HomeMy WebLinkAbout9400 S OCEAN DR BLDG B - PAPERWORKM L Engineering, Inc.
CONSULTING ENGINEER
11 6-43rd Ave. SW
VERO BEACH, FLORIDA 32968
Phone (561) 569-1257
Fax (561) 569-4041
OCEAN TOWERS
PROJECT NUMBER
COPY/FAX TO Mr. Jose Vasquez
THRESHOLD INSPECTION REPORT
PROJECT NAME Ocean Towers Condominiums
CLIENT Ocean Towers Condominiums
CONTRACTOR Trimble Contracting, Inc.
INSPECTED BY Michael Lue/Angel Miranda
St. Lucie County Bldg. Dept
Trimble Contracting, Inc.
fil 00 --
LDEC W22
DATE 12/14/99
LOCATION Jensen Beach, Florida
FOREMAN . Phil Trimble
WEA . THER Clear
WORK INSPECTED SCANNED
4th floor balcony replacement in progress BY
'St. Lue'o C.-Ounty
Reinforcing steel was inspected and the follwing defficeincies were noted:
#4 bar is to be added to splice the existing #4 bar which was cut at the north side of the elevator.
2#4 bars to be placed at column band 57
2#4 bars to be placed at column band 53
1#4 bar to be placed at colunnn band 55
2#4 bar to be added at column band 62
1#4 bar to be added at column band 63
2#4 bars to be added at column bamd 65
Per Engineer of Record the mead electrical cans are to remain and bar coated.
ACTION REQUIRED
All reinf. shall be placed prior to concrete
INSPECTOR/
M L Engineering, Inc.
CONSULTING ENGINEER
116-43rd Ave. SW
VERO BEACH, FLORIDA 32968
Phone (561) 569-1257
Fax (561) 569-4041
PROJECT NUMBER 99-259
COPY/FAX TO Mr. Jose Vasquez
OCEAN TOWERS CONDOME14JUMS
THRESHOLD INSPECTION REPORT
PROJECT NAME Ocean Towers Condominiums
CLIENT Ocean Towers Condominiums
CONTRACTOR Trimble Contracting, Inc.
INSPECTED BY
Michael Lue
St. Lucie County Bldg. Dept.
Trimble contracting, Inc.
DATE 12110/99
LOCATION Jensen Beach, Florida
FOREMAN Phil Trimble
WEATHER Clear SCANNED
nV
qt I I inie couMy
WORK INSPECTED
4th floor balcony replacement in progress
Reinforcing steel was being placed but not complete.
Corroded reinf. have been removed and the remaining dowels h
ave been cleaned and coated. Additonal
dowels have been epoxy anchored.
The necessary reinforcing was discussed with the contractor and the engineer of record as shown on
the permit and as built plan.
Ail reinforcing are to be placed as indicated on the plan per the Engineer of Record.
The existing corroded metal conduit and junction boxes have been replaced with new pvc conduits,
however the new electrical junction boxes are galv. metal and are to be removed and replaced with pvc
boxes.
ACTION REQUIRED
Call for steel inspection when all reinforcing are in place and complete.
��/' -06--e-
INSPECTOR/
M L Engineering, Inc.
CONSULTING ENGINEER
11 6-43rd Ave. SW
VERO BEACH, FLORIDA 32968
Phone (561) 569-1257
Fax (561) 569-4041
PROJECT NUMBER 99-259
COPY/FAX TO Mr. Jose Vasquez
St. Lucie County Bldg. Dept.
Trimble Contracting, Inc.
file
PROJECT NAME Ocean Towers Condominiums DATE 12/15/99
CLIENT
Ocean Towers Condominiums 1 0 k M ;A
LOCATION enSen eac , or a
CONTRACTOR Trimble Contracting, Inc.
INSPECTED BY Michael Lue/Angel Miranda -
; Is] 1.4 =1 kyj F11 IN
Phil Trimble
WEATHER Clear
BY
WORK INSPECTED I St.r Lucie County
4th Floor balconv reDlacement
Approximately 12 cu ycls of 5000 psi pump mix with silica fume and corrosion inhibitor was placed.
Reinf along the balcony perimter was adjusted to allow for clearance for future hand rail posts.
One #4 bar was placed at column band 53 as directed in previous report.
3#5 dowels were placed for the masonry rail wall, one at each end and at center as directed by the
Engieer of Record.
Slab was placed with as much positive slope as allowed due to the location of the existing reinforcing at
the wall line.
One test cylinder was taken which was supplied by the Engineer of Record.
All concrete was placed in substantial conformance with the design specifications.
ACTION REQUIRED
INSPE&OR
M L Engineering, Inc.
CONSULTING ENGINEER
116-43rd Ave. SW
VERO BEACH, FLORIDA 32968
Phone (561) 569-1267
Fax (561) 569-4041
PROJECT NUM13ER 99-259
COPY/FAX TO Mr. Jose Vazquez
OCEAN TOWERS CONDOMINIUMS
THRESHOLD INSPECTION REPORT
PROJECT NAME Ocean Towers Condominiums DATE
CLIENT
Ocean Towers Condominiums
CONTRACTOR Trimble Contracting, Inc.
INSPECTED BY Michael Lue, P.E.
WORK INSPECTED
LOCATION
St. Lucie County Bldg. Dept.
Trimble Contracting, Inc.
file
DIE
l�' npr,
12/23/99
Jensen l31-ach—,F'1'cFH'jaS1.E COUMY, FIL
FOREMAN Phil Trimble
WEATHER
overcast �7vfvp/-,
4th floor baciony
Final Punch List
The existing aluminum handrails have been re -installed by coring the slab and grouting. All handrail
connections have been completed including ends and to intermediate masonry rail wall.
Concete curing compound has been placed and ready for waterproof membrane and finish as directed
bv the Association.
The following item was noted and is to be corected.
There is an exposed dowel at the underside of the new slab near the elevator which is to be chipped out
and cut back, coated with rust inhibitor and the concrete patched.
ACTION REQUIRED
See above
INSPECTA
M L Engineering, Inc.
I I 6-43rd Ave. SW
Vero Beach, Florida 32968
(561) 569-1257
Fax: (561) 5694041
December 27, 1999
DEC
Mr. William Hatcher, Building Official
St. Lucie County Building Department
2300 Virginia Avenue
Fort Pierce, Florida 34982
Re: Ocean Towers Condominium - Building A
Walkway Concrete Restoration
9490 S. Ocean Drive O'C4&&
Jensen Beach, Florida 4 & V 5�0
Engineer's Project No. 99-259 "Cie 0007ty
Dear Mr. Hatcher:
The structural repairs to the 4th floor walkway balcony is complete, and we have performed periodic
inspections during construction. Please refer to copies of the attached inspection reports dated from
December 10 through December 23, 1999 which were sent to your office after each inspection.
To the best of our knowledge the construction has been completed in substantial conformance with the
design specifications.
If you have any questions, please give us a call.
Respectfully,
Michael A. Lue;P.E.
Consulting E?ngi�,per,
cc: Mr. Jose Vazque--, P.E. - Ocean Towers Condominiums
12:24 4078715883 TRIMBLE CONTRAaING
-Submit
Ai—w
Z: to � the.. 4�ft_`4
;k:
pted -by.. SV;:-. LUcie County lk)�%rd 6,1:
A-103-3.2 4' A..
.v 1991 Rditio��,-
Lon, aLfid Nj*��Aoj 199i 'edition in
D MAR .11*,
ew OeAfq rj,
.J. I
IA I- 4K,JEI�m em 6VA w WA LIP
Address
do
type of�cmstruc
tion and genera,�'
wig , a , , co'O.Mm.60'the requLrementw,
)05, gtraj�w4 loads and stability.Lr.
o tb*. 8UJA4UV OffieW, Copies, 02)L
tvd by t, bo pcojecte Authortkod,
q thAt alt*bnetruction activitiej(�
wce wlthzl�.*tbia ptoject pldnei and-
13Y.
fengineer
(-seal)
PAGE 01
DEC 2 9 fqW
WORKS
November 22, 1999
Mr. William Hatcher, Building Official
St. Lucie County Building Department
2300 Virginia Avenue
Fort Pierce, Florida 34982
Re: Ocean Towers Condominium - Building A
Walkway Concrete Restoration
9490 S. Ocean Drive
Jensen Beach, Florida
Engineer's Project No. 99-259
Dear Mr. Hatcher:
M L Engineering, Inc.
11 6-43rd Ave. SW
Vero Beach, Florida 32968
(561) 569-1257
Fax: (561) 569-4041
00
Please be advised that M L Engineering, Inc has been retained to perform the Threshold Inspection
services for the above referenced project.
The scope of the project is limited to the inspection of the rehabilitation and reconstruction of the 4th
floor exterior common walkway of Building A only. Our inspections will be based on the attached
Project specifications as provided by the Engineer of Record, Mr. Jose Vasquez, P.E.
Copies of all inspection reports will be forwarded to your office upon completion of each inspection.
Upon final compl&fion of the structural components, a certification of compliance in accordance with the
design specifications or as duly noted will be provided.
The licenses may be required for your files and are noted as follows:
Michael A. Luc, P.E.
Professional Engineering No. 47520
Special Inspector Certification No. 1061
If you have any questions, please give us a call.
Respectfully',
........ . �1�
Michael A. Luc, P.E.
Consulting Engineer
cc: Mr. Jose Vasquez, P.E. - Ocean Towers Condominiums
M L Engineering, Inc.
I I 643rd Ave. SW
Vero Beach, Florida 32968
(561) 569-1257
Fax: (561) 569-4041
November 22, 1999
Mr. William Hatcher, Building Official
St. Lucie County Building Department
2300 Virginia Avenue
Fort Pierce, Florida 34982
Re: Ocean Towers Condominium - Building A
Walkway Concrete Restoration
9490 S. Ocean Drive
Jensen Beach, Florida
Engineer's Project No. 99-259
Dear Mr. Hatcher:
Please be advised that M L Engineering, Inc has been retained to perform the Threshold Inspection
services for the above referenced project.
The scope of the project is limited to the inspection of the rehabilitation and reconstruction of the 4th
floor exterior common walkway of Building A only. Our inspections will be based on the attached
Project specifications as provided by the Engineer of Record, Mr. Jose Vasquez, P.E.
Copies of all inspection reports will be forwarded to your office upon completion of each inspection.
Upon final completion of the structural components, a certification of compliance in accordance with the
design specifications or as duly noted will be provided.
The licenses may be required for your files and are noted as follows:
Michael A. Lue, P.E.
Professional Engineering No. 47520
Special Inspector Certification No. 1061
If you have any questions, please give us a call.
1999
Respectfully,
St. j.)cie County %blic %Yc-rKs
Michael A. Luc, P.E.
Consulting Engineer
cc: Mr. Jose Vasquez, P.E. - Ocean Towers Condominiums
I
ro w (:q mE �uv�m
I I I Nov 2 a 1999
/�
r
I
I
M L Engineering, Inc.
I I 6-43rd Ave. SW
Vero Beach, Florida 32968
(561) 569-1257
Fax: (561) 5694041
November 22,1999
Mr. William Hatcher, Building Official
St. Lucie County Building Department
2300 Virginia Avenue
Fort Pierce, Florida 34982
Re: Ocean Towers Condominium - Building A
Walkway Concrete Restoration
9490 S. Ocean Drive
Jensen Beach, Florida
Engineer's Project No. 99-25 9
Dear Mr. Hatcher:
Please be advised that M L Engineering, Inc has been retained to perform the Threshold Inspection
services for the above referenced project.
The scope of the project is limited to the inspection of the rehabilitation and reconstruction of the 4th
floor exterior common walkway of Building A only. Our inspections will be based on the attached
Project specifications as provided by the Engineer of Record, Mr. Jose Vasquez, P.E.
Copies of all inspection reports will be forwarded to your office upon completion of each inspection.
Upon final completion of the structural components, a certification of compliance in accordance with the
design specifications or as duly noted will be provided.
The licenses may be required for your files and are noted as follows:
Michael A. Luc, P.E.
Professional Engineering No. 47520
Special Inspector Certification No. 1061
If you have any questions, please give us a call.
Respectfully,
vl/��
Michael A. Lue, P.E.
Consulting Engineer
cc: Mr. Jose Vasquez, P.E. - Ocean Towers Condominiums
Code Compliance Division Permit Page 1
2300 Virginia Avenue
Ft Plerce, FL 34982
Phone: (772) 462-1553 Paic (772) 462-1148
Address OCEAN FDR (Unit#)
City/State/Zip IJENSEN BEACH FFL Owner(s) I Inactive -Do Not Use
Parcel # 3535-702-0000-000/0 Judscliction F�7 I Zoning Lot #
Future Land Use Residential Medium Subdivision Block
APPLICATION INFORMATION Add Building Application >>
Application Type [Master Permit w/subs Status Expired
Activity Type F Conflimation
Other - Specify I
Permit Type commercial Renovatio Date Applied Taken By FAngela Piemonte
Location Date Issued Issued By
Manual Valuation Date Finaled Finaled By
Job Address cii0r6)&Kh j Expiration
CONTACT INFORMATION Add Application Contact >>
Contractor
Contractor
1 10877 NEEL TRAYCE SUZANNE
Name ITRAYCE SUZANNE NEEL
Open C ontractor
Registration Fonn
Property Owner
Contractor
Business Name COMMERCIAL CONCRETE RESTORATION INC
I
I Phone
Fax
Addressi
Mobile
City/State/Zip
Pager
Email
Sub-Trixle Permit # Sub Trade Permit Status
Pe"ItType Taken By
Contractor Issued By
Company Finaled By
Owner/ Buildier Date Applied Finaled
Sub -Trade Job Description lssuedF---� Expiration
CONSTRUCTION INFORMATION
Units MR Floors Buildings Bedrooms # Bathrooms
Total Sq. Ft. Minimum Flood Elevation Flood Map Flood Zone
FCC
Job Description
NOC Required E] NOC Received [3 Driveway Permit
Setbacks (Actual) in Feet
Front F00-0-1 Back F00-0-1 Left Side OF-0-0-1 Right SideFo--ool
Code Compliance Division
2300 Virginia Avenue
Ft. Pierce, FL 34982
Phone: (772) 462-1553 Fax: (772) 462-1148
Permit Page I
Address OCEAN DR (Unit#)
City I State I Zip JENSEN 13EACH FFL—� oviner(s) I Inactive -Do Not Use
Parcel # 13535-702-0000-00010 Jurisdiction [��e County Zoning Lot #
Future Land Use I Residential Medium —1 Subdivision I I Block
Addillionall info GAVE TO CODE ENF - STILL NEED ENGINEER LETTER TO SIGN FINAL INSP PER BILLY HATCHER
05/14101 MSO*RCVD ENG LETTER RE:INSPECTIONS WILL BE PERSONALLY PERFORMEDOBY ENG FOR
THE STEEL ON SLABS, COLUMNS OF BALCONIES OK PEROJ. GUANCH 7/13/98 MS-OTAX ID FOR OCEAN
TOWERS A/B 353570100000004/353570200000007
Code Compliance Division
2300 Virginia Avenue
Ft. Pierce, FL 34982
Phone: (772) 462-1553 Fm: (772) 462-1148
98060563
Job
Inspection Notes
Inspections
Job Address 19400 OCEAN DR
Application Type
Activity Type
Date
Scheduled
Priority Status
0
PermitType [Commercial Renovation
Other
Stores Inspection Area
Phone 1(941) 514-4512 1
M� Expiration Date F02/01/2000
Inspector (Code
Inspector Date Inspected
100
Threshold/Affidavits
1
100
Threshold/Affidavits
1
140
Construction Rough Framing
1
999
Final Inspection
2
12/2011999
100
Threshold/Affidavits
1
Approved
Billy Hatcher
12/20/1999
12/27/1999
100
Threshold/Afridavits
I
Approved
Billy Hatcher
12/2711999
12/15/1999
100
Threshold/Affidavits
1
Approved
Billy Hatcher
12/15/1999
12/2311999
100
Threshold/Affidavits
1
Approved
Billy Hatcher
12/23/1999
Inspector Comments
Jose F. Vazquez, P.E.
Civil - Structural Engineering
Consulting Services
103 Champions Run
West Palm Beach, FL 33407
(561) 848-5726
�9-
OCEAN TOWERS CONDOMINIUMS
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACIL FLORIDA
PROJECT MANUAL
FOR
OCEAN TOWERS CONDOMINIUM ASSOCIATION, INC.
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACH, FLORIDA 34957
(561) 229-2229
XQ5 I
OC..N TOWERS CONDOMINIU.'�.---,-
9400 SOUTH OCEAN DRIVE
HUMBINSON ISLAND
JENSEN BEACK FLORIDA
PROJECT MANUAL INDEX
CONTRACT DOCUMENTS
Standard Form of Agreement Between Owner and Contractor for a Small Project, AIA A105-1993
General Conditions of the Contract for Construction of Small Project, AIA A205-1993
PROJECT SPECMCATIONS
PART 1 - GENERAL
1.00 PROJECT SCOPE
1.01 DESCRIPTION OF THE WORK
i.o2 SITE ACCESS
im COORDINATION
1,04 FIELD INSPECTIONS
1.05 SUBMITTALS
1.06 QUALITY ASSURANCE & WARRANTIES
1.07 DELTVIERY, STORAGE AND HANDLING
1.08 REFERENCES
PART2-PRODUCTS
2.00 MANUFACTURERS
2.01 MATERIALS
2.02 ACCESSORIES
PART 3 - EXECUTION
3.00 SHORING
3.01 CUTTING, DEMOLITION & PATCHING
3.02 SURFACE PREPARATION
3.03 REINFORCING STEEL REPLACEMENT
3.04 FORMWORK
3.05 MIKING
TM —C60N'-0WW7,
51 d*R*W5*
3.06 APPLICATION
3.07 CURING
3.08 CRACK REPAIRS
3.09 ELECTRICAL REPAIRS
3.10 &00#j�NISHING
3.11 CAULK & JOINT SEALANTS
Jose F. Vv4uez, P.E., CiU-Studural Engineuing & Consft=don SeMces, (561) 848-5726
Ak
_1111111111F
AIA Documew A205
General Conditions of the Contract
for Construction of a Small Project
1993 SMALL PROJECTS EDITION
ARTICLE 1
GENERAL PROVISIONS
1.1 THE CONTRACT
The Contract represents the entire and integrated agreement
between the parties and supersedes prior negotiations, repre-
sentations or agreements, either written or oral. The Contract
may be amended or modified only by a written modification.
1.2 THEWORK
The term "Work" means the construction and services required
by the Contract Documents, and includes all other labor, mate-
nals, equipment and services provided by the Contractor to ful-
fill the Contractor's obligations.
1.3 INTENT
The intent of the Contract Documents is to include all items
necessary for the proper execution'and completion of the
Work by the Contractor. The Contract Documents are comple-
mentary, and what is required by one shall be as binding as if
required by all.
1.4 OWNERSHIP AND USE OF ARCHITECTS
DRAWINGS, SPECIFICATIONS
AND OTHER DOCUMENTS
Documen�s prepared by the Architect are instruments of the
Architect*s service for use solely with respect to this project.
The Architect shall retain all common law, statutory and other
reserved rights, including the copyright. They are not to be
used by the Contractor or any Subcontractor, Sub-subconirac-
tor or material or equipment supplier for other projects or for
additions to this project outside the scope of the Work with-
out the specific written consent of the Owner and Architect.
ARTICLE 2
OWNER
2.1 INFORMATION AND SERVICES
REQUIRED OF THE OWNER
2.1.1 If requested by the Contractor, the Owner shall furnish
and pay for a survey and a legal description of the site.
2.1.2 Except for permits and fees which are the responsibility
of the Contractor under the Contract Documents, the Owner
shall obtain and pay for other necessary approvals, m�ements.
assessments and charges.
2.2 OWNER'S RIGHT TO STOP THE WORK
if the Contractor fails to correct Work which is not in accor-
dance with the Contract Documents, the Owner mav direct
the Contractor in writing EO stop the Work until the correction
is made.
2.3 OWNER'S RIGHT TO CARRY OUT THE WORK
If the Contractor defaults or neglects to carry Out the Work in
accordance with the Contract Documents and fails within a
seven day period after receipt of written notice from the
Owner to correct such default or neglect with diligence and
promptness, the Owner may, without prejudice to other reme-
dies, correct such deficiencies. In such case, a Change Order
shall be issued deducting the cost of correction from pay
ments due the Contractor.
2.4 OWNER'S RIGHT TO PERFORM CONSTRUCTION
AND TO AWARD SEPARATE CONTRACTS
2.4.1 The Owner reserves.the right to perform construction or
operations related to the project with the owner's own forces,
and to award separate c ontracts in connection with other por-
tions of the project.
2.4.2 The Contractor shall coordinate and cooperate with
separate contractors employed by the Owner.
2.4.3 Costs caused by delays or by improperly timed activities
or defective construction skall be'borne by tile party respon-
sible therefor.
ARTICLE 3
3.1 EXECUTION OF THE CONTRACT
Execution of the Contract by the Contractor is a representa-
tion that the Contractor has visited the site. become familiar
with local conditions under which the Work is to be per-
formed and correlated personal observations with require-
ments of the Contract Documents.
3.2 REVIEW OF CONTRACT DOCUMENTS AND
FIELD CONDITIONS BY CONTRACTOR
The Contractor shall carefully study -and compare the Contract
Documents with each other and with information furnished bx-
the Owner. Before commencing activities, the Contracto r
shall: (1) take field measurements and verifi, field conditions:
(2) carefully compare this and other information known to
OCopi-right 1993 hy The American Institute of Architects. 1�35 %cw York Avenue. Washington. D.C. 20006-5292. Reproduction of the material herein
ursubmanual quotation of its provisions with,tul the written permw%nin uf the AIA violate.% the copynght laws (if the United Staics anti will subject the violatur to
legal prosecution.
AIA DOCUMENT A205 - GENERAL CONDITIONS OF THE CO.%"MCT FOR CONSMUCTION—
SMALL PROIECTS EDITION - AIA' - ID1993 - THEAMERICAN INSTmirrF. UP ARCImT.CTS. 1735 NEW
YORK AVE.%1:E..NV., WASHINGTO%. D.C. 2(XXX,5292 - WARNING: Unlicensed photocopying
violates U.S. copyright laws and Will subject the violator to legal prosecution.
A205-1993 1
the Contractor with tile Contract Dot.ments: and (3)
prompth. report errors. i . nconsistencies or omissions discOV_
ered to theArchitect.
3.3 SUPERVISION AND CONSTRUCTION PROCEDURES
3.3.1 The Contractor shall supervise and direct the Work.
using the Contractor's best skill and attention. The Contractor
shall be solely responsible for and have control over construc-
tion means, methods. techniques. sequences and procedures,
and for coordinating all portions of the Work.
