HomeMy WebLinkAboutOliver Technologies paperwork467 Swan Ave ° Hohenwald. TN 38462 (900)284-7437 www.olive rtech no l ogies.com Fax (931) 796-8811 OLIVER TECHNOLOGIES, INC. INSTALLATION INSTRUCTIONS FOR FLORIDA MODEL 1101 "V" SERIES ALL STEEL FOUNDATION SYSTEM PAN & CONCRETE (revision 5118) PATENT# 6634150 & OTHER PATENT PENDING REVISE® By SEAN SWONGER at 6.32 am, 6131118 E EWEDER at 6:33 M, 8/31/18 RECEIVED MAR 04 ?919 ST. Lucie County, Permitting -SCANNED BY St. Lucie County `t9ttlllf l: 1�°fe - . A/ .. °No. 042144 -Q STATE OF e^� e'11911119D9 Aug 24, 2016 467 Swan Ave • Hohenwald, TN 38462 (800) 284-7437 % www.olivertechnologies.com • Fax (931) 796-8811 OLIVER TECHNOLOGIES, INC. FLORIDA INSTALLATION INSTRUCTIONS FOR THE MODEL 1101 "V" SERIES ALL STEEL FOUNDATION SYSTEM MODEL 1101"V" (Steps 1-14) LONGITUDINAL ONLY: Follow Steps 1-9 LATERAL ONLY: Follow Steps 1-3 and Steps 10-14 ENGINEERS STAMP FOR CONCRETE APPLICATIONS: Follow Steps 15-18 ENGINEERS STAMP 1. SPECIAL CIRCUMSTANCES: If the following conditions occur - STOP! Contact Oliver Technologies at 1-800-284-7437: a) Pier height exceeds 48" c) Roof eaves exceed 16" e) Location is within 1500 feet of coast b) length of home exceeds 76' d) Sidewall height exceed 96" INSTALLATION OF GROUND PAN 2. Remove weeds and debris in an approximate two foot square to expose firm soil for each ground pan (C) . 3. Place ground pan (C) directly below chassis I-beam. Press or drive pan firmly into soil until flush or below soil then install pier per manufacturer's instructions or per Florida Regs. SPECIAL NOTE: The longitudinal "V" brace system may also serve as a pier under the home and should be loaded as any other pier. It is recommended that after leveling piers, and one-third inch (1/3") before home is lowered completely on to piers, complete steps 4 through 9 below then remove jacks. INSTALLATION OF LONGITUDINAL "V" BRACE SYSTEM (Model 1101 L "V") NOTE: WHEN INSTALLINGTHE LONGITUDINAL SYSTEM ONLY, A MINIMUM OF 2 SYSTEMS PER FLOOR SECTION IS REQUIRED. SOILTEST PROBE SHOULD BE USED TO DETERMINE CORRECTTYPE OF ANCHOR PER SOIL CLASSIFICATION. IF PROBE TEST READINGS ARE BETWEEN 175 & 275 A 5 FOOT ANCHOR MUST BE USED. IF PROBETEST READINGS ARE BETWEEN 276 & 350 A 4 FOOT ANCHOR MAY BE USED. USE GROUND ANCHORS WITH DIAGONALTIES AND STABILIZER PLATES EVERY 5'4" .VERTICALTIES ARE ALSO REQUIRED ON HOMES SUPPLIED WITH VERTICALTIE CONNECTION POINTS (PER FLORIDA REG.). 4. Choose one of the approved longitudinal tube installations; either Diagram A or B.Then select the correct square tube (E) length from the diagram for appropriate pier height at support location or cut and drill 1.5" square tube to achieve appropriate length. PIER HEIGHT 1.25" 1.50" PIER HEIGHT 1.50" (40" Min. - 45" Max.) Tube Length Tube Length 9/I6•D1a.(562) hole. _ (40" Min. - 60" Max.) Tube Length 7 3/4" to 25" 22" 18" 24 3/4" to 321 /4" 32" 33" to 41 " 44" 18" 40" to 48" 54" w . Diagram A Part E r. 14"to 18" 20" 18" to 25" 28" 24" to 35" 39" 30" to 40" 44" 36" to 48" 54" Diagram B 5. Install (2) of the 130" square tubes (E) into the "U" bracket 0), insert carriage bolt and leave nut loose for final adjustment. 