HomeMy WebLinkAboutCOMMISSIONING PLANSCANNED
BY
St Luce county
COMMISSIONING
PLAN
St. Lucie County
Rosser Boulevard Public Library
Commissioning Plan
Sims Wilkerson Cartier Engineering, Inc..
12124 High Tech Avenue
Suite 200
Orlando, FL 32817
Phone: 407 380 0400
December, 2017
Revision 2
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL
Document History.
SWC Project No.16021
Rev
Date
Reason for Issue
Author
0
04/04/2017
Initial Draft for Team Comment
Sam Siciliano, Cx - SWC
1
08/29/2017
Update DRAFT
Sam Siciliano Cx - SWC
2
12-11-2017
UPDATE PRELIM
Sam Siciliano Cx - SWC
Document Signoff and Acceptance.
Party
Name
On behalf of
Signature
Date
Owner
PM
FM
A/E
CM
St. Lucie County
Rosser Blvd Public Library
Port St, Lucie, FL
St. Lucie County Rosser Blvd Public Library
Contents:
Introduction
Commissioning Goals and Objectives
Abbreviations
Definitions
Project Description
Systems to be Commissioned
Commissioning Approach
Prefunctional Test
Equipment / System Start Up & Calibration
Test and Balance
Functional Acceptance Testing
Commissioning Team
Team Member Responsibilities
Owner (PM)
Architect / Engineers
Commissioning Agent
Construction Manager
Mechanical Contractor and Subcontractors
Electrical Contractor and Subcontractors
Controls Contractor
Test & Balance Contractor
Communication & Protocol
Commissioning Schedule
System Acceptance Criteria
Issue Resolution
Appendix:
Observation and Deficiency Log (template)
Notification to Observe Form:
SWC Pr*ct No. 16021
Page Number
2
2
4
4
6
6
6
7
7
8
8
10
11
11
11
11
12
13
14
14
15
15
16
17
17
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL
INTRODUCTION
SWC ProjectNo.16021
This document is the Commissioning Plan for the St. Lucie County Rosser Blvd. Public Library project.
The objective is to guide the project team through the specified commissioning processes by defining
the extent of responsibility, commitment and coordination required by the various project team members
involved in the commissioning process. This commissioning plan is a `living" document and as such, will
change, be updated and revised as the project evolves through construction, testing, validation,
handover and occupation of the building. The general responsibilities and requirements as outlined
within this document are not expected to change very much during the project timeline and are intended
as a further clarification of the requirements of the contract documents. Reference to the drawings,
related specification sections and general provisions of the contract, including general and
supplementary conditions should be made to ensure all contractual commissioning requirements are
satisfactorily implemented.
System Commissioning is required to be performed by the Florida Building Code - 2014 — Energy
Conservation, Section 408, and its requirements are listed below. It is a requirement of the code, that the
project team develops and utilizes a commissioning plan. This is that plan. The plan shall be used by the
project team as a working document to assist in achieving the goal of successfully completing and
commissioning the buildings systems, satisfying the requirements defined by the Contract Documents.
The Commissioning Agent (CxA) shall monitor the projects shared commissioning goals as planned
through the duration of the project, reporting observations directly to the Owner.
St. Lucie County (Owner) has contracted Sims Wilkerson Cartier Engineering, Inc. as their Independent
Commissioning Agent (CxA).
COMMISSIONING GOALS & OBJECTIVES
The intent of this plan is that commissioning services will provide an independent evaluation of
mechanical HVAC systems to confirm they are contract compliant, meet or exceed all standards and are
operating as designed and intended. Commissioning is to include demonstrating the integrated
performance of all equipment and systems serving the building. These services are critical for this
project as once the facility is occupied there will be limited opportunity to address any operational issues
without seriously compromising operations of the Owner.
Commissioning is a systematic process, the purpose of which is to verify and validate the functionality
and operation of the building systems in accordance with the Contract Documents, the engineering
Basis of Design (BOD) and the requirements of the FBC. Validation and review will encompass design,
installation, check out, start-up procedures, functional proving of operational systems, verification that
installations operate efficiently, are able to be maintained and comply with equipment manufacturer's
recommendations. Commissioning will verify the completeness and correctness of the projects record
documentation.
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County SWC Pp*dNo. 16021
Rosser Blvd Public Library
Port St. Lucie, FL
The commissioning procedures provide and establish processes to:
A. Evaluate commissioning elements of the design and the equipment
submittals with respect to the OPR and BOD.
B. Evaluate the ongoing and final equipment installations with
respect to the OPR, BOD, the contract, drawings, specifications,
and manufacturer's recommendations and instructions.
C. Direct and define responsibilities for participating members of the
project team regarding commissioning during construction, testing,
validation, turnover and occupation of the facility.
D. Coordinate activities relating to the commissioning processes of all
members of the commissioning team; including the CM, sub-
contractors, the facilities staff, the Owner PM team, the various
consultants and the CxA.
E. Validate that systems and equipment receive suitable attention,
prior to start up, with the installing sub -contractors performing and
documenting pre -functional testing (PFT) for CxA review.
F. Validate and evaluate operation of systems and components both
individually and together as complete, functional, integrated systems,
with functional testing executed by the commissioning agent with
assistance from the installing sub -contractors.
G. Evaluate and analyze the combined performance of individual
building systems, identifying and proposing solutions to any
operational conflicts between them.
H. Collect and compile all project commissioning documentation
into a single Systems Commissioning Manual.
3
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL
SWC Project No.16021
A/E
Architect/Engineer
FM
Facilities Maintenance Department
AHJ
Authority Having Jurisdiction
FTP
Functional Test Plan
AHU
Air Handling Unit
GPM
Gallons Per Minute
BMS
Building Management System
HVAC
Heating, Ventilating & Air Conditioning
BOD
Basis of Design
IST
Integrated Systems Test
cc
Controls Subcontractor
MC
Mechanical Contractor
CD
Contract Documents
0&M
Operation & Maintenance
CFM
Cubic Feet er Minute
OPR
Owners Project Requirements
Cx
Commissioning
OWN
Owner
CxA
Commissioning Agent
PFT
Pre -Functional Test
CM
Construction Manager
PM
Owner's Project Manager
DID
Design Intent Document
SC
Substantial Completion
DD
Design Development Documents
SIVIC
Sheet Metal Contractor
DDC
Direct Digital Controls
SEC
Security Electronics Contractor
EC
Electrical Subcontractor
TAB
Test, Adjust and Balance Agency
FAT
Functional Acceptance Test
UPS
Unintenu tible Power Source
FC
Final Completion
VAV
Variable Air Volume
FD
Fire Department
VFD
Variable Frequency Drive
DEFINITIONS
A. Acceptable Performance: A component or system being able to meet specked design
parameters and acceptance criteria under actual load, within acceptable tolerances including
satisfactory documented completion of all Functional Test Procedures.
B. Approval: Acceptance by the Engineer of Record that a piece of equipment or system is the
correct type for the given application, that installation considerations are compliant with the
requirements of the Contract Documents.
C. Areas of Conflict within Commissioning Documentation: Where Commissioning
Specifications and/or Commissioning Plan requirements conflict with technical specifications in
any individual specification section, or other Contract Document, the technical specification
and/or Contract Document requirements shall take precedence.