3.3.2 The Contractor, as soon as practicable after award of the
Contract. shall furnish in writing to the Owner through the
Architect the names of subcontractors or suppliers for each
portion of the Work. The Architect will promptly reply to the
Contractor in writing if the Owner or the Architect, aiter clue
investigation, has reasonable objection to the subcontractors
or suppliers listed.
3.4 LABOR AND MATERIALS
3.4.1 Unless otherwise provided in the Contract Document's
the Contractor shall provide and pay for labor, materials
equipment, tools, utilities, transportation, and other facilities
and services necessary for proper execution and completion of
the Work.
3.4.2 The Contractor shall deliver. handle, store and install
materials in accordance with manufacturers' instructions.
3.5 WARRANTY
The Contractor warrants to the Owner and Architect that:
(1) materials and equipment furnished under the Contract will
be new and of good quality unless otherwise required or per-
mitted bv the Contract Documents: (2) the Work will be free
from def�cts not inherent in the quality required or permitted;
and (3) the Work will conform to the requirements of the Con-
tract Documents.
3.6 TAXES
The Contractor shall pay sales. consumer. use and similar taxes
that are legally required A hen the Contract is executed.
3.7 PERMITS, FEES AND NOTICES
3.7.1 The Contractor shall obtain and pay for the building
permit and other permits and governmental fees. licenses and
inspections necessary, for proper execution and completion of
the Work.
3.7.2 The Contractor shall comply with anti give notices
required by agencies having jurisdiction over the Work. If tile
Contractor performs Work knowing it to be contrary to laws.
statutes. ordinances. building codes,. and rules and regulations
without notice to the Architect and Owner. the Contractor
shall assume full responsibility for such Work and shall hear
the attributable costs. The Contractor shall promptly notify
tile Architect in writing of any known inconsistencies in
the Contriict Documents with such gmernmental laws, rules
and regulations.
3.8 SUBMITTALS
The Contractor shall promptly review. approve in.wrifing
and submit to the Architect Shop Drawings, Product Data.
Samples and similar submittals required by the Contract Docu-
ments. Shot) Drawings, Product Data. Samples and similar sub -
Millais are not Contract Documents.
3.9 USE OF SITE ' -
The Contractor shall confine opemnons at the site to areas
permitted by law. ordinances. permus. the Contract Docu-
ments and the Owner.
3.10 CUTTING AND PATCHING
The Contractor shall be responsible for cutting. fitting or
patching required to complete the Work or to make its parts
fit together properly.
3.11 CLEANING UP
The Contractor shall keep the premises and surrounding area
free from accumulation of debris and trash related to the Work.
3.12 INDEMNIFICATION
To the fullest extent permitted hy law. the Contractor shall
indemnify and hold harmless the 6wner, Architect. Architect's
consultants and agents and employees of any of them from
and against claims, damages, losses and expenses. including
but not limited to attorneys' fees. arising out of or resulting
from performance of the Work. provided that such claim. dam-
age, loss or expense is attributable to bodily injurv, sickness,
disease or death, or to injury to or destruction of tangible
properry (other than the Work itself) including loss of use
resulting therefrom, but only to the extent caused in whole or
in part by negligent acts or oinissions of the Contractora Sub-
contractor, anvone directl%, or indirectly employed by them Or
anyone for whose acts they may be liable, regardless of
whether or not such claim, damage. loss or expense is caused
in part by a party indemnified hereunder.
ARTICLE 4
ARCHITECTS ADMINISTRATION OF THE CONTRACT
4.1 The Architect will provide administration of the Contract
as described in the Contract Documents. The Architect will
have audioritv to act on behalf of the Owner only to the extent
provided in tl�le Contract Documents.
4.2 The Architect will visit the site at intervals appropriate cc)
the stage of construction to become generally familiar with the
progress and quality of the Work.
4.3 The Architect will not have control over or charge of and
will not.be responsible for construction means. methods. tech-
niques. sequences or procedures. or forsafery precautions and
programs in connection with the Work. since these are soleiv
the Contractor's responsibility. The Architect will not be
responsible for the Contractor's failure to carry out the Work
in accordance with the Contract Documents.
4.4 Based on the Architect's observations and evaluations of
the Contractor's Applications for Payment. the Architect will
review and certifv the amounts due tile Contractor.
4.5 The Architect will have authority to reject Work that (toes
not conform to the Contract Documents.
4.6 The Architect will promptly review and approve or take
appropriate action upon ContractoCs submittals such as Shot)
Drawings, Product Data and Samples. but only for tile limited
purpose of checking for conformance with information given
and the design concept expressed in the Contract Documents.
4.7 Tile Architect will promptly interpret and decide mit.
ters concerning performance under and requirements of the
AIA DOCUMENT A205 - (;ENFRAI. CONDITIONS OF -nlF CO\71 K%C r FOR CONsrRUcnON—
SMALL PROIF.CNEDITION -.MA- - 01"3 - 111E AMERICAN INs"1111-11' OF ARCHITECIs. 1-35 NM'
YORKAVI-NVE. N.�.. WANDINGION. D.C. NXK�5292 - WARNING: Unlicensed photocopying
2 A205-1993 violates U.S. corivriallf laws and will suhi��t th� wm.m, t. i—i
I I . . r I
Contract Documents on wntten req uestu, _�cr the Owner
or Contractor.
the Contractor for perfo'. , ce of the Work under the Con-
tract Documents.
4.8 Interpretations and decisions of theArchitect will be con-
sistent with the intent of and reasonabiv inferable from the
Contract Documents and will be in writing or in the form of
drawings. When making such interpretations and decisions,
the Architect will endeavor to secure faithful performance by
both Owner and Contractor. will not show partiality to either
and will not be liable for results of interpretations or decisions
so tendered in good faith.
4.9 The Architect's duties, responsibilities and limits of
authoniry as described in the Contract Documents will not be
change� without written consent of the Owner, Contractor
and Architect. Consent shall not be unreasonably withheld.
0;4041114P
183 . FAZIC14-2 I Z 0 1 N WiT111=4
5.1 After execution of the Contract, changes in the Work may
be accomplished by Change Order or by order for a minor
change in the Woik. The Owner, without invalidating the
Contract, may order changes in the Work within the general
scope of the Contract consisting of additions, deletions or
other revisions, the Contract Sum and Contract Time being
adjusted according]%.
5.2 A Change Order shall be a written order to the Contractor
signed by the Owner and Architect to change the Work, Con-
tract Sum or Contract Time.
5.3 The Architect will have authority to order minor changes
in the Work not involving changes in the Contract Sum or the
Contract Time and not inconsistent with the intent of the Con-
tract Documents. Such changes shall be written orders and
shall be binding on the Owner and Contractor. The Contractor
shall cam, out such written orders promptly
5.4 if concealed or unknown physical conditions are encoun-
tered at the site that differ material]%- from those indicated
in the Contract Documents or from those conditions ordinar-
ih- found to exist. the Contract Sum and Contract Time shall be
subject to equitable adjustment.
ARTICLE 6
TIME
6.1 Time limits stated in the Contract Documents are of the
essence of the Contract.
6.2 If the Contractor is delayed at any time in progress Of
the Work by changes ordered in the Work, or by labor dis-
putes. fire. unusual delay in deliveries. unavoidable casualties
or other causes beyond the Cuntracror*s control, the Contract
Time shall be extended by Change Order for such reasonable
time as the Architect may �etermine�
ARTICLE 7
PAYMENTS AND COMPLETION
7.1 CONTRACTSUM
The Contract Sum stated in the Agreement, including audio-
nzed adjustments. is the total amount payable by the Owner to
7.2 APPLICATIONS FOR PAYMENT
7.2.1 At least ten days before the date established for each
progress payment. the Contractor shall submit to the Architect
an itemized Application for Payment for operations completed
in accordance with the values stated in the Agreement. Such
application shall be supported by such data substantiating the
Contractor's right to payment as the Owner or Architect may
reasonably require and reflecting retainage if provided for else-
where in the Contract Documents.
7.2.2 The Contractor warrants that title to all Work covered
by an Application for Payment will pass to the Owner no later
than the time of payment. The Contractor further warrants
that upon submittal of an Application for Payment, all Work for
which Certificates for Pavment have been previously issued
and payments received fi�orn the Owner shall, to the' best of
the Contractor's knowledge, information and belief. be free
and clear of liens, claims, security interests or other encum-
brances adverse to the Owner's interests.
7.3 CERTIFICATES FOR PAYMENT
The Architect will, within seven days after receipt of the Con-
tractor's Application for Pavment, either issue to the Owner a
Certificate for Payment, with a copy to the Contractor, for such
amount as the Architect determines is properly due, or notifv
the Contractor and Owner in writing of theArchiitect's reason's
for withholding certification in whole or in part.
7.4 PROGRESS PAYMENTS
7.4.1 After the Architect has issued a Certificate for Payment.
the Owner shall make payment in the manner provided in the
Contract Documents.
7.4.2 The Contractor shall promptly pay each Subcontractor
and material supplier. upon receipt of payment from the
Owner, out of the amount paid to the Contractor on account
of such entities' portion of the Work.
7.4.3 Neither the Owner nor the Architect shall have respon-
sibility for the payment of money to a Subcontractor or mater-
ial supplier.
7.4.4 A Certificate for Payment, a progress payment. or par-
tial or entire use or occupancy of the project by the Owner
shall not constitute acceptance of Work rfot in accordance
with the requirements of the Contract Documents.
7.5 SUBSTANTIAL COMPLETION
7.5.1 Substantial Completion is the stage in the progress of
the Work when the Work or designated portion thereof is
sufficiently complete in accordance with the Contract Docu-
ments so that the Owner can occupy or utilize the Work for its
intended use.
7.5.2 When the Work or designated portion thereof is sub-
stantially complete, the Architect will prepare a Certificate
of Substantial Completion which shall establish the date of
Substantial Completion, shall establish the responsibilities of
the Owner and Contractor, and shall fix the time within which
the Contractor shall finish all items on the list accompanying
the Certificate. Warranties required by the Contract Docu-
merits shall commence on the date of Substantial Completion
of the Work or designated portion thereof unless otherwise
provided in the Certificate of Substantial Completion.
AIA DOCUMENT A205 - GFNEIL�L CONDITIONS OF TIM CON-1RA(`T FOR CONSTRUCTION—
Sst�LLPROTFCTS EDITION -.At&-- 0199,i-THEAMERICAN lNSTrrL-MOrARCIuTEC7I5. 1-35NE'X'
YORKAVENUE_N.W.. WASHINGTON. D.C. 2LKXX�5292 - WARNING: Unlicensed photocopying
Violates U.S. copyright laws and will Subject the violator to legal prosecution.
A205-1993 3
7.6 FINAL COMPLETION AND FINAL,'MYMENT
7.6.1 Upon receipt of a final Application for Payment, the
Architect Will inspect the Work. When the Architect finds the
Work acceptable and the Contract fully performed, the Archi-
tea will promptly issue a final Certificate for Payment.
7.6.2 Final payment shall not become due until the Contrac.
tor submits to the Architect releases and waivers of liens, and
data establishing payment or satisfaction of obligations, such
as receipts, claims, security interests or encumbrances arising
out of the Contract.
7.6.3 Acceptance of final payment by the Contractor, a Sub-
contractor or material supplier shall constitute a waiver of
claims by that payee except those previously made in writing
and identified by that payee as unsettled at the time of final
Application for Payment.
ARTICLE 8
PROTECTION OF PERSONS AND PROPERTY
8.1 SAFETY PRECAUTIONS AND PROGRAMS
The Contractor shall be responsible for initiating, maintaining
and supervising all safety precautions and programs, includ-
ing all those required by law in connection with performance
of the Contract. The Contractor shall promptly remedy dam-
age and loss to property caused in whole or in part by the
Contractor, or by anyone for whose acts the Contractor may
be liable.
ARTICLE 9
CORRECTION OF WORK
9.1 The Contractor shall promptly correct Work rejected by
the Architect as failing to conform to the requirements of the'
contract bocuments. The Contractor shall bear the cost of
correcting such rejected Work.
9.2' In addition to the Contractor's other obligations including
warranties under the Contract, the Contractor shall, for a period
of one year after Substantial Completion, correct work not con-
forming to the requirements of the Contract Documents.
9.3 If the Contractor fails to correct nonconforming Work
Within a reasonable time, the Owner may correct it and the Con-
tractor shall reimburse the Owner for the cost of correction.
ARTICLE 10
MISCELLANEOUS PROVISIONS
10.1 ASSIGNMENT OF CONTRACT
Neither party to the Contract shall assign the Contract as a
whole without written consent of the other.
10.2 TESTS AND INSPECTIONS
10.2.1 Tests, inspections and approvals of portions of the
Work required by the Contract Documents or by laws, ordi-
e Printed on Recycled Paper 11193
nances, rules, regulations or orders of public acahoritie-s hav-
ing jurisdiction shall be made at an appropriate time.
10.2.2 If the Architect requires additional testing, the Con.
tractor shall perform these tests.
10.2.3 The Owner shall pay for tests except for testing Work
found to be defective for which the Contractor shall pay.
10.3 GOVERNING LAW
The Contract shall be governed by the law of the place where
the project is located.
ARTICLE 11
TERMINATION OF THE CONTRACT
11.1 TERMINATION BY THE CONTRACTOR
If the Owner fails to make payment when due or substantially
breaches any other obligation of this Contract, following seven
days' written notice to the Owner, the Contractor may termi-
nate the Contract and recover from the Owner payment for
Work executed and for proven loss with respect to materials,
equipment, tools, construction equipment and machinery,
including reasonable overhead, profit and damages.
I T"
11.2 TERMINATION BY THE OWNER
11-2.1 The Owner may terminate the Contract if the
Contractor:
.1 persistently or repeatedly refuses or fails to supply
enough properly skilled workers or proper materials;
.2 fails to make payment to Subcontr2ctors for materials
or labor in accordance With the respective agreements
between the Contractor and the Subcontractors;
.3 persistently disregards laws, ordinances, or rules,
regulations or orders of a public authority having juris.
diction; or
.4 is otherwise guilty of substantial breach of a provision
of the Contract Documents.
11.2.2 Vfhen am, of the above reasons exist. the Owner, after
consultation with the Architect. may without prejudice to any
other rights or remedies of the dwner and after giving the
Contractor and the Contractor's surety. if any, seven days'writ-
len notice, terminate employment of the Contractor and ma% -
.1 take possession of the site and of all materials thereon
owned by the Contractor;
.2 finish the Work by whatever reasonable method the
Owner may deem expedient.
11.2.3 When the Owner terminates the Contract for one of
the reasonsstated in Subparagraph 11.2.1, the Contractor shall
not be entitled to receive furEher-payment until the Work
is finished.
11.2.4 If the unpaid balance of the Contract Sum exceecis
costs of finishing the Work, such excess shall be paid to the
Contractor. If such costs exceed the unpaid balance, the Con-
tractor shall pay the difference to the Owner. This obligation
for payment shall survive termination of the Contract.
AIA DOCUMENT A205 - GENERAL CONDITIONS OF 'nIE COMMACT FOR CONSTRUCTION—
SMAI1.PRQW.C`IS FMITION - ALA" 01993 -THE AXIFRICAN INMnrF OFARCHITECTS, I7,35.NEW
4 A20S-1993 YORK AVENUE, N.W.. WASHINGTON. D.C. 20006-5292 -WARNING: Unlii:ensed P11011000Pying
violates U-r- conwl.ht I... ..A III qh� *. I ... I ___...,__
'lose F. Vazquez, P.E.
Civil - Structural Engineering
Consulting Services
103 Champions Run
West Palm Beach, FL 33407
(561) 848-5726
OCEAN TOWERS CONDOMINIUMS
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACEL FLORIDA
PROJECT SPECIFICATIONS
FOR
OCEAN TOWERS CONDOMINIUM ASSOCIATION, INC.
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACH, FLORIDA 34957
(561) 229-2229
Ocean Towers Condominiuf,
Building Floor
Concrete Walkway Restoratiop/Re -Iaieriiint
,p
Page I of 20
PART 1 - GENERAL
1.00 PROJECT SCOPE
A- LOCATION
Ocean Towers Condominium Building A
9400 South Ocean Drive
Hutchinson Island
Jensen Beach, Florida 34957
(561) 229-2M9
B. CURRENT SITUATION
C.
In response to the request of the Association, on or about May of 1999, field
inspections of the above referenced buildings were conducted by the Mr. Abdel
Karim-Conrado, P.E.. The purpose of the inspections was to identify areas of
degradation of the concrete structure(s). Based on the results of the inspection, W
Karim-Conrado submitted copies of the field data sheets indicating the deteriorated
areas at the balconies and walkways.
Based on the review of the data sheets by Jose F. Vazquez, P.E., it was determined
that typical concrete degradation (e.g., surface deck spall, overhead spall, column
spall, overhead beam spall, slab edge spall, and surface cracks) were found throughout
the building structure with variation in severity from minor (surface cracks and spalls)
to severe (exposed corroded reinforcing steel). The soffit of the Building "A"
walkway was identified as one of the areas requiring immediate attention.
The Association retained the services of Joso F. Vazquez, P.E. to develop the
necessary engineering documents for the restoration ofthe structures and to act as the
Asso ciation's agent in the capacity of 'Sngineer of Record" as defined in this proj ect
manual.
I The term "Owner" is hereby defined as Ocean Towers Condominium
Association, Inc. or their duly appointed representative and agents. This term
mav be used svnonvmouslv with "Associatiorf'.
Jose F
Ocean Towers Condomimuf.
Building "X'f6urth Floor
Concrete Walkway Restoration!Rib&66Q
N&x =—b e f 19 - , U999
Page 2 of 20
2. The term "Associatiorf 'is hereby defined as Ocean Towers Condominium
Association, Inc. and it's individual owners. This term may be -used
synonymously with "Owner".
The term 'Trigineer" or "Engineer of Record" are hereby defined as Jose F.
Vazquez, P.E. or his duly appointed representative and agents.
4. Where "request", "approval", "satisfactory" and similar words appear, it is the
request, approval or satisfaction of the Engineer that is intended.
1.01 DESCRIPTION OF THE WORK
A- The scope of work to be performed under the terms of this specification includes
furnishing of all materials, labor, services, utilities, permit fees, supervision, tools and
equipment, required or incidental to the demolition, replacement and repair of the
concrete areas located at the Building "N' third floor walkway soffit. Theworkwill
include, but is not limited to, the following elements:
1 .
W
Removal of deteriorated embedded electrical conduits & components�
6d) and replace with new PVC
conduits/components and copper wiring.
4. Disposal of deteriorated concrete, reinforcing steel, construction debris, etc.
generated during the course of the work.
Surface preparation and installation of repair materials and reinforcing steel
as identified by the Engineer.
Jose F. Vazquc7, P.E., Civil-ftuctural Fmginecri� & Consbuction Services, (561) 848-5726
Ocean Towers Condommmi'
Building "A7V
Floor
Concrete Walkway RestorationM—Ak�ent
Page 3 of 20
9. Application of concrete sealants pMqft��area,;
10. Provide barriers for the protection of the existing elements.
11. Application of stucco finish to all repair surfaces, as required to match existing
wall finish.
1.02 SITE ACCESS
The building will be fully operational and occupied for the duration of the project. All
work required under this Contract shall be performed from the exterior ofthe building
except as authorized by the Engineer.
2. The Contractor's access to the site shall be limited from 8:00 A-M to 6:00 P.M..
Monday through Friday, 8:00 A-Mto 4:00 P.M. on Saturday and in accordancewith
any applicable regulations by St. Lucie County agencies having jurisdiction in
Hutchinson Island and the Association. Work by the Contractor will not be permitted
on Sundays or any nationally observed holidays.
3. The Contractor, Subcontractors and their employees shall not be permitted inside any
of the Association's buildings and shall be prohibited from using any of the
Association's facilities such as restrooms, swimming pool, tennis courts, etc., and
shall be confined to those immediate areas necessary to accomplish their work and as
designated by the Association.
4. The Contractor shall be responsible to properly supervise his and his Subcontractor
employees as to proper language, conduct, dress and noise consistent with the
Association's rules & regulations.
Alcohol or drugs on the site or any individual or employee under the influence of
these substances will not be tolerated and will be grounds for dismissal.
6. The Engineer or the Association shall have the right to require the Contractor or
Subcontractors to remove from -the project, with cause, any employee.
The Contractor shall provide the Engineer with a Est of all personnel to be employed
at thejob site in accordance with the Association's security policy and requirements.
Jose F. Vazquez, P.E., Civil -Structural Enguie� & Construction Services, (561) 948-5726
Ocean Towers Condomunur
Building "A"Fourth Floor
Concrete Walkway Restoration�166&66nt
Page 4 of 20
1.03
The Contractor shall-,
A- Coordinate scheduling, submittals, and Work of various sections ofthe specifications
to ensure efficient and orderly sequence of installation of independent construction
elements.
B. Coordinate dumpster location, staging and storage requirements withthe Association.
The staging area -shall be acceptable to the Association and not interfere with the
operation of the facility.
C. Coordinate use of on -site utilities (e.g., potablewater and electricity) withthe Owner.
The Contractor may use at no cost to the Contractor, water and electricity available
on the exterior of the building for the performance ofthe work. Utility requirements
beyond those available on site shall be provided by the Contractor at his expense.
D. Coordinate access to the site and hours of operation with the Association.
E. Coordinate the location of on -site communication acceptable to the Association. The
Contractor shall provide a telephone fine or other means of on -site communication for
it's use. -
F. Provide and coordinate a location, acceptable to the Association, for on -site
temporary toilet facilities as required for it's use.
G. Coordinate with the Association concerning the delivery and removal of materials,
equipment and other items to and from the site.
H. Coordinate with. the Association the removal and replacement of exterior doors,
sliding glass doors and windows. The Association, at their option, request the
installation of new sliding glass doors or windows. New sliding glass doors or
windows shall be selected by the Association.
1.04 FIELD INSPECTIONS
A- The Engineer will observe and/or inspect all work as he deems necessary to verify that
existing site-canditions and substrate surfaces are acceptable for subsequent Work and
for general conformance to the contract documents. Surface preparation of all repair
areas shall be observed and accepted by the Engineer prior to placement of the repair
materials. Work shall not be covered until approved by the Engineer.
B. Engineer shall be notified a minimum of 24 hours prior to all observations.
C. The Contractor shall verify that utility services are available, of the correct
Jose F. Vazqacz, P.E., Civil-Struchnal Enguiecring & Consuuction Services, (561) 848-5726
Ocean Towers Condominim(-
Building "N'IL Floor
Concrete Walkwy. Restoration!Re�66i6i6nt
'1&) 1999
Page 5 of 20
characteristics and in the correct location.