6. Place I-beam connector (F) loosely on the bottom flange of the I-beam. 7. (For Diagram A installation) Slide the selected 1.25" tube (E) into a 1.50" tube (E) and attach to I-beam connectors (F) and fasten loosely with bolt and nut. (For Diagram B installation) Attach the selected 1.5"tubes (E) to the I-beam connectors (F) and fasten loosely with bolts and nuts. 8. Repeat steps 6 through 7 to create the "V" pattern of the square tubes loosely in place. 9. Using standard hand tools tighten all nuts and bolts. (For Diagram A installation only, secure 1.25" and 1 .50" tubes using four(4) 1 /4"-14 x 3/4" self -tapping screws in pre -drilled holes.) INSTALLATION OF LATERAL TELESCOPING TRANSVERSE ARM SYSTEM (Model 1101 T "V") THE MODEL 1101 'V" (LONGITUDINAL& LATERAL PROTECTION) ELIMINATESTHE NEED FOR STABILIZER PLATES & FRAMETIES. NOTE:THE USE OFTHIS SYSTEM REQUIRES VERTICALTIES SPACED AT T41". FOUR FOOT (4) GROUND ANCHOR MAY BE USED EXCEPT WHERE THE HOME MANUFACTURER SPECIFIES DIFFERENT. 10. Install remaining vertical tie -down straps and 4' ground anchors per home manufacturer's instructions. NOTE: Centerline anchors to be sized according to soil torque condition. Any manufacturer's specifications for sidewall anchor loads in excess of 4,0001bs. require a 5' anchor per Florida Code. 11. Select the correct square tube brace (H) length for set-up lateral transverse at support Iocation.The lengths come in either 60" or 72" lengths. (With the 1.50" tube as the bottom tube, and the 1.25" tube as the inserted tube.) 12. Install the 1.50 transverse brace (H) to the ground pan connector (D) with bolt and nut 13. Slide 1.25" transverse brace into the 1.50" brace and attach to adjacent I-beam connector (1) with bolt and nut. 14. Secure 1.50" transverse arm to 1.25" transverse arm using four (4)1 14" -14 x 3/4" self -tapping screws in pre -drilled holes. Page, pATFNTit r,ARd1 Sn R, OTHFR PATFNT PFNIIINr Revision 09/23/l E 167 Swan Ave Hohenwald. TN 38462 • (800) 284-7437 • www.olivertechnologies.com a Fax (931) 796-8811 INSTALLATION USING CONCRETE RUNNER/ FOOTER I S. A concrete runner, footer or slab may be used in place of the steel ground pan. a) The concrete shall be minimum 2500 psi mix b) A concrete runner may be either longitudinal or transverse, and must be a minimum of 8" deep with a minimum width of 16 inches longitudinally or 18 inches transverse to allow proper distance between the concrete bolt and the edge of the concrete (see below). c) Footers must have minimum surface area of 441 sq. in. (I.e. 21" square), and must be a minimum of 8" deep. d) If a full slab is used, the depth must be a 4" minimum . Special inspection of the system bracket installation is not required. Footers must allow for at least 4" from the concrete bolt to the edge of the concrete. NOTE: The bottom of all footings, pads, slabs and runners must be per local jurisdiction. LONGITUDINAL: (Model 1101 LC "V") 16. When using Part# 1101-W-CPCA (wetset) simply install the bracket in runner/footer OR When installing in cured concrete use Part# 101-D-CPCA (dryset).The 1101 (dryset) CA bracket is attached to the concrete using (2) 5/8"x3" concrete wedge bolts (Simpson part # 5162300H 5/8" X 3" or Powers equivalent). Place the CA bracket in desired location. Mark bolt hole locations, then using a 5/8" diameter masonry bit, drill a hole to a minimum depth of 3"- Make sure