D. Basis of Design (BOD): The Contract Documents authored by the design team explaining
the thought processes and assumptions behind design decisions that were made to satisfy the
Owners Project Requirements. The documents describe space use, redundancy, diversity,
space zoning, occupancy, operations and space requirements. It lists relevant standards,
guidelines, regulations and other references to which the project shall comply. It provides
performance criteria for the systems to be commissioned (Also referred to as the Design Intent
Document).
E. Commissioning Agent (CxA): The independent 3b party agency hired by the Owner to
validate the commissioning process and to document that the facility and all of its systems and
assemblies are planned, designed, installed, tested, operated and maintained satisfying the
intent of the Owner's Project Requirements.
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County SWC Project No,16021
Rosser Blvd Public Library
Pod St. Lucie, FL
F. Commissioning Plan: The Commissioning Plan (Cx Plan) is a living document that defines
and manages the commissioning process. It outlines the organization, schedule, sequence,
responsibility, and documentation requirements of the commissioning process.
G. Commissioning Meeting: A meeting attended by members of the commissioning team held at
the job site, chaired by the Commissioning Agent. Meetings will be scheduled on an agreed
basis. Initially they will be held infrequently as needed. Towards project completion they will be
scheduled to take place regularly during the testing phase.
H. Design Intent Document: Refer to the Basis of Design (BOD).
I. Electronic Format: Electronic files capable of being opened and read with MS Office or the
latest revision of Microsoft Word (.docx files), Microsoft Excel (.xlsx files), Adobe Acrobat
Reader (.pdf files), or approved equals as specked.
J. Functional Acceptance Test (FAT): A test to validate compliant functionality of a completed
stand-alone system against the specified contract requirements and detailed system/equipment
sequences of operation through all operating conditions.
K. Functional Acceptance Test Plan: A test procedure authored by the Commissioning Agent
detailing the speck process as to how functionality of a completed system or systems will be
validated.
L Integrated Systems Test (IST): A detailed test procedure authored by the Commissioning
Agent describing the specific process as to how functionality of complete integrated operation of
all installed systems operating together will be validated under load.
M. Observation and Deficiency Log: An ongoing record of observations made during the
commissioning process by the commissioning agent, owner or other members of the
commissioning team.
N. Point to Point Tests ( for DDC): Logical testing undertaken by the installing contractors.
Point to Point testing is to be documented by the installing contractors and shall confirm that
the addressing, monitoring and control of intelligent equipment is programmed, interfaced and
Wres are terminated correctly.
0. Pre Functional Test (PFT): System / Equipment inspections intended to confirm that the
system / equipment is installed as specified and approved and that all manufacturer's
recommendations and requirements have been met.
P. Start Up: The process of energizing systems or items of equipment for the first time. Startup is
carried out by the installing contractor with assistance from manufacturer's representatives.
Q. Static Test: A test carried out prior to a system or item of equipment being energized ( i.e. a
duct leakage test, a pipe pressure test, etc.)
R. Test and Balance (TAB): The process of systematically regulating and setting an air or hydronic
system to operate to satisfy design criteria as outlined in the Construction Documents.
S. Trend Log: Actual system 'live' operating data, set out by the FOR and CxA, collected and
recorded from the DDC control (BMS) system sensors set up by the Controls Contractor,
identifying actual system performance.
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL
PROJECT DESCRIPTION
SWC ProjedNo. 16021
The Project consists of a one story building with an area of approximately 21,000 sf, being re -purposed to a new public, county
branch library. The building will contain, a main lobby, book stack areas, reading and activity areas, offices and meeting rooms.
SYSTEMS TO BE COMMISSIONED
The following is a list of the elements of the building systems that will be commissioned:
A. Six (6) DX split HVAC systems with variable air volume air handling units.
B. One (1) mini -split DX system
C. Ductwork systems
D. Air distribution devices
E. General local exhaust systems
F. Building automation & management system. (BAS, DDC)
G. DDC integration to the St. Lucie County Energy Management System
Commissioning for the project shall be split into 3 phases; Design Familiarization Review Phase, Construction Inspection Phase,
Testing and Acceptance Phase. Responsibilities in relation to these activities is defined in the section, °Team Member
Responsibilities" and the contract documents.
Design Familiarization Phase commissioning shall include the following actives:
• Review the Basis Of Design drawings
• Develop the Commissioning Plan
• Preparation of installation inspection, check out and testing documentation (PFT, FAT)
Construction Inspection Phase commissioning shall include the following actives:
• Equipment Submittal Review
• Maintenance of the Commissioning Plan
• Commissioning Meetings
• Installation observations and reporting
• Development and maintenance of the Cx observation and deficiency log
• Finalization of Pre Functional Check procedures
• Finalization of Functional Acceptance Test Plans
• Static Testing compliance
• Validation of Pre functional Checks
• Point to Point Testing
Review Equipment Startup documentation
• Reviewing Test and Balance reports
Acceptance Phase commissioning shall include the following actives:
• CxA random testing of Test and Balance areas.
• Execution of the Functional Acceptance Tests
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County SWC Project No.16021
Rosser Blvd Public Library
Port St. Lucie, FL
• Maintenance of the Cx observation and deficiency log
Develop the commissioning systems manual
• Integrated Systems Testing
• Acceptance Recommendation to FOR
Development of Final Commissioning Report
PREFUNCTIONAL TESTS
The CxA will develop pre functional test sheets (PFT) for each item of equipment / system to be commissioned if none are
available from the manufacturer of the installed equipment. These will be issued to the CM a minimum of 2 weeks prior to the
planned startup of the equipment. The CM will manage subcontractor completion of these checks and shall submit checkout
documents to the CxA. Startup of equipment should not commence until pre functional testing is documented and approved. A
minimum of five working days' notice shall be provided to the CxA for witnessing.
If deficient or incomplete work is discovered, the CM & installing contractor are to ensure corrective action is taken and repeat
PFT checks until the results are satisfactory and the system is ready for CxA witnessing of start-up.
A copy of completed pre functional reports will be maintained by the CM and copies shall be issued to the Owners PM and CxA.
The contractors shall append to the reports, copies of all associated specified field test certification (e.g. pressure test certificates)
and field reports and records as appropriate.
EQUIPMENT/SYSTEM STARTUP AND CALIBRATION
Each MEP and specialty subcontractor shall develop start up procedures for each item of equipment. The documents will
include checks and procedures for all start up activities and testing (including flushing, cleaning and disinfection / treatment of
systems as appropriate) to be employed. Procedures shall include manufacturer's recommended start up procedures or
manufacturer's pre published forms, when available. Procedures shall include field calibration methods when appropriate. The
CM will collate these documents into a single start up plan. This plan will be issued by the CM to the Owner and the CxA a
minimum of 2 weeks prior to commencing pre functional checks. The plan will be reviewed by the CxA and comments provided
to the Owner as appropriate. The Contractors shall incorporate and execute any comments as directed by the Owner, update and
reissue as required.
Following the completion of equipment / system pre functional checks and validation of the same by the CxA, equipment and
systems shall be started up / energized per the startup procedures by the responsible contractors. Assistance may be required
from equipment manufacturers and factory representatives. Startup of equipment shall adhere to the equipment manufacturer's
recommendations and best industry practice and the published start up procedures. Formal written notice (5 working days
minimum) of the intent start up or energize equipment I systems shall be provided to the Owners PM and the CxA by the CM.