D. The Contractor shall inspect upon receipt on site all finished products (e.g.,balusters
and railings, doors and frames, shutters, etc.) and assume full responsibility for proper
handling and storage. Any damage to delivered and/or stored items as a result of
storage or handling shall be at the Contractor's expense.
E. The Contractor shall be responsible for inspecting all items to be removed (e.g.,
railings,- shutters, doors & frames, etc.) and document, via video tape, photoi
- sketches, written description, etc., the condition ofthe ftem(s) prior to performing any
work in their immediateArea. Any remedy (including replacement) to damage to the
item(s) as a result of the work, handling, storage, etc. shall be at the sole expense of
the Contractor and to the satisfaction of the Engineer.
1.05 SUBN=ALS
A- Contractor shall subn-dt to the Engineer for review and acceptance, concrete mix
designs, manufacturer's product information and manufacturer's installation
'instructions for all materials specified prior to proceeding with the Work.
& Manufficturers and products shall be considered "or equivalent", as accepted by the
Engineer.
C. Submit the executed warranty, with authorized signatures (e.g., General Contractor,
Construction Company Officer/Owner), after acceptance of the repairs.
D. A copy of all required permits, licenses, certificates and approvals shall be delivered
to the Engineer and a copy shall be posted in a prominent location at the work site
prior to commencement of the work:
E. Submit partial and final release of liens as required.
1.06 QUALM ASSURANCE & WARRANTIES
A- Contractor Qualifications: Company or individual contractorwith a minimum ofthree
(3) years' documented experience acceptable to the Owner.
B. Comply with Manufacturer's instructions related to mixing and placing of the
materials.
C. Protection of work: Protect installed work and prohibit traffic or storage upon
repaired, waterproofed, or coated surfaces.
D. At project completion, Contractor shall issue a five (5) year warrantv against defective
Ocean Towers Condominim,
Building "A7'Fourth Floor
..........
Concrete Walkway Restoratio eat
Page 6 of 20
materials and/or workmanship of Contractor's work.
E. Within the Contractor's warranty period, any defective areas shall be repaired -to the
satisfaction of the Engineer, at the Contractor's sole expense. Contractor's expense
will include all costs for material, equipment and labor as necessary to correct the
defective work. This work shall be completed by the Contractor immediately after
receiving notification.
1.07 DELIVERY, STORAGE AND HANDLING
A- Deliver products in original unopened containers with the manufacturer's name,
labels, product identification and batch numbers.
B. Store and condition the specified products as recommended by the manufacturer.
Products shall remain unopened until ready for use.
C. Where mixing of components is required, use complete pre -measured units.
1.08 REFERENCES
The following references are incorporated into the specifications. Unless noted otherwise, the
specification, standard, etc. listed below shall be the latest revision in effect on the date noted
on the Project Manual.
A- ACI 301 "Specification for Structural Concrete for Buildings".
B. ACI 305 "Hot Weather Concreting".
C. ACI 304 "Recommended Practice for Measuring, Mixing, Transporting, and Placing
D.
E.
F.
G.
H.
1.
K.
N..
0.
N
Concrete".
ACI 308 "Recommended Practice for Curing Concrete".
ACI 309 "Guide for Consolidation of Concrete'
ACI 311 "Recommended Practice for Concrete Inspection".
ACI 318 'Building Code Requirements for Reinforced Concrete".
ACI 347 "Recommended Practice for Concrete Formwork".
ACI 546R "Concrete Repair Guide'.
ACI 614 "Recommended Practice for Measuring, Mixing, and Placing Concrete".
ASTM A615 "Standard Specifications for Deformed and Plain Billet -Steel Bars for
Concrete Reinforcement".
ICRI - Guideline No. 03730, "Surface Preparation for Repair of Deteriorated
Concrete Resulting from Reinforcing Steel Corrosion7'
Ocean Towers Condominim( -1
Building Floor
Concrete Walkwg RestorationIRWacement
0a R9-9
Page 7 of 20
Q. ICRI - Guideline No. 03 73 1, "Guide for Selectii�g Application Methods for the Repair
of Concrete Surfaces".
R. ICRI - Guideline No. 0373 3, "Guide for Selecting and Specifying Materials for Repair
of Concrete Surfaces".
S. SSPC - SP6, "Commercial Blast Cleaning7.
T. SSPC - SPI I, 'Tower Tool Cleaning to Bare Metar'.
PART2-PRODUCTS
2.00 MANUFACTURERS
A- Master Builders (Concrete Repair)
B. Sonneborn Building Products (Caulk & Joint Sealants)
C. Other Manufacturers may be used upon approval of the Engineer. Alternate product
data shall include verification that the alternate products are equivalent to the
specified Master Builders products listed below.
2.01 MNTERLALLS
Subject to compliance with other requirements in this specification, provide the following
materials
CAS
:r
401,
Jose F. Vazquez, P.E., Civil-Sftuctural Engineering & Constuction Scrvices, (561) 848-5726
Ocean Towers Condominiu(- Y
Building "A"F.6"i'irth Floor
Concrete Walkwqy
Page 8 of 20
B. CONCRETE CAST -IN -PLACE
1. EMACO S66 CL - Flowable, shrinkage -compensated structural repair
concrete. Provide a single component shrinkage -compensated, silica fume
modified, cement based mortar for structural repairs of distressed horizontal,
vertical or overhead concrete.
2. Aggregate: Shall conform to ASTM C33, aggregate for incorporation with
bagged mortar shall be 3/8", well graded and clean.
A- SURFACE REPAIR MORTAR
1 EMACO S88 CL - Sprayable, shrinkage -compensated structural repair
mortar. ' Provide a single component shrinkage-comperisated, -silica fume
modified, cement based mortar for structural repairs of distressed vertical or
overhead concrete.
2. SHOT?ATCH 21 — Sprayable silica fume structural shotcrete repair mortar.
Provide a single component (prepackaged) shrinkage -compensated, silica
fiune modified, cement based mortar for structural repairs of distressed
vertical or overhead concrete.
B. ANTI -CORROSION & BONDING AGENTS
1. EMACO P-22 - Flexible cementitious rebar coating. Provide polymer
modified, cement based coating with corrosion inhibiting admixtureto provide
protection for reinforcing steel.
2. EMACO P-�24 - Water based epoxy/cementitious bonding agent and rebar
coating. Provide Water based epoxy/cementitious for bonding concrete and
mortar to exiting concrete. Also, may be used as a rebar coating system to
protect against corrosion.
C. WATER
1. Water to be clean and potable free of oil, alkali or other deleterious material.
D. PORTLAND CEMENT PLASTER (STUCCO)
All CBS masonry and concrete surfaces shall be coated/patched to match
existing adjacent surface to the extent practical. Stucco shall be applied after
the repair material has cured for the required time.
2. Stucco material shall be
Jose F. Vazquez, P
Ocean Towers Condominiwr-�)
Building Floor
Cpncrete Walkway
Page 9 of 20
2.02
and/or plastic cement conforming to ASTM C 926.
E. REINFORCEMENT
1 Reinforcing steel: ASTM C 615, Grade 60 (Grade 40 for stirrups & ties) billet
steel deformed bars.
H. DISSHVIILAR MATERIALS
- 1 All dissimilar metals and materials shall be adequately isolated. Metal
electrkA conduits and components shall be isolated from all structural steel.
The Engineer shall be notified of any conditions where proper isolation can
not be achieved.
1. CAULKS & JOINT SEALANTS
I Caulk & Joint Sealants shall be as manufactured by Sormebom Building
Products or approved equal.
2. Interior general purpose acrylic latex caulk shall be "Sonolae' conforming to
ASTM C 834.
3. Sealant for exterior vertical or horizontal joints not subject to traffic shall be
Sonolastic NP 1, one component gun -grade polyurethane sealant conforming
to Federal Specification TT-S-00230C.
4. Sealant for exterior horizontal joints subject to traffi shallbeEpolithPor
Epolith G epoxy joint filler.
5. Backer Rod shall be a closed cell foam, non -staining, compatible with sealant
and primer and of a resilient nature equal to Sonofoam Backer -Rod. Install in
accordance with manufacturer's recommendation as to size required to suit
joint width to depth ratio.
6. Solvents, cleaning agents, and other accessory materials shall be as
recommended by caulking or sealant manufacturer.
7. Colors for exposed (visible) applications and not subject to painting or
covering shall be as selected by Engineer.
A- Forms
I . Type: Metal or wood sealed to prevent faces from absorbing water from
Ocean Towers Condomimu
Building "X'Fou�- Floor
Concrete Walkway BeL qo#Qnd1'ep t
i ii�
Page 10 of 20
concrete.
2. Treat with release agent compatible with concrete.
3. Forms shall be rigid, liquid -tight, and conforming to ACI 347R Class A-
B. Reinforcing Steel Supports & Spacers
Reinforcing steel chaks and spacers shallbe ofnon-ferrous materials or 100%
vinyl coated free of rust, nicks, cuts or damage that will expose the metal
base.
PART 3 - EXECUTION
3.00 SHORING
A. Contractor shall provide shoring if necessary, bracing or support for all existing
structural elements to remain until all structural modifications have been conitileted
B. Shoring shall remain in place until components are adequate to maintain structural
loads.
3.01 CUTTING, DEMOLMON & PATCHING
A. The Contractor shall be responsible for cutting, demolishing, fitting, and patching all
degraded areas of the structure required to complete the Work. The contractor shall
not endanger other Work by cutting, excavating, demolishing or otherwise altering
other work and shall not cut or alter other Work except with written consent of the
Association and Engineer. Costs caused by defective or ill-timed Work shall beborne
by the Contractor.
B. Cutting, demolition or restoration performed by the Contractor which isimacceptable
by the Owner and Engineer shall have such correction or restoration work performed
when so instructed. The cost of such Work shall be home by the Contractor for
defective Work.
C. The Contractor shall not cut or demolish any portion of the building or structural
component(s) that may jeopardize the structural integrity or strength of the building
or its components without acceptance by the Engineer.
D. No holes except for small screws or bolts may be drilled in the beams or other
structural members for the purpose of supporting or attaching work without
obtaining prior approval from the Association.
Jose F. VazWcz, P.E., Civil -Structural Engineering & Constniction Services, (561) 848-5726
Ocean Towers Condominiu�
Building "A"E6 Floor
Concrete Walkw�_�4estoration!Reojidefikfit
Page I I of 20
r-V1
IKI
F-79
3.02 SURFACE PREPARATION
A- All repair areas shall be prepared in accordance with International Concrete Repair
Institute's "Guide for Surface Preparation for the Repair of Deteriorated Concrete
Resulting from Reinforcing Steel Corrosion!' (Guideline No. 03730). This includes
but not limited to the following.
1. Concrete edge and surface spall repairs shall be used for those areas identified
with spalling and cracking of the concrete, and with a deterioration of the
reinforcing of not exceeding 15% of the original bar cross sectional area or
8% of the original bar diameter and as determined by the Engineer.
2. Remove all loose, spalled, and unsound concrete in the area of the
deterioration. Removal shall be performed with small pointed tools (e.g.,
chipping hammers) rather than wide chisel edges to prevent n-dcro cracking
and continued spalling ofthe concrete to remain. Chipping hammers shall not
be in excess of 15 pound rating.
3. The area of concrete to be removed shall extend along the length of the
reinforcing, beyond the Emits of the reinforcing deterioration a minimum of
2" into sound concrete. Care shall be taken not to damage the bond between
the non -corroded bar and the sound concrete. W6
4. Concrete shall be removed completely around the reinforcing providing a
minimum clearance of I " between the reinforcing and the concrete to remain,
where possible.
Jose F. Tazq= PX., CivH-Structuzut Endneerinp & Construction Services. (561) 948-5726
Ocean Towers Condomimm
Building "X'i.6- .. Floor
Concrete Walkway Restoration)R ement
Page 12 of 20
5. Provide a 112." minimum depth saw -cut,
(iemoiltiowatme�stMAo*ers�,,_*Olglq�W
_4(144fto to prevent feathering of
the patch material. Do not cut any reinforcing, except as directed and
accepted by the Engineer prior to cutting.
7. Loose reinforcement shall be secured in place by tying to other secured bars
or by Engineer approved method.
8. Engineer shall determine the necessity of replacing or supplementing
reinforcing steel with reduced cross sectional areas caused by corrosion
damage.
9. Repair configuration should be kept as simple as possible to minimize
boundary edges.
10. Prepare all concrete surfaces to receive the repair material, including the saw -
cut, to achieve a surface profile depth of 'A" minimum with a new fractured
aggregate surface to adequately anchor the patch material. All bonding
inhibiting materials shall be removed by abrasive blasting or high pressure
water blasting.
11. Remove all rust and scaling of the reinforcing thoroughly by mechanical
means to SSPC-SPI I or sandblasting to SSPC-SPIO.
12.
T,T-
Thoroughly clean the exposed concrete surface to receive the
To
Oatrh of all traces of dirt, grease, oil, dust, loose aggregates, and other
13. Pre-soak repair substrate to a saturated surface dry condition.
B. BAR COATING AND BONDING
Following the completion of the surface preparation, coat all reinforcing steel using
one ofthe following two options. All existing and exposed concrete surfaces shall be
bonded using option (2) below.
I - Apo3ranti-corrosion reinforcing bar coating EMACO P-22 in accordance
Ocean Towers Condonumul.
Building "N'y Floor
Concrete Walkway Restoration/
Page 13 of 20
with the manufacturer's instructions.
2. Apply the epoxy bonding agent EMACO P-24 to the repaired concrete
surface in accordance with the manufacturer's instruction. Do not allow the
slurry to dry prior to application of the repair material. The slurry bonding
coat shall not be retempered.
3.03 REINFORCING STEEL REPLACEMENT
A- All reinforcing with deterioration exceeding 15% of the original bar cross sectionil
area or 8% of the ori __ bar diameter sha#U be r
gp
d, as determined and directed
by the Engineer. AEf "t? .....
B. Priorto the repair, contractor shall shore, brace and otherwise support, the areato be
repaired, until the reinforcing has been replaced and the repair is completed.
C. The concrete removal shall be sufficient to achieve a minimum clearance of I " around
the existing reinforcing and the new reinforcing, placed beside the existing.
D. To permit lapping of the new reinforcing steel, the concrete shall be removed along
the length of the reinforcing, a minimum of 12" beyond the deterioration into sound
concrete to permit splicing of the reinforcing.
E. After the reinforcing has been prepared, lap the new reinforcing beside the entire
length of the exposed reinforcing, secure in place with the wires.
F. Where the removal of concrete to achieve the required lap length is not practical as
determined by the Engineer, bar development can be achieved by embedding the
reinforcing into existing sound concrete a minimum of 6" with Simpson Epoxy -Tie
system, or equal.
G. Reinforcing steel shall be ASTM A615 Grade 60 minimum (Grade 40 minimum for
stirrups & ties).
Jose F. Vazquez, P.E., Civil -Structural Engineering & Constuction Services, (561) 848-5726
Ocean Towers Condorniniui�
Building "N'F-PuFth Floor
Concrete Walkway Restoration?"19�
U�pv'.
Page 14 of 20
3.04 FORMWORK
A- Keep unrestr ained surface area of repair to a minimum.
B. Provide outlets to drain presoaking water, access points for placing concrete into
forms, and air vents as required.
C. Application of repair concrete shall not be less than 1/2" in depth.
3.05 NEDUNG
3-.05A.
All mixing shall be in accordance with the manufacturer's instructions and the following
recommendations. Where there is a conflict between the manufacturer's instruction and these
recornmendation, the manufacturer's instructions shall govern.
A- Mechanical mixing is recommended with the use of a slow speed drill and a jiffier
type paddle, or in an appropriate mortar mixer.
B. Typical mixing time is 3 to 5 minutes. Do not mix longer than 5 minutes.
C. Do not add more water than it is recommended by the manufacturer.
D. Only that portion of the material that can be properly mixed within 10 minutes of
application should be used.
1
2.
S
Jose F. Vazq=, P.E., Civil-Strucauul Engineenng & Construction Services, (561) 848-5726
Ocean Towers Condominiums
Building."k, MIFloor
Concrete RestoratioAAM_"��'
"'AMMM99
Page 15 of 20
T,
M
6 9 FRI
71
wgj— uguaw- na.-i
3.06 APPLICATION
A- All repair material shall be applied in accordance with the manuflicturer's instructions.
B . Evaporation Retarder Where rapid surface evaporation may occuri in hot, windy
conditions, apply evaporation retarder according to the manufacturer's
recommendations.
C. Finishing- Completed repair surfaces should be straight, true and match eidsting
profiles. Do not overwork the surface.
F. VazquezP..E.,.CiviI-StntcturaI Engineering& Construction Services, (561) 848-5726
Ocean Towers Condominiu�.
Building 'W'Fo-utth Floor
Concrete Walkway. Restoratio q'lgqqWM
p
Page 16 of 20
D. Remove formwork after concrete has hardened sufficiently to permit forms to be
removed without damaging concrete, and having achieved 1450 psi compressive
st rength, but not less than 24 hours.
3.07 CURING
All repaired surfaces must be cured for a minimum. of 5 days with one of the following
methods.
3. Wet cure with burleen or wet burlap.
4. Ponding
5— Sheeting material
6. Liquid membrane forming curing compound per manufacturer's recommendations.
3.08 CRACK REPAIRS
A- GENERAL
I . Crack repairs will be performed for all areas identified by the Engineer.
2. Remove all loose and unsound concrete within and adjacent to the crack.
B. CRACK SEALING BY GRAVITY (SURFACE CRACK�)
Vee notch the surface of the crack with a mechanical router or hand chipping
,tool to a maximum width of 1/4".
2. Remove loose debris and dust out of cracks and voids by compressed air or
other mechanical means as recommended bythe manufacturer. Substratemay
be dry or damp prior to product application.
3. If the crack propagates through the slab or beam and where accessibility to
the underside of the beam or slab is available, seal all visible cracks with an
epoxy resin or portland cement based quick setting compound to act as a dam
to hold the liquid epoxy resin adhesive until cured.
4. Fill crack with EMACO S 8 8 CL by trowel method or p our neat (no sa-nd) low
viscosity mterial s recommended by manufacturer.
5. Finish the material flush and to match with existing.
C. CRACK SEALING BY EPDXY INJECTION
Surfaces adjacent to cracks or other areas of application shall be cleaned of
Jose F. Vazquez, P.E., Civil-Strumural Engineering & Constraction Services, (561) 948-5726
Ocean Towers Condominiu
Building "N' Floor
Concrete Walkway, Restoration't ent
2
Page 17 of 20
dirt, dust, oil, and grease or other foreign matter which may be detrimental to.
bond of injection surface seal.
2. Entry ports shall be provided along the crack at intervals of not less than the
thickness of concrete at that location.
3. Surface seal material shall be applied to the face of the crack between the
entry ports. Allow surface seal material to gain strength prior to injection.
4. Equipment for Injection: Provide injection equipmemthat is portable, positive
displacement type pump. The pump shall be electric or air powered and shall
provide in -line metering and mixing. Equipment shall have the capability of
maintaining the volume ratio for the epoxy adhesive within a tolerance of
5% by volume at any discharge pressure up to 160 psi.
5. injection: Shall begin at the lowest entry port and continue until there is an
appearance of epoxy adhesive at the next port adjacent to the entry port being
pumped. The epoxy injection shall be transferred to the next adjacent port
where the adhesive has appeared. Injection shall be performed until cracks are
completely filled.
6. Finishing: When cracks are completely filled, epoxy adhesive shall be cured
for sufficient time to allow removal of surface seal without any draining or
run -back of epoxy adhesive material. SurfiLce seal material and any adhesive
runs shall be removed from concrete surfaces. The face of the crack shall be
finished flush with concrete, showing no indentations or protrusions caused
by placement of entry ports.
7. Ming Cored Holes: After the Work has been accepted by the Engineer, cored
holes shall be repaired using a two component bonding agent and a suitable
repair mortar. The bonding agent shall be applied to the surfaces ofthe cored
holes, followed by application of repair mortar placed by hand trowel,
thoroughly rodded and tamped in place, and finished to match color, finish,
and texture of existing concrete
3.09 ELECTRICAL REPAIRS
A- All electrical work shall be performed by qualified licensed electrical contractors in
accordance with the National EIectriCCode and all applicable local Wilding codes,
ordinances and regulations.
B. Degraded and/or corroded electrical conduits and components embedded in the
damaged concrete shall be removed and replaced as directed by the Engineer.
C. The electrical wires shall be disconnected and pulled back to the previousjunction box
Jose F. Vazq=, PX., Civil-Struchiral Engineering & Constructicm Services, (561) 848-5726
Ocean Towers Condominiu,
Building "N'IE Floor
Concrete Walkway Restoration./Replacement
Page 18 of 20
or electrical fixture box prior to the removal ofthe degraded conduits or components.
Deteriorated or damaged wiring shall be replaced with new copper wiring ofthe same
or higher ampacity rating (size).
D. All new (replaced) electrical conduits shall be'Tigid Non-Metallie' (PVC, Type A,
Sch. 40 min.). All new (replaced) electrical fittings, boxes, support clips, etc. shall be
PVC and compatible with the "Rigid Non-Metallid" system.
I H
E. New conduits shall be embedded in the concrete with a I" minimum cover and /2
(min.) clearance from existing concrete surface to ensure repair material completely
encases the conduit without air pockets or voids around the conduit.
F. Temporary power or provisions shall be made to ensure uninterrupted service to
stairwell fights, emergency exit signs, elevators, fire alarms, etc. is maintained.
G. Restore all wiring to its original configuration or as required by Code.
11�.
HJ
U Vi SV Do 01 1�1 &I. I 1�
A-
B. STUCCO
I In areas where new concrete has been placed, and areas adjacent to such
areas, install coat of stucco, as required, to fill voids and match the surface
and texture of surrounding areas.
2. Exterior use of Portland cement plaster (stucco) shall comply with the
application and material requirements of ASTM C 926.
The limits of the stucco area affected by the repair shall be saw cut to sound
and well bonded stucco. All loose, damaged and degraded stucco shall be
removed.
4. Masonry and concrete surfaces on which stucco is applied shall be roughen,
cleaned, and damped (without visible sudace water) to the degree required to
achieve mechanical bond. Apply bonding agent as required for proper
adhesion.
Jose F. Vazquez, P.E., Civil-Struchual Engineering & Construction Services, (561) 848-5726
Ocean Towers Condorniniu�,,,
Building "N'F Floor
Concrete Walkway Restoratio
Page 19 of 20
6
5. All concrete surfaces to receive stucco shall be coated with one of the
following bonding agents:
Weld -Crete, Larsin Products Corps.
