil in Place by Nuclear Method
• The Hand Cone Penetrometer (14CP) test, in conjunction with information about the soil type, is empirically correlated to the
relative density of the subsurface soils.
• The laboratory Proctor maximum dry density was determined in accordance with A ,SHTO T 180.
Distribution: Reviewed by:
Client - 2 A. Gld\TtJFW NG AND TFSTING, INC.
106
Paul C. Martin, P.E.
Florida'Registration N6. 65051 :
llServer-mtrelcotrtpaHYIPOr: Pierce 0fce1N'e(Apps► J2 MR 40G 900,KlConu rercialJobs►r+tsdget Constrnctiont0leander Warehoase10545-10548
Density
I
Rates effective 10-1-06
Sewer Security Deposit: Base Id on Meter Size $
Meter Size
5/8" x 3/4" $ 118.00
1" � $ 275.00
1 1/, 2" $ 925.00
2" $1,175.00
3" $1,400.00
4" and above (2 months estimated bill)
Multi -family $ 40.00 Per Unit (Master Meter)
SEWER GRINDER FEES: The Utility Department has two approved low flow
system designs:
• One, a single-phase I duplex system, is typically used with a single
building structure, with low flows (4.0 ERCs / 1,000 GPD or less).
• The second system, !a 3-phase duplex system, is typically used with
higher flow applications (greater than 1,000 GPD).
Each system design is site specific and is determined once applicable service
applications and plans have been submitted for utility review. Applicants must
retain a professional engineer'to design the system in accordance with City of
Port St. Lucie Utility Systems, Technical Specifications and Construction Stan-
dards and applicable regulatory agency standards.
The Utility supplies the single -;phase duplex grinder system. Current costs (in-
cludes basin, pumps, and electrical control panel) are:
Grinder Size
6' De th
8' Depth
10' Depth
Price
$4,335.00
$4,710.00
$5,150.00
A licensed contractor retained by the developer must supply all other miscella-
neous materials and labor costs to install single-phase systems.
For 3-phase systems, the developer or applicable licensed contractor is respon-
sible for obtaining the grinder system from an authorized Myers pump represen-
tative.
MONTHLY BILLINGS: The monthly usage bills for properties located outside of
the City's limits in unincorporated St. Lucie County are surcharged 25%.
- 3 -
10-27-'06 15:43 FROM -AM ENGINEERING 712-461-8880 T-285 P005/005 F-699
A. M. ENGMERING AND TESTING, INC.
3504 IMUMMAL 3r SMET
FORT JPMRC�, FLOMA'34946
(772)4617508OFFicE (772)461-aasoFax
Rates effective 10-1-06
Meter Installation Fee:
Water Security Deposit:
Based on Meter Size
Mete'r Size
5/8"'x 3/4'
V,
1 1/2"
2" I
3" and above
Based on Meter Size
Meter Size
5/8" x 3/4"
1" -
1 1/2"
2„
3„
4" and above
Mufti -family
$
$ 350.00
$ 400.00
$ 600.00
$1,100.00
(T.B.D. at time of application for service)
$
$ 45.00
$ 95.00
$ 150.00
$ 425.00
$ 500.00
(2 months estimated bill)
$ 10.00 Per Unit (Master Meter)
LANDSCAPE IRRIGATION SERVICE: ERC's are determined using a specific
design formula (total number of heads / gal. per. min. per head / min. per day /
days per week). The Water Plant Capacity Fee for irrigation service, meter
charges, and deposits are calculated the same as for potable water service.
I
FIRE PROTECTION / SPRINKLERS: ERC'S are based on project's professional
engineering design for required fire line/s and interior sprinkler system.
