July 28, 2016
In the Matter of an Application for Permit by:
Mr. Jesus A. Merejo, Utility System Director
Port St. Lucie Utility Services Department
900 S.E. Ogden Lane
Port St. Lucie, Florida 34983
Email: jmereiona,cityofpsl.com
Rick Scott
Governor
Carlos Lopez-Cantera
Lt. Governor
Jonathan P. Steverson
Secretary
SCANNED
St. LuBY
ce Countv
DEP File No. 0081064-332-DSC
St. Lucie County
Coastal Floors & Granite Dry -Line
PWS ID: 4560954
NOTICE OF PERMIT ISSUANCE
Enclosed is Permit Number 0081064-332-DSC to construct a Dry -Line to provide a future water
distribution for a proposed commercial development. This permit is issued pursuant to Section(s)
403.087, Florida Statutes.
A person whose substantial interests are affected by this permit may petition for an
administrative proceeding (hearing) in accordance with sections 120.569 and 120.57 of the
Florida Statutes. The petition must contain the information set forth below and must be filed
(received) with the Agency Clerk for the Department of Environmental Protection, Office of
General Counsel, Mail Station 35, 3900 Commonwealth Boulevard, Tallahassee, Florida 32399-
3000, within 14 days of receipt of this Notice. Petitioner shall mail a copy of the petition to the
applicant at the address indicated above at the time of filing. Failure to file a petition within this
time period shall constitute a waiver of any right such person may have to request an
administrative determination (hearing) under sections 120.569 and 120.57 of the Florida Statutes.
Any subsequent intervention will only be at the approval of the presiding officer upon motion
filed pursuant to Rule 28-106.205, F.A.C.
A petition must contain the following information:
(a) The name and address of each agency affected and each agency's file or identification
number, if known;
(b) The name, address, and telephone number of the petitioner; the name, address, and
telephone number of the petitioner's representative, if any, which shall be the address
for service purposes during the course of the proceeding; and an explanation of how
the petitioner's substantial interests will be affected by the agency determination;
(c) A statement of how and when the petitioner received notice of the agency decision;
(d) A statement of all disputed issues of material fact. If there are none, the petition must
so indicate;
Mr. Jesus Merejo, Utility Systems Director liar File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
(e) A concise statement of the ultimate facts alleged, including the specific facts which
petitioner contends warrant reversal or modification of the Department's action;
(f) A statement of the specific rules or statutes the petitioner contends requires reversal
or modification of the Department's action, including an explanation of how the
alleged facts relate to the specific rules or statutes; and
(g) A statement of the relief sought by petitioner, stating precisely the action that the
petitioner wants the Department to take.
A petition that does not dispute the materials facts on which the Department's action is based
shall state that no such facts are in dispute and otherwise contain the same information as set
forth above, as required by Rule 28-106.301, F.A.C.
Because the administrative hearing process is designed to formulate final agency action, the
filing of a petition means that, the Department's final action may be different from the position
taken by it in this Notice. Persons whose substantial interests will be affected by any such final
decision of the Department on the petition have the right to petition to become a party to the
proceeding, in accordance with the requirements set forth above.
When the Order (Permit) is final, any party to the Order has the right to seek judicial review of
the Order pursuant to section 120.68 of the Florida Statutes, by filing a Notice of Appeal
pursuant to Rule 9.110 of the Florida Rules of Appellate Procedure, with the Clerk of the
Department in the Office of General Counsel, Mail Station 35, 3900 Commonwealth Boulevard,
Tallahassee, Florida 32399-3000; and by filing a copy of the notice of appeal accompanied by
the applicable filing fees with the appropriate district court of appeal. The notice of appeal must
be filed within 30 days from the date when the final order is filed with the Clerk of the
Department.
Executed in West Palm Beach, Florida.
STATE OF FLORIDA DEPARTMENT
OF ENVIRONMENTAL PROTECTION
Diane Pupa
Permitting Program Administrator
Southeast District
1' �I:i�ITil�l7
Enclosure: Permit No. 0081064-332-DSC
Mr. Jesus Merejo, Utility Systems Director Lr File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
CERTIFICATION OF SERVICE
The undersigned duly designated deputy agency clerk hereby certifies that this NOTICE OF
PERMIT ISSUANCE and all copies were emailed or mailed before the close of business on
July 28, 2016 to those persons listed.
FILING AND ACKNOWLEDGEMENT
Filed, on this date, under section 120.52(7), Florida Statutes, with the designated Department
Clerk, receipt of which is hereby acknowledged.
COao.V wijcSza-l. July 28, 2016
Name Date
Electronic Copies Furnished to:
FDEPSED—Michele.Owens@do.state.fl.us Jocelyn.Labbe@dep.state.fl.us
Mark.Petersna,dep.state.fl.us
St. Lucie Health Department —David Koemer@doh.state.fl.us
Roderick J. Kennedy, P.E., David C. Baggett, P.E.— Engineering Design & Construction Inc.
rodkennedyna.edc-inc.com davidbaseett@edc-inc.com
Florida Department of
Environmental Protection
Southeast District Office
3301 Gun Club Road, MSC 7210-1
West Palm Beach, Florida 33406
561-681-6600
July 28, 2015
PERMITTEE:
Mr. Jesus A. Merejo, Utility System Director
Port St. Lucie Utility Services Department
900 S.E. Ogden Lane
Port St. Lucie, Florida 34983
Email: imereiona.citvofnsl.com
Rick Scott
Governor
Carlos Lopez-Cantera
Lt. Governor
Jonathan P. Steverson
Secretary
PWS ID NUMBER: 4560954
PERMIT NUMBER: 0081064-332-DSC
DATE OF ISSUE: July 28, 2016
EXPIRATION DATE: July 27, 2021
COUNTY: St. Lucie
PROJECT: Coastal Floors & Granite Dry -Line
This permit is issued under the provisions of Chapter 403, Florida Statutes (F.S.), and Florida
Administrative Code (F.A.C.) Chapters 62-4, 62-550, 62-555 and 62-560. The above named
permittee is hereby authorized to perform the work or operate the facility shown on the
application and approved drawings, plans, and other documents attached hereto or on file with the
Department and made a part hereof and specifically described as follows:
TO CONSTRUCT: A Future water distribution system extension for the Port St. Lucie Utility
(PSLU), a total of 290 linear feet (11) of water main (dry line) to provide potable water for a
proposed commercial development in St. Lucie County, Florida. This permit is for dry line
construction only.
PROPOSED CONSTRUCTION INCLUDES:
• Approximately 2701f of 12-inch PVC C900 water main
• 201f of 12-inch HDPE with fusible fitting
• Two (2) Sample Points
• All the associated appurtenance
IN ACCORDANCE WITH: The construction permit application and engineering specifications
and drawings sheets 1 through 10 dated July 7, 2016 prepared by Mr. Roderick J. Kennedy, P.E.
of Engineering Design & Construction Inc. and received by DEP on July 11, 2016. Additional
information in respond to DEP request for additional information dated July 12, 2016 prepared by
Mr. David C. Baggett, P.E., and received by DEP on July 28, 2016.