Polyweld, Chern-Masters Corp.
Chernweld, Florida Laboratories.
6. Provide and install expansion joints where provided by original construction.
7. The first coat (base coat) shall be applied to a true surface approximately 1/2
the total thickness.
8. The base coat shall be damp cured for a period of 24 hours (min.).
9. The finish coat shall be applied over a uniformly damp but surface dry base.
10. The stucco shall be kept damp for a period not less than 48 hours. In lieu
thereot approved water proofing curing agents may be used.
I"I',,',',,, . , , �-- -
7M I
I J -'l-
-2-41 Mk�flfrdl-
3.11 CAULK & JOINT SEALANTS
A- All caulk and joint sealants shall be installed in strict accordance with the
manufacturer's instructions and recommendations.
Jose F. Vazquez, PE., CM-Stractural Engineering & ConstraWon Services, (561) 948-5726
Ocean Towers Condominiur.,
�"Q'
Building "N't Floor
Concrete Walkway RestoratiopM.H-QQ"'
p
Page 20 of 20
B. After installation, all exposed and visible surfaces shall be thoroughly cleaned and free
from damage and defects. All damaged material or defects shall be replaced or
corrected at the Contractor's expense.
C. The Contractor shall notify the Engineer when the work has been completed and is
ready for the Engineer's inspection.
D. The Contractor shall ffirnish written warrantee that the work executed under this
section is free'from. defects of material and workmanship for a period of 2 (two)
- years from date offinal adeeptance of this work, that he will, without delay and at his
own expense repair and replace all such defects as may develop during the term ofthis
guarantee.
OCEAN TOWERS WALKWAY SPEC Rml
Jose F. Vazquez, P.E., Civil -Structural Engineering & Consftuction Services, (561) 848-5726
S. stair tower
OCEAN TOWERS CONDOMINIUM
BUILDING A
4TH FLOOR WALKWAY REPLACEMENT
elevator tower
replace these sections
N. stair tower
jose F. Vazquez, P.E.
Civil - Structural Engineering
Consulting Services
103 Champions Run
West Palm Beach, FL 33407
(561) 848-5726
keyisedz ey. I) November-.19JIJ.99
OCEAN TOWERS CONDOMINIUMS
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACI-L FLORIDA
PROJECT MANUAL
FOR
OCEAN TOWERS CONDOMINIUM ASSOCIATION9 INC.
9400 SOUTH OCEAN DRIVE
RUTCLUNSON ISLAND -
JENSEN BEACH9 FLORIDA 34957
(561) 229-2229
OCL.A TOWERS CONDOMINIUNia'
9400 SOUTH OCEAN DRIVE
HUTCBINSON ISLAND
JENSEN BEACIL FLORIDA
PROJECT MANUAL INDEX
CONTRACT DOCUMENTS
Standard Form of Agreement Between Owner and Contractor for a Small Project, AIA A105-1993
General Conditions of the Contract for Construction of Small Project, AIA A205-1993
PROJECT SPECIFICATIONS
PART1-GENERAL
1.00 PROJECT SCOPE
1.01 DESCRIPTION OF TUE WORK
1.02 SITE ACCESS
1.03 COORDINATION
1.04 FIELD INSPECTIONS
1.05 SUBMITIALS
1.06 QUALITY ASSURANCE & WARRANTIES
1.07 DELIVERY, STORAGE AND HANDLING
1.08 REFERENCES
PART2-PRODUCTS
2.00 MANUFACTURERS
2.01 MATERIJALS
2.02 ACCESSORIES
PART 3 - EXECUTTON
3.00 SHORING
3.01 CUTTING, DEN40LITION & PATCHING
3.02 SURFACE PREPARATION
3.03 REINFORCING STEEL REPLACEMENT
3.04
FORMWORK
3.05
MDCNG
CONCB��'
'&
L05 B
E ��Rt�
3.06
�N& _AIR
APPLICATION
3.07
CURING
3.08
CRACK REPAIRS
3.09
ELECTRICAL REPAIRS
3.10
��FINISHING
3.11
CAULK & JOINT SEALANTS
Jose F. Vazquez, P.E., Civil-Struchn-al Engineering & Construction Services, (561) 848-5726
A/A Documew A-905
General Conditions of the Contract
for Construction of a Small Project
1993 SMALL PROJECTS EDITION
AR71CLE 1
GENERAL PROVISIONS
1.1 THE CONTRACT
The Contract represents the entire and integrated agreement
between the parties and supersedes prior negotiations, repre-
sentations or agreements, either written or oral. The Contract
may be amended or modified only by a written modification.
1.2 THE WORK
The term "Work" means the construction and services required
by the Contract Documents, and includes all other labor, mate-
nals, equipment and services provided by the Contractor to ful-
fill the Contractor's obligations.
1.3 INTENT
The intent of the Contract Documents is to include all items
necessary for the proper execution'and completion of the
Work by the Contractor. The Contract Documents are comple-
mentary, and what is required by one shall be as binding as if
required by all.
1.4 OWNERSHIP AND USE OF ARCHITEcrs
DRAWINGS, SPECIFICATIONS
AND OTHER DOCUMENTS
Dcicumen�s prepared by the Architect are instruments of the
Architect's service for use solely with respect to this project.
The Architect shall retain all common law, statutory and other
reserved rights, including the copyright. They are not to be
used bv the Contractor or anv Subcontractor, �ub-subcontrac-
tor or material or equipment supplier for other projects or for
additions ED this project outside the scope of the Work with-
out the specific written consent of the Owner and Architect.
ARTICLE 2
OWNER
2.1 INFORMATION AND SERVICES
REQUIRED OF THE OWNER
2.1.1 If requested by the Contractor, the Owner shall furnish
and pay for a survey and a legal description of the site.
2.1.2 Except for permits and fees which are the responsibility
of the Contractor under the Contract Documents, the Owner
shall obtain and pay for other necessary approvals, easements,
assessments and charges.
2.2 OWNER'S RIGHT TO STOP THE WORK
if the Contractor fails to correct Work which is not in accor-
dance with the Contract Documents, the Owner mav direct
the Contractor in writing to SLOP the Work until the correction
is made.
2.3 OWNER'S RIGHT TO CARRY OUT THE WORK
If the Contractor defaults or neglects to carry out the Work in
accordance with the Contract Documents and fails within a
seven day period after receipt of written notice from the
Owner to correct such default or neglect with diligence and
promptness, the Owner may, without prejudice to other reme-
dies, correct such deficiencies. In such case, a Change Order
shall be issued deducting the COSE of correction from pay
ments due the Contractor.
2.4 OWNER'S RIGHT TO PERFORM CONSTRUCTION
AND TO AWARD SEPARATE CONTRACTS
2.4.1 The Owner reserves the right to perform construction or
operations related to the project with the Owner's own forces,
and to award separate contracts in connection with other por-
tions of the project.
2.4.2 The Contractor shall coordinate and cooperate with
separate contractors employed by the Owner.
2.4.3 CONES caused by delav�q or by improperly timed activities
or defective construction shall be'bome by the party respon-
sible therefor.
ARTICLE 3
CONTRACTOR
3.1 EXECUTION OF THE CONTRACT
Execution of the Contract bv the Contractor is a representa-
tion that the Contractor has visited the site. become familiar
With local conditions under which the Work is to be per-
formed and correlated personal observations with require-
ments of the Contract Documents.
3.2 REVIEW OF CONTRACT DOCUMENTS AND
FIELD CONDITIONS BY CONTRACTOR
The Contractor shall carefully study and compare the Contract
Documents with each other and w :
ith information furnished bv
the Owner. Before commencing activities, the Contractor
shall: (1) take field measurements and verify field conditions:
(2) carefully compare this and other information known to
OCupyright 1993 bv The American Inst it ute of Architects. 1�35 New Yc irk Avenue. N V'.. Wa.shinglon. D.C. 20006-5292. Reproduction Elf the mat enal herein
or substantial quotation (if its provisions without the written permission of the ALA violate.% the copynght lawl, (if the United States anti will subject the %iolanor ill
lepi fun."ution.
ALA DOCUMENT A205 - GENERAL CONDITIONS OF THE CONTRAL-T FOR CONSTRUCTION—
SSIALL IRCIECTS EDITION - AIA' - 01993 - THE AMERICAN INST[n-17 OF ARCI 11TECTS.. 1-35 NEW
YORK AVENCE.N.W., WASHINGTON. D.C. axx�9292 - WARNING: Unlicensed photocopying
Violates U.S. Copyright laWS and ivill Subject the violator to legal prosecution.
A205-1993 i
the Contractor with the Contract Documents: and (3)
promptly report errors. inconsistencies or ornismons discov-
ered to the Architect.
3.3 SUPERVISION AND CONSTRUCTION PROCEDURES
3.3.1 The Contractor shall supervise and direct the Work.
using the Contractor's best skill and attention. The Contractor
shall be solely responsible for and have control over construe-
tion means, methods. techniques. sequences and procedures,
and for coordinating all portions of the Work.
3.3.2 The Contractor, as soon as practicable after award of the
Contract. shall furnish in writing EO the Owner through the
Architect the names of subcontractors or suppliers for each
portion of the Work. The Architect will promptly reply to the
Contractor in writing if the Owner or the Archit'ect. afier clue
investigation, has reasonable objection to the subcontractors
or suppliers listed.
3.4 LABOR AND MATERIALS
3.4.1 Unless otherwise provided in the Contract Documents
the Contractor shall provide and pay for labor. materials.
equipment, tools, utilities, transportation, and other facilities
and services necessary for proper execution and completion of
the Work.
3.4.2 The Contractor shall deliver. handle, store and install
materials in accordance with manufacturers' instructions.
3.5 WARRANTY
The Contractor warrants to the Owner and Architect that:
(1) materials and equipment fumished under the Contract will
be new and of good quality unless otherwise required or per-
mitted bv the Contract Documents; (2) the Work will be free
from def�crs not inherent in the quality required or pemitted;
and (3) the Work will conform to the requirements of the Con -
[met Documeni�s.
3.6 TAXES
The Contractor shall pay sales. consumer. use and similar taxes
chat are legally required when the Contract is executed.
3.7 PERMITS, FEES AND NOTICES
3.7.1 The Contractor shall obtain and pay for the building
permit and other permits and governmental fees. licenses and
inspections necessary, for proper execution and completion of
the Work.
3.7.2- Tile Contractor shall comph. with and give notices
required by agencies having jurisdiction over the Work. if tile
Contractor performs Work knowing it to be contrary to laws.
statutes. ordinances. building codes. and rules and regulations
without notice to the Architect and Owner. the Contractor
shall assume full responsibility for.such Work and shall bear
the attributable costs. The Contractor shall promptly notify
the -Architect in writing of any known inconsistencies in
the Contract Documents with such governmental laws, rules
and regulations.
3.8 SUBMITTALS
The Contractor shall promptly review. approve in writing
and submit to the Architect Shop Drawings. Product Data.
Samples and similar submittals required by the Contract Docu-
merits. Shop Drawings. Product Data. Samples andsinular sub.
initials are not Contract Documents.
3.9 USE OF SITE
The Contractor shall confine operations at the site to areas
permitted by law. ordinances. permits. the Contract Do,u.
ments and the Owner.
3.10 CUTTING AND PATCHING
The Contractor shall be responsible for cutting. filling or
patching required to complete the Work or to make its parts
fit together properly.
3.11 CLEANING UP
The Conimctor shall keep the premises and surrounding area
free from accumulation of debris and trash related it) the Work.
3.12 INDEMNIFICATION
To the fullest extent permitted by law. the Contractor shall
indemnify and hold harmless the6wner, Architect. Architect's
consultants and agents and employees of any of them from
and against claims, damages, losses and expenses. including
but not limited to attorneys' fees. arising out of or resulting
from performance of the Work. provided that such claim. dam-
age, loss or expense is attributable to bodily injury, sickness.
disease or death, or to injury to or destruction of tangible
properry (other than the Work itselfl including loss of use
resulting therefrom, but only to the extent caused in whole or
in part by negligent acts or oinissions of the Contractor.a Sub-
contractor, anyone directly or indirectly employed by them or
anyone for whose acts they may be liable, regardless of
whether or not such claim, damage. loss or expense is caused
in part by a party indemnified hereunder.
ARTICLE 4
ARCHITECT'S ADMINISTRATION OF THE CONTRACT
4.1 The Architect will provide 2dministration of the Contract
as described in the Contract Documents. The Architect will
have authorav to act on behalf of the Owner only to the extent
provided in the Contract Documents.
4.2 The Architect will visit the site at intervals appropriate to
the stage of construction to become generally familiar with the
progre.ssand quality of the Work.
4.3 The Architect will not have control over or charge of and
will notbe responsible for construction means. methods, tech-
niques. sequences or procedures, or forsafiety precautions and
programs in connection with the \Vork. since these aresoich-
the Contractor's responsibility. Tile Architect will not be'
responsible for the Contractor's failure to carn, out the Work
in accordance with the Contract Document.,.
4.4 Based on the ArChil&CCS observations and evaluations of
the Contractor's Applications for Payment. the Architect will
reviewarld certift- the amounts due the Contractor.
4.5 The.Axchitw will have authority to rejeci Work that does
not conform to the Contract DocumLills.
4.6 The Architect will promptly review and approve or take
appropriate action upon Contractor's submittals such as Shop
Drawin(�s. Product Data and Sarnple.s. but oil[%. for tile limited
purpose of checking for conformance with information given
and tile design concept expressed in the Contract Documents.
4.7 The Architect will promptl%. interpret and decide mar.
ters concerning performance under and requirements (if the
AIA DOCUMEKTA205 - GENFRALCONDMONS OF THECON-IRM.1- FOR CON5l`Rt:Cn0N—
SM1.1-ROIE.C17SEDITION -.UA'- 01993-11JEAMERICAN INS1111 'IT OF.-UtClulTM, I_A� NUIA'
ORKAVI-NIT.N.W.. WASHIN61 ON. D.C. 2(xx�5292 -WARNING: Unlicensed P11011000pying
2 A205-1993 21-. 1. . __� ... 11, _. .-- .- .-
Contract Document% on written request ci� - 'er the Owner
or Contractor.
/_ 1,
the Contractor for perfioi�, Jce of the Work under the Con-
traict Documents.
4.8 Interpretations and decisions of the Architect will be con-
sisient with the intent of and reasonably inferable from the
Contract Documents and will be in writing or in the form of
drawings. When making such interpretations and deci sions.
[he Architect will endeavor to secure faithful performance by
both Owner and Contractor, will nor show partiality to either
and will not be liable for results of interpretations or decisions
so rendered in good faith.
4.9 The Architect's duties, responsibilities and limits of
authority as described in the Contract Documents will not be
changeci without written consent of the Owner, Contractor
and Architect. Consent shall not be unreasonably withheld.
ARTICLE 5
CHANGES IN THE WORK
5.1 After execution of the Contract, changes in the Work may
be accomplished by Change Order or by order for a minor
change in the Work. The Owner, without invalidating the
Contract. may order changes in the Work within the general
scope of the Contract consisting of additions, deletions or
other revisions, the Contract Sum and Contract Time being
adjusted accordingly
5.2 A Change Order shall be a written order to the Contractor
signed by the Owner and Architect to change the Work, Con-
traCE Sum or Contract Time.
5.3 The Architect will have authority to order minor changes
in the Work nor involving changes in the Contract Sum or the
Contract Time and not inconsistent with the intent of the Con-
tract Documents. Such changes shall be written orders and
shall be binding on the Owner and Contractor. The Contractor
shall carry our such written orders, promptly
5.4 if concealed or unknown physical conditions are encoun-
tered at the site that differ materially from those indicated
in the Contract Documents or from those conditions ordinar-
ih, found to exist, the Contract Sum and Contract Time shall be
subject to equitable adjustment.
ARTICLE 6
TIME
6.1 Time limits stated in the Contract Documents are of the
essence of the Contract.
6.2 If the Contractor is delayed at any time in progress of
the Work by changes ordered in the Work, or bv labor dis-
putes. fire. unusual delay in deliveries. unavoidable casualties
or other causes bevand the Contractor's control, the Contract
Time shall be extended by Change Order for such reasonable
time as the Architect may �etermine.
ARTICLE 7
PAYMENTS AND COMPLETION
7.1 CONTRACT SUM
The Contract Sum stated in the Agreement, including autho.
rized adjustments, is the total amount payable by the Owner to
7.2 APPLICATIONS FOR PAYMENT
7MI At least ten days before the date established for each
progress payment. the Contractor shall submit to the Architect
an itemized Application for Payment for operations completed
in accordance with the values stated in the Agreement. Such
application shall be supported by such data substantiating the
Contractor's right to payment as the Owner or Architect may
reasonably require and reflecting retainage if provided for else-
where in the Contract Documents.
7Z2 The Contractor warrants that title to all Work covered
by an Application for Payment will pass to the Owner no later
tl�ian the time of payme'nt. The Contractor further warrants
that upon submittal of an Application for Payment. all Work for
which Certificates for Payment have been previously issued
and payments received from the Owner shall, to the best of
the Contractor's knowledge, information and belief, be free
and clear of liens, claims, security interests or other encum-
brances adverse to the Owner's interests.
7.3 CERTIFICATES FOR PAYMENT
The Architect will, within seven days after receipt of the Con-
' Application for Payment, either issue to the Owner a
tractor s
Certificate for Payment, with a copy to the Contractor. for such
amount as the Architect determines is properIv due, or notify
the Contractor and Owner in writing of the Architect's reason's
for withholding certification in whole or in part.
7.4 PROGRESS PAYMENTS
7.4.1 After the Architect has issued a Certificate for Pavmem.
the Owner shall make payment in the manner provided in the
Contract Documents.
7.4.2 The Contractor shall promptly pay each Subcontractor
and material supplier. upon receipt Of payment from the
owner. out of the amount paid to the Contractor on account
of such entities' portion of the Work.
7.4.3 Neither the Owner nor the Architect shall have respon-
sibility for the payment of money to a Subcontractor or mater-
ial supplier.
7.4.4 A Certificate for Payment, a progress payment. or par-
fial or entire use or occupancy of the project by the Owner
shall not constitute acceptance of Work not in accordance
with the requirements of the Contract Documents.
7.5 SUBSTANTIAL COMPLETION
7.5.1 Substantial Completion is the stage in the progress of
the Work when the Work or designated portion thereof is
sufficiently complete in accordance with the Contract Docu-
merits SO that the Owner can occupy or utilize the Work for its
intended use.
7.5.2 When the Work or designated portion thereof is sub-
stamially complete. the Architect will prepare a Certificate
of Substantial Completion which shall establish the date of
Substantial Completion, shall establish the responsibilities of
the Owner and Contractor, and shall fix the time within which
the Contractor shall finish all items on the list accompany ng
the Certificate. Warranties required by the Contract Docu.
ments shall commence on the date Of Substantial Completion
of the Work or designated portion thereof unless otherwise
provided in the Certificate of Substantial Completion.
AIA DOCUMENT A205 - GFNEI�L CONDITION'S OF TIM C0%TMCT FOR CONSTRUCTIO%—
S.%tkU_PR0TF.CTSF1)lT10N - ALA-- 01993-TIIEAMERIC�_N INSTln-MOIrARCIIrrFCrS- 1735NEW
YORKAWMT. N.Nt.. WASHINGTON. D.C. 2(xxx�5292 - WARNING: Unlicensed photocopying
violates U.S. copyright laws and Will subject the violator to legal prosecution.
A205-1993 3
7.6 FINAL COMPLETION AND FINAL'PAYMENT
7.6.1 Upon receipt of a final Application for Payment. the
Architect will inspect the Work. When the Architect finds the
Work acceptable and the Contract fully performed, the Archi-
tect will promptly issue a final Certificate for Payment.
7.6.2 Final payment shall not become due until the Contrac-
tor submits to the Architect releases and waivers of liens, and
data establishing payment or satisfaction of obligations, such
as receipts, claims, security interests or encumbrances arising
out of the Contract.
7.6.3 Acceptance of final payment by the Contractor, a Sub-
contractor or material supplier shall constitute a waiver of
claims by that payee except those previously Made in writing
and identified by that payee as unsettled at the time of final
Application for Payment.
ARTICLE 8
PROTECTION OF PERSONS AND PROPERTY
8.1 SAFETY PRECAUTIONS AND PROGRAMS
The Contractor shall be responsible for initiating, maintaining
and supervising all safety precautions and programs, includ-
ing all those required by law in connection with performance
of the Contract. The Contractor shall promptly remedy dam-
age and loss to property caused in whole or in part by the
Contractor, or by anyone for whose acts the Contractor may
be liable.
ARTICLE 9
CORRECTION OF WORK
9.1 The Contractor shall promptly correct Work rejected by
the Architect as failing to conform to the requirements of the'
Contract bocuments. The Contractor shall bear the cost of
correcting such rejected Work.
9.2 In addition to the Contracior's other obligations including
warranties under the Contract. the Contractor shall, for a period
of one year after Substantial Completion. correct work not con-
forming to the requirements of the Contract Documents.
9.3 If the Contractor fails to correct nonconforming Work
within a reasonable time, the Owner mav correct it and the Con-
tractor shall reimburse the Owner for the cost of correction.
ARTICLE 10
MISCELLANEOUS PROVISIONS
10.1 ASSIGNMENT OF CONTRACT
Neither party to the Contract shall assign the Contract as a
whole without written consent of the other.
10.2 TESTS AND INSPECTIONS
10.2.1 Tests, inspections and approvals of portions of the
Work required by the Contract Documents or by laws, ordi-
0 Printed on Reoded Paper 11193
nances, rules, regulations or orders of public authorities hav-
ing jurisdiction shall be made at an appropriate time.
10.2.2 If the Architect requires additional testing, the Con.
tractor shall perform these tests.
10.2.3 The Owner shall pay for tests except for testing Work
found to be defective forwhich the Contractor shall pay.
10.3 GOVERNING LAW
The Contract shall be governed by the law of the place where
the project is located.
ARTICLE 11
TERMINATION OF TNE CONTRACT
11.1 TERMINATION BY THE CONTRACTOR
If the Owner fails to make payment when due or substantially
breaches anv other obligation of this Contract, following Seven
days' written notice to the Owner, the Contractor may termi.
nate the Contract and recover from the Owner payment for
Work executed and for proven loss with respect to materials,
equipment, tools, construction equipment and machinery,
including reasonable overhead, profit and damages.