The CxA will observe startup of systems I equipment. Startup procedures shall be documented by the responsible contractor.
Completed start up reports for each item of equipment / system shall be issued to the CM by the installing contractor with 5
working days of starting up the equipment.
7
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County SWC Project No.16021
Rosser Blvd Public Library
Port St. Lucie, FL
The following information will be included in the startup procedures and reports.
A. Certify that pre functional checks are satisfactorily completed.
B. Record Manufacturer, model number, serial number, and relevant capacity information for each item of
equipment as installed. Record equipment nameplate data.
c. List start up steps conducted as recommended by the manufacturer / best practice and check off each step as
satisfactorily performed.
D. Describe device Isensor /actuator field calibration procedure.
E. Record calibration results for each device / sensor/ actuator.
F. Append copies of calibration certificates for test instrumentation used for field tests.
G. Confirm correct rotation, vibration and noise levels, current, voltage, resistance, continuity, insulation, isolation
etc. are acceptable as applicable.
H. If applicable measure and record motor volts and amps.
I. Append manufacturers technician start up reports where applicable.
J. Certify specified field tests are satisfactorily completed.
A copy of completed start up reports will be maintained by the CM and copies shall be issued to the Owners PM and CxA.
The contractors shall append to the reports copies of all associated specified test certification, including as appropriate:
Electronic DDC Systems Point to point checks, calibration records. Certified field test reports as specked.
TEST AND BALANCE
The test and balance agency will provide TAB services as defined in the contract documents. The test and balance agency will
provide a TAB execution plan as documented in the project specifications. The TAB execution plan shall include TAB test
sheets to be used to record TAB results and settings, a description of all TAB activities and copies of the calibration certificates for
instrumentation to be used during the TAB exercise. The TAB process for each system to be balanced will not commence until
completion of all related pre functional checks and equipment startup has been validated by the CxA. The TAB agency shall give
minimum 5 days written notification of the intent to commence any TAB activity. The TAB agency shall complete TAB procedures
in accordance with the approved TAB execution plan. The TAB agency will notify the CM, A/E and CxA as soon as possible in
writing of any system installation or performance issues that may compromise the ability to balance the systems per the design
requirements. On completion of TAB activities the TAB agency shall issue a preliminary TAB report to the A/E for approval and to
the CxA for review. The TAB agency shall undertake any corrective actions required by the A/E or CxA and directed by the
Owner and shall record any resulting revised TAB data in the final TAB report, which shall be issued to the Owner, A/E and CxA.
The CxA will independently validate a random representative sample of TAB results as recorded in the A/E approved TAB report
later in the schedule, to confine the balance validation and repeatability. Copies of all TAB reports will be maintained by the CM.
FUNCTIONAL ACCEPTANCE TESTING
Functional Acceptance Tests (FATs) shall be developed by the CxA for each of the systems to be commissioned. These FATs
shall be used to document and validate the Functional Performance of systems and equipment operating in accordance with the
EOVs sequence of operation and the contract documents.
The objective of these tests is to demonstrate and validate that completed systems are operating and complying with specified
performance requirements. CxA executed Functional Acceptance Tests (FATs) shall only be performed on completed
systems. FATs shall validate system performance with respect to approved system sequence of operation on item by item basis
with assistance from the relevant installing contractor or supplier. Execution of the tests shall follow the approved written test
procedures developed by the CxA. Functional Testing will not commence until the project equipment are accepted by the RE as
substantially complete, general electrical testing is complete, the systems are reported as functioning as per the design intent,
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County SWC Project No.16021
Rosser Blvd Public Library
Port St. Lucie, FL
contractor start up and specified field test documentation has been issued, the associated TAB report has been approved by the
Engineer of Record and all associated pre -functional checks, documented start up and TAB activities have been validated as
complete by the CxA.
CM's written verification is required prior to the CxA executing Functional Acceptance Testing confirming the following:
A. Systems have been checked out and signed off by the CM and or Subcontractor confirming
proper installation, they have been adjusted accordingly, and are calibrated. Written notice shall
be provided by the CM that systems are ready for functional testing as specified.
B. System elements and checklists shall be reviewed by the CxA through site observation to verify
that they have been installed properly and that all connections have been made correctly.
C. All discrete elements and sub -systems have been adjusted and have be checked for proper
standalone operation.
D. All inter -system interfaces shall have been checked and shall be confirmed as functional.
E. All contractor performed pre start and pre functional tests are complete, documented and
identified issues and deficiencies addressed.
F. Start-up and operational tests and interfacing of systems shall be complete, with all required
Installation checklists and Pre -functional tests and checks documented and records shall be
submitted for review by Commissioning Agent, prior to commencement of Operational and
Functional Acceptance Testing.
G. The TAB activities shall be complete and the final TAB report approved by the A/E prior to
commencing Functional Acceptance Testing.
H. Functional Acceptance Test results shall be recorded by the CxA and signed off by Owner and
A/E upon satisfactory completion of each system FAT.
I. Actual testing program shall be conducted in accordance with previously approved procedures
and schedules with minimum seven (7) days' notice given prior to the intended date of execution
of Functional Acceptance Tests.
J. If it becomes apparent that a system being tested is not ready for testing by observing repeated
failure of test procedures, the Commissioning Agent shall halt that test procedure. The team will
identify and action remedial actives to resolve deficiencies and the CM shall coordinate
resolution of the identified deficiencies and schedule future retesting, giving formal not cation
that issues are resolved, checked and the system is ready to be retested.
The responsible contractors shall assist the CxA during functional testing including operating each system / item of equipment
through all modes of system operation and failure (for example, normal, altemative, emergency, seasonal, occupied, unoccupied,
warm-up, cool -down, power failure, etc. as applicable) including interlocks, safeties and conditional controlled logical events. All
control sequences, both full -load and part -load conditions and simulation of abnormal conditions for which there is a specified
parameter requiring controlled response. Alarming and trending functions will be checked and validated, all as per the agreed
FAT's under the direction of the CxA. It will be necessary for the Controls Contractor to provide experienced and qualified
personnel to assist the CxA during Functional Testing of HVAC systems. CM shall provide for electrical personal as required to
facilitate testing of all live electrical systems.
When the Functional Acceptance Testing of individual systems has been validated, the interface and coordinated response
between systems will be checked by performing an Integrated Systems Test. The CM shall assure all required attendances from
Contractors of all disciplines are provided to facilitate Integrated Systems Testing.
Corrective Measures: If acceptable performance cannot be achieved, then necessary corrective measures shall be executed at
the direction of the Owner/CM.
