Answers to Plan Review Comments 3-30-09
Reviews and Comments
Permit Number 0807-0168
Dear Sir:
Attached are the answers to the Plan Review Comments:
Plans Examiner Review: Ed DeGennaro
Comment #02/2012009 3, Page 2:
Provide on drawings the following information per FBC
Section 106.3.5, "commercial buildings", occupancy group,
type of construction, occupant load, SF, ETC.
Classification FBC Section 302.
Building area & height, actual & allowed per table 503.
Occupant load FBC table 1004.1.2
Answer: See revised sheet SP- I and LS- I for corrections.
Crexent Business Center* 2101 VistoParkwoy a Suite 108 @ West Palm Beoch, FL33411 - (561) 684-1988/ Fox (561) 228-6132
AFIK0021 81
Comment #02/20/2009 4, Page 2:
Provide a Life Safety Plan complying with FBC 106.3.5(6)
and tablel 0 15. 1.
Answer: See new sheet LS-1.
If you have any questions with regards to these plans for this building please call our
office.
Thanks,
Richard Wensing
RW/em
I
Richard Wensing Rrchitects & Planners, PR
member american institute of architects
4-1-09
Code Compliance Division
2300 Virginia Avenue
Ft. Pierce, F1 34982
Attention: Plan Reviewers
Answers to 3rd Plan Review Comments 3-30-09
Reviews and Comments
Permit Number 0807-0168
Dear Sir:
Attached are the answers to the Plan Review Comments:
Plans Examiner Review: Ed DeGennaro
Comment #03/24/2009 21, Page 2:
Englert series 1300 aluminum metal panel roofing
submitted requires a fire barrier board per system A-1,
NOA #05-033 1.01.
Answer: As per attached Florida Approvals the Fire Barrier Board is
not necessary. This test only applied to Dade County and is
not applicable to the rest of the State. See attached
Evaluation Report, Certificate of Independence for
Evaluation and Installation Method. See attachment 'C'.
Crexent Business Center - 2101 VistoPorUway-Sulte 108 - West Palm Beach, FL 33411 - (561) 684-1988/Fox(561) 228-6132
AXC002181
Comment #03/25/2009 22, Page 2:
Johns Manville NOA #06-0626.04 submitted must be
highlighted fQrskeLproducts being used, and including the
deck type application, meeting the design pressure on sheet
S-2, and general limitation page and including engineers
calculations (general limitation #7) if required.
Answer: See attachment 'A' (NOA #06-0626.04) and sheet A-6.
Comment #03/25/2009 23, Page 2:
Exterior stucco must conform to FBC section 1404.2. 1.
Answer: See detail I on revised sheets A-9 and A- 10.
Plans Examiner Review: Lydia Galbraith
Comment #03/25/2009 22, Page 3:
The generator is not meeting code. Minimum distance to a
building is 10'. If there are no windows and doors on the
side of the building where the generator is located and the
exhaust is not going into any vents, the distance can be
reduced to 5'.
Answer: See Attachment '13' and revised sheet A- I for exact
location and dimensions.
Comment H03/25/2009 23, Page 3:
The generator requires a separate permit.
Answer: Issue will be handled by Owner and General Contractor.
Comment #03/25/2009 24, Page 3:
The name on the tank and piping plan still needs to be
revised.
Answer: Issue will be handled by company in charge.
If you have any questions with regards to these plans for this building please call our
office.
Thanks,
Richard Wensing
RW/em
Richard Wensing Rrchitects & Planners, PA
member american institute of architects
2-26-09
Code Compliance Division
2300 Virginia Avenue
Ft. Pierce, Fl 34982
Attention: Plan Reviewers
Answers to 2 nd Plan Review Comments 2-20-09
Reviews and Comments
Permit Number 0807-0169
Dear Sir:
Attached are the answers to the Plan Review Comments:
Plans Examiner Review: Ed DeGennaro
Comment #02/20/2009 1, Page 2:
Answer:
Provide three signed and sealed copies of St. Lucie County
"Design Certification for Wind Load Compliance"
See attachment 'I'.
Comment #02/20/2009 2, Page 2:
Provide three signed and sealed copies of St. Lucie County
"Product review Affidavit" completely filled out for all
cladding components.
Crexent Business Center - 2101 Vista Parkway - Suite 108 - West Palm Beach, FL 33411 - (561) 684-1988 / Fox (561) 228-6132
AFIK002181
Answer: See attachment '2'.
Comment #02/20/2009 3, Page 2:
Provide on drawings the following information per FBC
Section 106.3.5, "commercial buildings", occupancy group,
type of construction, occupant load, SF, ETC.
Answer: See Revised sheet SP- I for corrections.
Comment #02/20/2009 4, Page 2:
Provide a Life Safety Plan complying with FBC 106.3.5(6)
and table 10 15. 1.
Answer: See new sheet LS-1.