11.2 TERMINATION BY THE OWNER
11-2.1 The Owner may terminate the Contract if the
Contractor:
.1 persistently or repeatedly refuses or fails to supply
enough properly skilled workers or proper materials;
.2 fails to make payment to Subcontractors for materials
or labor in accordance with the respective agreements
between the Contractor and the Subcontractors;
.3 persistently disregards laws, ordinances, or rules,
regulations or orders of a public authority having juris.
diction; or
.4 is otherwise guilty of substantial breach of a provision
of the Contract Documents.
11.2.2 When any of the above reasons e.xisit. the Owner, after
consultation wnl� the Architect, may without prejudice to any
other rights or remedies of the Owner and after giving the
Contractor and the-Contractues surety. if any. seven days' writ-
ten notice, terminate employment of the Contractor and D12V:
.1 take possession of the site and of all materials thereon
owned by the Contractor;
.2 finish the Work by whatever reasonable method the
Owner may deem expedient.
11 .2.3 When the Owner terminates the Contract for one of
the reasons stated in Subparagraph 11.2.1, the Contractor shall
not be entitled to receive further payment until the Work
is finished.
11.2.4 If the unpaid balance of the Contract Sum exceeds
costs of finishing the Work, such excess Shall be paid to the
Contractor. If such costs exceed the unpaid balance, the Con.
mictor.shall pay the difference to the Owner. This obligation
for payment shall survive termination of the Contract.
AIA DOCUMENT A205 - GENERAL CONDITIONS 01"IllE CONTRACT FOR CONSTRUCnoN_
SMALL PROJEC'M FMITON - AIA" 01993 - THEAMMUCAN INSIMIT. OFARCHITECTS. I73S NEW
4 A205-1993 YORK AVENUF N.W.. WASHINGTON, D.C. 20006-5292 - WARNING: Unlicensed.phatocapying
Jose F. Vazquez, P.E.
Civil - Structural Engineering
Consulting Services
103 Champions Run
West Palm Beach, FL 33407.
(561) 848-5726
OCEAN TOWERS CONDOMINIUMS
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACI-L FLORIDA
PROJECT SPECIFICATIONS
10M
OCEAN TOWERS CONDOMINIUM ASSOCIATION9 INC.
9400 SOUTH OCEAN DRIVE
HUTCIII[NSON ISLAND
JENSEN BEACH, FLOREDA 34957
(561) 229-2229
Ocean Towers Condommium.�- -
Building "X'E6dft
2� Floor
Concrete Walkwav RestorationlYRep
16V66 a9, LION
Page 1 of 20
PART 1 - GENERAL
1.00 PROJECT SCOPE
A. LOCATION
Ocean Towers Condominium Building A
9400 South Ocean Drive
Hutchinson Island
Jensen Beach, Florida 34957
(561) 229-2229
B. CURRENT SITUATION
In response to the request of the Association, on or about May of 1999, field
inspections of the above referenced buildings were conducted by the Mr. Abdel
Karint-Conrado, P.E.. The purpose of the inspections was to identify areas of
degradation of the concrete structure(s). Based on the results of the inspection, W
Karim-Conrado submitted copies of the field data sheets indicating the deteriorated
areas at the balconies and walkways.
Based on the review of the data sheets by Jose F. Vazquez, P.E., it was determined
that typical concrete degradation (e.g., surface deck spall, overhead spall, column
spall, overhead beam spall, slab edge spall, and surface cracks) were found throughout
the building structure with variation in severity from minor (surface cracks and spalls)
to severe (exposed corroded reinforcing steel). The soffit of the Building "A"
walkway was identified as one of the areas requiring immediate attention.
The Association retained the services of Jose F. Vazquez, P.E. to develop the
necessary engineering documents for the restoration ofthe structures and to act as the
Association's agent in the capacity of "Engineer of Record" as defined in this project
manual.
C. DEFINITIONS
1 The term "Owner" is hereby defined as Ocean Towers Condominium
Association, Inc. or their- duly appointed representative and agents. This term
may be used synonymously with "Associatiorf'.
Jose F. Vazauez. P.E.. Civil -structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condominium. -
Building "N'Fj Floor
Concrete Walkwa) F �qq r a� i on/R� 0 1 dc 6 merit
g§v
�iLedj�g
�6 �-1 �N
Page 2 of 20
2. The term "Association7' is hereby defined as Ocean Towers Condominium
Association, Inc. and it's individual owners. This term may be used
synonymouslywith "Owner".
3. The term "Engineer" or "Engineer of Record" are hereby defined as Jose F.
Vazquez, P.E. or Iris duly appointed representative and agents.
4. Where "request", 11approval", "satisfactory" and similar words appear, it is the
request, approval or satisfaction of the Engineer that is intended.
1.01 DESCRYPTION OF THE WO
A. The scope of work to be performed under the terms of this specification includes
furnishing of all materials, labor, services, utilities, permit fees, supervision, tools and
equipment, required or incidental to the demolition, replacement and repair of the
concrete areas located at the Building "A" third floor walkway soffit. Theworkwill
include, but is not limited to, the following elements:
1.
Removal of deteriorated embedded electrical conduits & component gj
u and replace with new PVC
conduits/components and copper wiring.
4. Disposal of deteriorated concrete, reinforcing steel, construction debris, etc.
generated during the course of the work.
5. Sur -face preparation and installation of repair materials and reinforcing steel
as identified by the Engineer.
Z69 Ecg�jpi��aftreca�stt b j-��—c&sdctions�6
FL71i k�constru �quialINES,� ��aff-:Ifighwajja�_W@�I�]
Jose F
Ocean Towers CondominiumF'
Building "N'E_ Floor
Concrete WalkwaV Restoratior�R'60"Iddleinii'Lt"'nA�
)LN6j6.mbR.J9Q1.999
Page 3 of 20
8D ke�&all-origijlal handiails.
9. Application of concrete sealants &yer �efitire_lkwayaRrj
lKa
10, Provide barriers for the protection of the existing elements.
Application of stucco finish to all repair surfaces, as required to match existing
wall finish.
1.02 SM ACCESS
1. The building will be fillly operational and occupied for the duration of the project. All
work required under this Contract shall be performed from the exterior ofthe building
except as authorized by the Engineer.
2. The Contractor's access to the site shall be limited from 8:00 A.M to 6:00 P.M.
Monday through Friday, 8:00 A.M to 4:00 P.M. on Saturday and in accordance with
any applicable regulations by St. Lucie County agencies having jurisdiction in
Hutchinson Island and the Association. Work by the Contractor will not be permitted
on Sundays or any nationally observed holidays.
3. The Contractor, Subcontractors and their employees shall not be permitted inside any
of the Association's buildings and shall be prohibited from using any of the
Association's facilities such as restrooms, swimn-dng pool, tennis courts, etc., and
shall be confined to those immediate areas necessary to accomplish their work and as
designated by the Association.
4. The Contractor shall be responsible to properly supervise his and his Subcontractor
employees as to proper language, conduct, dress and noise consistent with the
Association's rules & regulations.
Alcohol or drugs on the site or any individual or employee under the influence of
these substances will not be tolerated and will be grounds for dismissal.
6. The Engineer or the Association shall have the right to require the Contractor or
Subcontractors to remove from the project, with cause, any employee.
7. The Contractor shall provide the Engineer with a Est of all personnel to be employed
at the job site in accordance with the Associatiores security policy and requirements.
Jose F. Vazquez, P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condominium�7 I
7
Building "N'Po fthl Floor
Concrete Walkwav RestoratioA01a
AgLvis6&jq�No�einbe
RyL6pj_LI9.'l990
Page 4 of 20
1.03 COORDINATION
1.04
The Contractor shall;
A. Coordinate scheduling, submittals, and Work ofvarious sections ofthe specifications
to ensure efficient and orderly sequence of installation of independent construction
elements.
B. Coordinate dumpster location, stagingand storage requirements with the Association.
The staging area shall be acceptable to the Association and not interfere with the
operation of the facility.
C� Coordinate use of on -site utilities (e.g., potablewater and electricity) withthe Owner.
The Contractor may use at no cost to the Contractor, water and electricity available
on the exterior of the building for the performance of the work. Utility requirements
beyond those available on site shall be provided by the Contractor at his expense.
D. Coordinate access to the site and hours of operation with the Association.
E. Coordinate the location of on -site communication acceptable to the Association. The
Contractor shall provide a telephone line or other means of on -site communication for
it's use.
F. Provide and coordinate a location, acceptable to the Association, for on -site
temporary toilet facilities as required for it's use.
G. Coordinate with the Association concerning the delivery and removal of materials,
equipment and other items to and from the site.
H. Coordinate with the Association the removal and replacement of exterior doors,
sliding glass doors and windows. The Association, at their option, request the
installation of new sliding glass doors or windows. New sliding glass doors or
windows shall be selected by the Association.
A. The Engineer will observe and/or inspect all work as he deems necessary to verify that
existing site conditions and substrate surfaces are acceptable for subsequent Work and
for general conformance to the contract documents. Surface preparation of all repair
areas shall be observed and accepted by the Engineer prior to placement ofthe repair
materials. Work shall not be covered until approved by the Engineer.
r
C.
Engineer shall be notified a minimum of 24 hours prior to all observations.
The Contractor shall
that utilitv services are available, of the correct
Civil -Structural
Ocean Towers Condorniniuni�;
Building "N' — =otifth Floor
Concrete W alkway RestorationlReplaceMe_nt
Kv:isejd:�—�'JhiWyirribe -49J§0
Page 5 of 20
characteristics and in the correct location.
D. The Contractor shall inspect upon receipt on site all finished products (e.g.,balusters
and railings, doors and frames, shutters, etc.) and assume ffill responsibility for proper
handling and storage. Any damage to delivered and/or stored items as a result of
storage or handling shall be at the Contractor's expense.
E. The Contractor shall be responsible for inspecting all items to be removed (e.g.,
railings, shutters, doors & frames, etc.) and document, via video tape, photos,
sketches ' written description, etc., the condition ofthe item(s) prior to performing any
work in their immediate area. Any remedy (including replacement) to damage to the
item(s) as a result of the work, handling, storage, etc. shall be at the sole expense of
the Contractor and to the satisfaction of the Engineer.
1.05 SUBMITTALS
A. Contractor shall submit to the Engineer for review and acceptance, concrete mix
designs, manufacturer's product information and manufacturer's installation
instructions for all materials specified prior to proceeding with the Work.
B. Manufacturers and products shall be considered "or equivalenf', as accepted by the
Engineer.
C. Subrnit the executed warranty, with authorized signatures (e.g., General Contractor,
Construction Company Officer/Owner), after acceptance of the repairs.
D. A copy of all required permits, licenses, certificates and approvals shall be delivered
to the Engineer and a copy shall be posted in a prominent location at the work site
prior to commencement of the work.
E. Submit partial and final release of Hens as required.
1.06 QUALITY ASSURANCE & WARRANTIES
A. Contractor Qualifications: Company or individual contractor with a minimum ofthree
(3) years' documented experience acceptable to the Owner.
B Comply with Manufacturer's instructions related to mixing and placing of the
materials.
C. Protection of work: Protect installed work and prohibit traffic or storage upon
repaired, waterproofed, or coated surfaces.
D . At
Contractor shall issue a five
Jose F. Vazquez, P.E., Civii-Struerural Engineering & Construction Services, (561) 848-5726
6cean Towers Condominium�
Building "N'Fo=urth Floor -77, -------
Concrete Walkway Rest oratio 'placement
Page 6 of 20
materials and/or worlananship of Contractor's work.
E. Within the Contractor's warranty period, any defective areas shall be repaired to the
satisfaction of the Engineer, at the Contractor's sole expense. Contractor's expense
will include all costs for material, equipment and labor as necessary to correct the
defective work. This work shall be completed by the Contractor immediately after
receiving notification.
1.07 DELINERY, STORAGE AND HANDLING
1.08
A. Deliver products in original unopened containers with the manufacturer's name,
labels, product identification and batch numbers.
B. Store and condition the specified products as recommended by the manufacturer.
Products shall remain unopened until ready for use.
C. Where mixing of components is required, use complete pre -measured units.
The following references are incorporated into the specifications. Unless noted otherwise, the
specification, standard, etc. fisted below shall be the latest revision in effect on the date noted
on the Project Manual.
A. ACI 301 "Specification for Structural Concrete for Buildings".
B. ACI 305 "Hot Weather Concreting".
C., ACI 304 "Recommended Practice for Measuring, Mixing, Transporting, and Placing
Concrete".
D.
E.
F.
G.
H.
I.
J.
K
EA
N
0.
N
ACI 308 "Recommended Practice for Curing Concrete".
ACI 309 "Guide for Consolidation of Concrete"
ACI 311 "Recommended Practice for Concrete Inspection".
ACI 318 "Building Code Requirements for Reinforced Concrete".
ACI 347 "Recommended Practice for Concrete Formwork".
ACI 546R "Concrete Repair Guide".
ACI 614 "Recommended Practice for Measuring, Mixing, and Placing Concrete".
ASTM A615 "Standard Specifications for Deformed and Plain Billet -Steel Bars for
Concrete Reinforcemenf'.
ICRI - Guideline No. 03730, "Surface Preparation for Repair of Deteriorated
Concrete Resulting from Reinforcing Steel Corrosion".
848-5726
Ocean Towers CondorniniumL,
Building "A" .' urt F oor
Corlicrete Walkwav RestorationYlteoldbetrEiLe�
(R�1'.NoV6mbef-KA999
Page 7 of 20
Q. ICRI - GuidelineNo. 0373 1, "Guide for Selecting Application Methods fortheRepair
of Concrete Surfaces".
K ICRI - GuidelineNo. 03733, "Guide for Selecting and Specifjing Materials forRepair
of Concrete Surfaces".
S. SSPC - SP6, "Commercial Blast Cleaning".
T. SSPC - SPI I, "Power Tool Cleaning to Bare Metal".
PART2-PRODUCTS
2.00 AIANUFACTURERS
A. Master Builders (Concrete Repair)
B. Sonneborn Building Products (Caulk & Joint Sealants)
C. Other Manufacturers may be used upon approval of the Engineer. Alternate product
data shall include verification that the alternate products are equivalent to the
specified Master Builders products listed below.
2.01 MATERLAIS
Subject to com Hance with other reguirements in this specification, provide the following
�-,, . �11 -17 --, 7-7
materials WrEfid
gin
FAI
7
51
Jose F. Vazquez, P.E., Civil-Structuml Engineering & Construction Services, (561) 848-5726
Ocean Towers CondominiurrP
Building "X'Eahl Floor
Concrete Walkway Restoration�aepS&ffieni
geVi�e -,J) NbVeer, 19 L149�9901
�d (Rev r�hb
Page 8 of 20
B. CONCRETE CAST -IN -PLACE
1. EMACO S66 CL - Flowable, shrinkage -compensated structural repair
concrete. Provide a single component shrinkage -compensated, silica fume
modified, cement based mortar for structural repairs of distressed horizontal,
vertical or overhead concrete.
2. Aggregate: Shall conform to ASTM C33, aggregate for incorporation with
bagged mortar shall be 3/8", well graded and clean.
A. SURFACE REPAIR MORTAR
EMACO S88 CL - Sprayable, shrinkage -compensated structural repair
mortar. Provide a single component shrinkage -compensated, silica fume
modified, cement based mortar for structural repairs of distressed vertical or
overhead concrete.
2. SHOT`PATCH 21 — Sprayable silica fume structural shotcrete repair mortar.
Provide a single component (prepackaged) shrinkage -compensated, silica
fume modified, cement based mortar for structural repairs of distressed
vertical or overhead concrete.
B . ANTI -CORROSION & BONDING AGENTS
EMACO P-22 - Flexible cementitious rebar coating. Provide polymer
modified, cementbased coatingwith corrosion inhibiting admixtureto provide
protection for reinforcing steel.
2. EMACO P-24 - Water based epoxy/cementitious bonding agent and rebar
coating. Provide Water based epoxyleementitious for bonding concrete and
mortar to exiting concrete. Also, may be used as a rebar coating system to
protect against corrosion.
C. WATER
Water to be clean and potable free of oil, alkali or other deleterious material.
D. PORTLAND CEMENT PLASTER (STUCCO)
All CBS masonry and concrete surfaces shall be coated/patched to match
existing adjacent surface to the extent practical. Stucco shall be applied after
the repair material has cured for the required time.
2. Stucco material shall be
Jose F. Vazquez, P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
. J
Ocean Towers Condominiurri-
Building"A" o JiFloor
Concrete Walkwav RestoratiorRe�ld&mdni
hq�jsed ev,--
Page 9 of 20
and/or plastic cement conforming to ASTM C 926.
E. REINFORCEMENT
I Reinforcing steel: ASTM C 615, Grade 60 (Grade 40 for stirrups & ties) billet
steel deformed bars.
H. DISSHVJILAR MATERIALS
All dissimilar metals and materials shall be adequately isolated. Metal
electrical conduits and components shall be isolated from all structural steel.
The Engineer shall be notified of any conditions where proper isolation can
not be achieved.
I. CAULKS & JOINT SEALANTS
I Caulk & Joint Sealants shall be as manufactured by Sonneborn Building
Products or approved equal.
2. Interior general purpose acrylic latex caulk shall be "Sonolae'conforniing to
ASTM C 834.
3. Sealant for exterior vertical or horizontal joints not subiect to traffic shall be
Sonolastic NP 1, one component gun -grade polyurethane sealant conforming
to Federal Specification TT-S-00230C.
4. Sealant for exterior horizontal joints �ub
ject to traffic shall be Epolith P or
Epolith G epoxy joint filler.
5. Backer Rod shall be a closed cell foam, non -staining, compatible with sealant
and primer and of a resilient nature equal to Sonofoam Backer -Rod. Install in
accordance with manufacturer's recommendation as to size required to suit
joint width to depth ratio.
6. Solvents, cleaning agents, and other accessory materials shall be as
recommended by caulking or sealant manufacturer.
7. Colors for exposed (visible) applications and not subject to painting or
covering shall be as selected by Engineer.
2.02 ACCESSORIES
A� Forms
I . Type: Metal or wood sealed to prevent faces from absorbing water from
Jose F. Vazquez. P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condominiurr�
Building "A"fo-u@0 Floor T
ftrae
Concrete Walkw
,)y �Llca . Restor o e
er.,
Page 10 of 20
concrete.
2. Treat with release agent compatible with concrete.
3. Forms shall be rigid, liquid -tight, and conforming to ACI 347R Class A.
B. Reinforcing Steel Supports & Spacers
I Reinforcing steel chairs and spacers shall be ofnon-feffous materials or 100%
vinyl coated free of rust, nicks, cuts or damage that will expose the metal
base.
PART 3 - EXECUTION
3.00 SHORING
A. Contractor shall provide shoring if necessary, bracing or support for all existing
structural elements to remain until all structural modifications have been completed
B. Shoring shall remain in place until components are adequate to maintain structural
loads.
3.01 CUTTING, DEMOLITION & PATCHING
A. The Contractor shall be responsible for cutting, demolishing, fitting, and patching all
degraded areas of the structure required to complete the Work. The contractor shall
not endanger other Work by cutting, excavating, demolishing or otherwise altering
other work and shall not cut or alter other Work except with written consent of the
Association and Engineer. Costs caused by defective or ill-timed Work shall be borne
by the Contractor.
B. Cutting, demolition or restoration performed by the Contractor which is unacceptable
by the Owner and Engineer shall have such correction or restoration work performed
when so instructed. The cost of such Work shall be home by the Contractor for
defective Work.
C. The Contractor shall not cut or demolish any portion of the building or structural
component(s) that may jeopardize the structural integrity or strength of the building
or its components without acceptance by the Engineer.
D. No holes except for small screws or bolts may be drilled in the beams or other
structural members for the purpose of supporting or attaching work without
obtaining prior approval from the Association.
Jose F. Vazc[uez, P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condomimunz- -
Building "N'F �ijhh Floor
Concrete Walkway Restoration?Reol�deihefif
77
Page 11 of 20
F7=,.
a
DO
3.02 SURFACE PREPARATION
A. All repair areas shall be prepared in accordance with International Concrete Repair
Institute's "Guide for Surface Preparation for the Repair of Deteriorated Concrete
Resulting from Reinforcing Steel Corrosiorf' (Guideline No. 03730). Thisincludes
but not limited to the following.
1. Concreteedge and surface spall repairs shall be used for those areas identified
with spalling and cracking of the concrete, and with a deterioration of the
reinforcing of not exceeding 15% of the original bar cross sectional area or
8% of the original bar diameter and as determined by the Engineer.
2. Remove all loose, spalled, and unsound concrete in the area of the
deterioration. Removal shall be performed'with small pointed tools (e.g.,
chipping hammers) rather than wide chisel edges to prevent micro cracking
and continued spalling ofthe concrete to remain. Chipping hammers shall not
be in excess of 15 pound rating.
3. The area of concrete to be removed shall extend along the length of the
reinforcing, beyond the limits of the reinforcing deterioration a minimum of
2" into sound -concrete. Care shall be taken not to damage the bond-between-
4. Concrete shall be removed completely around the reinforcing providing a
minimum clearance of I " between the reinforcing and the concrete to remain,
where possible.
Jose F. Vazquez, P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers CondonumunZ.-
'Lb F I o o r
Building "X' . r 777--"
Concrete Walkw e r e cement
eI
Page 12 of 20
5. Provide a I/z" minimum depth saw -cut, perpendicular or slightly underctit o
L_
if ifi6 k6�seaii.tN &el�� to prevent feathering of
the patch material. Do not cut any reinforcing, except as directed and
accepted by the Engineer prior to cutting.
r6l
7. Loose reinforcement shall be secured in place by tying to other secured bars
or by Engineer approved method.
8. Engineer shall determine the necessity of replacing or supplementing
reinforcing steel with reduced cross sectional areas caused by corrosion
damage.
9. Repair configuration should be kept as simple as possible to minin&e
boundary edges.
10. Prepare all concrete surfaces to receive the repair material, including the saw -
cut, to achieve a surface profile depth of 1/8" minimum with a new fractured
aggregate surface to adequately anchor the patch material. All bonding
inhibiting materials shall be removed by abrasive blasting or high pressure
water blasting.
11. Remove all rust and scaling of the reinforcing thoroughly by mechanical
means to SSPC-SPI I or sandblasting to SSPC-SPIO.
12.
Thoroughly clean the exposed concrete surface to receive the i6p
r1_73 I _ �a�if material
hgtt� of all traces of dirt, grease, oil, dust, loose aggregates, and other
13. Pre-soak repair substrate to a saturated surface dry condition.
B. BAR COATING AND BONDING
Following the completion of the surface preparation, coat all reinforcing steel using
one ofthe following two options. All existing and exposed concrete surfaces shall be
bonded using option (2) below.