9
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL
SWC Project No.16021
Role Definitions
A
Architect
MC
Mechanical Contractor
ME
Mechanical Design Engineer
EC
Electrical Contractor
EE
Electrical Design Engineer
RIG
PE
Plumbing Design Engineer
PM
Owners Project Manager
CC
Controls Contractor
CM
Design Build Contractor
TAB
Test Adjust & Balance Agency
CxA
Owner's Commissioning Agent
FM
Owner's Facility Management Staff
FOR
Engineer of Record
Role
Member Firm & Address
Contact Person
Phone
Email Address
Saint Lucie County
James Clasby
772-462-2567
clasbyj@stlucieco.org
PM
Project Manager
Bob Ettswold
772-462-2136
ettswold@stlucieco.org
FM
SLC Facilities Maintenance
John Binkley
772-569-4320
edbvero@bellsouth.net
A
EDB Architects
SWC Mechanical
Kyle Cartier
407-380-0400
kjc@swceng.com
ME
Engineer
Sam Alexander
407-380-0400
sra@swceng.com
EE
SWC Electrical
En ineer
Joe Geosits `
561-906-2425
jgeosits@anatomconstruction.com
CM
Anatom Construction
John Browning
772-634-6315
jbrowning@gmail.com
MC
JBA/C
Mike Pride
772-461-2777
mike@pride-electrical.com
EC
pride Electrical
CC
Siemens
Tom Bolko
954-802-8631
Thomas.bolko@siemens.com
TAB
M&MTest &Bal.
MicEllacobacci
321-751-0123
mmtestandbalance.com
CxA
Sims Wilkerson Cartier
Sno
407-380-0400
sfs@swceng.com
Engineering, Inc.
10
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL
TEAM MEMBER RESPONSIBILITIES
Owner (PM):
SWC PiojectNo. 16021
Generally the Owner will facilitate and support the Cx process and will give final approval of all commissioning related work.
A. Will review, direct and approve commissioning related tasks in relation to the requirements of the
contract documents.
B. Will arrange and coordinate Owners facilities staff participation in the commissioning process as
required.
C. Will participate in commissioning related meetings as required.
Architect/Engineers (A, ME, EE, PE, SE):
Generally the A/E will support the Cx process. The AIE develops the contractual requirements and review compliance of the works
in relation to the requirements of the contract.
A. Will review CxA comments, recommendations & observations and shall address CxA comments and
recommendations as required at the direction of the Owner.
B. Will review the commissioning documentation and provide comments as necessary.
C. Will assist in resolution of commissioning related issues as required.
D. Will review and approve the TAB report.
E. Will review and approve the Functional Acceptance Test results.
F. Will review and approve the Operation and Maintenance Documents.
G. Will participate in commissioning related meetings as required.
Commissioning Agent (CxA):
Generally the CxA will lead, review, and oversee the completion of all commissioning process activities. The CxA shall
coordinate all commissioning related activities through the Owners Project Manager. The CxA will report directly to the Owner.
The CxA observes, reports and recommends, the CxA does not approve or accept.
A. Will review and comment on the BOD.
B. Will organize and chair a commissioning kick off meeting.
C. Will participate in OAC meetings as required.
D. Will review and comment on the contract documents.
E. Will develop, issue and maintain a commissioning plan revising and updating, incorporating Owner
approved comments from the commissioning team as required.
F. Will develop, maintain and issue a commissioning Observation and Deficiency Log.
G. Will assist the CM with scheduling commissioning activities.
H. Will perform review of contractors technical submittals to verify suitability and compliance of
proposed equipment with respect to the OPR and BOD and commissioning.
I. Will provide installation and pre -functional check sample forms for completion, submission, and
execution by Contractors.
J. Will develop and issue Functional Acceptance Tests (FATS) for the equipment and systems to be
commissioned.
K. Will coordinate and chair construction phase commissioning meetings.
L. Will perform site observations and report.
M. Will observe and witness the first contractor performed pre functional testing and checks for each
11
Commissioning Report
Rev 2 Issued December. 2017
St. Lucie County
Rosser Blvd Public Library
Pod St. Lucie, FL
SWC Project No.16021
type of system. The CxA shall validate installations against the contractor completed pre functional
check sheets.
N. Will observe and witness contractor performed equipment startup of each major item of equipment.
0. Will review and comment on the TAB agencies proposed procedures.
P. Will review all installation, pre -functional, start-up and other commissioning related documentation
provided by the Contractors. This includes installation checklists, point-to-point checklists and TAB
Contractor's completed preliminary TAB report.
Q. Will assist in troubleshooting commissioning related issues.
R. Will review and comment on the final TAB report, approved by the EOR.
s. Will execute the equipment Functional Acceptance Tests with assistance from the installing
contractors per the FAT procedures.
U. Will assemble all commissioning related documentation and provide to the owner a commissioning
report and commissioning systems manual.
Construction Manager (CM):
Generally the CM provides all methods and means necessary to discharge responsibilities as defined by the Contract Documents.
With specific regard to commissioning, the CM directs, organizes and coordinates the activities of the CM's own staff and the
commissioning activities of the subcontractor members of the commissioning team. The CM schedules and coordinates, with
assistance from the CXA, all commissioning actives to take place in a timely and appropriate manner in order to meet the
requirements of the construction schedule and the contract. The CM obtains and distributes all commissioning related
documents and deliverables received from the subcontractors to the Owner and the CxA. The CM distributes all commissioning
related documentation and deliverables issued by the Owner and the CxA to the construction team.
A. Will obtain and coordinate all Subcontractor and/or supplier information and records required for
equipment pre -start check and startup and shall provide this information timely to the CxA.
B. Will review the Owner's commissioning plan and documentation and confine in writing to the Owner,
AIE and CxA any identified areas of conflict with the contract documents or any items requiring
clarification with the Owner's final commissioning plan.
C. Will coordinate with assistance from the CxA all commissioning related activities including testing,
witnessing, pre -functional checks, start-up, TAB & DDC activities, functional testing and the like,
either self -performed or performed by Subcontractors, suppliers, etc.
D. Will develop a schedule with assistance from the CxA incorporating Cx milestone dates as identified
in this plan. The schedule is to be coordinated with the Construction Schedule. The schedule will
allow for specified functional testing to commence upon achieving substantial completion of system
installations, but prior to owner occupation of the building.
E. Will coordinate directly with each Subcontractor, and ensure their specific commissioning
responsibilities and contractual obligations are discharged.
F. Will participate in commissioning meetings as required.
G. Will ensure availability of qualified personnel, tools, calibrated test instruments, and access
equipment necessary to perform all commissioning related activities as required by Contract
Documents.
H. Will provide the Owner, AIE and CxA written notification that individual on site commissioning
activities are planned to take place. The Owner, NE and CxA require 5 days' notice of all
commissioning related activities.
I. Will coordinate actives requiring attendance of the Owners Staff, the AIE and the CxA so that
personnel can make best use of their time in visiting site in a concurrent visit.
J. Will coordinate and issue documentation relating to, pre functional check out, start-up, initial testing,
setting and TAB of equipment and systems and issue copies of records to the Owner and CxA for
12
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County
Rosser Blvd Public Library
Port St, Lucie, FL
SWC Project No.16021
validation and inclusion in the commissioning systems manual.
K. Will provide assistance as required to enable the CxA to execute Functional Testing.
L. Will assist coordinating and participate in all integrated system testing as required.
nn. Will document inconsistencies or deficiencies identified by CM staff and third parties in system
operations and system compliance identified and with assistance from the CxA provide a plan for
resolution of deficiencies as required.