all dust and concrete is blown out of the holes. Place wedge bolts into drille holes, then place 1101 (dry set) CA bracket onto wedge bolts and start wedge bolt nuts.Take'a hammer and lightly drive the wedge bolts down by hitting the nut (making sure not to hit the top of threads on bolt). The sleeve of concrete wedge bolt needs to be at or below thl ton of concrete. Complete by tightening nuts. LATERAL. (Model 1101 TC "V") 17. For wet set (part # 1101-W TACA) installation simply install the anchor bolt into runner/footer. For dry set installation (part It I I01-D TACA mark bolt hole locations, then using a 5/8" diam. masonry bit. drill a hole to'a minimum depth of 3". Make sure all dust and concrete is blown out of the hole. Place wedge bolts (Simpson part #S162300H 5/8" X 3" or Powers equivalent) into (D) concrete dry transverse connector and into drilled hole. If needed, take a hammer and lightly drive the wedge bolts down by hitting the nut (making sure not to hit the top of threads on bolt), then remove the nut. The sleeve of concrete wedge bolt needs to be at or below the too of concrete. 19. When using part# 1101 CVW (wetset) or 1101 CVD (dryset), install per steps 17 & 18. Notes: 1. LENGTH OF HOUSE ISTHE ACTUAL BOX SIZE 2. =. LOCATION OF TRANSVERSE BRACING ONLY 3 = LOCATION OF LONGITUDINAL BRACING ONLY 4.;C -=TRANSVERSE AND LONGITUDINAL LOCATIONS ALL WIDTHS AND LENGTHS UP TO 52' I� �I ii Ij I it I is ! ALL WIDTHS AND LENGTHS OVER 52'TO 80" HOMES WITH 5/12 ROOF PITCH REQUIRE: PER FLORIDA REGULATIONS 6 systems for home lengths up to 52' and 8 systems for homes over S2' and up 80'. PATENT# 6634150 & OTHER PATENT PENDING Paae 2 Revision 08/23/1 E u I-Twweeme Arm. I -Beam Connector H-Transverse Arm /p (15') BottToom (151 C- Ground Model # 1101 T "V" I -Transverse Ann, I -Beam Connector Part 1101-13-TACA j H-Transverse Arm Part#11D1-%V-TACAnotsoo o Top 11.15'I k t i i Bottom (15") I Cement Block 1 ICh1U-Pier Omitted i Omitted LFor Clarity J D-Concrete'ransvers `Fos Clarity J y Connector y rete51a6! > 4 Poocer Foote, Anchor ( Bolts Model # 1161 TC "V" Florida approved 4' ground anchors maybe used in all locations except where home manufacturers specifications for sidewall straps are in excess of 4,0001bs. These locations require a 5' anchor. Per Florida code. C = GROUND PAN / CONCRETE FOOTER OR RUNNER D = GROUND PAN / CONCRETE U BRACKETS TRANSVERSE CONNECTOR (connects with grade 5 -1/2"x 2" 1/2"carriage bolt and nut) E =TELESCOPING V BRACETUBE ASSEMBLY 0.5" TUBE BOTTOM AND 1.25" TUBE INSERT) OR 1.5" TUBE F ="V" BRACE I -BEAM CONNECTOR ASSEMBLY H = TELESCOPING TRANSVERSE ARM ASSEMBLY I =TRANSVERSE ARM I -BEAM CONNECTOR (connects with grade 5 -1/2"x 2" 1/2"carriage bolt and nut) J = V PAN BRACKET (connects with grade 5 -1/2"x 2" 1/2" carriage bolt and nut) i -Transverse Arm, I -Beam Connector F- "V'Brace l-Beam Connectors H-Transverse Arm ` Bottom 0.57 D - Pan Transverse Connector / Concrete Transverse Bracket C - Ground Pan / Concrete Footer - Pan V Bracket t _ Concrete V Bracket E-"V'Brace Tube(1.5") Model # 1101 "V" Pane 1101 D-CPCA 8 Part 011011 - PCA no's mvn PATENT# 6634150 & OTHER PATENT PENDING Model # 1101 C "V" Page3 Revision 08/23/1 E HANEIRAll GRIP SIJA. E �d NONCtRCULAR CIRCULAR RECESSED R .Dln 4-�UI PRM4101 ". -HANDRAIL HEIGHT. MEASURED VSRTICALLY FROM THE SLOPED PLANE ADX JOMUG :HE TREAD NOSING, OR FI141SH SURFACE OF RAMP -LOPE. SHALL BE NOT LESS THAN 34 INCHES AND NOT MORE THAN 3B INCHES. -HANDRAIL SHALL BE PROMOED ON AT LEAST ONE SIDE OF EACH CONTINUOUS RUN OF TREADS OF FLIGHT WIN FOUR OR MORE RISERS. • HANDRAIL AESENBLJES AND GUARDS SHALL BE DESIGNED TO RESIST A LOAD OF 50 PU' APPMED IN ANY DRECMCH AT THE TOP AND TO TRANSFER THIS LDAD THROUGH THE SUPPORTS TD THE STRUCTURE, MF EUAROS NAl9E MCA, ALDIYNW, NNY., OR EQUIVALENT. 2 X 2 BALUS MIN, (3) SIMPSON'S SIDS 1/4- X 1-1/2' — WOOD SCREV6 FOR RIM JOIST TO POST CCNNECRON. (B) 16d NAILS OR EQUIVALENT P.T. STEP LANDING MOOR TO HOST FLOOR MERGERS USINE 1/4' X 3-1/2' SUS WOOD `- EQUIV, AT 12' D.C, STACGERF.O SCREI 2X6 P.T. LANDING 16- O.C. FLOOR JOISTS USING (0) EQUIVALENT AT EACH JOIST HECHT SHALL BE 7-3/4 INCHES. ME RISEN VERTICALLY MINTER LEADING EDGES Of THE ME GREATEST RISER NEVBO WMIN ANY RICHT R CXCEED VIE CNALUSt BY NONE MAN 3/31=1 DEPTH SHALL: or 10 Marc%. N¢ TRCAD DEPTH GHAL BE ALLY SCORER THE WflInCAL PLANES or ME FGTEUOST ARMENIAN S AND AT A NIGHT ANGLE 10 ME TREAD'S LLADNG EDGE D IIEPM YOUR ANY MIGHT U STAINS SHALL NOT EX..F0 ME MAN 3/0 LYCH, rAiNm' Al ME LANE [cCC DE 1 MEAD SHALL DE NO CREAM 1. S/C X B BOARD HAIL CAP 30' GROUND ANCHOR W'/ THE DOWN STRAP STRAP TO WRAP AROJND P.T. 2 X 6 TIGHTLY (00 Nor OVER 1E11BON STRAPS) (EACH SIDES OF LANDINC) AN, MD LAN0w0 IuuuNAna ncOUAm (I) 2 X G P.T. ATTACHED TO POSTS USING (Bl 160 NALS OR EGULVAJ.ENT AT EACH S-0' UNMxG HEIGHT • 3 EmP6 p 2XG 10 POST CONNECTOR. - P-LY LAxwln ncXPrt - T STmS (M) EACH AEST WOOD ALL NOT ALLOW i OF A 4' OIAINCTER SPIICRC 2 X 4 TOP k BOTTOM ATTACHED TD TO POSTS WITH (2)9B WOOD F.CREVIS ON INSIDE FACE. MS TO TOP k BOTTOM (11dB WCOD SCREW OR EOUIV. / ' / /'� EXISTING STRUCTURE '35 0 P.T. BANNER (SAIL O.0 SVADNC. FAST. NAILS CA EQUAL .1 .6 AYITS WM COIIOI OP" S 'I IF STEP6 ARE NSTALLED CIS EASIING CONCRETE. THE OROUNO AMMONS AND REDOV01 STRAP CAN BE ¢WITTED. (3) 2 X 12 P.T. STAR STRINGERS RIC P.T, 4 X .I POSTS SHALL BE ANCHORED TO THE EXISINC CONCRETE SLAG USING SIMPSON'S L-UAACHEI CN EQUIVALENT. NOTE: Cne TRACTRR SHAH RP RESPONSIBLE FOR VERIF)MG ALL DHA NSIONS� ANa CONDITIONS PRIOR TO CONSTRUCTION, ALL STAIR COMPONENTS TO RE PRESSURE TRFATED-LUAIOM AL FAS�RS IN CONTACT 4411N P.1. LUMBE&JO BF HOT DIP GALIL6NRER_OR-aT CILESS.-STEEL WL'INE'ECCaG11Wn06F£EU. IIJAIVI I:..v.uawl 4 VERTICAL VINYL SKIRTING ( components S installation i i TDA$ACKK AT.TgG{tE0 WM4 9'F d6c+1 SCROwS 16"gPA¢r - i SNAPS IN TO _"OP BAWL "ices SeRr Yak AND PANEL cvrJ VdTED PA, NEL ----------- � _ BLOCK SuPPO0.T 3.91A4KC-S Pee FOOT a SECuREB b,F VEMTItATbM �b :bP.9PCtG AND gb%'i'bM Rhly Wf INCN SCgf�rS �P;1 �.P 16.OL TALI PANELS 4926 A"r 4, B,E ey REft%0vuw4 ibP r-ob*jT A&n (WLmuG I lip ON PANEL) ATTACH60 TO GRpptip wrrh 7MCa GAL 4N1%60: NAIL 19�Oa (IF SO%(. IS SANDY!T71EA1 02/02/2018 467 Swan Ave a Hohenwald. TN 38462 a (800) 284-7437 www.oiivertechnologies.com Fax (931) 796-88 i 1 OLIVER TECHNOLOGIES, INC. INSTALLATION INSTRUCTIONS FOR FLORIDA MODEL 1101 "V" SERIES ALL STEEL FOUNDATION SYSTEM PAN SrCONCRETE (revision 5/18) PATENT# 6634150 & OTHER PATENT PENDING •`REVISED REVIEWED 8y SEAN SWONGER at 6:33 am, 8/3f/98 SCANNED BY St, Lucie County ,0}99199:8IIr r � U o...0aaz C -X� ice. � :gym a-0 = STATE OF q:4 •i , s 0 R X •,C6 °°prr9e999°°4 Aug 24, 2016 467 Swan Ave • Hohenwald, TN 38462 • (800) 284-7437 www.olivertechnologies.com • Fax (931) 796-8811 OLIVER TECHNOLOGIES, INC. FLORIDA INSTALLATION INSTRUCTIONS FOR THE MODEL 1101 "V'_' SERIES ALL STEEL FOUNDATION SYSTEM MODEL 1101"V" (Steps 1-14) LONGITUDINAL ONLY: Follow Steps 1-9 LATERAL ONLY: Follow Steps 1-3 and Steps 10-14 ENGINEERS STAMP FOR CONCRETE APPLICATIONS: Follow Steps 15-18 ENGINEERS STAMP 1. SPECIAL CIRCUMSTANCES: If the following conditions occur -STOP! Contact Oliver Technologies at 1-800-284-7437: a) Pier height exceeds 48" c) Roof eaves exceed 16" e) Location is within 1500 feet of coast b)length of home exceeds 76' d) Sidewall height exceed 96" INSTALLATION OF GROUND PAN 2. Remove weeds and debris in an approximate two foot square to expose firm soil for each ground pan (C) . 3. Place ground pan (C) directly below chassis 1-beam. Press or drive pan firmly into soil until flush or below soil then install pier per manufacturer's instructions or per Florida Regs. SPECIAL NOTE: The longitudinal "V" brace system may also serve as a pier under the home and should be loaded as any other pier. It is recommended that after leveling piers, and one-third inch (1 /3") before home is lowered completely on to piers, complete steps 4through 9 below then remove jacks. INSTALLATION OF LONGITUDINAL "V" BRACE SYSTEM (Model 1101 L "V") NOTE: WHEN INSTALLINGTHE LONGITUDINAL SYSTEM ONLY, A MINIMUM OF 2 SYSTEMS PER FLOOR SECTION 15 REQUIRED. SOILTEST PROBE SHOULD BE USEDTO DETERMINE CORRECTTYPE OF ANCHOR PER SOIL CLASSIFICATION. IF PROBETEST READINGS ARE BETWEEN 175 & 275 A 5 FOOT ANCHOR MUST BE USED. IF PROBETEST READINGS ARE BETWEEN 276 & 350 A 4 FOOT ANCHOR MAY BE USED. USE GROUND ANCHORS WITH DIAGONALTIES AND STABILIZER PLATES EVERY 5W. VERTICALTIES ARE ALSO REQUIRED ON HOMES SUPPLIED WITH VERTICALTIE CONNECTION POINTS (PER FLORIDA REG.). 4. Choose one of the approved longitudinal tube installations; either Diagram A or B.Then select the correct square tube (E) length from the diagram for appropriate pier height at support location or cut and drill 1.5" square tube to achieve appropriate length. PIER HEIGHT 1.25" 1.50" PIER HEIGHT 1.50" (40' Min. - 45' Max.) Tube Length Tube Length 9/16'Dia. (.5627 hole (40" Min. - 60" Max.) Tube Length 7 3/4" to.25" 22" 18" - 243/4"to321/4" 32" 18".,'.. 33"to 41" 44" 18" 40" to 4B" 54" 18, , Diagram A Part E 11 14" to 18' 20" 18" to 25" 28" 24" to 35" 39" 30" to 40" 44" 36"to48" 54" Diagram B S. Install (2) of the 1.50" square tubes (E) into the "U" bracket (A insert carriage bolt and leave nut loose for final adjustment. 6. Place I-beam connector (F) loosely on the bottom flange of the I-beam. 7. (For Diagram A installation) Slide the selected 1.25" tube (E) into a 1.50" tube (E) and attach to I-beam connectors (F) and fasten loosely with bolt and nut. (For Diagram B installation) Attach the selected 1.5" tubes (E) to the I-beam connectors (F) and fasten loosely with bolts and nuts. S. Repeat steps 6 through 7 to create the "V" pattern of the square tubes loosely in place. 