1 . Apply anti -corrosion reinforcing bar coating EMACO P-22 in accordance
Jose F. Vazqaez, P.E., Civil -Structural Enginc�nn & Construction Services, (561) 848-5726
Ocean Towers Condomi
Building "A"E" Floor
Concrete IA'4!&w e drit
M Restoratio
gy
,se � 1� I — M*-,
Page 13 of 20
with the manufacturer's instructions.
2. Apply the epoxy bonding agent EMACO P-24 to the repaired concrete
surface in accordance with the manufacturer's instruction. Do not allow the
slurry to dry prior to application of the repair material. The slurry bonding
coat shall not be retempered.
3.03 REINFORCING STEEL REPLACEMENT
A. All reinforcing with deterioration exceeding 15% of the original bar cross sectional
area or 8% of the o#,p * A
bar diameter shall be replaced, as determined and directed
by the Engineer. Wfl-�
L �mper�atu
B. Prior to the repair, contractor shall shore, brace and otherwise support, the area to be
repaired, until the reinforcing has been replaced and the repair is completed.
C. The concrete removal shall be sufficient to achieve a minimum clearance of I " around
the existing reinforcing and the new reinforcing, placed beside the existing.
D. To permit lapping of the new reinforcing steel, the concrete shall be removed along
the length of the reinforcing, a minimum of 12" beyond the deterioration into sound
concrete to permit splicing of the reinforcing.
E. After the reinforcing has been prepared, lap the new reinforcing beside the entire
length of the exposed reinforcing, secure in place with the wires.
F. Where the removal of concrete to achieve the required lap length is not practical as
determined by the Engineer, bar development can be achieved by embedding the
reinforcing into existing sound concrete a minimum of 6" with Simpson Epoxy -Tie
system, or equal.
Lei,
Reinforcing steel shall be ASTM A615 Grade 60 minimum (Grade 40 minimum for
stirrups & ties).
Ocean Towers Condonu*m*urne.�
Building "N'Eourth Floor
Concrete Walkway Restoration4dolitbemeni,
)k�Lsed,@Lej.J1 -No �efijbbrJ9 1999.
Page 14 of 20
,-I
3.
94'-
3.04 FORMWORK
A. Keep unrestrained surface area of repair to a minimum.
B. Provide outlets to drain presoaking water, access points for placing concrete into
forms, and air vents as required.
C. Application of repair concrete shall not be less than 1/2" in depth.
3.05 NI]XING
E051A
All mixing shall be in accordance with the manufacturer's instructions and the following
recommendations. Where there is a conflict between the manufacturer's instruction and these
recommendation, the manufacturer's inkructions shall govern.
A. Mechanical mixing is recommended with the use of a slow speed drill and a jiffier
type paddle, or in an appropriate mortar mixer.
B. Typical mbicing time is 3 to 5 minutes. Do not mix longer than 5 minutes.
C. Do not add more water than it is recommended by the manufacturer.
D. Only that portion of the material that can be properly mixed within 10 minutes of
application should be used.
F4 �eklectl ro o' tiofiq�fh�,notmal,wei
r � - . 1 12 777=
21 rovi econcrete,td.l�h�-f6il6�hng.-'cnt--
R. eriw
Jose F. Vazquez, P.E., Civil-Stiuctural En&eering & Construcfion Services, (561) 848-5726
Ocean Towers Condominium�
Building "N' =01irth Floor
Concrete Walkway RestoratioA60k-e-in',e
Rg�jsed'(ReL-i� y6mber 19 LJ �99 9
� -1 No.
Page 15 of 20
KOR
91
0
DJ
5 r
1
2
-all
accor ance- se ion
gEe au surfraqesjo,
t _e 6 new ner
FA
lyjk�t -Arrild
,p) ��r__
IiiMistercuief 00i�
3.06 APPLICATION
A- All repair material shall be applied in accordance with the manufacturer's histructions.
B. Evaporation Retarder: Where rapid surface evaporation may occur, in hot, windy
conditions, apply evaporation retarder according to the manufacturer's
recommendations.
C. Finishing: Completed repair surfaces should be straight, true and match existing
profiles. Do not over -work the surface.
Jose F. Vazquez, P.E., Civil -Structural EngincerLmg & Construction Services, (561) 848-5726
Ocean Towers Condominium. -
Building "N' 6u4 Floor Fr777=
Concrete Walkway RestorationMeblii6elhe`
�-- 1. --- -
B��wsLed
.W,LJ).E(�vember- 19�,.
Page 16 of 20
D. Remove formwork after concrete has hardened sufficiently to permit forms to be
removed without damaging concrete, and having achieved 1450 psi compressive
strength, but not less than 24 hours.
3.07 CURING
All repaired surfaces must be cured for a minimum of 5 days with one of the following
methods.
3. Wet cure with burleen or wet burlap.
4. Ponding
5. Sheeting material
6. Liquid membrane forming curing compound per manufacturer's recommendations.
3.08 CRACK REPAIRS
A. GENERAL
Crack repairs will be performed for all areas identified by the Engineer.
2. Remove all loose and unsound concrete within and adjacent to the crack.
B. CRACK SEALING BY GRAVITY (SURFACE CRACKS)
Vee notch the surface of the crack with a mechanical router or hand chipping
tool to a maximum width of 1/4".
2. Remove loose debris and dust out of cracks and voids by compressed air or
other mechanical means as recommended by the manufacturer. Substratemay
be dry or damp prior to product application.
If the crack propagates through the slab or beam and where accessibility to
the underside of the beam or slab is available, seal all visible cracks with an
epoxy resin or �ortland cement based quick setting compound to act as a dam
to hold the liquid epoxy resin adhesive until cured.
4. Fill crack with EMACO S 88 CL-by trowel method or pour neat (no sand) low
viscosity material as recommended by manufacturer. -
5. Finish the material flush and to match with existing.
C. CRACK SEALING BY EPDXY INJECTION
Surfaces adjacent to cracks or other areas of application shall be cleaned of
Jose F. Vazquez, P.E., Civil-Stractural Engineering & Congraction Services, (561) 848-5726
Ocean Towers CondominituL—'
Building "N' E'd��qh� Floor
Concrete Walkwav RestorafionYR�tl
vr_
'Vise
embek",,12,
Page 17 of 20
dirt, dust, oil, and grease or other foreign matter which may be detrimental to
bond of injection surface seal.
2. Entry ports shall be provided along the crack at intervals of not less than the
thickness of concrete at that location.
3. Surface seal material shall be applied to the face of the crack between the
entry ports. Allow surface seal material to gain strength prior to injection.
4. Equipment for Injection: Provide injection equipment that is portable, positive
displacement type pump. The pump shall be electric or air powered and shall
provide in -line metering and mixing. Equipment shall have the capability of
maintaining the volume ratio for the epoxy adhesive within a tolerance of
5% by volume at any discharge pressure up to 160 psi.
5. Injection: Shall begin at the lowest entry port and continue until there is an
appearance of epoxy adhesive at the next port adjacent to the entry port being
pumped. The epoxy injection shall be transferred to the next adjacent port
where the adhesive has appeared. Injection shall be performed until cracks are
completely filled.
6. Finishing: When cracks are completely filled, epoxy adhesive shall be cured
for sufficient time to allow removal of surface seal without any draining or
run -back of epoxy adhesive material. Surface seal material and any adhesive
runs shall be removed from concrete surfaces. The face of the crack shall be
finished flush with concrete, showing no indentations or protrusions caused
by placement of entry ports.
7. Filling Cored Holes: After the Work has been accepted by the Engineer, cored
holes shall be repaired using a two component bonding agent and a suitable
repair mortar. The bonding agent shall be applied to the surfaces of the cored
holes, followed by application of repair mortar placed by hand trowel,
thoroughly rodded and tamped in place, and finished to match color, finish,
and texture of existing concrete
3.09 ELECTRICAL REPAIRS
A. All electrical work shall be performed by qualified licensed electrical contractors in
accordance with the National Electric Code and all applicable local building codes,
ordinances and regulations.
B. Degraded and/or corroded electrical conduits and components embedded in the
damaged concrete shall be removed and replaced as directed by the Engineer.
C. The electrical wires shall be disconnected and pulled back to the previousjunction box
Jose F. Vazquez, P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condominiun�_
Building "X'F' Floor
Concrete Walkway RestorationK�lacetften'
Page 18 of 20
or electrical fixture box prior to the removal ofthe degraded conduits or components.
Deteriorated or damaged wiring shall be replaced with new copper wiring ofthe same
or higher ampacity rating (size).
D. All new (replaced) electrical conduits shall be'Tigid Non -Metallic" (PVC, Type A,
Sch. 40 min.). All new (replaced) electrical fittings, boxes, support clips, etc. shall be
PVC and compatible with the "Rigid Non-MetaHic7' system.
E. New conduits shall be embedded in the concrete with a 1 " minimum cover and 1/2"
(min.) clearance from existing concrete surface to ensure repair material completely
encases the conduit without -air pockets or voids around the conduit.
F. Temporary power or provisions shall be made to ensure uninterrupted service to
stairwell lights, emergency exit signs, elevators, fire alarms, etc. is maintained.
G. Restore all wiring to its original configuration or as required by Code.
M
3.10 KVQ� FMSYIING
0
B. STUCCO
In areas where new concrete has been placed, and areas adjacent to such
areas, install coat of stucco, as required, to fill voids and match the surface
and texture of surrounding areas.
2. Exterior use of Portland cement plaster (stucco) shall comply with the
application and material requirements of ASTM C 926.
3. The limits of the stucco area affected by the repair shall be saw cut to sound
and well bonded stucco. All loose, damaged and degraded stucco shall be
- -removed. --- - -
4. Nbsonry and concrete surfaces on which stucco is applied shall be roughen,
cleaned, and damped (without visible surface water) to the degree required to
achieve mechanical bond. Apply bonding agent as required for proper
adhesion.
Jose F. Vazquez, P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condommiuir.,.��
Building Floor
Concrete Walkway Restoratioid/Roplib6fi6fit
C
Page 19 of 20
5. All concrete surfaces to receive stucco shall be coated with one of the
following bonding agents:
Weld -Crete, Larsin Products Corps.
Polyweld, Chem -Masters Corp.
Chemweld, Florida Laboratories.
6. Provide and install expansion joints where provided by original construction.
7. The first coat (base coat) shall be applied to a true surface approximately 1/2
the total thickness.
8. The base coat shall be damp cured for a period of 24 hours (min.).
9. The finish coat shall be applied over a uniformly damp but surface dry base.
10. The stucco shall be kept damp for a period not less than 48 hours. In lieu
thereof, approved water proofing curing agents may be used.
7�
C] ffi&D
BERRI
3.11 CAULK & JOINT SEALANTS
A. All caulk and joint sealants shall be installed in strict accordance with the
manufacturer's instructions and recommendations.
Jose F. Vazquez, RE., Civil-Stiuctural Enginccring & Construction Services, (561) 848-5726
Ocean Towers Condonuruurr.,.�
Building."N' oiLfthFloor r;.—
Concrete Walkway Restoration7116blib6inent
�,..Novernbek-,L9 ][990,
Page 20 of 20
B. After installation, all exposed and visible surfaces shall be thoroughly cleaned and free
from damage and defects. All damaged material or defects shall be replaced or
corrected at the Contractor's expense.
C. The Contractor shall notify the Engineer when the work has been completed and is
ready for the Engineer's inspection.
D. The Contractor shall furnish written warrantee that the work executed under this
section is free from defects of material and workmanship for a period of 2 (two)
years from date of final acceptance of this work, that he will, without delay and at his
own expense repair and replace all such defects as may develop during the term ofthis
guarantee.
OCEAN TOWERS WALKWAY SPEC R�I
Jose F. Vazquez, P.E., Civil -Structural Engineering& Construction Services, (561) 848-5726
Jose F. Vazquez, P.E.
Civil - Structural Engineering
Consulting Services
103 Champions Run
West Palm Beach, FL 33407
(561) 848-5726
kievij� i-November 1�'�'09'q
OCEAN TOWERS CONDOMINIUMS
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACI-I, FLORIDA
EXHIBIT "A"' - DRAWINGS
FOR
OCEAN TOWERS CONDOMINIUM ASSOCIATION� INC.
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEAC% FLORIDA 34957
(561) 229-2229
S. stair tower
14
4
OCEAN TOWERS CONDOMINIUM
BUILDING A
4TH FLOOR WALKWAY REPLACEMENT
elevator tower
replace these sections
ItligIR?
N. stair tower
Jose F. Vazquez, P.E.
Civil - Structural Engineering
Consulting Services
103 Champions Run
West Palm Beach, FL 33407
(561) 848-5726
OCEAN TOWERS CONDOMINIUMS
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACI-I, FLORIDA
PROJECT MANUAL
1010
-OCEAN TOWERS CONDOMINIUM ASSOCIATION, INC.
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACH, FLORIUDA 34957
(561) 229-2229
OCEAN TOWERS CONDOMINIMi'�-
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACH, FLORIDA
PROJECT MANUAL INDEX
CONTRACT DOCUMENTS
Standard Form of Agreement Between Owner and Contractor for a Small Project, AIA A105-1993
General Conditions of the Contract for Construction of Small Project, AIA A205-1993
PROJECT SPECMCATIONS
PARTI-GENERAL
1.00 PROJECT SCOPE
1.01 DESCRIPTION OF THE WORK
1.02 SITE ACCESS
1.03 COORDINATION
1.04 FIELD INSPECTIONS
1.05 SUBMITTALS
1.06 QUALITY ASSURANCE & WARILNNTIES
1.07 DELrvERY, STORAGE AND HANDLING
1.08 REFERENCES
PART2-PRODUCTS
2.00 MANUFACTURERS
2.01 MATERIALS
2.02 ACCESSORIES
PART 3 - EXECUT70N
3.00 SHORING
3.01 CUTTING, DEMOLITION & PATCHING
3.02 SURFACE PREPARATION
3,03 REINFORCING STEEL REPLACEMENT
3.04 FORMWORK
3.05 MD(ING
ERR EONCRETE TM
10513
3.06 APPLICATION
3.07 CURING
3.08 CRACK REPAIRS
3.09 ELECTRICAL REPAIRS
3.10 ��FINISHING
3.11 CAULK & JOINT SEALANTS
Jose F. Vazquez, P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
AIA Documeytt A-905
General Conditions of the Contract
for Construction of a Small Project
1993 SMALL PROJECTS EDITION
F-1AIN111=51
GENERAL PROVISIONS
1.1 THE CONTRACT
The Contract represents the entire and integrated agreement
between the parties and supersedes prior negotiations, repre-
sentations or agreements, either written or oral. The Contract
may be amended or modified only by a written modification.
1.2 THEWORK
The term "Work" means the construction and services required
by the Contract Documents, and includes all other labor, maEc-
nals, equipment and services provided by the Contractor to ful-
fill the Comirrictor's obligations.
1.3 INTENT
The intent of the Contract Documents is to include all items
necessary for the proper execution'and completion of the
Work by the Contractor. The Contract Documents are comple-
mentary, and what is required by one shall be as binding as if
required by all.
1.4 OWNERSHIP AND USE OF ARCHITECTS
DRAWINGS, SPECIFICATIONS
AND OTHER DOCUMENTS
Dcicumen�s prepared by the Architect are instruments of the
Architect*s service for use solely With respect to this project.
The Architect shall retain all common law, statutory and other
reserved rights, including the copyright. They are not to be
used by the Contractor or any Subcontractor, Sub-subcontrac-
for or material or equipment supplier for other projects or for
additions to this project outside the scope of the Work with-
out the specific written consent of the Owner and Architect.
ARTICLE 2
OWNER
2.1 INFORMATION AND SERVICES
REQUIRED OF THE OWNER
2.1.1 If requested by the Contractor, the Owner shall furnish
and pay for a survey and a legal description of the site.
2.1.2 Except for permits and fees which are the responsibility
of the Contractor under the Contract Documents, the Owner
shall obtain and pay for other necessary approvals, easements,
assessments and charges.
2-2 OWNER'S RIGHT TO STOP THE WORK
if the Contractor fails to correct Work which is not in accor-
dance with the Contract Documents, the Owner may direct
the Contractor in writing to stop the Work until the correction
is made.
2.3 OWNER'S RIGHT TO CARRY OUT THE WORK
if the Contractor defaults or neglects to carry out the Work in
accordance with the Contract Documents and fails within a
seven day period after receipt of written notice from the
Owner to correct such default or neglect With diligence and
promptness, the Owner may' without prejudice to other reme-
dies, correct such deficiencies. In such case, a Change Order
shall be issued deducting the cost of correction from pay
ments due the Contractor.
2.4 OWNER'S RIGHT TO PERFORM CONSTRU
AND TO AWARD SEPARATE CONTRACTS
2.4.1 The Owner reserves the right to perform construction or
operations related to the project with the Owner's own forces,
and to award separate contracts in connection with other por-
tions of the project.
2.4.2 The Contractor shall coordinate and cooperate with
separate contractors employed by the Owner.
2.4.3 Costs caused by. delays or by improperly timed activities
or defective construction shall be borne by the party respon-
sible therefor.
ARTICLE 3
CONTRACTOR
3.1 EXECUTION OF THE CONTRACT
Execution of the Contract bv the Contractor is a representa-
tion that the Contractor has visited the site. become familiar
With local conditions under which the Work is to be per-
formed and correlated personal observations with require-
ments of the Contract Documents.
3.2 REVIEW OF CONTRACT DOCUMENTS AND
FIELD CONDITIONS BY CONTRACTOR
The Contractor shall carefully study and compare the Contract
Documents with each other and with information furnished b%-
the Owner. Before commencing activities, the Contracto r
shall: (1) take field measurements and veriA, field conditions:
(2) carefully compare this and other information known to
OCopynght 1993 hv The American Institute of Architects. 1�35 xvw %'ork Aventle. N.W.. Wa�hmgton. D.C. 20006-5292. Reproduction of the material herein
or submantial quotation of its fmavtsiori without the written perntission of the A" violate.% the copyright law,% of the United State% and will subject the %loialor (0
lepi prosecution.
JUA DOCUMENT A205 - GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION—
SNIA11 PRQIECTS EDITION - AIA" 01993 - THE AINIERICAN INSTITIT-M. OF ARCHITECTS. 1735 NEW
YORKAVENUE. N.W.. WASHINGTON. D.C. 2LXXX�5292 - WARNING: Unlicensed photocopying
violates U.S. copyright laws and Will subject the violator to leg8i prosecution.
A205-1993 1
the Contractor with Elie Contract Documents: and (31
promptly report errors. I . ncorimstencies or onlissions discov-
ered to the Architect.
3.3 SUPERVISION AND CONSTRUCTION PROCEDURES
3.3.1 The Contractor shall supervise and direct the Work.
using the Contractor's best skill and attention. The Contractor
shall be solely responsible for and have control over construic-
ticin means, methods. techniques. sequences and procedures,
and for coordinating all portions of the Work.
3.3.2 The Contractor, US Soon as practicable after award of the
Contract. shall furnish in writing to the Owner through the
Architect the names of subcontractors or suppliers for each
portion of the Work. The Architect will promptly reph, to the
Contractor in writing if the owner or the Architect. ai�ter due
investigation, has reasonable objection to the subcontractors
or suppliers listed.
3.4 LABOR AND MATERIALS
3.4.1 Unless otherwise provided in the Contract Documents '
the Contractor shall provide and pay for labor. materials,
equipment, tools, utilities, transportation, and other facilities
and services necessary for proper execution and completion of
the Work.
3.4.2 The Contractor shall deliver. handle, store and install
materials in accordance with manufacturers' instructions.
3.5 WARRANTY
The Contractor warrants to the Owner and Architect that:
(1) materials and equipment furnished under the Contract will
be new and of good quality unless otherwise required or per-
mitted b%, the Contract Documents: (2) the Work will be free
from def�cts not inherent in the quality required or permitted:
and (3) the work will conform ED the requirements of the Con-
tract Documents.
3.6 TAXES
The Contractor shall Pay sales. consumer. use and similar taxes
that are legally required when the Contract is executed.
3.7 PERMITS, FEES AND NOTICES
3.7.1 The Contractor shall obtain and pay for tile building
permit and other permits and governmental fees. licenses and
inspections, necessary for proper execution and completion of
the Work.
3.7.2 Tile Contractor shall comply with and give notices
required by agencies having jurisdiction over the Work. If tile
Contractor performs Work knowing it to be contrary to laws.
statutes. ordinances. building codes. and rules and regulations
without notice to the Architect and Owner. the Contractor
shall assume full responsibility for such Work and shall bear
the attributable costs. The Contractor shall promptly noofi,
the Architect in writing of any known inconsistencies in
the Contract Documents with such governmental laws, rules
and regulations.
3.8 SUBMITTALS
The Contractor shall promptly review. approve in writing
and submit to Elie Architect Shop Drawings, Product Data.
Samples and similar submittals required by the Contract Docu-
merits. Shop Drawings, Product Data, Samples and shnilarsub-
Initials are not Contract Documents.
3.9 USE OF SITE
The Contractor shall confine operations at the site ill areas
permitted bv law, ordinances. permits. the Contract Docu-
menLs and & Owner.
3.10 CUTTING AND PATCHING
The Contractor shall be responsible for cutting. fitting or
patching required to complete the Work or to make its part.%
fit together properly.
3.11 CLEANING UP
The Contractor shall keep the premv�cs and surrounding area
free from accumulation of debris and trash related to the Work.
3.12 INDEMNIFICATION
To the fullest extent permitted by law. the Contractor shall
indemnify and hold harmless the6wner, Architect. Architect's
consultants and agents and employees of any of them from
and against claims. damages, losses and expenses. including
but not limited to attorneys' fees. arising out of or resulting
from performance of the Work. provided that such claim, dam-
age, loss or expense is attributable Lo bodily injurv, sickness.
disease or death, or to injury to or destruction of tangible
property (other than the Work itself) including loss of use
resulting therefrom, but only to the extent caused in whole or
in part by ne,
gligent acts or clinissions of the Contractor.a Sub-
contractor, anyone directIv or indirectly emploved by them or
anyone for whose acts they mav be liable, regardless of
whether or not such claim, damage. loss or expense is caused
in part by a party indemnified hereunder.
ARTICLE 4
ARCHITECT'S ADMINISTRATION OF THE CONTRACT
4.1 The Architect will provide administration of the Contract
as described in the Contract Documents. The Architect %N ill
have audioritv to act on behalf of the Owner oniv to the extent
provided in t�e Contract Documents.
4.2 The Architect will visit the site at intervals appropriate to
the stage of construction to become generally familiar with the
progress and quality of the Work.
4.3 The Architect will not have control Over or charge of and
will not.be responsible for consmction means. methods. tech.
niques. sequences or procedures. or for Safety precautions and
programs in connection with the Work. since these are solelv
the Contractor's responsibility. The Architect will not he'
responsible for the Contractor's failure to carn, out the Work
in accordance with the Contract Documents.