N. Will retain copies of all commissioning related documentation on site, including that developed by the
CxA and other members of the commissioning team, including: manufacturer's information and cut
sheets, installation checklists, testsheets, pre -functional checklists, manufacturer's start-up forms,
flush -out verification, pressure tests, electrical tests, testing and balancing data (TAB), Functional
Acceptance Tests (FAT), recorded performance data, record of equipment settings and any other
reports used to document the commissioning process. Make these items available as required to all
members of the commissioning team. At substantial completion provide a copy of this information to
the Commissioning Agent.
Mechanical Contractors and Subcontractors (MC, PC, FPC):
A. Will coordinate and direct participation of the Mechanical Subcontractors and suppliers in the
commissioning process.
B. Will review and comment on the Commissioning Plan, Cx milestone schedule and assist in preparing
the Operational and Functional Acceptance Test Procedures if required. Provide input and
documentation required to develop final plans and procedures.
C. Will complete pre functional check sheets and start up procedures for each mechanical item of
equipment and system to be commissioned. Collate these documents into a single check out and
start up plan. Incorporate and execute any comments as directed by the CM, update and reissue
as required.
D. Will participate in commissioning meetings as required. Will coordinate participation of suppliers and
subcontractors as required.
E. Will coordinate installation of mechanical systems and equipment with equipment suppliers,
mechanical and electrical subcontractors. Verify that coordination, installation, quality control, and
subcontractor testing have been completed and that installed systems and equipment comply with
the requirements of the contract documents.
F. Will issue formal notice to the CM of the intent to perform any commissioning related activity. Give
adequate notice of each and every planned event (minimum 5 days).
G. Will notify the CM in writing as soon as possible of any issues identified during construction that may
affect the commissioning process or final system performance.
H. Will respond to commissioning related directions issued by the CM.
I. Will perform pre functional checks, start-up and testing of mechanical equipment and systems as
specified and document as required issuing copies to the CM.
J. Will operate equipment and systems as required for Operational and Functional Acceptance Testing
and provide the CxA assistance as required to execute functional testing.
K. Will participate in and provide attendance of vendors at integrated systems testing as required.
L Will participate in the fine-tuning or troubleshooting of system performance if either of these
measures becomes necessary.
m Will coordinate and provide qualified personnel, tools, calibrated test instruments and access
equipment necessary to perform all mechanical commissioning related activities.
N. Will execute, under the direction of the CxA, functional tests relating to all mechanical systems
and equipment.
0.
13
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL
Electrical Contractors and Subcontractors (EC):
SWC Project No.16021
A. Will coordinate and direct participation of the Electrical Subcontractors and suppliers in the
commissioning process.
B. Will review and comment on the Commissioning Plan, Cx milestone schedule and assist in preparing
the Operational and Functional Acceptance Test Procedures if required. Provide input and
documentation required to develop final plans and procedures.
C. Will participate in commissioning meetings as required. Will coordinate panicipafion of suppliers and
subcontractors as required.
D. Will coordinate and schedule electrical installations and testing to be complete prior to the scheduled
start up of mechanical equipment.
E. Will notify the CM in wrifing as soon as possible of any issues identified during construction that may
affect the commissioning process or final system performance.
F. Will respond to commissioning related directions issued by the CM.
G. Will perform pre functional checks, start-up and testing of electrical equipment and systems as
specified and document as required issuing records to the CM.
H. Will operate equipment and systems as required for Operational and Functional Acceptance Testing
and provide the CxA assistance as required to execute functional testing.
I. Will participate in and provide attendance of vendors at integrated systems testing as required.
J. Will participate in the fine-tuning or troubleshooting of system performance if either of these
measures becomes necessary.
IC Will coordinate and provide qualified personnel, tools, calibrated test instruments and access
equipment necessary to perform all electdcal commissioning related activities.
Controls Subcontractor (CC)
A.
Will review and comment on the Commissioning Plan, Cx milestone schedule and assist in preparing
the Operational and Functional Acceptance Test Procedures K required. Provide input and
documentation. Will provide FOR accepted controls system and wiring diagrams, narrative sequences
of operation, list of set points and printout of actual programmed sequences in time for use in point to
point testing. Provide single line diagrams of system configurations on 11 X 17 inch sheets to the CM
/ Owner. Provide images of all head end graphical user interfaces pages for Owner, A/E and CxA
comment.
B.
Will review and comment on the Commissioning Plan, Cx milestone schedule and assist in preparing
the Operational and Functional Acceptance Test Procedures if required. Provide input and
documentation required to develop final plans and procedures.
C.
Will participate in commissioning meetings as required.
D.
Will participate in any required efforts to finalize sequences of operations and interfaces of systems
with Owner, Designers and Commissioning Agent.
E.
Verify that coordination, installation, quality control, and final subcontractor testing have been
completed such that installed systems and equipment comply with the requirements of the contract
documents.
F.
Will issue formal notice to the CM / Owner of the intent to perform any commissioning related activity.
Give adequate notice of each and every planned event (minimum 5 days).
G.
Will notify the CM / Owner, A/E, Commissioning Agent as soon as possible of any system installation
or interface issues identified during construction that may compromise system control capability.
H.
Will complete Installation and Pre -Commissioning Test Checklists and other supporting
documentation as required and demonstrate completion of control system installation, point-to-point
verification (including sensor and device calibration and operation), start-up and testing, BMS
graphical interfaces, functionality, alarms and monitoring, remote communications and networking
14
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL
SWC Project No.16021
and submit to the CM, CxA and Owner.
I. Will execute and schedule installation, pre, commissioning, testing and commissioning of the control
systems such that systems are operable and checked out and complete prior to commencement of
the Test and Balance activities. Demonstrate operation of the controls systems to the A/E and CxA.
J. Will provide coordination of control system hardware and software to the TAB agency as required.
K� Will provide commissioning related directions issued by the CM / Owner.
L Will participate in start-up and Operational and Functional Acceptance Testing as required. This will
require dedicated, full time support of the Operational and Functional Acceptance Testing efforts and
assisting the CxA in executing system Functional Tests. This will require setting up maintaining,
recording and downloading system trend logs as required at the direction of the CxA.
M. Will participate in Integrated Functional Testing as required.
N. Will participate in fine-tuning or troubleshooting of system performance with the CxA and Owner as
necessary during Operational and Functional Acceptance Testing and fault -free running periods.
Test, Adjust and Balance Contractor (TAB):
A. Will review the Commissioning Plan, schedule, and Functional Acceptance Test scripts. Provide the
input required to develop final TAB plans and procedures.
B. Will coordinate balancing activities with those of the Mechanical and Controls Subcontractors.
Schedule TAB actives such that they are complete and the final TAB report is approved by the A/E
prior to scheduled commencement of system and equipment functional testing.
C. Will notify the CM, A/E and Cx as soon as possible of any system installation or performance issues
that may compromise the ability to balance the systems per the design requirements.
D. Will assist Commissioning Agent as required for start-up and pre -functional testing and documenting.
E. Will document all TAB activities and record actual measurements as a percent of design data.
F. Will execute the test and balance procedures and assist the CxA in system verification. Provide
preliminary TAB reports, indicating all actual field values recorded, to the A/E and Commissioning
Agent within 48 hours of TAB of a system. Final TAB report will be issued prior to initiation of
Functional Acceptance Testing.
G. Will assist the CxA during the Functional Acceptance Testing as required.
The following is being suggested and can be superseded if the project contract differs and provides for a definite
communication protocol.