LOCATED: 8532 S. US Highway 1, Port St. Lucie, FL 34952.
Work must be conducted in accordance with the General and Specific Conditions, attached
hereto.
r
Mr. Jesus Merejo, Utility Systems Director bEr File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
Issued this 28th day of July. 2016.
STATE OF FLORIDA DEPARTMENT
OF ENVIRONMENTAL PROTECTION
Diane Pupa
Permitting Program Administrator
Southeast District
DP/JKE/MEP
Enclosure: Permit No. 0081064-332-DSC
Attachments: General Conditions, Regulatory Section, Construction Standards, Operational
Requirements, Monitoring Provisions, Clearance Requirements
Electronic Copies Furnished to:
FDEP SED — Mlchele.OWens@dep.state.fl.us Jocelyn.Labbe@dep.state.fl.us
Mark.Petersgdep.state.fl.us
St. Lucie Health Department —David Koemer@doh.state.fl.us
Roderick J. Kennedy, P.E. David C. Baggett, P.E.— Engineering Design & Construction Inc.
rodkennedy@a,edc-inc.com davidbaggett@ede-ine.com
Mr. Jesus Merejo, Utility Systems Director y,af File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
A. General Conditions
The permittee shall be aware of and operate under the Permit Conditions below. These
applicable conditions are binding upon the permittee and enforceable pursuant to Chapter
403, Florida Statutes. [F.A.C. Rule 62-555.533(1)]
1. The terms, conditions, requirements, limitations and restrictions set forth in this permit, are
"permit conditions" and are binding and enforceable pursuant to Sections 403.141,
403.727, or 403.859 through 403.861, F.S. The permittee is placed on notice that the
Department will review this permit periodically and may initiate enforcement action for
any violation of these conditions.
2. This permit is valid only for the specific processes and operations applied for and indicated
in the approved drawings or exhibits. Any unauthorized deviation from the approved
drawings, exhibits, specifications, or conditions of this permit may constitute grounds for
revocation and enforcement action by the Department.
3. As provided in Subsections 403.087(6) and 403.722(5), F.S., the issuance of this permit
does not convey any vested rights or any exclusive privileges. Neither does it authorize any
injury to public or private property or any invasion of personal rights, nor any infringement
of federal, state, or local laws or regulations. This permit is not a waiver of or approval of
any other department permit that may be required for other aspects of the total project
which are not addressed in this permit.
4. This permit conveys no title to land or water, does not constitute State recognition or
acknowledgment of title, and does not constitute authority for the use of submerged lands
unless herein provided and the necessary title or leasehold interests have been obtained
from the State. Only the Trustees of the Internal Improvement Trust Fund may express
State opinion as to title.
5. This permit does not relieve the permittee from liability for harm or injury to human health
or welfare, animal, or plant life, or property caused by the construction or operation of this
permitted source, or from penalties therefore; nor does it allow the permittee to cause
pollution in contravention of Florida Statutes and Department rules, unless specifically
authorized by an order from the Department.
6. The permittee shall properly operate and maintain the facility and systems of treatment and
control (and related appurtenances) that are installed and used by the permittee to achieve
compliance with the conditions of this permit, as required by Department rules. This
provision includes the operation of backup or auxiliary facilities or similar systems when
necessary to achieve compliance with the conditions of the permit and when required by
Department rules.
7. The permittee, by accepting this permit, specifically agrees to allow authorized
Department personnel, upon presentation of credentials or other documents as may be
required by law and at reasonable times (reasonable time may depend on the nature of the
concern being investigated), access to the premises where the permitted activity is located
or conducted to:
3
�l
Mr. Jesus'Merejo, Utility Systems Director File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
a. Have access to and copy any records that must be kept under conditions of the
permit;
b. Inspect the facility, equipment, practices, or operations regulated or required under
this permit; and
c. Sample or monitor any substances or parameters at any location reasonably
necessary to assure compliance with this permit or Department rules.
8. If, for any reason, the permittee does not comply with or will be unable to comply with any
condition or limitation specified in this permit, the permittee shall immediately provide the
Department with the following information:
a. A description of and cause of noncompliance; and
b. The period of noncompliance, including dates and times; or, if not corrected, the
anticipated time the noncompliance is expected to continue, and steps being taken
to reduce, eliminate, and prevent recurrence of the noncompliance. The permittee
shall be responsible for any and all damages which may result and may be subject
to enforcement action by the Department for penalties or for revocation of this
permit.
9. In accepting this permit, the permittee understands and agrees that all records, notes,
monitoring data and other information relating to the construction or operation of this
permitted source which are submitted to the Department may be used by the Department as
evidence in any enforcement case involving the permitted source arising under the Florida
Statutes or Department rules, except where such use is prescribed by Sections 403.111 and
403.73, F.S. Such evidence shall only be used to the extent it is consistent with the Florida
Rules of Civil Procedure and appropriate evidentiary rules.
10. The permittee agrees to comply with changes in Department rules and Florida Statutes after
a reasonable time for compliance; provided, however, the permittee does not waive any
other rights granted by Florida Statutes or Department rules. A reasonable time for
compliance with a new or amended surface water quality standard, other than those
standards addressed in Rule 62-302.500, shall include a reasonable time to obtain or be
denied a mixing zone for the new or amended standard.
11. This permit is transferable only upon Department approval in accordance with Rule 62-
4.120 and 62-730.300, F.A.C., as applicable. The permittee shall be liable for any non-
compliance of the permitted activity until the transfer is approved by the Department.
12. This permit or a copy thereof shall be kept at the work site of the permitted activity.
13. This permit also constitutes:
a. Determination of Best Available Control Technology (BACT)
b. Determination of Prevention of Significant Deterioration (PSD)
c. Certification of compliance with State Water Quality Standards (Section 401, PL
92-500)
4
Mr. Jesus Merejo, Utility Systems Director ifl Pr File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
d. Compliance with New Source Performance Standards
14. The permittee shall comply with the following:
a. Upon request, the permittee shall furnish all records and plans required under
Department rules. During enforcement actions, the retention period for all records
will be extended automatically unless otherwise stipulated by the Department.
b. The permittee shall hold at the facility or other location designated by this permit
records of all monitoring information (including all calibration and maintenance
records and all original strip chart recordings for continuous monitoring
instrumentation) required by the permit, copies of all reports required by this
permit, and records of all data used to complete the application for this permit.