4.4 Ba.sed on the Architect's observations and evaluations of
the Contractor's Applications for Payment. the Architect will
reviewand certift, the amounts due Elie Contractor.
4.5 The Architect will have authoritv to reject Work that does
not conform to the Contract Documents.
4.6 The Architect will prompdy review and approve or take
appropriate action upon Contractor's submittals such US Shop
Drawings. Product Data and Samples. but oil[%. for Elie limited
purpose of checking for conformance with information given
anti the design concept expressed in tile Contract Documents.
4.7 The Architect will promptly interpret and decide mat.
ters concerning performance under and requirements of the
AIA DOCUMENT A205 - (;F.\i:RAI. CONDITIONS OF TIIH CON -I RM.7 FOR CONSnl:cnO.\'—
SMAIIA-R011'.CIN'RDITION -MA-01993 -11 IF NNIERIC&N 1-31 NIN'
NORKMINI E. NA'.. WASHIS6110N. D.C. 2()(X�5292 - WARNING: Unlicensed phot0copying
2 A205-1993 11 Q 1 -A —ill .l. .�_ — I --- I
Contract Documents on written request o� - .!-er the Owner
or Contractor.
11-1
the Contractor for perfa, ce of the Work under the Con-
tract Documents.
4.8 Interpretations and decisions of the Architect will be con-
SISEent with the intent of and reasonably inferable from the
Contract Documents and will be in writing or in the form of
drawings. When making such interpretations and deci sions '
the Aschitect will endeavor to secure faithful performance by
both Owner and Contractor, will not show partiality to either
and will not be liable for results of interpretations or decisions
so rendered in good faith.
4.9 The Architect's duties, responsibilities and limits of
authoritv as described in the Contract Documents will not be
changed without written consent of the Owner. Contractor
and Architect. Consent shall not be unreasonably withheld.
ARTICLE 5
CHANGES IN THE WORK
5.1 After execution of the Contract, changes in the Work may
be accomplished by Change Order or by order for a minor
change in the Work. The Owner, without invalidating the
Contract, may order changes in the Work Within the general
scope of the Contract consisting of additions, deletions or
other revisions, the Contract Sum and Contract Time being
adjusted accordingly.
5.2 A Change Order shall be a written order to the Contractor
signed by the Owner and Architect to change the Work, Con-
tract Sum or Contract Time.
5.3 The Architect will have authority to order minor changes
in the Work not involving changes in the Contract Sum or the
Contract Time and not inconsistent with the intent of the Con-
tract Documents. Such changes shall be written orders and
shall be binding on the Owner and Contractor. The Contractor
shall carry out such written orders promptly.
5.4 If concealed or unknown physical conditions are encoun-
tered at the site that differ maleriallv from (hose indicated
in the Contract Documents or from il�ose conditions ordinar-
i1v found to exist. the Contract Sum and Contract Time shall be
subject to equitable adjustment.
ARTICLE 6
TIME
6.1 Time limits stated in the Contract Documents are of the
essence of the Contract.
6.2 If the Contractor is delaved at any time in progress of
the Work by changes ordered in the iork, or by labor dis-
puEes. fire, unusual delay in deliveries. unavoidable casualties
or other causes bevond the Contractor's control, the Contract
Time shall be extended by Change Order for such reasonable
time as�rhe Architect may determine.
ARTICLE 7
PAYMENTS AND COMPLETION
7.1 CONTRACT SUM
The Contract Sum stated in the Agreement, including audit)-
rized adjustments. is the total amount payable by the Owner to
72 APPLICATIONS FOR PAYMENT
7.2.1 At least ten days before the date established for each
progress payment. the Contractor shall submit to the Architect
an itemized Application for Payment for operations completed
in accordance with the values stated in the Agreement. Such
application shall be supported by such data substantiating the
Contractor's right to payment as the Owner or Architect may
reasonably require and reflecting retainage if provided for else-
where in the Contract Documents.
7.2.2 The Contractor warrants that title to all Work covered
by an Application for Payment will pass to the Owner no later
than the time of payment. The Contractor further warrants
that upon submittal of an Application for Payment, all Work for
which Certificates for Pavment have been previously issued
and payments received from the Owner shall. to the best of
the Contractor's knowledge, information and belief, be free
and clear of liens, claims, security interests or other encum-
brances adverse to the Owner's interests.
7.3 CERTIFICATES FOR PAYMENT
The Architect will, within seven days after receipt of the Con-
tractor's Application for Payment, either issue to the Owner a
Certificate for Payment, with a copy to the Contractor, for such
amount as the Architect determines is properlv due, or notifir
the Contractor and Owner in writing of theArchitect's reason's
for withholding certification in whole or in part.
7.4 PROGRESS PAYMENTS
7.4.1 After the Architect has issued a Certificate for Payment,
the Owner shall make payment in the manner provided in the
Contract Documents.
7.4.2 The Contractor shall promptly pay each Subcontractor
and material supplier. upon receipt 4 payment from the
Owner. out of the amount paid to the Contractor on account
of such entities' portion of the Work.
7.4.3 Neither the Owner nor the Architect shall have respon-
sibility for the payment of money to a Subcontractor or mater-
ial supplier.
7.4.4 A Certificate for Payment. a progress payment. or par-
tial or entire use or occupancv of the project by the Owner
shall not constitute acceptan'�e of Work -not in' accordance
with the requirements of the Contract Documents.
7.5 SUBSTANTIAL COMPLETION
7.5.1 Substantial Completion is the stage in the progress of
the Work when the Work or designated portion thereof is
sufficiently complete in accordance with the Contract Docu.
ments so that the Owner can occupy or utilize the Work for its
intended use.
7.5.2 When the Work or designated portion thereof is sub-
stantialiy complete. the Architect will prepare a Certificate
of Substantial Completion which shall establish the date of
Substantial Completion, shall establish the responsibilities of
the Owner and Contractor, and shall fix the time within which
the Contractor shall finish all items on the list accompanying
[he Certificate. Warranties required by the Contract Docu-
ments shall commence on the date of Substantial Completion
of the Work or designated portion thereof unless otherwise
provided in the Certificate of Substantial Completion.
AIA DOCUMENT A205 - GFNER�l CONDITIONS OFTIIE CONTRACT FOR CONMUCTION—
S%tA11PR0iF.CrS EDITION -.-JA- - 01993 - T11EAMERICAN INSITM-M OFARCHITTiCTS. 1735NEW
YORKAVE.NIT N.W.. WASHINGT0%. D.C. 21)(0�5292 - WARNING: Unlicensed photocopying
violates U.S. copyright laws and will subject the violator to legal prosecution.
A205-1993 3
7.6 FINAL COMPLETION AND FINAL PAYMENT
7.6.1 Upon receipt of a final Application for Pavment. the
Architect will inspect the Work. Nnen the Architec't finds the
Work acceptable and the Contract filly performed, the Archi-
tect will promptly issue a final Certificate for Payment.
7.6.2 Final payment shall not become due until the Conirac-
tor submits to the Architect releases and waivers of liens, and
data establishing payment or satisfaction of obligations, such
as receipts, claims, security interests or encumbrances arising
out of the Contract.
7.6.3 Acceptance of final payment by the Contractor, a Sub-
contractor or material supplier shall constitute a waiver of
claims by that payee except those previously made in writing
and identified by that payee as unsettled at the time of final
Application for Payment.
ARTICLE 8
PROTECTION OF PERSONS AND PROPERTY
8.1 SAFETY PRECAUTIONS AND PROGRAMS
The Contractor shall be responsible for initiating, maintaining
and supervising all safety precautions and programs, includ-
ing all those required by law in connection with performance
of the Contract. The Contractor shall promptly remedy dam-
age and loss to property caused in whole or in part by the
Contractor, or by anyone for whose acts the Contractor may
be liable.
ARTICLE 9
CORRECTION OF WORK
9.1 The Contractor shall promptly correct Work rejected by
the Architect as failing to conform to the requirements of th�
Contract 'Documents. The Contractor shall bear the cost of
correcting such rejected Work.
9.2 In addition to the Contractor's other obligations including
warranties under the Coniract, the Contractor shall, for a period
of one year after Substantial Completion. correct work not con-
forming to the requirements of the Contract Documents.
9.3 If the Contractor fails to correct nonconforming Work
within a reasonable time, the Owner may correct it and the Con.
tractor shall reimburse the Owner for the cost of correction. -
ARTICLE 10
MISCELLANEOUS PROVISIONS
10.1 ASSIGNMENT OF CONTRACT
Neither party to the Contract shall assign the Contract as a
whole without written consent of the other.
10.2 TESTS AND INSPECTIONS
10.2.1 Tests, inspections and approvals of portions of the
Work required by the Contract Documents or by laws, ordi-
@ Printed on Rectcled Paper 11/93
nances. rules, regulations or orders of public authorities hav-
ing jurisdiction shall be made at an appropriate time.
10.2.2 If the Architect requires additional testing, the Con-
tractor shall perform these tests.
10.7-3 The Owner shall pay for tests except for testing Work
found to be defective for which the Contractor shall pay.
10.3 GOVERNING LAW
The Contract shall be governed by the law of the place where
the project is located.
ARTICLE 11
TERMINATION OF THE CONTRACT
11.1 TERMINATION BY THE CONTRACTOR
If the Owner fads to make payment when' due or substantially
breaches any other obligation of this Contract, following seven
days' written notice to the Owner, the Contractor may termi-
Date the Contract and recover from the Owner payment for
Work executed and for proven loss with respect to materials,
equipment, tools, construction equipment and machinery,
including reasonable overhead, profit and damages.
11.2 TERMINATION BY THE OWNER
11-2.1 The Owner may terminate the Contract if the
Contractor:
.1 persistently or repeatedly refuses or fails to supply
enough properly skilled workers or proper materials;
.2 fails to make payment to Subcontractors for materials
or labor in accordance with the respective agreements
between the Contractor and the Subcohtractors;
.3 persistently disregards laws, ordinances, or rules,
regulations or orders of a public authority having juris-
diction; or
.4 is otherwise guilty of substantial breach of a provision
of the Contract Documents.
11.2.2 When any of the above reasons exist. the Owner, after
consultation %ith the Architect, may without prejudice to any
other rights or remedies of the Owner and after giving the
Contractor and the Contractor's surety. if any, seven days' wriE-
ten notice, terminate.employment of the Contractor and may:
.1 take possession of the site and of all materials thereon
owned by the Contractor;
.2 finish the Work by whatever reasonable method the
Owner may deem expedient.
11.2.3 When the Owner terminates the Contract for one of
the reasons stated in Subparagraph 11.2. 1, the Contractor shall
not be entitled to receive further payment until the Work
is finished.
11.2.4 If the unpaid balance of the Contract Sum exceeds
costs of finishing the Work, such excess shall be paid to the
Contractor. If such costs exceed the unpaid balance, the Con-
tractor shall pay the difference to the Owner. This obligation
for payment shall survive termination of the Contract.
ALA DOCUMENT A205 - GENERAL OONDrnONS OF TI IE CON'TRACT FOR CONSTRUCTION —
SMALL PR(IIECTS FI)MON - ALA-' 01993 -THE AMF1UC4N INSTM-a.OFARCHITECTS. 1735 NEW
4 A205-1993 YORK AVFNUF N.W.. WASHINGTOX, D.C. 20006-5292 - WARNING: Unlicensedpholt0c0pying
Jose F. Vazquez, PE.
Civil - Structural Engineering
Consulting Services
103 Champions Run
West Palm Beach, FL 33407
(561) 848-5726
OCEAN TOWERS CONDOMMIUMS
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACEL FLORIDA
PROJECT SPECIFICATIONS
MIRI
OCEAN TOWERS CONDOMINIUM ASSOCIATION, INC.
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACH, FLORIDA 34957
(561) 229-2229
Ocean Towers Condorniniumb
Building "X'FZdrPh Floor
Concrete Walkwav RestorationYltepl4c
�emen�
se ev N6v&rfiber-j 2J.919
Pagel of20
PART I - GENERAL
1.00
A- LOCATION
Ocean Towers Condominium Building A
9400 South Ocean Drive
Hutchinson Island
Jensen Beach, Florida 34957
(561) 229-2229
B. CURRENT SITUATION
C.
In response to the request of the Association, on or about May of 1999, field
inspections of the above referenced buildings were conducted by the Mr. Abdel
Karim-Conrado, P.E.. The purpose of the inspections was to identify areas of
degradation of the concrete structure(s). Based on the results of the inspection, W
Karim-Conrado submitted copies of the field data sheets indicating the deteriorated
areas at the balconies and walkways.
Based on the review of the data sheets by Jose F. Vazquez, P.E., it was determined
that typical concrete degradation (e.g., surface deck spall, overhead spall, column
spall, overhead beam spall, slab edge spall, and surface cracks) were found throughout
the building structure with variation in severity from minor (surface cracks and spalls)
to severe (exposed corroded reinforcing steel). The soffit of the Building "N'
walkway was identified as one of the areas requiring immediate attention.
The Association retained the services of Jose F. Vazquez, P.E. to develop the
necessary engineering documents for the restoration ofthe structures and to act as the
Association's agent in the capacity of 'Engineer of Record" as defined in this proj ect
manual.
The term "Owner" is hereby defined as Ocean Towers Condominium
Association, Inc. or their duly appointed representative and agents. This term
may be used synonymously with "Association".
M8-zo 126
Ocean Towers Condominiumb' -
Building "A"NZill Floor
Concrete Walkway RestorationMeplacemcht
Page 2 of 20
2. The term "Association7' is hereby defined as Ocean Towers Condomirrium
Association, Inc. and it's individual owners. This term may be used
synonymously with "Owner".
3. The term "Engineer" or 'Engineer of Record" are hereby defined as Jose F.
Vazquez, P.E. or his duly appointed representative and agents.
4. Where "request", "approval", "satisfactory" and similar words appear, it is the
request, approval or satisfaction of the Engineer that is intended.
1.01 DESCRUMON OF THE WORK
A. The scope of work to be performed under the terms of this specification includes
furnishing of all materials, labor, services, utilities, permit fees, supervision, tools and
equipment, required or incidental to the demolition, replacement and repair of the
concrete areas located at the Building "N'third floor walkway soffit. The work will
include, but is not limited to, the following elements:
I .
0
3.
Removal of deteriorated embedded electrical conduits & component , e�'
9-
iundtiori-boxd,��and lijht�ffid and replace with new PVC
conduits/components and copper wiring.
4. Disposal of deteriorated concrete, reinforcing steel, construction debris, etc.
generated during the course of the work.
5. Surface preparation and installation of repair materials and reinforcing steel
as identified by the Engineer.
L�-7 7= 1 1 � ��
Fdrin�ifi&Le—c4t the � removed �Ledt —'i6nTsbY w—ajI—kw"ayL]J
Civil-Structurd Engineerine & Construction Services, (561) 848-5726
Ocean Towers Condommiumb
�J
Building"N' .6driliFloor
Concrete Walkway Restoration�*�h
ve
Page 3 of 20
�8
9. Application of concrete sealants6vef ent* ' wal!gALay
ire �A �ezd
10. Provide barriers for the protection of the existing elements.
11. Application of stucco finish to all repair surfaces, as required to match existing
wall firrish.
1.02 SITE ACCESS
I The building will be fully operational and occupied for the duration ofthe project. All
work required under this Contract shall be performed from the exterior ofthe building
except as authorized by the Engineer.
2. The Contractor's access to the site shall be limited from 8:00 AM to 6:00 P.M.
Monday through Friday, 8:00 A.Mto 4:00 P.M. on Saturday and in accordance with
any applicable regulations by St. Lucie County agencies having jurisdiction in
Hutchinson Island and the Association. Work bythe Contractor will not be permitted
on Sundays or any nationally observed holidays.
3. The Contractor, Subcontractors and their employees shall not be permitted inside any
of the Association's buildings and shall be prohibited fi7om using any of the
Association's facilities such as restrooms, swimming pool, tennis courts, etc., and
shall be confined to those immediate areas necessary to accomplish their work and as
designated by the Association.
4. The Contractor shall be responsible to properly supervise his and his Subcontractor
employees as to proper language, conduct, dress and noise consistent with the
Association's rules & regulations.
Alcohol or drugs on the site or any individual or employee under the influence of
these substances will not be tolerated and will be grounds for dismissal.
6. The Engineer or the Association shall have the right to require the Contractor or
Subcontractors to remove from the project, with cause, any employee.
7. The Contractor shall provide the Engineer with a Est of all personnel to be employed
at thejob site in accordance with the Association's security policy and requirements.
Jose F. Vazquez, P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condominium��
Buil ing "A" ourt oor
Concrete W estoratiorillkeolace-rnLn�
6q&
Page 4 of 20
1.03
The Contractor shall;
A. Coordinate scheduling, submittals, and Work of various sections of the specifications
to ensure efficient and orderly sequence of installation of independent construction
elements.
B Coordinate dumpster location, staging and storage requirements with the Association.
The staging area shall be acceptable to the Association and not interfere with the
operation of the facility.
C. Coordinate use of on -site utilities (e.g., potable water and electricity) with the Owner.
The Contractor may use at no cost to the Contractor, water and electricity available
on the exterior of the building for the performance of the work. Utility requirements
beyond those available on site shall be provided by the Contractor at his expense.
D. Coordinate access to the site and hours of operation with the Association.
E. Coordinate the location of on -site communication acceptable to the Association. The
Contractor shall provide a telephone fine or other means of on -site communication for
it's use.
F. Provide and coordinate a location, acceptable to the Association, for on -site
temporary toilet facilities as required for it's use.
G. Coordinate with the Association concerning the delivery and removal of materials,
equipment and other items to and from the site.
H. Coordinate with the Association the removal and replacement of exterior doors,
sliding glass doors and windows. The Association, at their option, request the
installation of new sliding glass doors or windows. New sliding glass doors or
windows shall be selected by the Association.
1.04 FTELD INSPECITONS
A. The Engineerwill observe and/or inspect all work ashe deems necessary to verifythat
existing site conditions and substrate surfaces are acceptable for subsequent Work and -
for general conformance to the contract documents. Surface preparation of all repair
areas shall be observed and accepted by the Engineer prior to placement of the repair
materials. Work shall not be covered until approved by the Engineer.
B. Engineer shall be notified a minimum of 24 hours prior to all observations.
C. The Contractor shall verify that utility services are available, of the correct
Jose F. Vazc[uez, P.R. Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condominiumb
Building "N' oor
Concrete Walkwav Restoratior�Re�licefti6fii
Page5 of`20
characteristics and in the correct location.
D. The Contractor shall inspect upon receipt on site all finished products (e.g.,balusters
and railings, doors and frames, shutters, etc.) and assume fill! responsibility for proper
handling and storage. Any damage to delivered and/or stored items as a result of
storage or handling shall be at the Contractor's expense.
E. The Contractor shall be responsible for inspecting all items to be removed (e.g.,
railings, shutters, doors & frames, etc.) and document, via video tape, photos,
sketches, written description, etc., the condition ofthe item(s) prior to performing any
work in their immediate area. Any remedy (including replacement) to damage to the
item(s) as a result of the work, handling, storage, etc. shall be at the sole expense of
the Contractor and to the satisfaction of the Engineer.
1.05 SUBMITTALS
A. Contractor shall submit to the Engineer for review and acceptance, concrete mix
designs, manufacturer's product information and manufacturer's installation
instructions for all materials specified prior to proceeding with the Work.
B. Manufacturers and products shall be considered "or equivalenf" as accepted by the
Engineer.
C. Submit the executed warranty, with authorized signatures (e.g., General Contractor,
Construction Company Officer/Owner), after acceptance of the repairs'.
D. A copy of all required permits, licenses, certificates and approvals shall be delivered
to the Engineer and a copy shall be posted in a prominent location at the work site
prior to commencement of the work.
E. Submit partial and final release of liens as required.
1.06 QUALITY ASSURANCE & WARRANTIES
A- Contractor Qualifications: Company or individual contractor with a minimum ofthree
(3) years' documented experience acceptable to the Owner.
B. Comply with Manufacturer's instructions related to mixing and placing of the
materials.
C. Protection of work: Protect installed work and prohibit traffic or storage upon
repaired, waterproofed, or coated surfaces.
D. Atproject completion, Contractor shall issue afive (5) yearwarranty against defective
Jose F. Vazouez. P.E.. Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condomintumb
Building Floor ----------
ConcreteWalkwayRestoratio pladefti6rit
Xe
Page 6 of 20
materials and/or worlananship of Contractor's work.
E. Within the Contractor's warranty period, any defective areas shall be repaired to the
satisfaction of the Engineer, at the Contractor's sole expense. Contractor's expense
will include all costs for material, equipment and labor as necessary to correct the
defective work. This work shall be completed by the Contractor immediately after
receiving notification.
1.07 DELIVERY, STORAGE AND EANDLING
1.08
A. Deliver products in original unopened containers with the manufacturer's name,
labels, product identification and batch numbers.
B. Store and condition the specified products as recommended by the manufacturer.
Products shall remain unopened until ready for use.
C. Where mixing of components is required, use complete pre -measured units.
The following references are incorporated into the specifications. Unless noted otherwise, the
specification, standard, etc. fisted below shall be the latest revision in effect on the date noted
on the Project Manual.
A. ACI 301 "Specification for Structural Concrete for Buildings".
B. ACI 305 "Hot Weather Concreting".
C. ACI 304 "Recommended Piactice for Measuring, Mixing, Transporting, and Placing
Concrete".
D.
E.
F.
G.
H.
-K.
0.
ACI 308 "Recommended Practice for Curing Concrete".
ACI 309 "Guide for Consolidation of Concrete"
ACI 311 "Recommended Practice for Concrete Inspection".
ACI 318 "Building Code Requirements for Reinforced Concrete"
ACI 347 "Recommended Practice for Concrete Formwork".
ACI 546R "Concrete Repair Guid&'.
ACI 614 "Recommended Practice for Measuring, Mixing, and Placing Concrete".
ASTM A615 "Standard Specifications for Deformed and Plain Billet -Steel Bars for
Concrete Reinforcemenf '.
ICRI - Guideline No. 03730, "Surface Preparation for Repair of Deteriorated
Concrete Resulting from Reinforcing Steel Corrosion".
N
Ocean Towers Condominiums
Building "N' 0 Floor
Concrete Walkwav Restoratiolf/k6placerneni
't '', "— -1� -Ir ---- -� � � —
&e vember 19- 1994'
3 �ed(Apv. 1).No_.
Page 7 of 20
Q. ICRI - GuidelineNo. 0373 1, "Guide for Selecting Application Methods fortheRepair
of Concrete Surfacee'.