The Owners PM will facilitate and support the Cx process and will direct and give final approval of all commissioning related
work.
The CM and A/E will act under the direction of the Owners PM. They will report directly to the Owners PM. They will interface
and communicate with the CxA as required by the Contract. The ME will approve all related work and installations with the
requirements of the contract.
The CxA will act under the direction of the Owners PM. The CxA will report directly to the Owners PM. The CxA will interface.
and communicate with the A/E and CM as directed by the Owner. The CxA will observe, verify, report and validate
commissioning activities are completed in accordance with the requirements of the OPR and the BOD. The CxA will assist the
CM in coordinating commissioning activities.
The CM will act under the direction of the Owners PM. The CM will report directly to the Owners PM. The CM will interface and
communicate with the A/E and CxA as directed by the Owner. The CM will ensure all means and methods are discharged
15
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County SWC Project No.16021
Rosser Blvd Public Library
Pod St. Lucie, FL
necessary to comply with the requirements of the contract documents. The CM will coordinate and direct the commissioning
actives of the sub -contractors and equipment suppliers. The CM shall identify a suitably qualified and experienced staff member
as the single point of contact for coordinating all commissioning related actives.
The Installing Contractors will act under the direction of the CM. They will report directly to the CM. The Contractors will
discharge commissioning activities as defined by the contract documents.
Commissioning Meetings will be arranged by the CxA as required and coordinated through the PM and CM. The CxA will chair
commissioning meetings and record and distribute a summary of each meeting. Members of the commissioning team shall
attend commissioning meetings as required.
COMMISSIONING SCHEDULE
The Commissioning Schedule shall be organized as an integral part of the CM Construction Schedule. All Construction Phase
Commissioning activities shall be scheduled in advance as separate line items on the master schedule. The Construction
Schedule will detail all commissioning activities and shall include dedicated milestones for the following events:
a) Commissioning milestones
1. Individual MEP and special systems installations complete.
2. Building normal, alternative and emergency power available to Building systems plant, equipment and devices.
3. Individual system pre -functional testing and checks.
4. Individual system energization and startup.
5. Controls system point-to-point field tests.
6. Individual system start up.
7. Controls and controllers set to work.
8. Controls Head -End and graphic user interface (GUI) tests.
9. Sequence of operation auto running checks.
10. Test Adjust and Balance
11. Operational and Functional tests.
1, Mechanical
ii, Electrical
12. Systems commissioning complete.
The Commissioning elements of the construction schedule will be linked to the construction tasks scheduled to plan successful
completion of all commissioning activities prior to turnover of the facility to the Owner. The CxA will assist the CM in scheduling
commissioning activities. The CM is responsible for monitoring and updating the schedule and reporting slippage and recovery
actions to maintain program commissioning milestones. Commissioning progress is to be reported by the CM and the CxA at the
OAC progress meetings.
16
Commissioning Report
Rev 2 Issued December, 2017
St. Lucie County
Rosser Blvd Public Library
Pod St. Lucie, FL
SYSTEM ACCEPTANCE CRITERIA
SWC Project No.16021
Prior to Functional Acceptance Testing of systems, the Commissioning Agent shall observe and verify that the physical
installation, static testing, and pre -functional commissioning of components and systems are complete in accordance with the
Contract Documents and manufacturer's recommendations and report his observations to the Owner. Ultimately system
acceptance is the responsibility of the CM, Architect and Engineers. The Commissioning agent will validate, verify, observe and
report on the commissioning process, noting completeness and compliance with respect to the contract requirements the OPR
and BOD. The AIE shall be responsible for accepting installations as complete and compliant with the requirements of the
contract. The CxA does not approve or accept, however, the CxA's observations, comments and reports may be taken into
account by the AIE.
An important element of system completion includes the training of Owners facility staff, as noted in the Contract Documents
and the completeness and issue of project record documentation.
ISSUE RESOLUTION
Many different elements, under varying operating conditions may result in additional work being required to commission the
systems to satisfy the Owners Requirements. Resolution of any identified deficiencies will be completed under the direction of the
Owner and the supervision of the CM with input from the AIE, the installing contractor, Equipment Supplier, TAB agency, and
commissioning agent. All associated parties will have input and the opportunity to discuss the work required to resolve identified
commissioning issues. The Owner will have final jurisdiction on the necessary work to be undertaken to achieve adequate
performance.
The commissioning agent will provide only observations and recommendations and as such will not be responsible for the means
or methods of the AIE the CM or his subcontractors.
Corrective work shall be performed in a timely fashion to keep completion of the commissioning process on schedule.
When a deficiency is reported, the CM shall notify the appropriate parties to initiate corrective action in an expeditious manner.
The Commissioning Agent will keep an ongoing Observation Issues and Deficiency Log, lisfing and tracking identified
deficiencies and tracking the resolution of identified issues. An up to date copy of this Observation Issues and Deficiency Log will
be kept by the CxA. The CM, Owner, AIE and CxA will monitor the resolution of identified deficiencies.
17
Commissioning Report
Rev 2 Issued December, 2017
APPENDIX
St Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL.
Issue Date - 07/24/2017 Revision 1
St. Lucie County Rosser Blvd Public Library SWC Project No. 16021
I.D. #
Date
Entered
Location /
TAG
Observation / Deficiency
Response / Resolution
Date
rechecked
Issue
cleared
(Y/N)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
PreriminaryCo n nissiming Plan
Rev Draft Issue January2017
Project St. Lucie County Rosser Blvd Public Library Sheet No
System ... Date
Notification to Observe Test
To....................................................................................
Please arrange to inspect/witness the following test:
Natureoftest...........................................................................................................................................
Date of test ..................................................... Duration of test............................................................
Testsheetsattached................................................................................................................................
................................................................................................................................................................
Signed ........................................... for and on behalf of ............................................. Trade Contractor
Notice required: Off Site - 7 days On Site Testing - 3 days On Site Inspection -1 day
Observed by:
........................................................ Signed ........................................................
Accepted/Not accepted
........................................................ Signed ........................................................
Accepted/Not accepted
........................................................ Signed ........................................................
Accepted/Not accepted
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL.
COMMISSIONING / DEFICIENCY LOG
These items will need to be addressed prior to scheduling any Functional Acceptance Testing
Issue Date - 07/25/2017 Revision 1
St. Lucie County Rosser Blvd Public Library SWC Project No. 16021
I.D. #
Date
Location /
Observation / Deficiency
Response / Resolution
Date
Issue
Entered
TAG
rechecked
cleared
(Y/N)
1
/20/2017
General
Provide Prefunctional Checklists for HVAC
Received checklists.
12-11-17
Y
equipment. Refer to report comment 1.e.
2
7/20/2017
General
Provide preliminary Siemens DDC point
Received point listing.
12-11-17
y
list. Refer to report comment 1.f.
3
7/20/2017
General
Provide preliminary Test and Balance
Received final report.
12-11-17
y
report. Refer to report comment 1.g.
4
7/20/2017
General
PRH relief hoods (PRH-1, 2, 3, 4) are not
Hoods are installed.
12-11-17
y
installed on roof. Refer to report
comment 2.f.1 and 2.
5
/20/2017
General
EAH-1 for EF-3 is not installed on roof..
Not observed.