SEWER:
Sewer Plant Capacity Fee: $1,112.00 per ERC
Sewer Line Capital Fee:
$1,112.00 x
$390.00 per ERC
$390.00 x
- 2 -
ERCs = $
ERCs = $
10-27-'06 15:43 FROM -AM ENGINEERING 772-461-8880 T-289 P004/005 F-699
A. M. ENGINEERING AND TESTING9 INC.
3 504 INDUSTRIAL 33RD STREET
FT, PIERCE, FLORIDA 34946
LocALOFFICE: _;(772) 461-7508 :FAX: ; (772)A61=$8$D -
I DENSITY OF SOIL IN PLACE
Client: Budget Construction, Report Date: 10127/06
Contractor: Client Technician: R. Ankrom
Site: Oleander Warehouse
Base
Test
No.
Date
Tested
Location
Eleva-
tion
00
Field
Test Results
Prroctor
Max
Dry
Density
{ Cf)
Com action
pass/
Fail
HCP
920
: , Dry
Density
e
Probe
Depth
In
In
Place
(%)
Min
Req'd
10550
10/23/06
Map Location ,1
Base
5.8
'124.1
6
125.5
98.9
98
P
10551
1,
6.5
123,5
6
125,5
98.4
98
P
10552
; ' 3
6.1
123.0
6
125.5
98.0
98
P
10553
4
6,3
123,2
6
125.5
98.2
98
P
I
4.4
t
Remarks:
• The field density tests were performed in general compliance with ASTM D 2922, Density of Soil in Place by Nuclear Method
• The Nand Cone Penetrometer (IICP) test, in conjunction with information about the soil type,' is empirically correlated to the
relative density of the subsurface soils.
• The laboratory Proctor maximum dry density was determined in accordance with AASHTO T 180.
Distribution: Reviewed by:
Client - 2 A. M. NGINEERING AND TESTING, INC.
4 4 /427-7/OcO_
Paul C. Martin, .k
Florida Registration No. 65051
S:IFortPierce OfcelNetAPPALIMELOG BOOKICoennierciolJobsl a&eConstruction101ednderWarehousel105$0-10553Density,Base
October 16, 2006
Derek Foxx
St. Lucie County Fire District
2400 Rhode Island Ave.
Fort Pierce, FL 34950 � '..-",,
Re: National Wat orks
Lots 41, 42, 43, Block
Fire Distric Review
Dear Mr.
Kings Highway Industrial Park Unit 2
The project co ists the additi of 21,747 sq. ft. of pavement at an existing light
industrial devel pm on 2.4 5 acres. The following are attached:
1. Application�orm & fee$217.50)
2. 3.5" Diskette\\
If you have any quest ns, lease call.
Sincerely,
Joseph T. Friscia, P. .
cc: File 06972slcf .doc
10-27-'06 15:42 FROM -AM ENGINEERING 772-461-18880 T-289 P0011005 F7699
A. M. ENGINEERING AND TESTING, INC.
4W 3504 INDUSTRIAL 33RD STREET
FORT PIERCE, FLORIDA 34946
LOCAL OFFICE: (772) 461-7508 FAX (772) 461-8880
Client: Budget Construction
Project: Oleander Warehouse
Contractor: Client
SAMPY,V T)A.TA
LIMEROCK ]BEARING RATIO
Report Date: October 27, 2006
Project No.:
Test No.: 10544
Date Sampled: October 23, 2006
Sampled by: R. Ankrom
Location: NW Corner of Parking
Elevation: Subgroe
Description: Brown fine sand, some shell, little silt and clay
MOISTURE DENSITY CUR'V1E
120
45 118
A 116
1144
6
Distribution:
Client - 2
PM/ah
8 10
Moisture, %
TEST METHOD'- FM 5-515
Technician:
J. Martin
Preparation:
Dry
Hammer:
Mechanical
hammer Face:
Sector
RESULTS
Maximum) Dry Dealt
118.5 pcf
Optimum Moisture Content
9.2 %
1
Limelrock Bearing Ratio (LBR)
68
4 *The maximum density is reported to 0.1 Ib.teu. ft. and optimum moisture
12 to the nearest 0.1 61. for information only. The FM calls for these to be
reported to the nearest whole number.
Reviewed by:
A. M. EN IN'EEWN'G AND TESTING, INC.
Ao//
Paul C. Martin, P.E.
Florida Registration No. 65051