Comment #02/20/2009 5, Page 2:
Provide on plans design pressure at openings FBC
1609.62.2 and table 1609.6.2.1 (1).
Answer: See revised sheets A-3 and A-4 for revisions.
Comment #02/20/2009 6, Page 2:
Provide design pressure, gauge, attachment details and
assembly for Englert series 2000 standing seam roofing.
Answer: See detail number 4 and 5 on revised sheet A-9. Also see
detail 4 on revised Sheet A- 10.
Comment #02/20/2009 7, Page 2:
Provide three sets of manufacturers truss placement plans,
reviewed and approved for construction by engineer of
records.
Answer: It will be provided by Contractor.
Comment #02/20/2009 8, Page 2:
Provide roofing system details for flat roof and adjacent
walls.
Answer: See detail I and 3 on Sheet A-9 and detail I and 2 on Sheet
A- 10 for roof system details for flat roof and adjacent
walls.
Comment #02/20/2009 9, Page 2:
Provide eve attachment details complying with FBC
section 1609 and 1404.2.1
Answer: See revised Roof Framing Plan and Schedule on Sheet S-2.
Calculations have been made for each individual situation
for uplift at the soffits and schedules changes accordingly.
Also, see sections on A-9 & A- 10 for vapor barrier shown
on C-Store as required under 1404.2. 1.
Comment #02/20/2009 10, Page 2:
Provide Thermal Expansion protection.
Answer: See revised Sheet P-2.
Comment #02/20/2009 11, Page 2:
Provide water hammer arrestors for solenoid valves and
urinal.
Answer: See revised Sheet P-2.
Comment NO2/20/2009 12, Page 2:
Provide shut-off valves for each hose Bibb.
Answer: See water riser on revised Sheet P-2.
Comment #02/20/2009 13, Page 2:
Provide P-3 list electric water heater manufacturers that we
are not familiar with, if used they must meet code.
Answer: See revised Sheet P-2 and Sheet P-3.
Comment #02/20/2009 14, Page 3:
Plan page E-1: show disconnects means at water heater.
Answer: See revised Sheet E-1.
Comment #02/20/2009 15, Page 3:
Plan Page E-1: show location of panel "G".
Answer: See Sheet E- I and E-2 for location.
Comment #02/20/2009 16, Page 3:
Plan Page E-1: show location of conduits to canopy and
fuel pump if passing under store.
Answer: See revised Sheet E-1.
Comment #02/20/2009 17, Page 3:
Plan Page E-1: show location, size and type of conduits
from panel "B" to future lift station.
Answer: See revised Sheet E-1.
Comment #02/20/2009 18, Page 3:
Plan Page E-2; show service entrance and 3 V2" feeder
conduits to transfer switch and gutter on riser diagram.
Answer: See revised Sheet E-2.
Plans Examiner Review: Lydia Galbraith
Comment #07/18/2008 3, Page 3:
We need a sub summery and sub agreements for electrical,
plumbing, mechanical and roof.
The roof sub requires a roof contractor GC is not allowed
to do metal roof.
8/22/08 they will bring it in before pick up, they don't
know yet who the subs are going to be.
2/11/09 will submit subs when ready for pick up.
Answer: Will be provided by General Contractor.
Comment #01/23/2009 16, Page 3:
E-mail from Yvette, ERD, site plan extension approved,
still working on their issues with the scrubs jays, need to be
resolved before they can clear the site.
Answer: Issues will be handled by Owner and General Contractor.
Comment #02/11/2009 18, Page 3:
2/11/09 the submitted page in not having the same as the
site plan and the rest of the building set.
Answer: Architectural site plan has been changes to agree with Civil
engineer's plan which was the Site Plan Review Plan.
Generator has been moved. See architectural plan. When
site plan was approved the Generator was not shown.
Comment 902/11/2009 19, Page 3:
I . . a
The pages SP-1, A- I A and A-7 still need to be revised
showing the correct location of parking space 1, the
location of the air vacuum and the location of the tank slab.
All the pages in the building set need to show the same
information.
Please submit from each page 3 signed and sealed corrected
pages by the engineer and/ or architect of records.
Answer: Architectural plans SP- I and A-7 have been changed. The
underground petroleum tanks as shown on A- I A are
required to be positioned as shown in order for the tanker
truck to drop their load. This is only done'off of the rear,
passenger, side of the truck.
Comment #02/16/2009 20, Page 4:
License from the General Contractor is still on hold. We
updated the state license, but the fees for the county cert.
still need to be paid. License is still on hold.
Answer: Will be done by the Contractor.
Comment #02/17/2009 21, Page 4:
2/16/09 new comments to contractor by fax and owner by
mail.
2/17/09 forwarded to plan review.
Need to return to zoning for ERD and storm water check.
Plan review fee needs to be adjusted.
Answer: N/A.
If you have any questions with regards to these plans for this building please call our
office.
Thanks,
Richard Wensing
RW/em