12-11-17
Refer to report comment 2.f.3.
6
7/20/2017
General
ALL AHUs —AFMS sensor probes are not
All sensor probes are installed.
12-11-17
y
installed at this time. Refer to report
comments.
7
7/20/2017
Mtg Rm 1
No airflow from sidewall diffusers. Refer
Airflow issue has been resolved as shown
12-11-17
y
o report comment 2.a.1.
on the Final Test and balance report.
B
7/20/2017
ME#1(41)
AFMS transmitter- sensor probe
Issue resolved.
12-11-17
y
installation/ AHU Identification issue.
Refer to report comment 2.a.6.3.
9
/20/2017
ME#2(28)
AHU-2 fan motor/VFD compatibility. Refer
Issue resolved.
12-11-17
y
o report comment 2.b.6.iv and v.
10
7/20/2017
ME#2(28)
CU-4 circuit breaker tripping. Refer to
Issue resolved.
12-11-17
y
report comment 2.b.6.vi and vii.
11
7/20/2017
Men RR
EF-5 not operating. Refer to report
Issue resolved.
12-11-17
y
comment 2.b.3. and 5.
12
7/20/2017
Women RR
EF-4 not operating. Refer to report
Issue resolved.
12-11-17
y
comment 2.b.4. and 5.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
Test= AMU-1 /CU. 1
- Connection to St Lucie County Siemens BAS monitorlctrl
system
CONNECTED SLC remote data connection is
AND RUNNING 12/1112017 established and online.
Step
Test Description
Acceptance Criteria
Measurement /Setpoint
Result
Date
Test Notes
Final, approved report received by
-TAB Complete and report provided
chk
12/11/2017
Anatom today.
Pre Function Testing Prereq
- BMS point-to-point complete and report provided
n/a
Point-to-point listing received today.
We
Checking programming today
- Control program checkout complete
Running according to BMS Schedule
MO 5:00 AM TO 10:00 PM
12/11/2017
Building CLOSED
TU
Building OPEN
WE
Building OPEN
TH
Building OPEN
FIR
Building OPEN
SA
Building OPEN
SU
Building CLOSED
OPERATE CONTINUOUSLY AND THE OUTDOOR AIR DAMPER
SHALL BE IN THE FULLY OPEN POSITION. EITHER THE STAGES
OF COMPRESSION SHALL BE TURNED ON OR OFF OR THE
ELECTRIC HEATER SHALL BE STAGED TO MAINTAIN THE
(5) Temperature sensors serving this
area. One sensor is misreading
Repair/replace sensor).
1
Scheduled Occupancy - OCCUPIED
MODE
REQUIRED DISCHARGE AIR TEMPERATURE.
Cooling and heating setpoints were
adjusted per owner request from
default of 75 F /72 F , to the same
value of 72 F 172 F. Unit currently is
THE SUPPLY FAN SPEED SHALL BE MODULATED TO MAINTAIN
controlling to maintain a 55 F coil
THE ROOM TEMPERATURE AT THE COOLING SET POINT (USER
discharge temperature (LAT). This is
ADJUSTABLE). THE FAN SPEED
causing problems of cycle overshoot
SHALL BE MODULATED FROM A MINIMUM OF 65% (39 HZ) TO A
in the control system moving rapidly
MAXIMUM OF 100% (60 HZ). ONCE THE FAN SPEED FALLS TO
from cooling to heating modes.
THE MINIMUM AND THE SPACE TEMPERATURE CONTINUES TO
Recommended to place a deadband
FALL, THE SUPPLYAIR SET POINT SHALL BE RESET TO
between cooling -heating setpoints,
MAINTAIN THE ROOM TEMPERATURE AT THE HEATING SET
provide a coil LAT reset, as noted in
POINT (USER ADJUSTABLE). THE ELECTRIC DUCT HEATER
dsn sequence and provide a
SHALL BE STAGED TO MAINTAIN THE HEATING DISCHARGE
compressor delay to ensure both
TEMPERATURE (USER ADJUSTABLE).
don't slam on simultaneously.
Cooling and heating setpoints have
been readjusted to 72 (CLG) and 70
(HTG). Compressor reset and delay
needs to be programmed.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 -2017 -08 -10
2
LAT Control! SPD ctrl
Supply fan VFD
CLG Setpoint: LAT =55
CLG LAT=
69F
SP=55F-62F
HTG Setpoint: LAT=
HTG LAT=
VARIES
OCC COOLING SP = 72 71-73
OCC COOLING T =
71.5 F
CLG SP chg per owner request to 72
F (adjusted temp span to 71-73)
OCC HEATING SP = 70 69-71
OCC HEATING T =
HTG
SP stays at 72 F
OCC RH % SP =
OCC RH %=
31.74%
VFD MIN speed 65% 39 Hz
VFD MIN speed =
65%
VFD MAX speed = 100 % 60 Hz
VFD MAX speed =
N/A
MIXED AIR TEMP
MAT =
RETURN AIR TEMP
RAT=
73.42 F
AIR FILTER DP SP =
FILTER DP =
-0.02
3
CA damper position
Verify operation -
AFMS = 600 CFM MIN
OPEN / CLOSED
15 % OF
AFMS CFM =
506.91
4
Electric Heater
Verify operation
Fan speed - minimum at heating
HEATING STAGES =2
ON / OFF
Forced on to test because room
VFD speed =
65%
temperature was satisfied.
HEATINGSTAGES=
1,2
ROOM T = -
72.5 F
LAT =
93 F
5
Supply Temp Sensor
Instrument:
BAS:
6
Duct SP Sensor
Instrument: SP STPT =
Instrument: SP =
N/A
NOT A RED CTRL POINT
7
DX Compressor
Compressor #1
Compressor #2
COND UNIT FAN
NO. STAGES =
1.2
IN COOL MODE ONLY
BAS:
ON / OFF
8
OSA AFMS
Verify calibration of OSA airflow, station.
Measure OSA and modulate OSA DMPR to allow MIN CA (ached)
DSN MIN OSA (Schell) =
ACTUAL OSA CFM =
506.91 / 600
Damper overshoots between
cool/heat, then settles down.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017.08 -10
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS EQUAL
ECONOMIZER MODE sequence is
TO OR LESS THAN 28 BTUILB OF AIR, THE OUTSIDE AIR
not programmed into the control
DAMPER SHALL FULLY OPEN AND THE RETURN AIR DAMPER
system, per owner request.
- Forced system into Economizer
SHALL FULLY CLOSE TO ALLOW 100% OUTSIDE AIR TO THE
mode to check points.
UNIT.
THE AIR HANDLING UNIT FAN SPEED SHALL CONTINUE TO
-AFMS reading low.
CONTROL TO MAINTAIN SPACE TEMPER ATURE SET POINT AS
Found RA damper shaft came loose
DETERMINED BY THE AVERAGING THERMOSTAT AND TEMPER
from the actuator. This will need to
ATURE SENSORS AND THE COMPRESSOR STAGES SHALL
be readjusted for proper operation.
MODULATE OR TURN ON/OFF TO MAINTAIN OFF COIL
- Test points - OAT = 61.02 F OA
9
ECONOMIZER MODE
TEMPERATURE SET POINT.