9. Using standard hand tools tighten all nuts and bolts. (For Diagram A installation only, secure 1.25" and 1 .50" tubes using four(4)1 /4"-14 x 3X'self-tapping screws in pre -drilled holes.) INSTALLATION OF LATERAL TELESCOPING TRANSVERSE ARM SYSTEM (Model 1101 T "V") THE MODEL 1101 "V" (LONGITUDINAL & LATERAL PROTECTION) ELIMINATES THE NEED FOR STABILIZER PLATES & FRAME TIES. NOTE:THE USE OF THIS SYSTEM REQUIRES VERTICAL TIES SPACED AT 5'4". FOUR FOOT (4') GROUND ANCHOR MAY BE USED EXCEPT WHERE THE HOME MANUFACTURER SPECIFIES DIFFERENT. 10. Install remaining vertical tie -down straps and 4' ground anchors per home manufacturer's instructions. NOTE: Centerline anchors to be sized according to soil torque condition. Any manufacturer's specifications for Sidewall anchor loads in excess of 4.000 lbs. require a 5' anchor per Florida Code. 11. Select the correct square tube brace (H) length for set-up lateral transverse at support location. The lengths come in either 60" or 72" lengths. (With the 1.50" tube as the bottom tube, and the 1.25" tube as the inserted tube.) 12. Install the 1.50 transverse brace (H) to the ground pan connector (D) with bolt and nut. 13. Slide 1.25" transverse brace into the 1.50" brace and attach to adjacent 1-beam connector (1) with bolt and nut. 14. Secure 1.50" transverse arm to 1.25" transverse arm using four (4) 1 /4" -14 x 3/4" self -tapping screws in pre -drilled holes. Page, E no",,, pATFNTE A,h1A1 Sn R, A)THFR PATFNT PFNr)INf, Revision '67 Swan Ave Hohenwald. TN 38462 (800) 284-7437 • www.olivertechnologies.com • Fax (931) 796-8811 INSTALLATION USING CONCRETE RUNNER/ FOOTER 15. A concrete runner, footer or slab may be used in place of the steel ground pan. a) The concrete shall be minimum 2500 psi m_i-x b) A concrete runner may be either longitudinal or transverse, and must be a minimum of 8" deep with a minimum width of 16 inches longitudinally or 18 inches transverse to allow proper distance between the concrete bolt and the edge of the concrete (see below). c) Footers must have minimum surface area of 441 sq. in. (I.e. 21" square), and must be a minimum of 8" deep. d) If a full slab is used, the depth must be a 4" minimum . Special inspection of the system bracket installation is not required. Footers - must allow for at least 4" from the concrete bolt to the edge of the concrete. NOTE: The bottom of all footings, pads, slabs and runners must be per local jurisdiction. LONGITUDINAL: (Model 1101 LC "V") 16. -When using Part# 1101-W-CPCA (wetset) simply install the bracket in runner/footer OR When installing in cured concrete use Part# 101-D-CPCA (dryset).The 1101 (dryset) CA bracket is attached to the concrete using (2) 5/8"x3" concrete wedge bolts (Simpson part # S 162300H 5/8" X 3" or Powers equivalent). Place the CA bracket in desired location. Mark bolt hole locations, then using a 51W diameter masonry bit, drill a hole to a minimum depth of 3". Make sure all dust and concrete is blown out of the.holes. Place wedge bolts into drille holes; then place 1101 (dry set) CA bracket onto wedge bolts and start wedge bolt nuts. Take a hammer and lightly drive the wedge bolts down by hitting the nut (making sure not to hit the top of threads on bolt). The sleeve of concrete wedge bolt needs to be at or below thi too of concrete. Complete by tightening nuts. LATERAL: (Model 1101 TC "V") 17. For wet set (part # 1101-W TACA) installation simply install the anchor bolt into runner/footer. For dry set installation (part # 1101-D TACA mark bolt hole locations, then using a 5/8" diam. masonry bit. drill a hole to a minimum depth of 3". Make sure all dust and concrete is blown out of the hole. Place wedge bolts (Simpson part #5162300H 5/8" X 3" or Powers equivalent) into (D) concrete dry transverse connector and into drilled hole. If needed, take a hammer and lightly drive the wedge bolts down by hitting the nut (making sure not to hit the top of threads on bolt), then remove the nut. The sleeve of concrete wedge bolt needs to be at or below the too of concrete. 18. When using part# 1101 CVW (wetset) or 1101 CVD (dryset), install per steps 17 & 18. Notes: 1. LENGTH OF HOUSE IS THE. ACTUAL BOX SIZE 2.;^^ = LOCATION OF TRANSVERSE BRACING ONLY 3 = LOCATION OF LONGITUDINAL BRACING ONLY 4. =TRANSVERSE AND LONGITUDINAL LOCATIONS ALL WIDTHS AND LENGTHS UP TO 52' i I ki ! it PH f: { ALL WIDTHS AND LENGTHS OVER 52' TO 80" It l ,l E it ! it 1 Il ss1 p f` �! , l HOMES WITH 5/12 ROOF PITCH REQUIRE: PER FLORIDA REGULATIONS 6 systems for home lengths up to 52' and 8 systems for homes over 52' and up 80'. PATENT# 6634150 & OTHER PATENT PENDING Paae Revision 08/23/1 E 1-Transv\er`se Arm, I -Beam Connector D-Pan H -Transverse Arm / Tap (12S') Bottom (15') C-Ground Pan Model # 1101 T "V" I -Transverse Arm, 1-Beam Connector / Part: 1101-D-TA a H-T,.mvene Arm Pan I101-W-TAG notm.n Tap p 2S'1 Bottom (151 t 1 1 Cement Block I 1CMU-Pier l Omitted r Omitted LFor Clarity D-Concrete Transverse `For Clarit"v y Connector y C-Concrete Slab/ 72` 18'Maz. Foote, ( Ancbor Bdu Model # 1101 TC "V" Florida approved 4' ground anchors maybe used in all locations except where home manufacturers specifications for sidewall straps are in excess of 4,000 lbs. These locations require a 5' anchor. Per Florida code. C = GROUND PAN / CONCRETE FOOTER OR RUNNER D = GROUND PAN / CONCRETE U BRACKETS TRANSVERSE CONNECTOR (connects with grade $ -1/2"x 2" 1/2" carriage bolt and nut) E =TELESCOPING V BRACE TUBE ASSEMBLY (1.5" TUBE BOTTOM AND 1.25" TUBE INSERT) OR 1.5" TUBE F = "V" BRACE I -BEAM CONNECTOR ASSEMBLY H =TELESCOPING TRANSVERSE ARM ASSEMBLY I =TRANSVERSE ARM I -BEAM CONNECTOR (connects with grade 5 -1 /2" x 2"'112" carriage bolt and nut) J = V PAN BRACKET (connects with grade 5 - 1/2"x 2" 1/2" carriage bolt and nut) i-Transverse Arm, I -Beam Connector F- "V"Brace I -Beam Connectors H-Transverse Arm Bottom (1.5i D - Pan Transverse Connector / Concrete Transverse Bracket C - Ground Pan — / Concrete Footer 1- Pan V Bracket 1 Concrete V Bracket E -"V"Brace Tube (i.5") Model # 1101 "V" PATENT# 6634150 & OTHER PATENT PENDING Part: 1101 o-CPG 8 Pang 11011Y-CPCA not flown Model # 1101 C "V" Pace 3 Revision 0812311 E � E NONCIRCULAR CIRCULAR REGES6E0 mnNrelm 4;'. N)' Vemtcmr>E; •HANDRAIL HEIGHT. MEASURED VERTICALLY FROM THE SLOPED PLANE ADJOINING THE TREAD NOSING. OR FINISH SURFACE OF RAMP SLOPE, SHALL BE NOT LESS THAN 34 INCHES AND NOT MORE THAN 38 INCH-e5. -HANDRAIL SHALL BE PROVIDED ON AT LEAST ONE SIDE OF EACH CONTINUOUS RUN OF TREADS OF FLIGHT WITH FOUR OR MORE RISERS e HANGNAIL ASSEMBLIES AND GUARDS SHALL BE DESIGNED TO RESIST A LOAD OF 50 PLF APPLIED IN ANY DIRECTION AT THE