These materials shall be retained at least three years from the date of the sample,
measurement, report, or application unless otherwise specified by Department rule.
c. Records of monitoring information shall include:
i. the date, exact place, and time of sampling or measurements;
ii. the person responsible for performing the sampling or measurements;
iii.the dates analyses were performed;
iv. the person responsible for performing the analyses;
v. the analytical techniques or methods used;
vi.the results of such analyses.
15. When requested by the Department, the permittee shall within a reasonable time furnish
any information required by law which is needed to determine compliance with the permit.
If the permittee becomes aware the relevant facts were not submitted or were incorrect in
the permit application or in any report to the Department, such facts or information shall be
corrected promptly.
B. Regulatory Section
All construction must be in accordance with this permit. Before commencing work on
project changes for which a construction permit modification is required per 62-555.536(1),
the permittee shall submit to the Department a written request for a permit modification.
Each such request shall be accompanied by one copy of a revised construction permit
application, the proper processing fee and one copy of either a revised preliminary design
report or revised drawings, specifications and design data. [F.A.C. Rule 62-555.536].
2. Permitted construction or alteration of public water supply systems must be supervised
during construction by a professional engineer registered in the State of Florida if the project
was designed under the responsible charge of a professional engineer licensed in the State of
Florida. The permittee must retain the service of a professional engineer registered in the
State of Florida to observe that construction of the project is in accordance with the
Mr. Jesus Merejo, Utility Systems Director ,. File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
engineering plans and specifications as submitted in support of the application for this
permit. [F.A.C. Rule 62-555.520(3)].
3. If prehistoric or historic artifacts, such as pottery or ceramics, stone tools or metal
implements, dugout canoe remains, or any other physical remains that could be associated
with Native American cultures, or early colonial or American settlement are encountered at
any time within the project site area, the permitted project should cease all activities
involving subsurface disturbance in the immediate vicinity of such discoveries. The
permittee, or other designee, should contact the Florida Department of State, Division of
Historical Resources, Compliance and Review Section at 850.245.6333 or 800.847.7278, as
well as the appropriate permitting agency office. Project activities should not resume without
verbal and/or written authorization from the Division of Historical Resources and the
permitting agency. In the event that unmarked human remains are encountered during
permitted activities, all work shall stop immediately and the proper authorities notified in
accordance with Section 872.05, Florida Statutes.
4. If delays will cause project completion to extend beyond the expiration date of this permit,
the permittee shall submit to the Department a request to extend the expiration date of this
permit including the appropriate processing fee. This request shall "specify the reasons for the
delay and shall be submitted to the Department for approval prior to the expiration date of
this permit. Note that no specific construction permit shall be extended so as to remain in
effect longer than five years. [F.A.C. Rule 62-555.536(4)]. {OPTIONAL)
5. In accordance with General Condition 411 of this permit, this permit is transferable only
upon Department approval. Persons proposing to transfer this permit must apply jointly for a
transfer of the permit within 30 days after the sale or legal transfer of ownership of the
permitted project that has not been cleared for service by the Department using form, 62-
555.900(8), Application for Transfer of a PWS Construction Permit along with the
appropriate fee. [F.A.C. Rule 62-555.536(5)]
6. This permit satisfies Drinking Water permitting requirements only and does not authorize
construction or operation of this facility prior to obtaining all other necessary permits from
other program areas within the Department, or required permits from other state, federal, or
local agencies.
7. If gasoline contamination is found at the construction site, work shall be stopped and the
proper authorities notified. With the approval of the Department, ductile iron pipe and
fittings, and solvent resistant gaskets materials shall be used in the contaminated area. The
ductile pipe shall be used in the contaminated area. The ductile iron pipe shall extend 100
feet beyond any solvent noted. Any contaminated soil that is excavated shall be placed on an
impermeable mat, covered with waterproof covering, and held for disposal. If the site cannot
be properly cleaned then consultation with the Department is necessary prior to continuing
with the project construction.
8. This permit does not constitute approval of construction on jurisdictional wetland areas;
therefore such approval must be obtained separately from the Water Management District or
from DEP ERP Section, as applicable, Permittee shall provide a copy of the permit approval
to the Department if water main installation involves activities on wetlands.
Mr. Jesus Merejo, Utility Systems Director liLY File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
9. Permittee shall ensure that the well and drinking water treatment facilities will be protected
to prevent tampering, vandalism, and sabotage as required by Rule 62-555.315(1) & 62-
555.320(5), F.A.C.
C. Construction Standards
1. All products, including paints, which shall come into contact with potable water, either
directly or indirectly, shall conform to National Sanitation Foundation (NSF) International,
Water Chemicals Codex, Food Chemicals Codex, American Water Works Association
(AW WA) Standards and the Food and Drug Administration, as provided in Rule 62-
555.320(3), F.A.C.
2. Water supply facilities, including mains, pipe, fittings, valves, fire hydrants and other
materials shall be installed in accordance with the latest applicable AW WA Standards and
Department rules and regulations. The system shall be pressure and leak tested in
accordance with AW WA Standard C600 C603, or C605, as applicable, and disinfected in
accordance with AWWA Standard C651-653, as well as in accordance with Rule 62-
555.340, F.A.C.
3. The installation or repairs of any public water system, or any plumbing in residential or
nonresidential facilities providing water for human consumption, which is connected to a
public water system shall be lead free in accordance with Rule 62-555.322, F.A.C.
4. The new or altered aboveground piping at the drinking water treatment plant shall be color
coded and labeled as recommended in Section 2.14 of "Recommended Standards for Water
Works, 1997 Edition". [F.A.C. Rule 62-555.320(10)]
5. Permittee shall ensure that there shall be no cross -connection with any non -potable water
source in accordance with Rule 62-555.360, F.A.C.
A Operational Requirements
1. The supplier of water shall operate and maintain the public water system so as to comply with
applicable standards in F.A.C. Rule 62-550 and 62-555.350.
2. The permittee shall provide an operation and maintenance manual for the new or altered
treatment facilities to fulfill the requirements under subsection 62-555.350(13), F.A.C. The
manual shall contain operation and control procedures, and preventative maintenance and
repair procedures, for all plant equipment and shall be made available for reference at the
plant or at a convenient location near the plant. Bound and indexed equipment manufacturer
manuals shall be considered sufficient to meet the requirements of the subsection.
4. The permittee shall have complete record drawings produced for the project in accordance
with Rule 62-555.530(4), F.A.0
Mr. Jesus Merejo, Utility Systems Director Lr File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
5. The permittee or suppliers of water shall telephone the State Warning Point (SWP), at 1-800-
320-0519 immediately (i.e., within two hours) after discovery of any actual or suspected
sabotage or security breach, or any suspicious incident, involving a public water system in
accordance with the F.A.C. Rule 62-555.350(10).
