February 26, 2021
PROJECT: Self Storage Kings Highway
REF: MJSP-11202025892
TO: Bethany Grubbs
FROM: Grant Chambers
Deficiency Review:
The following comments are offered based on plans dated February 1, 2021.
1. A legal access agreement for the southern driveway will be required before a site
development permit can be issued.
2. The driveway connection to Miramar Avenue does not meet the side property line
setback requirements. The driveway also does not meet minimum setback requirements
from the intersection for driveways allowing left turn movements serving uses generating
more than 50 vehicle trips per day. A driveway variance from the Board of Adjustments
will be required for the proposed location of the driveway on Miramar Avenue.
3. Property line cross sections should be provided for each property line. The typical cross
section appears to be only the east side of the property. Ensure that there is a flat area
at the base of the berm before reaching the property line.
4. Additional comments may be issued at time of Site Development Permit application
review.
5. For discussion regarding these comments, please contact myself at 772-462-2741 or
chambersg@stlucieco.org.