HomeMy WebLinkAboutDRIVEWAY PERMIT ISSUANCEDriveway Permit Issuance
1. Driveway Permits to be applied for through the Planning and Development Services
Department, although Driveway Permits are issued through the Water Quality
Division.
2. All Payments for Driveway Permits, including reinspect fees, should be made in the
Planning and Development Services Department. The Water Quality Division cannot
SCANNED receive payments.
BY
S1 I_UCIe COUC1-4y If a Driveway Permit is required, The Planning and Development Services
Department should mark on that Building Permit that a "C.O." will not be granted
until driveway final is accepted by the Driveway Inspector.
4. If a Driveway Permit is required, at the time the owner or builder pays for a building
permit, an additional $155.00 will be charged for the driveway permit.
5. Once the owner/builder has completed the permit application, they should mail or
deliver it to the Planning and Development Services Department.
6. Once the Driveway Inspector has completed the Driveway Permit, it should be
delivered back to the Planning and Development Services Department to be mailed
or made available for pick-up.
7. The Owner or Builder is to call 772-462-2511 with their Driveway Permit number and
address of the construction site. Please give a 24 hour notice when requesting a
Driveway Pre -pour or Final inspection.
8. If the Pre -Pour Inspection has been accepted, the Driveway Inspector is to place a
sticker on the job site stating that it has been approved.
9. If the Pre -Pour Inspection has been rejected, the Driveway Inspector is to place a
"Red Tag" on site and explain what was rejected. The "Red Tag" should also include
the amount of the Re -Inspect Fee to be paid at the Planning and Development
Services Department ($20.00 for the First, $40.00 for the Second, and $60.00 for the
Third or more) and where to pay it.
10. Upon acceptance of the final inspection, the Inspector is to call the Planning and
Development Services Department with the address to release the C.O. hold on that
permit.
11. Driveway Permits for other than new construction will be paid for and application
received at the Planning and Development Services Department and follows the
same procedure.
12. Driveway Permits for Commercial Sites must include a Copy of the County Approved
Site Plan with the application. Some of these sites may need a Right -of -Way Permit
instead of a Driveway Permit.
13. Driveway Upgrades (changing dirt driveway to concrete or asphalt where applicable)
or culvert replacement permits will be applied for on the same form as a regular
driveway. A $25.00 upgrade fee is to be charged for this type of permit and is to be
applied for through the Planning and Development Services Department.