HomeMy WebLinkAboutFIELD - LAB REPORTl G1(Da �d
UNIVERSAL
- ENGINEERING -SCIENCES
Consultants In: Geotechnical Engineering • Environmental Sciences
Geophysical Services • Materials Testing • Threshold Inspection
Building Code Administration, Compliance Inspection & Plan Review
820 Brevard Avenue, Rockledge, FL 32955 - P: 321.638.0808 - F: 321.638.0978
UEb Project No.: 0310.1700251.0046
Date Typed: March 11, 2019
Construction Materials Testing Services
FIELD AND LABORATORY REPORT COVER PAGE SCA
Client: Ryan Homes By
1450 Centrepark Blvd Suite 340 UCfe C01 �"
West Palm Beach, FL 33401 nay
Project: Oakland Lake Subdivision Lot 55 _
5251 Oakland Lake Circle Permit`#1902_ 06 0 Ft. Pierce, St. Lucie County, FL
As requested, Universal Engineering Sciences, Inc. (LIES) representative(s) performed construction materials testing and/or
field inspection services on the above project. Testing results and/or inspection observations are reported on the attached
sheets. The contents of this package are summarized below:
Scope of Work
Work Order No. Date Type of Report
107621-1 1 02/28/2019 In -Place Density Test Report w/Activity Record
We hope this information is sufficient for your immediate needs. If you have any questions, please do not hesitate to contact
the undersigned.
Attachments (1)
Sincerely,
Universal Engineering Sciences, Inc.
Certificate of Authorization No. 00000549
Richard E.
c,�• tjCEN-4*%0, , Hoaglin, P.E.
2019.03.12
No.48798 —
15:34:12
STATE OF -04'00'
Richard E. Hoaglin, P.E.
FLORIDA
Professional Engineer No. 48796
This item has been electronically signed and sealed by
Richard E. Hoaglin, P.E. using a Digital Signature. Printed
copies of this document are not considered signed and
sealed and the signature must be verified on any electronic
copies.
ICC Email: cbugg@nvrinc.com; rhager@nvrinc.com: signtseal MAIL to ryan homes at 5369 Oakland Lake, Ft. Pierce, FL 32941
Revised May 2015
0
Po
M.
'
UES _ject No: 0310.1700251.0046
H
IV,j
- �_1�1 �'
UES DOCS No:
UES Report No:_ 107621-1 ARC 022819-
-ENGINEERING SCIENCES On -Site Time (hrs): 1.00
Consultants In: Geotechnical Engineering s Environmental Sciences Lab Time (hrs): 0.00
Geophysical Services • Materials Testing • Threshold Inspection Travel Time (hrs): 0.50
Building Code Administration, Compliance Inspection &Plan Review Total Time (hrs): 1.50
820 Brevard Avenue, Rockledge, FL 32955 - P: 321.638.0808 - F: 321.638.0978
Activity Record
Client: Ryan Homes
1450 Centrepark Blvd Suite 340
West Palm Beach, FL 33401
Project: Oakland Lake Subdivision Lot 55
5251 Oakland Lake Circle Permit #1902-0090, Ft. Pierce, St. Lucie County, FL
Date of Activity: Thursday, 28 February, 2019
Technician: Cliff Cherrnav
As requested, a Universal Engineering Sciences Technician was present at the above referenced project site for the purpose of
earthwork testing for the House pad.
While on site, the technician observed the general condition of the areas to be tested and performed 4 density test(s) for House
pad. All test(s) were performed in accordance with the ASTM D-6938 Nuclear Gauge Method and were found to meet the
project compaction requirements of 95% of the maximum dry density perASTM D-1557.
The Contractor was notified of the test results or a copy was left for their records.
TUN1VERSAL
Consultants In: eaEngineering• Environmental Sciences
Geophysical Servicrvicess - Materials Testing •Threshold Inspection
Building Code Administration, Compliance Inspection & Plan Review
820 Brevard Avenue, Rockledge, FL 32955 - P: 321.638.0808 - F: 321.638.0978
Uea Project No: 0310.1700251.0046
UES DOCS No:
IA-DT-02281-9
In -Place Density Test Report
Client: Ryan Homes
1450 Centrepark Blvd Suite 340
West Palm Beach, FL 33401
Project: Oakland Lake Subdivision Lot 55
5251 Oakland Lake Circle Permit #1902-0090, Ft. Pierce, St. Lucie County, FL
Area Tested: House pad
Type of Test: Field: ASTM D-6938 Nuclear Gauge Method Date of Test: 02/28/2019
Lab: ASTM D1557 Modified Proctor
Technician: Cliff Cherrnay
Requirements: 95% of Proctor maximum dry density. These tests apply to the fill and/or surficial soil conditions
only and do not address the condition of the underlyinq soils below the tested depths.
Test
No.
Location of Test
Range
Depth
(inch)
Proctor
(2)
Field Dry
Density
(PCF)
Field
Moisture
%
%
Compaction
Comments
(3)
1
NM/ Test
0-1 ft
12.00
23343
109.0
12.0
100
A
2
N/E Test
0-1 ft
12.00
23343
108.8
12.4
99
A
3
S/E Test
0-1 ft
12.00
23343
108.0
11.6
99
A
4
S/1N Test
0-1 ft
12.00
23343
108.8
12.3
99
A
(1) Ref. Datum: 0 = Top of Final Grade
(2)
Maximum
Optimum
Proctor
Dry
Moisture
#
Density
Content
23343
109.5
12.5
This test was performed without deviation from ASTM procedures.
(3) Comments Key
A. Compaction meets min. requirements
B. Compaction does not meet min. requirements
C. Moisture does not meet requirements
D. Recompaction required
E. Recompacted, Retested, Meets Requirements
This report shall not be reproduced, except in full, without the written approval of Universal Engineering Sciences.