R. ICRI - GuidelineNo. 03733, "Guide for Selecting and Specifying Materials forRepair
of Concrete Surfaces".
S. SSPC - SP6, "Commercial Blast Cleaning".
T. SSPC - SPI I, 'Tower Tool Cleaning to Bare Metar'.
PART 2 - PRODUCTS
2.00 ALANUFACTURERS
A. Master Builders (Concrete Repair)
B. Sonneborn Building Products (Caulk & Joint Sealants)
C. Other Manufacturers may be used upon approval of the Engineer. Alternate product
data shall include verification that the alternate products are equivalent to the
specified Master Builders products listed below.
2.01 MATERULS
Subject to compliance with other requirements in this specification, provide the following
materials aij 67eiinigg appzW6�v�d
WA
r1i
151
Jose F. Vazquez, P.E., Civil -Structural Engineering & Constmction Services, (561) 848-5726
Ocean Towers Condommiumb
Building "N'f'
L6�h Floor
Concrete Walkwav RestorationMpla6biii6rif
Page 8 of 20
B. CONCRETE CAST -IN -PLACE
1. EMACO S66 CL - Flowable, shrinkage -compensated structural repair
concrete. Provide a single component shrinkage -compensated, silica fume
modified, cement based mortar for structural repairs of distressed horizontal,
vertical or overhead concrete.
2. Aggregate: Shall conform to ASTM C33, aggregate for incorporation with
bagged mortar shall be 3/8", well graded and clean.
A� SURFACE REPAIR MORTAR
EMACO S88 CL - Sprayable, shrinkage -compensated structural repair
mortar. Provide a single component shrinkage -compensated, silica fume
modified, cement based mortar for structural repairs of distressed vertical or
overhead concrete.
2. SHOTPATCH 21 — Sprayable silica fume structural shotcrete repair mortar.
Provide a single component (prepackaged) shrinkage -compensated, silica
fume modified, cement based mortar for structural repairs of distressed
vertical or overhead concrete.
B. ANTI -CORROSION & BONDING AGENTS
EMACO P-22 - Flexible cementitious rebar coating. Provide polymer
modified, cement based coating with corrosion inhibiting admixture to provide
protection for reinforcing steel.
2. EMACO P-24 - Water based epoxy/cementitious bonding agent and rebar
coating. Provide Water based epoxy/cementitious for bonding concrete and
mortar to exiting concrete. Also, may be used as a rebar coating system to
protect against corrosion.
C. WATER
Water to be clean and potable free of oil, alkali or other deleterious material.
D. PORTLAND CEMENT PLASTER (STUCCO)
All CBS masonry and concrete surfaces shall be coated/patched to match
existing adjacent surface to the extent practical. Stucco shall be applied after
the repair material has cured for the required time.
2. Stucco material shall be
Ocean Towers Condominiums -
Building "X'E� Floor '7��-
Concrete Walkwa)(Restoration�Rd�l�-tLee�en
— — , 1,� �
�6�vem�ef-19149-09
Page 9 of 20
and/or plastic cement conforming to ASTM C 926.
E. REINFORCEMENT
Reinforcing steel: ASTM C 615, Grade 60 (Grade 40 for stirrups & ties) billet
steel deformed bars.
H. DISSEVI]LAR. MATERIALS
All dissimilar metals and materials shall be adequately isolated. Metal
electrical conduits and components shall be isolated from all structural steel.
The Engineer shall be notified of any conditions where proper isolation can
not be achieved.
1. CAULKS & JOINT SEALANTS
1 Caulk & Joint Sealants shall be as manufactured by Sonnebom Building
Products or approved equal.
2. Interior general purpose acrylic latex caulk shall be "Sonolac7conforming to
ASTM C 834.
Sealant for exterior vertical or horizontal joints not subject to traffic shall be
Sonolastic NP 1, one component gun -grade polyurethane sealant conforming
to Federal Specification TT-S-00230C.
4. Sealant for exterior horizontal joints subject to traffic shall be Epolith P or
Epohth G epoxy joint filler.
5. Backer Rod shall be a closed cell foam ' non -staining, compatible with sealant
and primer and of a resilient nature equal to Sonofoam Backer -Rod. Install in
accordance with manufacturer's recommendation as to size required to suit
joint width to depth ratio.
6. Solvents, cleaning agents, and other accessory materials shall be as
recommended by caulking or sealant manufacturer.
- 7. Colors for exposed (visible) applications and not subject to- painting or
covering shall be as selected by Engineer.
2.02 ACCESSORIES
A. Forms
1. Type: Metal or wood sealed to prevent faces from absorbing water from
Jose F. Vazquez, P.E., Civil -Structural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condominiums
Building "X't Floor
Concrete W�" Restorationa Me
Page 10 of 20
concrete.
2. Treat with release agent compatible with concrete.
3. Forms shall be rigid, liquid -tight, and conforming to ACI 347R Class A.
B. Reinforcing Steel Supports & Spacers
1. Reinforcing steel chairs and spacers shall be oftion-ferrous materials or 100%
vinyl coated free of rust, nicks, cuts or damage that will expose the metal
base.
PART 3 - EXECUTION
3.00 SHORING
A. Contractor shall provide shoring if necessary, bracing or support for all existing
structural elements to remain until all structural modifications have been completed
B. Shoring shall remain in place until components are adequate to maintain structural
loads.
3.01 CUTTING, DEMOILMON & PATCHING
A. The Contractor shall be responsible for cutting, demolishing, fitting, and patching all
degraded areas of the structure required to complete the Work. The contractor shall
not endanger other Work by cutting, excavating, demolishing or otherwise altering
other work and shall not cut or alter other Work except with written consent of the
Association and Engineer. Costs caused by defective or ill-timed Work shall be borne
by the Contractor.
B. Cutting, demolition or restoration performed by the Contractor which is unacceptable
by the Owner and Engineer shall have such correction or restoration work performed
when so instructed. The cost of such Work shall be bome by the Contractor for
defective Work.
C. The Contractor shall not cut or demolish any portion of the building r structural
component(s) that may jeopardize the structural integrity or strength of the building
or its components without acceptance by the Engineer.
D. No holes except for small screws or bolts may be drilled in the beams or other
structural members for the purpose of supporting or attaching work without
obtaining prior approval from the Association.
Jose F.,Vazquez, P.E., Civil-Stiuctural Engineering & Construction Services, 561) 848-5726
Ocean Towers"CondonfimunIzi
1171_�,_T,R�
Building 'Floor
Concrete Walkw RestorationMefilade ffikfiR'
e
Page 11 of 20
I
M
KU_l
3.02 SURFACE PREPARATION
A- All repair areas shall be prepared in accordance with International Concrete Repair
Institute's "Guide for Surface Preparation for the Repair of Deteriorated Concrete
Resulting from Reinforcing Steel CorTosion7 (Guideline No. 03730). This includes
but not limited to the following.
Concrete edge and surface spall repairs shall be used for those areas identified
with spalling and cracking of the concrete, and with a deterioration of the
reinforcing of not exceeding 15% of the original bar cross sectional area or
8% of the original bar diameter and as determined by the Engineer.
2. Remove all loose, spalled, and unsound concrete in the area of the
deterioration. Removal shall be performed with small pointed tools (e.g.,
chipping hammers) rather than wide chisel edges to prevent micro cracking
and continued spalling ofthe concrete to remain. Chipping hammers shall not
be in excess of 15 pound rating.
The area of concrete to be removed shall extend along the length of the
reinforcing, beyond the limits of the reinforcing deterioration a minimum of
-2" into sound -concrete. Care shall be taken not -to -damage the bond between-
4. Concrete shall be removed completely around the reinforcing providing a
minimum clearance of I " between the reinforcing and the concrete to remain,
where possible.
jose F. Vazc1nez, P.E., Civil-StructuW Engineering & Construction Services, (561) 848-5726
Ocean Towers Condomml'umb
==71M;
Building "A" I -- or
Concrete Walkwa m it
,XAcstoration?k66lk'6
Page 12 of 20
5. Provide a 112." minimum depth saw -cut,
the concrete surface at the limits of the
to prevent feathering of
the patch material. Do not cut any reinforcing, except as directed and
accepted by the Engineer prior to cutting.
0
7. Loose reinforcement shall be secured in place by tying to other secured bars
or by Engineer approved method.
8. Engineer shall determine the necessity of replacing or supplementing
reinforcing steel with reduced cross sectional areas caused by corrosion
damage.
9. Repair configuration should be kept as simple as possible to minimize
boundary edges.
10. Prepare all concrete surfaces to receive the repair material, including the saw -
cut, to achieve a surface profile depth of %" minimum with a new fractured
aggregate surface to adequately anchor the patch material. All bonding
inhibiting materials shall be removed by abrasive blasting or high pressure
water blasting.
11. Remove all rust and scaling of the reinforcing thoroughly by mechanical
means to SSPC-SP1 I or sand blasting to SSPC-SPl 0.
12.
Thoroughly clean the exposed concrete surface to receive the L
RG1-1.1
of all traces of dirt, grease, oil, dust, loose aggregates, and other
13. Pre-soak repair substrate to a saturated surface dry condition.
B. BAR COATING AND BONDING
Following the completion of the surface preparation, coat all reinforcing steel using
one ofthe following two options. All existing and exposed concrete surfaces shall be
bonded using option (2) below.
I . Apply anti -corrosion reinforcing bar coating ENUCO P-22 in accordance
Jose F.
Ocean Towers Condominiums
Building "X'� Floor
Concrete Walkway Restoration7.RW66-e'm'euf
iv
KeA�ejdlf k
)tj�JILN,o
�,Veifi
Page 13 of 20
with the manufacturer's instructions.
2. Apply the epoxy bonding agent EMACO P-24 to the repaired concrete
surface in accordance with the manufacturer's instruction. Do not allow the
slurry to dry prior to application of the repair material. The slurry bonding
coat shall not be retempered.
3.03 REINFORMG STEEL REPLACEMENT
A. All reinforcing with deterioration exceeding 15% of the original ba * r cross sectional
area or 8% of the o6fi'nal bar diameter shall be replaceo ermin and directed
as det med
by the Engineer. LA.ULie 1-be!'Leenio'y'ed &,,f �'1466cdl
�L�
B. Prior to the repair, contractor shall shore, brace and otherwise support, the area to be
repaired, until the reinforcing has been replaced and the repair is completed.
C. The concrete removal shall be sufficient to achieve a minimum clearance of I " around
the existing reinforcing and the new reinforcing, placed beside the existing.
D. To permit lapping of the new reinforcing steel, the concrete shall be removed along
the length of the reinforcing, a minimum-of-12" beyond the deterioration into sound
concrete to permit splicing of the reinforcing.
E. After the reinforcing has been prepared, lap the new reinforcing beside the entire
length of the exposed reinforcing, secure in place with the wires.
F. Where the removal of concrete to achieve the required lap length is not practical as
determined by the Engineer, bar development can be achieved by embedding the
reinforcing into existing sound concrete a minimum of 6" with Simpson Epoxy -Tie
system, or equal.
IV]
Reinforcing steel shall be ASTM A615 Grade 60 minimum (Grade 40 minimum for
stirrups & ties).
Ocean Towers Condomimunts -
1
Building "N' kM Floor
Concrete Walk"�U RestorationOteplacern t
AM V
Page 14 of 20
V5
j
3.04 FORM"
A. Keep unrestrained surface area of repair to a minimum.
B. Provide outlets to drain presoaking water, access points for placing concrete into
forms, and air vents as required.
C. Application of repair concrete shall not be less than 1/2" in depth.
U�I V4 �11
All mixing shall be in accordance with the manufacturer's instructions and the following
recommendations. Where there is a conflict between the manufacturer's instruction and these
recommendation, the manufacturer's instructions shall govern.
A. Mechanical mixing is recommended with the use of a slow speed drill and a jifller
type paddle, or in an appropriate mortar mixer.
B. Typical mbdng time is 3 to 5 minutes. Do not mix longer than 5 minutes.
C. Do not add more water than it is recommended by the manufacturer.
D. Only that portion of the material that can be properly mixed within 10 minutes of
application should be used.
K--I 6
E
IRE
121
Jose F. Vazquez, P.E., Civil-Stnwtuml Engineering & Construction Services, (561) 848-5726
Ocean Towers Condomimumb
Building F Floor
Concrete Walkway RestorationmtWAce'
6V-I - 9-99
Page 15 of 20
'II-=IdCi lul
-2- r
11
I 5B CON REPA19
11
El
5
�gtdtk—Ntfi s �M�
3.06 APPLICATION
A- All repair material shall be applied in accordance with the manufacturer's instructions.
B. Evaporation Retarder: Where rapid surface evaporation may occur, in hott, * y
conditions, apply evaporation retarder according to the manufacturer's
recommendations.
C. Finishing: Completed repair surfaces should be straight, true and match existing
profiles. Do not over -work the surface.
Jose F. Vazquez, P.E., Civil -Structural Engineering & Conkmction Services, (561) 848-5726
Ocean Towers Condominiunis;-,
Building "A7'E_ 4 Floor r��777M
Concrete WQ�A
,u � a
x Regg�
�t�io
�7M7,� =-7- - 7 7,
MM—OXBLe
Page 16 of 20
D. Remove formwork after concrete has hardened sufficiently to permit forms to be
removed without damaging concrete, and having achieved 1450 psi compressive
strength, but not less than 24 hours.
3.07 CURING
All repaired surfaces must be cured for a minimum of 5 days with one of the following
methods.
3. Wet cure with burleen or wet burlap.
4. Ponding
5. Sheeting material
6. Liquid membrane forming curing compound per manufacturer's recommendations.
3.08 CRACK REPAIRS
A. GENERAL
Crack repairs will be performed for all areas identified by the Engineer.
2. Remove all loose and unsound concrete within and adjacent to the crack.
B. CRACK SEALING BY GRAVITY (SURFACE CRACKS)
Vee notch the surface of the crackwith a mechanical router or hand chipping
tool to a maximum width of 1/4".
2. Remove loose debris and dust out of cracks and voids by compressed air or
other mechanical means as recommended by the manufacturer. Substratemay
be dry or damp prior to product application.
3. If the crack propagates through the slab or beam and where accessibility to
the underside of the beam or slab is available, seal all visible cracks with an
epoxy resin or portland cement based quick setting compound to act as a dam
to hold the liquid epoxy resin adhesive until cured.
4. Fill crack with EMACO S88 CL by trowel method or pour neat (no sand) low
- - viscosity material -as -recommended -by manufacturer.
5. Finish the material flush and to match with existing.
C. CRACK SEALING BY EPDXY INJECTION
I . Surfaces adjacent to cracks or other areas of application shall be cleaned of
— Jose F. Vazquez, P.E., Civil -Structural F� & Construction Services, (561) 848-5726
Ocean Towers Condominiumb"
Building "N' &L� Floor
Concrete Walkw 977777777779
storationYftlab6iiiefif
�;�G!.J-_N�v6nrber-19_4999,
Page 17 of 20
dirt, dust, oil, and grease or other foreign matter which may be detrimental to
bond of injection surface seal.
2. Entry ports shall be provided along the crack at intervals of not less than the
thickness of concrete at that location.
3. Surface seal material shall be applied to the face of the crack between the
entry ports. Allow surface seal material to gain strength prior to injection.
4. Equipment for Injection: Provide injection equipment that is portable, positive
displacement type pump. The pump shall be electric or air powered and shall
provide in -line metering and mixing. Equipment shall have the capability of
maintaining the volume ratio for the epoxy adhesive within a tolerance of
5% by volume at any discharge pressure up to 160 psi.
5. Injection: Shall begin at the lowest entry port and continue until there is an
appearance of epoxy adhesive at the next port adjacent to the entry port being
pumped. The epoxy injection shall be transferred to the next adjacent port
where the adhesive has appeared. Injection shall be per -formed until cracks are
completely filled.
6. Finishing: When cracks are completelyfilled, epoxyadhesive shall be cured
for sufficient time to allow removal of surface seal without any draining or
run -back of epoxy adhesive material. Surface seal material and any adhesive
runs shall be removed from concrete surfaces. The face of the crack shall be
finished flush with concrete, showing no indentations or protrusions caused
by placement of entry ports.
Filling Cored Holes: After the Work has been accepted by the Engineer, cored
holes shall be repaired using a two component bonding agent and a suitable
repair mortar. The bonding agent shall be applied to the surfaces ofthe cored
holes, followed by application of repair mortar placed by hand trowel,
thoroughly rodded and tamped in place, and finished to match color, finish,
and texture of existing concrete
3.09 ELECTRICAL REPAERS
A. All electrical work shall be performed by qualified licensed electrical contractors in
- accordance with the National Electric Code and -all applicable local building -codes,
ordinances and regulations.
B. Degraded and/or corroded electrical conduits and components embedded in the
damaged concrete shall be removed and replaced as directed by the Engineer.
C. The electrical wires shall be disconnected and pulled back to the previousjunction box
— Jose F. Vazquez, P.E., Civil-Stnictural Engineering & Construction Services, (561) 848-5726
Ocean Towers Condominiums -'
Building '-A"Eo=iiftfi Floor r�vl
Concrete WalkwR
,Y Restoratiorrlltepl�6eirrnt
�K(RLey.'J)LN-6 99
Page 18 of 20
or electrical fixture box prior to the removal ofthe degraded conduits or components.
Deteriorated or damaged wiring shall be replaced with new copper wiring ofthe same
or higher ampacity rating (size).
D. All new (replaced) electrical conduits shall be'Tigid Non -Metallic" (PVC, Type A,
Sch. 40 min.). All new (replaced) electrical fittings, boxes, support clips, etc. shall be
PVC and compatible with the'T%igid Non-Metaflic" system.
E. New conduits shall be embedded in the concrete with a V minimum cover and V2"
(min.) clearance from existing concrete surface to ensure repair material completely
encases the conduit without air pockets or voids around the conduit.
F. Temporary power or provisions shall be made to ensure uninterrupted service to
stairwell lights, emergency exit signs, elevators, fire alarms, etc. is maintained.
G. Restore a wiring to its original configuration or as required by Code.
3.10 RU4�U FTMSYUNG
F.11
B. STUCCO
In areas where new concrete has been placed, and areas adjacent to such
areas, install coat of stucco, as required, to fill voids and match the surface
and texture of surrounding areas.
2. Exterior use of Portland cement plaster (stucco) shall comply with the
application and material requirements of ASTM C 926.
3. The Iiinits of the stucco area affected by the repair shall be saw cut to sound
and well bonded stucco. All loose, damaged and degraded stucco shall be
- — --remove&-
4. Masonry and concrete surfaces on which stucco is applied shall be roughen,
cleaned, and damped (without visible surface water) to the degree required to
achieve mechanical bond. Apply bonding agent as required for proper
adhesion.
— Jose F. Vazquez, P.E., CiA-Stmctural Engineerigg & Construction Services, (561) 848-5726
Ocean Towers Condoniiniuni'9
Building "N'F' Floor
Concrete Walkway Restoratiop�g8�*,eM nt
Page 19 of 20
5. All concrete surfaces to receive stucco shall be coated with one of the
following bonding agents:
Weld -Crete, Larsin Products Corps.
Polyweld, Chem -Masters Corp.
Chemweld, Florida Laboratories.
6. Provide and install expansion joints where provided by original construction.
7� The first coat (base coat) shall be applied to a true surface approximately V2
the total thickness.
8. The base coat shall be damp cured for a period of 24 hours (min.).
9. The finish coat shall be applied over a uniformly damp but surface dry base.
10. The stucco shall be kept damp for a period not less than 48 hours. In lieu
thereof, approved water proofing curing agents may be used.
UF. 1 11- 1 - - , �� . " 71147177,77�
s � Z 77",7_7�
ILI
MArk , Y�
'04V.,`,twb,�66ats� Ii fld6r§ 77= ",777M
p IrOW6106f
3.11 CAULK & JOINT SFALANTS
A- All caulk and joint sealants shall be installed in strict accordance with the
manufacturer's instructions and recommendations.
Jose F. Vazqttez, P.E., Civil-Stiuctural En&qe#qg & Construction Services, (561) 848-5726
Ocean Towers Condommrunii�-
Building "N' =,quilli Floor
Concrete Walkway Kestoratio -16cement
777�---F - `=- �91
dVemh,�r-'11Q,-.I -9-99
Page 20 of 20
B. After installation, all exposed and visible surfaces shall bethoroughly cleaned and free
from damage and defects. All damaged material or defects shall be replaced or
corrected at the Contractor's expense.
C. The Contractor shall notify the Engineer when the work has been completed and is
ready for the Engineer's inspection.
D. The Contractor shall furnish written warrantee that the work executed under this
section is free from defects of material and workmanship for a period of 2 (two)
years from date of final acceptance ofthis work, that he will, without delay and at his
own expense repair and replace all such defects as may develop during the term of this
guarantee.
OCEAN TOWERS WALKWAY SPEC R"I
Jose F. Vazquez, P.E., Civil-Sftuctural Engineering & Constraction Services, (561) 848-5726
lose F. Vazquez, P.E.
Civil - Structural Engineering
Consulting Services
103 Champions Run
West Palm Beach, FL 33407
(561) 848-5726
OCEAN TOWERS CONDOMINIUMS
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACH, FLORIDA
EXHMIT "A"' - DRAWNGS
FOR
OCEAN TOWERS CONDOMINIUM ASSOCIATION� INC.
9400 SOUTH OCEAN DRIVE
HUTCHINSON ISLAND
JENSEN BEACH, FLORIDA 34957
(561) 229-2229
OCEAN TOWERS CONDOMINIUM
BUILDING A
4TH FLOOR WALKWAY REPLACEMENT
S. stair tower elevator tower
replace these sections
91f . ef I �
N. stair tower
04
?ABKAR ENGINEERING INC.
Consulting Engineers
July 9,1998
W Jose Guanch
St. Lucie Building Department
2300 Virginia Ave., Room 201
I
Fort Pierce, FL 34982-5652 Ar
Ref: Structural Repairs at
Ocean Towers Condominium JUL 13 1998
Permit A�98-0-605-63-1 ri
Dear Mr. Guanch:
The undersigned will be personally performing inspections of the prepared steel
on the slabs, beams, and columns of the balconies of Ocean Towers Condominium prior to
the pouring of concrete by the Contractor.
If you have any questions, please do not hesitate to call.
Sincerely,
ABKAR ENGE�EERING INC.
Abdel Karim-Conrado P.E., Ph.D.
President
FL. Reg. # 35551
c.: Ocean Towers Condominium
Commercial Concrete Restoration
2 19575 Carolina Circle. Ii9ca Raton, FL 33434
W Phone and Fax (561) 488-9065