E. Monitoring Provisions
I. Permittee shall follow the guidelines of Chapters 62-550, 62-555, and 62-560, F.A.C.,
regarding public drinking water system standards, monitoring, reporting, permitting,
construction, and operation.
2. The water treatment plant shall maintain throughout the distribution system a minimum
combined chlorine residual of 0.6 mg/1 or its equivalent. A minimum system pressure of 20
psi must be maintained throughout the system. Also, safety equipment shall be provided and
located outside of chlorine room.
F. Clearance Requirements
The permittee must instruct the engineer of record to request system clearance from the
Department within sixty (60) days of completion of construction, testing and disinfecting the
system. Bacteriological test results shall be considered unacceptable if the test were
completed more than 60 days before the Department received the results. [F.A.C. Rule 62-
555.340(2)(c)]
Permitted construction or alteration of a public water system may not be placed into service
until a letter of clearance has been issued by this Department. [F.A.C. Rule 62-555.3451
2. Prior to placing this project into service, Permittee shall submit, at a minimum, all of the
following to the Department for evaluation and approval for operation, as provided in Rules
62-555.340 and 62-555.345, F.A.C.:
a. the engineer's Certification of Construction Completion and Request for Clearance to
Place Permitted PWS Components Into Operation {DEP Form 62-555.900(9)};
b. certified record drawings, if there are any changes noted for the permitted project.
c. two consecutive days of satisfactory bacteriological analytical results (see paragraph 3
below).
d. copy of a satisfactory pressure test of the process piping performed in accordance with
AWWA Standards. [F.A.C. Rule 62-555.320(21)(a)(1)]
3. The new facilities shall be cleaned, disinfected, and bacteriologically cleared in
accordance with Chapter 62-555, F.A.C. The bacteriological clearance data representative
distribution system (in accordance with the instructions for Bacteriological Sampling
Locations shown below) shall be submitted to the Department with the engineer's
Mr. Jesus Merejo, Utility Systems Director 1 1M�K File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
certification of construction completion. [Section 62-555.340 and 62-555.315(6)(b),
F.A.C.]
Bacteriological Sampling Locations: Copies of satisfactory bacteriological analyses
taken from locations within the distribution system or water main extension to be cleared,
in accordance with Rules 62-555.315 (6), 62-555.340 and 62-555.330, F.A.C. and
American Water Works Association (AWWA) Standard C 651-92 as follows:
• The endpoint of the proposed addition;
• Any water lines branching off a main extension;
• Every 1, 200 feet of water main;
• Each location shall be sampled on two separate days (at least 6 hours apart) with
sample point locations and chlorine residual readings clearly indicated on the
report and/or drawings.
• Bacteriological'sample results will be considered unacceptable if the tests were
completed more than 60 days before the Department receives the results
In order to facilitate the issuance of a letter of clearance, the Department requests that all of the
above information be submitted as one package.
r .
SCANNED
BY
AM9199bPAitment of
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road
Tallahassee, Florida 32399-2400
Rick Scott
Governor
Carlos Lopez-Cantera
Lt. Governor
Jonathan P. Steverson
Secretary
SELF CERTIFICATION FOR
A STORMWATER MANAGEMENT SYSTEM IN UPLANDS SERVING
LESS THAN 10 ACRES OF TOTAL PROJECT AREA AND
LESS THAN 2 ACRES OF IMPERVIOUS SURFACES
Owner(s)/Permittee(s):
File No:
File Name:
Site Address:
County:
Latitude:
Longitude:
Total Project Area:
Total Impervious Surface Area:
Nicholas Elliott
0346164001EG
COASTAL FLOOR AND GRANITE
8532 S US Highway 1
Port Saint Lucie FL - 34952 3307
St. Lucie
270 18' 50.8698"
-800 18' 45.672"
1.25
0.63
Approximate Date of Commencement 11/01/2016
of Construction:
Registered Florida Professional:
License No.:
Company:
Date: July 28, 2016
I Wel 01:3 R [0) 0424 WINa�Y1
56218
Engineering Design & Construction, Inc.
David Baggett certified through the Department's Enterprise Self -Service Application portal that the
project described above was designed by the above -named Florida registered professional to meet the
following requirements:
1. The total project area involves less than 10 acres and less than 2 acres of impervious surface;
2. No activities will impact wetlands or other surface waters;
3. No activities are conducted in, on, or over wetlands or other surface waters;
4. Drainage facilities will not include pipes having diameters greater than 24 inches, or the hydraulic
equivalent, and will not use pumps in any manner;
5. The project is not part of a larger common plan, development, or sale; and
6. The project does not:
1. Cause adverse water quantity or flooding impacts to receiving water and adjacent lands;
2. Cause adverse impacts to existing surface water storage and conveyance capabilities;
3. Cause a violation of state water quality standards; or
4. Cause an adverse impact to the maintenance of surface or ground water levels or surface water
flows established pursuant to s. 373.042 or a work of the district established pursuant to s.
373.086, F.S.
This certification was submitted within approximately 30 days after initiation of construction of the above
project. As such, construction, alteration, and maintenance of the stormwater management system serving
this project is authorized in accordance with s. 403.814(12), F.S., and that there is a rebuttable presumption
that the discharge from such system will comply with state water quality standards when the stormwater
management system for this project is designed, operated, and maintained in accordance with applicable
rules adopted pursuant to part IV of chapter 373, F.S.
Applicants are advised to contact the applicable water management district for requirements that must be
followed to properly abandon any existing water wells that need to be removed because they are located
where construction is occurring.
In accordance with s. 373.416(2), F.S., if ownership of the property or the stormwater management system
is sold or transferred to another party, continued operation of the system is authorized only if notice is
provided to the Department within 30 days of the sale or transfer.
This notice can be submitted to:
FDEP Southeast District
3301 Gun Club Road, MSC 7210-1 West Palm Beach 33406
This certification was submitted along with the following electronic documents:
If you have submitted this certification as a Florida Registered Professional, you may wish to sign and seal
this certification, and return a copy to the Department, in accordance with your professional practice act
requirements under Florida Statutes.
I, RODERICK KENNEDY, License No. 56218, do hereby certify that the above information is true and
accurate, based upon m i ifw1ormation and belief. In the space below, affix signature, date, seal,
company name, addr,e0� a�jd . _ (rfr'uthorization (if applicable).