TOP AND TO TRANSFER THIS LOAD THROUGH THE SUPPORTS TO THE STRUCTURE. ENE CUMDS NAVIIE WDCD, AW WNUN, WNtt, Mi EOUIWLENT, 'TAW nFAT AMR�ItFiIR ME MANMVM RISW HEIGHT SHALL BE 7-3/4 INCHES. THE RISER SHALL SE MASLOW VENTI N Y BETWEEN LEADING EDGES DF TH: ADJACENT TREADS. THE GREATEST RISER FFIGNT WRAP ANY OUGHT OF STAIRS WALL NOT CADGER TIC SMALLEST BY MORE 14AM 3/8 INW, BIG M.NINUN EGAD DEPTH SHALL OE 10 INCHES. THE TREAD DEPTH SHALL DE MFA,VW HORRM (ALLY BETJIEEN WE VERTICAL PLANES OF THE FOREMOST PROJECTION Oi AD)AC.ENT TREADS MD AL A RIGHT ANGLE TO THE ]RENTS LEADNG EDGE. THE GREATEST ]READ BROTH M,,, ANY FIGHT Or STAIRS SHALL NOT EXEEE➢ E-E WV'oST RY MWHE THAN 3/8 "E" THE RADIUS OF WRYATIIRE Ar WE LEMNR EOGC OF 9E T1EAO SHALL DE NO GREATER THAN 9)16 NCH. A NOSNG NOT LEST MAN3/4 NCH OUT NOT MORE THAN 1-1 41NDXE6 SHAIt bE PARADED fN STAIRWAYS WW SWS RISERS. A NOSING 15 HOT REMIS ANERE THE INEAD DEPTI IS A NiNNUN OF II WCHEA _ x X 2 BALUSTER MIN, (3) SIMPSON'S SDS 1/4- WOOD SCREWS FOR RIM JOIST TO POST CONNECTION. (5) 16E NAILS OR EDUIVALENT P.T. STEP LANCING FLOOR FASTENED TO FIOS1 FLOOR MEMOCRS USING SIMPON$ 1/4' X 3-1/2' BOB WDOU) SCREW$ OR F • ` P', ECUIV, AT'12' 0,0. STAGGERED SCREW PATTERN iax 2M6 P.T. LANDING CONSTRUCTION 16' O.C. FLOOR JOISTS USING SO) 100 NAILS OR EQUIVALENT AT EACH JOIST TO RIM JOIST CONNECTION. 30' GROUND ANCHIXH w'/ TIE DOWN STRAP STRAP 10 WRAP AROUND P.T. 2 k 6 TIGHTLY (DONOT OVER (E N SIDES TENSION LANDING) 5/4' X G BOARD RAIL CAP EXISTING STRUCTURE / �� ipsr uswc �i) 1/4' vi-1%2' IMPOOR EDI MW GCREN OR EnHWAUEN IENINGS SHALL NOT ALLOW, iE PASSAGE OF A 4' DIAMETER SPHCRE 2 X 4 TOP & BOTTOM .ATTACHED 10 TO POSTS WITH (2TIS WOOD SCREWS ON INSIDE FACE. / OPENINGS FOR REQUIRED WARDS ON THE ERC Or SPHERE 4-3/8- TREADS8- TOPASS THROUGLLGW A H� ggLUETERS TO TOP & BOTTOM (I S V100D SCREW OR EQUIV. (3) 2 X 12 P.T. STAIR STRINGERS STAIR AND LMOINO LUAwwnTM REOWRED USING2 X G P.T. ATTACHED Q VALEN USING (5) 160 NAILSONNE OR EQUIVALENT IT EACH 3'-0' LANDING HERNIT 5 s1FP6 (wM) 4%6 TO PPOST CONNECTION, 4'-0' LANDING IIDCIT I STEP^ MR) NOTE: TDAr•TOR SH&L.UE R SPON 15LE FOR VERIEYING III I DIEAEUIONS AND CONDITIONS PRIOR TO CONSTRUCTIOM. Al l _STAIR CRMPIIN T9j,5 TO B PRE5_9SlBE_T6EAIEQ-.I.1IMBEI; Al l FASTFNFHS IN QQH TACT W11H P.I�IJjL(flEH_LQ_@,EJ1Q.L�71eSALYBNIZER_OEL.SS.IAINLEIS. IEEL LUVOEN RSSTS WTI FEuDE L04IED A =oral-Iarsa. wnI1NGussAurs AunAT ARC le"ILR 40Rt MAN!OMRED VERTULLY 10 ME mi 1 dTAt AHY PANT W1HH w INCHES 10 ME EG, OF iH[ OR. 5IX. [ANCHORS +fR�Tr pPT0.4_ tEP5 AHE NSTALLED ON EXISTING CONCRETE. THE GROUND ANO TEOOWN STRAP CAN BE OMNTEO. P.T. 4 X •1 POSTS SHALL BE ANCHORED TO THE EMOSINGCRETE SLAB USWG SIMPSON'S L-BRACXEI CH EQUIVALENT. •. n F EA,,41-30-2018 .•��NCENi Nit,; w i ND.-- J: _ SAT FED •mm+aTEorpaNWno ArEED. nonrl IITMAILLe N AL iI11NVRNa YFEO• IY' 4M1II R+«Np�l 4 VERTICAL VINYL SKIRTIING ( Component® d installation y AT•TAGHEa wtT�+ ;,"C,4 9C4fi W$ jID'�APAF'r -- FLOOR SNAPS INTO -MP g --�¢ NIDG9 SCR4CWr ANLb PAPIEL GVTJ BLOCK SuPPORT s 3.91n I,rs Me FOOT- SECVREA bF vEMTILAbN �y TaT P�64CIC 13or7brA R0.il6;Y 44LL DAME LS 446 Ar-CE5 �9+-E $y RErnouuvG ZbP F bAi r Own H,"vu up ON P0.)vEl� i A-rTACHEO TO GROoub YJlTN 71nCw eALVANIZEO NAIL 19"0D (W S6tL IS 5AND4ITilEA1 02/0212018