_ � r
0 l
This sealed certifica !���.��,`0�' e A o the Department, either electronically (as an attachment in
Adobe PDF or other se at at Erp.selfcerts@dep.state.fl.us, or as a hardcopy, at the postal
address below:
Florida Department of Environmental Protection
Office of Submerged Lands and Environmental Resources
2600 Blair Stone Road MS 2500
Tallahassee FL 32399-2400
,At
SCANNED
BY
St. Lucie County
Florida Department of
Enviromnental Protection
Bob Martinez Center
2600 Blair Stone Road
Tallahassee, Florida 32399-2400
Rick Scott
Governor
Carlos Lopez-Cantera
Lt. Governor
Jonathan P. Steverson
Secretary
SELF CERTIFICATION FOR
A STORMWATER MANAGEMENT SYSTEM IN UPLANDS SERVING
LESS THAN 10 ACRES.OF TOTAL PROJECT AREA AND
LESS THAN 2 ACRES OF IMPERVIOUS SURFACES
Owner(s)/Permittee(s):
File No:
File Name:
Site Address:
County:
Latitude:
Longitude:
Nicholas Elliott
0346164001EG
COASTAL FLOOR AND GRANITE
8532 S US Highway 1
Port Saint Lucie FL - 34952 3307
St. Lucie
270 18' 50.8698"
-800 18' 45.672"
Total Project Area: 1.25
Total Impervious Surface Area: 0.63
Approximate Date of Commencement 11/01/2016
of Construction:
Registered Florida Professional:
License No.:
Company:
Date: July 28, 2016
RODERICK KENNEDY
56218
Engineering Design & Construction, Inc.
David Baggett certified through the Department's Enterprise Self -Service Application portal that the
project described above was designed by the above -named Florida registered professional to meet the
following requirements:
1. The total project area involves less than 10 acres and less than 2 acres of impervious surface;
2. No activities will impact wetlands or other surface waters;
3. No activities are conducted in, on, or over wetlands or other surface waters;
4. Drainage facilities will not include pipes having diameters greater than 24 inches, or the hydraulic
equivalent, and will not use pumps in any manner;
5. The project is not part of a larger common plan, development, or sale; and
6. The project does not:
1. Cause adverse water quantity or flooding impacts to receiving water and adjacent lands;
2. Cause adverse impacts to existing surface water storage and conveyance capabilities;
3. Cause a violation of state water quality standards; or
4. Cause an adverse impact to the maintenance of surface or ground water levels or surface water
flows established pursuant to s. 373.042 or a work of the district established pursuant to s.
373.086, F.S.
This certification was submitted within approximately 30 days after initiation of construction of the above
project. As such, construction, alteration, and maintenance of the stormwater management system serving
this project is authorized in accordance with s. 403.814(12), F.S., and that there is a rebuttable presumption
that the discharge from such system will comply with state water quality standards when the stormwater
management system for this project is designed, operated, and maintained in accordance with applicable
rules adopted pursuant to part IV of chapter 3.73, F.S.
Applicants are advised to contact the applicable water management district for requirements that must be
followed to properly abandon any existing water wells that need to be removed because they are located
where construction is occurring.
In accordance with s. 373.416(2), F.S., if ownership of the property or the stormwater management system
is sold or transferred to another party, continued operation of the system is authorized only if notice is
provided to the Department within 30 days of the sale or transfer.
This notice can be submitted to:
FDEP Southeast District
3301 Gun Club Road, MSC 7210-1 West Palm Beach 33406
This certification was submitted along with the following electronic documents:
If you have submitted this certification as a Florida Registered Professional, you may wish to sign and seal
this certification, and return a copy to the Department, in accordance with your professional practice act
requirements under Florida Statutes.
I, RODERICK KENNEDY, License No. 56218, do hereby certify that the above information is true and
accurate, based upon m i�blb l/� ormation and belief. In the space below, affix signature, date, seal,
company name, addr�oa�d w authorization (if applicable).
ITT!
This sealed certifica e u o the Department, either electronically (as an attachment in
Adobe PDF or other se ,I l� at) at Erp.selfcerts@dep.state.fl.us, or as a hardcopy, at the postal
address below:
Florida Department of Environmental Protection
Office of Submerged Lands and Environmental Resources
2600 Blair Stone Road MS 2500
Tallahassee FL 32399-2400
July 28, 2016
SCANNED
BY
FloriclOW RMbrit of
Environmental Protection
Southeast District Office
3301 Gun Club Road, MSC 7210-1
West Palm Beach, Florida 33406
56 SCAV - D
BY
St. Lucie Count%,
In the Matter of an Application for Permit by:
Rick Scott
Governor
Carlos Lopez-Cantera
Lt. Governor
Jonathan P. Steverson
RSecretary
JUL 2 9 zV;S
Mr. Jesus A. Merejo, Utility System Director DEP File No. 0081064-332-DSC
Port St. Lucie Utility Services Department St. Lucie County
900 S.E. Ogden Lane Coastal Floors & Granite Dry -Line
Port St. Lucie, Florida 34983 PWS ID: 4560954
Email: imereio0..citvofnsl.com
NOTICE OF PERMIT ISSUANCE
Enclosed is Permit Number 0081064-332-DSC to construct a Dry -Line to provide a future water
distribution for a proposed commercial development. This permit is issued pursuant to Section(s)
403.087, Florida Statutes.
A person whose substantial interests are affected by this permit may petition for an
administrative proceeding (hearing) in accordance with sections 120.569 and 120.57 of the
Florida Statutes. The petition must contain the information set forth below and must be filed
(received) with the Agency Clerk for the Department of Environmental Protection, Office of
General Counsel, Mail Station 35,3900 Commonwealth Boulevard, Tallahassee, Florida 32399-
3000, within 14 days of receipt of this Notice. Petitioner shall mail a copy of the petition to the
applicant at the address indicated above at the time of filing. Failure to file a petition within this
time period shall constitute a waiver of any right such person may have to request an
administrative determination (hearing) under sections 120.569 and 120.57 of the Florida Statutes.
Any subsequent intervention will only be at the approval of the presiding officer upon motion
filed pursuant to Rule 28-106.205, F.A.C.
A petition must contain the following information:
(a) The name and address of each agency affected and each agency's file or identification
number, if known;
(b) The name, address, and telephone number of the petitioner; the name, address, and
telephone number of the petitioner's representative, if any, which shall be the address
for service purposes during the course of the proceeding; and an explanation of how
the petitioner's substantial interests will be affected by the agency determination;
(c) A statement of how and when the petitioner received notice of the agency decision;
(d) A statement of all disputed issues of material fact. If there are none, the petition must
so indicate;
I -
Mr. Jesus Merejo, Utility Systems Director ;,r: File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
(e) A concise statement of the ultimate facts alleged, including the specific facts which
petitioner contends warrant reversal or modification of the Department's action;
(t) A statement of the specific rules or statutes the petitioner contends requires reversal
or modification of the Department's action, including an explanation of how the
alleged facts relate to the specific rules or statutes; and
(g) A statement of the relief sought by petitioner, stating precisely the action that the
petitioner wants the Department to take.
A petition that does not dispute the materials facts on which the Department's action is based
shall state that no such facts are in dispute and otherwise contain the same information as set
forth above, as required by Rule 28-106.301, F.A.C.
Because the administrative hearing process is designed to formulate final agency action, the
filing of a petition means that, the Department's final action may be different from the position
taken by it in this Notice. Persons whose substantial interests will be affected by any such final
decision of the Department on the petition have the right to petition to become a party to the
proceeding, in accordance with the requirements set forth above.
When the Order (Permit) is final, any party to the Order has the right to seek judicial review of
the Order pursuant to section 120.68 of the Florida Statutes, by filing a Notice of Appeal
pursuant to Rule 9.110 of the Florida Rules of Appellate Procedure, with the Clerk of the
Department in the Office of General Counsel, Mail Station 35, 3900 Commonwealth Boulevard,
Tallahassee, Florida 32399-3000; and by filing a copy of the notice of appeal accompanied by
the applicable filing fees with the appropriate district court of appeal. The notice of appeal must
be filed within 30 days from the date when the final order is filed with the Clerk of the
Department.
Executed in West Palm Beach, Florida.
STATE OF FLORIDA DEPARTMENT
OF ENVIRONMENTAL PROTECTION
Diane Pupa
Permitting Program Administrator
Southeast District
DP/JKE/MEP
Enclosure: Permit No. 0081064-332-DSC
Mr. Jesus Merejo, Utility Systems Director File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
CERTIFICATION OF SERVICE
The undersigned duly designated deputy agency clerk hereby certifies that this NOTICE OF
PERMIT ISSUANCE and all copies were emailed or mailed before the close of business on
July 28, 2016 to those persons listed.
FILING AND ACKNOWLEDGEMENT
Filed, on this date, under section 120.52(7), Florida Statutes, with the designated Department
Clerk, receipt of which is hereby acknowledged.
Ff6aJ-iw4aLL July 28, 2016
Name Date
Electronic Copies Furnished to:
FDEP SED — Michele.OWens@dep.State.fl.us Jocelvn.Labbegdep.state.fl.us
Mark.Peters@dep.state.fl.us
St. Lucie Health Department — David Koernernadoh.state.fl.us
Roderick J. Kennedy, P.E., David C. Baggett, P.E.— Engineering Design & Construction Inc.
rodkennedy(a),,edc-inc.com davidbaggett@edc-inc.com
Florida Department of
Environmental Protection
Southeast District Office
3301 Gun Club Road, MSC 7210-1
West Palm Beach, Florida 33406
561-681-6600
July 28, 2015
PERMITTEE:
Mr. Jesus A. Merejo, Utility System Director
Port St. Lucie Utility Services Department
900 S.E. Ogden Lane
Port St. Lucie, Florida 34983
Email: imerejo@cityofosl.com
Rick Scott
Governor
Carlos Lopez-Cantera
Lt. Governor
Jonathan P. Steverson
Secretary
PWS ID NUMBER: 4560954
PERMIT NUMBER: 0081064-332-DSC
DATE OF ISSUE: July 28, 2016
EXPIRATION DATE: July 27, 2021
COUNTY: St. Lucie
PROJECT: Coastal Floors & Granite Dry -Line
This permit is issued under the provisions of Chapter 403, Florida Statutes (F.S.), and Florida
Administrative Code (F.A.C.) Chapters 62-4, 62-550, 62-555 and 62-560. The above named
permittee is hereby authorized to perform the work or operate the facility shown on the
application and approved drawings, plans, and other documents attached hereto or on file with the
Department and made a part hereof and specifically described as follows:
TO CONSTRUCT: A Future water distribution system extension for the Port St. Lucie Utility
(PSLU), a total of 290 linear feet (10 of water main (dry line) to provide potable water for a
proposed commercial development in St. Lucie County, Florida. This permit is for dry line
construction only.
PROPOSED CONSTRUCTION INCLUDES:
• Approximately 2701f of 12-inch PVC C900 water main
• 20 If of 12-inch HDPE with fusible fitting
• Two (2) Sample Points
• All the associated appurtenance
IN ACCORDANCE WITH: The construction permit application and engineering specifications
and drawings sheets 1 through 10 dated July 7, 2016 prepared by Mr. Roderick J. Kennedy, P.E.
of Engineering Design & Construction Inc. and received by DEP on July 11, 2016. Additional
information in respond to DEP request for additional information dated July 12, 2016 prepared by
Mr. David C. Baggett, P.E., and received by DEP on July 28, 2016.
LOCATED: 8532 S. US Highway 1, Port St. Lucie, FL 34952.
Work must be conducted in accordance with the General and Specific Conditions, attached
hereto.
Lr`i File No.
0081064-332-DSC
Mr. Jesus Merejo, Utility Systems Director
Port St. Lucie Utility Systems Department
Issued this 28th day of July, 2016.
STATE OF FLORIDA DEPARTMENT
OF ENVIRONMENTAL PROTECTION
Diane Pupa
Permitting Program Administrator
Southeast District
DP/JKE/1V1EP
Enclosure: Permit No. 0081064-332-DSC
Attachments: General Conditions, Regulatory Section, Construction Standards, Operational
Requirements, Monitoring Provisions, Clearance Requirements
Electronic Copies Furnished to:
FDEPSED—Michele.Owens@dW.state.fl.us Jocelyn.Labbe@dep.state.fl.us
Mark.Petersna demstate.fl.us
St. Lucie Health Department —David KoernerCa�doh.state.fl.us
Roderick J. Kennedy, P.E. David C. Baggett, P.E.— Engineering Design & Construction Inc.
rodkennedy@edc-inc.com davidbaggett(@,edc-inc.com
Mr. Jesus Merejo, Utility Systems Director iyzr File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
A. General Conditions
The permittee shall be aware of and operate under the Permit Conditions below. These
applicable conditions are binding upon the permittee and enforceable pursuant to Chapter
403, Florida Statutes. [F.A.C. Rule 62-555.533(1)]
1. The terms, conditions, requirements, limitations and restrictions set forth in this permit, are
"permit conditions" and are binding and enforceable pursuant to Sections 403.141,
403.727, or 403.859 through 403.861, F.S. The permittee is placed on notice that the
Department will review this permit periodically and may initiate enforcement action for
any violation of these conditions.
2. This permit is valid only for the specific processes and operations applied for and indicated
in the approved drawings or exhibits. Any unauthorized deviation from the approved
drawings, exhibits, specifications, or conditions of this permit may constitute grounds for
revocation and enforcement action by the Department.
3. As provided in Subsections 403.087(6) and 403.722(5), F.S., the issuance of this permit
does not convey any vested rights or any exclusive privileges. Neither does it authorize any
injury to public or private property or any invasion of personal rights, nor any infringement
of federal, state, or local laws or regulations. This permit is not a waiver of or approval of
any other department permit that may be required for other aspects of the total project
which are not addressed in this permit.
4. This permit conveys no title to land or water, does not constitute State recognition or
acknowledgment of title, and does not constitute authority for the use of submerged lands
unless herein provided and the necessary title or leasehold interests have been obtained
from the State. Only the Trustees of the Internal Improvement Trust Fund may express
State opinion as to title.
5. This permit does not relieve the permittee from liability for harm or injury to human health
or welfare, animal, or plant life, or property caused by the construction or operation of this
permitted source, or from penalties therefore; nor does it allow the permittee to cause
pollution in contravention of Florida Statutes and Department rules, unless specifically
authorized by an order from the Department.
6. The permittee shall properly operate and maintain the facility and systems of treatment and
control (and related appurtenances) that are installed and used by the permittee to achieve
compliance with the conditions of this permit, as required by Department rules. This
provision includes the operation of backup or auxiliary facilities or similar systems when
necessary to achieve compliance with the conditions of the permit and when required by
Department rules.
The permittee, by accepting this permit, specifically agrees to allow authorized
Department personnel, upon presentation of credentials or other documents as may be
required by law and at reasonable times (reasonable time may depend on the nature of the
concern being investigated), access to the premises where the permitted activity is located
or conducted to:
Mr. Jesus Merejo, Utility Systems Director iize File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
a. Have access to and copy any records that must be kept under conditions of the
permit;
b. Inspect the facility, equipment, practices, or operations regulated or required under
this permit; and
c. Sample or monitor any substances or parameters at any location reasonably
necessary to assure compliance with this permit or Department rules.
8. If, for any reason, the permittee does not comply with or will be unable to comply with any
condition or limitation specified in this permit, the permittee shall immediately provide the
Department with the following information:
a. A description of and cause of noncompliance; and
b. The period of noncompliance, including dates and times; or, if not corrected, the
anticipated time the noncompliance is expected to continue, and steps being taken
to reduce, eliminate, and prevent recurrence of the noncompliance. The permittee
shall be responsible for any and all damages which may result and may be subject
to enforcement action by the Department for penalties or for revocation of this
permit.
9. In accepting this permit, the permittee understands and agrees that all records, notes,
monitoring data and other information relating to the construction or operation of this
permitted source which are submitted to the Department may be used by the Department as
evidence in any enforcement case involving the permitted source arising under the Florida
Statutes or Department rules, except where such use is prescribed by Sections 403.111 and
403.73, F.S. Such evidence shall only be used to the extent it is consistent with the Florida
Rules of Civil Procedure and appropriate evidentiary rules.
10. The permittee agrees to comply with changes in Department rules and Florida Statutes after
a reasonable time for compliance; provided, however, the permittee does not waive any
other rights granted by Florida Statutes or Department rules. A reasonable time for
compliance with a new or amended surface water quality standard, other than those
standards addressed in Rule 62-302.500, shall include a reasonable time to obtain or be
denied a mixing zone for the new or amended standard.
11. This permit is transferable only upon Department approval in accordance with Rule 62-
4.120 and 62-730.300, F.A.C., as applicable. The permittee shall be liable for any non-
compliance of the permitted activity until the transfer is approved by the Department.
12. This permit or a copy thereof shall be kept at the work site of the permitted activity.
13. This permit also constitutes:
a. Determination of Best Available Control Technology (BACT)
b. Determination of Prevention of Significant Deterioration (PSD)
c. Certification of compliance with State Water Quality Standards (Section 401, PL
92-500)
Mr. Jesus Merejo, Utility Systems Director my a File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
d. Compliance with New Source Performance Standards
14. The permittee shall comply with the following:
a. Upon request, the permittee shall furnish all records and plans required under
Department rules. During enforcement actions, the retention period for all records
will be extended automatically unless otherwise stipulated by the Department.
b. The permittee shall hold at the facility or other location designated by this permit
records of all monitoring information (including all calibration and maintenance
records and all original strip chart recordings for continuous monitoring
instrumentation) required by the permit, copies of all reports required by this
permit, and records of all data used to complete the application for this permit.
These materials shall be retained at least three years from the date of the sample,
measurement, report, or application unless otherwise specified by Department rule.
c. Records of monitoring information shall include:
i. the date, exact place, and time of sampling or measurements;
ii. the person responsible for performing the sampling or measurements;
iii.the dates analyses were performed;
iv.the person responsible for performing the analyses;
v. the analytical techniques or methods used;
vi.the results of such analyses.
15. When requested by the Department, the permittee shall within a reasonable time furnish
any information required by law which is needed to determine -compliance with the permit.
If the permittee becomes aware the relevant facts were not submitted or were incorrect in
the permit application or in any report to the Department, such facts or information shall be
corrected promptly.
B. Regulatory Section
All construction must be in accordance with this permit. Before commencing work on
project changes for which a construction permit modification is required per 62-555.536(1),
the permittee shall submit to the Department a written request for a permit modification.
Each such request shall be accompanied by one copy of a revised construction permit
application, the proper processing fee and one copy of either a revised preliminary design
report or revised drawings, specifications and design data. [F.A.C. Rule 62-555.536].
2. Permitted construction or alteration of public water supply systems must be supervised
during construction by a professional engineer registered in the State of Florida if the project
was designed under the responsible charge of a professional engineer licensed in the State of
Florida. The permittee must retain the service of a professional engineer registered in the
State of Florida to observe that construction of the project is in accordance with the
'Mr. Jesus Merejo, Utility Systems Director br File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
engineering plans and specifications as submitted in support of the application for this
permit. [F.A.C. Rule 62-555.520(3)].
3. If prehistoric or historic artifacts, such as pottery or ceramics, stone tools or metal
implements, dugout canoe remains, or any other physical remains that could be associated
with Native American cultures, or early colonial or American settlement are encountered at
any time within the project site area, the permitted project should cease all activities
involving subsurface disturbance in the immediate vicinity of such discoveries. The
permittee, or other designee, should contact the Florida Department of State, Division of
Historical Resources, Compliance and Review Section at 850.245.6333 or 800.847.7278, as
well as the appropriate permitting agency office. Project activities should not resume without
verbal and/or written authorization from the Division of Historical Resources and the
permitting agency. In the event that unmarked human remains are encountered during
permitted activities, all work shall stop immediately and the proper authorities notified in
accordance with Section 872.05, Florida Statutes.
4. If delays will cause project completion to extend beyond the expiration date of this permit,
the permittee shall submit to the Department a request to extend the expiration date of this
permit including the appropriate processing fee. This request shall specify the reasons for the
delay and shall be submitted to the Department for approval prior to the expiration date of
this permit. Note that no specific construction permit shall be extended so as to remain in
effect longer than five years. [F.A.C. Rule 62-555.536(4)]. {OPTIONAL]
In accordance with General Condition #11 of this permit, this permit is transferable only
upon Department approval. Persons proposing to transfer this permit must apply jointly for a
transfer of the permit within 30 days after the sale or legal transfer of ownership of the
permitted project that has not been cleared for service by the Department using form, 62-
555.900(8), Application for Transfer of a PWS Construction Permit along with the
appropriate fee. [F.A.C. Rule 62-555.536(5)]
6. This permit satisfies Drinking Water permitting requirements only and does not authorize
construction or operation of this facility prior to obtaining all other necessary permits from
other program areas within the Department, -or required permits from other state, federal, or
local agencies.
If gasoline contamination is found at the construction site, work shall be stopped and the
proper authorities notified. With the approval of the Department, ductile iron pipe and
fittings, and solvent resistant gaskets materials shall be used in the contaminated area. The
ductile pipe shall be used in the contaminated'area. The ductile iron pipe shall extend 100
feet beyond any solvent noted. Any contaminated soil that is excavated shall be placed on an
impermeable mat, covered with waterproof covering, and held for disposal. If the site cannot
be properly cleaned, then consultation with the Department is necessary prior to continuing
with the proiect construction.
8. This permit does not constitute approval of construction on jurisdictional wetland areas;
therefore such approval must be obtained separately from the Water Management District or
from DEP ERP Section, as applicable, Permittee shall provide a copy of the permit approval
to the Department if water main installation involves activities on wetlands.
Mr. Jesus Merejo, Utility Systems Director uj�` File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
9. Permittee shall ensure that the well and drinking water treatment facilities will be protected
to prevent tampering, vandalism, and sabotage as required by Rule 62-555.315(1) & 62-
555.320(5), F.A.C.
C. Construction Standards
1. All products, including paints, which shall come into contact with potable water, either
directly or indirectly, shall conform to National Sanitation Foundation (NSF) International,
Water Chemicals Codex, Food Chemicals Codex, American Water Works Association
(AWWA) Standards and the Food and Drug Administration, as provided in Rule 62-
555.320(3), F.A.C.
2. Water supply facilities, including mains, pipe, fittings, valves, fire hydrants and other
materials shall be installed in accordance with the latest applicable AWWA Standards and
Department rules and regulations. The system shall be pressure and leak tested in
accordance with AWWA Standard C600 C603, or C605, as applicable, and disinfected in
accordance with AWWA Standard C651-653, as well as in accordance with Rule 62-
555.340, F.A.C.
3. The installation or repairs of any public water system, or any plumbing in residential or
nonresidential facilities providing water for human consumption, which is connected to a
public water system shall be lead free in accordance with Rule 62-555.322, F.A.C.
4. The new or altered aboveground piping at the drinking water treatment plant shall be color
coded and labeled as recommended in Section 2.14 of "Recommended Standards for Water
Works, 1997 Edition". [F.A.C. Rule 62-555.320(10)]
5. Permittee shall ensure that there shall be no cross -connection with any non -potable water
source in accordance with Rule 62-555.360, F.A.C.
A Operational Requirements
1. The supplier of water shall operate and maintain the public water system so as to comply with
applicable standards in F.A.C. Rule 62-550 and 62-555.350.
2. The permittee shall provide an operation and maintenance manual for the new or altered
treatment facilities to fulfill the requirements under subsection 62-555.350(13), F.A.C. The
manual shall contain operation and control procedures, and preventative maintenance and
repair procedures, for all plant equipment and shall be made available for reference at the
plant or at a convenient location near the plant. Bound and indexed equipment manufacturer
manuals shall be considered sufficient to meet the requirements of the subsection.
4. The permittee shall have complete record drawings produced for the project in accordance
with Rule 62-555.530(4), F.A.0
Mr. Jesus Merejo, Utility Systems Director ";re File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
5. The permittee or suppliers of water shall telephone the State Warning Point (SWP), at 1-800-
320-0519 immediately (i.e., within two hours) after discovery of any actual or suspected
sabotage or security breach, or any suspicious incident, involving a public water system in
accordance with the F.A.C. Rule 62-555.350(10).
E. Monitoring Provisions
1. Permittee shall follow the guidelines of Chapters 62-550, 62-555, and 62-560, F.A.C.,
regarding public drinking water system standards, monitoring, reporting, permitting,
construction, and operation.
2. The water treatment plant shall maintain throughout the distribution system a minimum
combined chlorine residual of 0.6 mg/l or its equivalent. A minimum system pressure of 20
psi must be maintained throughout the system. Also, safety equipment shall be provided and
located outside of chlorine room.
F. Clearance Requirements
The permittee must instruct the engineer of record to request system clearance from the
Department within sixty (60) days of completion of construction, testing and disinfecting the
system. Bacteriological test results shall be considered unacceptable if the test were
completed more than 60 days before the Department received the results. [F.A.C. Rule 62-
555.340(2)(c)]
Permitted construction or alteration of a public water system may not be placed into service
until a letter of clearance has been issued by this Department. [F.A.C. Rule 62-555.3451
2. Prior to placing this project into service, Permittee shall submit, at a minimum, all of the
following to the Department for evaluation and approval for operation, as provided in Rules
62-555.340 and 62-555.345, F.A.C.:
a. the engineer's Certification of Construction Completion and Request for Clearance to
Place Permitted PWS Components Into Operation {DEP Form 62-555.900(9));
b. certified record drawings, if there are any changes noted for the permitted project.
c. two consecutive days of satisfactory bacteriological analytical results (see paragraph 3
below).
d. copy of a satisfactory pressure test of the process piping performed in accordance with
AWWA Standards. [F.A.C. Rule 62-555.320(21)(a)(1)]
3. The new facilities shall be cleaned, disinfected, and bacteriologically cleared in
accordance with Chapter 62-555, F.A.C. The bacteriological clearance data representative
distribution system (in accordance with the instructions for Bacteriological Sampling
Locations shown below) shall be submitted to the Department with the engineer's
Mr. Jesus Merejo, Utility Systems Director iizr File No.
Port St. Lucie Utility Systems Department 0081064-332-DSC
certification of construction completion. [Section 62-555.340 and 62-555.315(6)(b),
F.A.C.]
Bacteriological Sampling Locations: Copies of satisfactory bacteriological analyses
taken from locations within the distribution system or water main extension to be cleared,
in accordance with Rules 62-555.315 (6), 62-555.340 and 62-555.330, F.A.C. and
American Water Works Association (AWWA) Standard C 651-92 as follows:
• The endpoint of the proposed addition;
• Any water lines branching off a main extension;
• Every 1,200 feet of water main;
• Each location shall be sampled on two separate days (at least 6 hours apart) with
sample point locations and chlorine residual readings clearly indicated on the
report and/or drawings.
• Bacteriological sample results will be considered unacceptable if the tests were
completed more than 60 days before the Department receives the results
In order to facilitate the issuance of a letter of clearance, the Department requests that all of the