RH = 43% Building pressure
WHEN THE OUTSIDE AIR ENTHALPY, AS MEASURED BY THE
measured at 0.027 to 0.030 in wg,
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS
per TAB measurement.
GREATER THAN 28 BTUILB, THE OUTSIDE AIR DAMPER SHALL
RETURN TO THE MINIMUM OUTSIDE AIR POSITION OR TO
THAT POSITION NEEDED TO MAINTAIN THE MINIMUM
OUTDOOR AIRFLOW REQUIRED AS MEASURED BY THE
OUTSIDE AIR AIR FLOW MONITORING STATION.
THE UNIT RETURN AIR DAMPER SHALL OPEN TO ALLOW
RETURN AIR BACK TO THE UNIT TO MIX WITH THE OUTSIDE
AIR.
No sequence programmed into the
system for economizer operation.
- Sensor not operating,
repair/replace.
- OA Enthalpy = 21.21 btuAb as
OA ENTHALPY SP = 28 BTUILB
OA ENTHALPY =
54.5 F
measured by TAR
OA DAMPER POSITION = O/C
OA DAMPER =
100%
OA FLOW = MAX DESIGN CFM = 3600
AFMS =
2552
70.89 %—Low flow
RELIEF HOOD BAROM DAMPER POSITION = O/C
REL DAMPER POS =
NIA
Damper shaft loose on actuator.
Repair damper shaft/actuator
connection.
RETURN DAMPER POSITION = O/C
IRA DAMPER POS =
CL
I
I- Need to retest.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 .08 -10
MO 10:OOPM to 5:00 AM
Building CLOSED
TU
Building CLOSED
WE
Building CLOSED
10
Scheduled Occupancy -
Running according to BMS Schedule
UNOCCUPIED MODE
TH
Building CLOSED
FR
Building CLOSED
SA
Building CLOSED
SU
Building CLOSED
IN THE UNOCCUPIED MODE THE AHU SUPPLY FAN SHALL
Unoccupied temperature sequence
OPER ATE ONLY ON A CALL FOR COOLING OR HEATING.
is not programmed, per owner
OUTSIDE AIR DAMPER SHALL REMAIN CLOSED.
reguest.
UN A CALL FOR COOLING I Hi- SUPPLY FAN SHALL fit
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
Owner commented that Compressor
#1 is not cooling when activated.
Need to verify operation of
ONCE THE UNOCCUPIED SPACE TEMPERATURE SET POINT IS
Compressor #1.
ACHIEVED THE COOLING COIL SHALL CLOSE AND THE SUPPLY
FAN SHALL STOP.
ON A CALL FOR HEATING, THE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
RA damper sticking in position. See
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
problem iden8fied in economizer
HEATER SHALL BE STAGED TO MAINTAIN THE DISCHARGEAIR
mode.
TEMPERATURE SET POINT. ONCE THE UNOCCUPIED SPACE
TEMPER ATURE SET POINT IS ACHIEVED THE HEATER SHALL
BE DISABLED AND THE SUPPLY FAN SHALL STOP.
SUPPLY FAN STATUS - ON / OFF
SF STATUS =
OFF
UNOCC COOLING SP = 80
CLG MODE =
None
UNOCC HEATING SP = 60
HTG MODE =
None
CA DAMPER POSITION = O/C
OA DMPR POS =
CL
minimum cfm, slowto close when
AFMS CFM =
AFMS CFM =
145
forced.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
11
HUMIDITY CONTROL
(UNOCCUPIED)
IF THE ROOM HUMIDITY RISES ABOVE THE UNOCCUPIED
MAXIMUM SPACE RELATIVE HUMIDITY SET POINT DURING THE
UNOCCUPIED PERIOD, PROVIDE NOTIFICATION AND THE
SUPPLY FAN SHALL BE STARTED AND ALLOWED TO ADJUST
FAN SPEED BASED ON SPACE TEMPERATURE.
THE OUIDOOR AIR DAMPER SHALL REMAIN CLOSED, AND THE
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
ONCE THE SPACE HUMIDITY FALLS BELOW 55 % THE COOLING
COIL SHALL CLOSE AND THE SUPPLY FAN SHALL STOP.
Program is not available for this
sequence. Provide notification of low
humidity per sequence.
Not tested.
SF = START/STOP
CA DMPR POS = O/C
UNOCC RH %= 60
RH % _
COOLING T =
HEATING T=
12
LAT Control SPD ctrl
Supply fan VFD
CLG Set oink. LAT=55
CLG LAT=
HTG Setpoint: LAT=
HTG LAT =
VFD MIN speed = 65% 39 Hz
VFD speed =
VFD MAX speed = 100% 60Hz
13
ALARMS
No alarms programmed. Advised
controls contractor to verify with
owner for alarm setpoints.
High RH%
RH%> 60
BAS alarm activated.
CA Alarm
10%+/- DSN MIN CA
BAS alarm activated.
Supply Fan Failure
BAS alarm
BAS alarm activated.
CA Damper failure
BAS alarm
BAS alarm activated.
RA Damper failure
BAS alarm
BAS alarm activated.
High Supply Duct SP
BAS alarm
RAS alarm activated.
Hi h SAT
BAS alarm
BAS alarm activated.
Low SAT
BAS alarm
BAS alarm activated.
lFilterDirty,
BAS alarm
BAS alarm activated.
14
EMERGENCY SHUTDOWN
SHUTDOWN
(Smoke Detector)
WHEN ANY ONE OF THE SYSTEM DUCT SMOKE DETECTORS IS
ACTIVATED, THE UNIT SHALL SHUT DOWNUPON RECEIVING
AN EMERGENCY SHUTDOWN / SMOKE DETECTIONSIGNAL
FROM THE FIRE ALARM PANEL.
SMOKE DETECTOR INDICATION =
Smoke detector / AHU shutdown
witnessed and passed by Fire
Inspector, per owner.
OA Damper
CA Damper status
CA Damper status =
RA Damper
RA Damper status
RA Damper status =
SAFETY SHUTDOWN
STATIC PRESSURE
SP=
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
Test= AHU-2 /CU. 2
Step
Test Description
Acceptance Criteria
Measurement/Setpoint
Result
Date
1 set Notes
Fine, approved report received by
-TAB Complete and report provided
chk
12/11/2017
Analom today.
Pre Function Testing Prereq
- BMS point-to-point complete and report provided
n/a
Point-to-point listing received today.
n/a
Checking programming today
-Control program checkout complete
Running according to BMS Schedule
MO 5:00 AM TO 10:00 PM
12/11/2017
Building CLOSED
TU
Building OPEN
WE
Building OPEN
TH
Building OPEN
FR
Building OPEN
SA
Building OPEN
SU
Building CLOSED
OPERATE CONTINUOUSLY AND THE OUTDOOR AIR DAMPER
1
Scheduled Occupancy -OCCUPIED
MODE
SHALL BE IN THE FULLY OPEN POSITION. EITHER THE STAGES
OF COMPRESSION SHALL BE TURNED ON OR OFF OR THE
ELECTRIC HEATER SHALL BE STAGED TO MAINTAIN THE
OAT = 65.26 F; OA RH=38% per
pgm
REQUIRED DISCHARGE AIR TEMPERATURE.
Cooling and heating setpoints were
adjusted per owner request from
default of 75 F /72 F , to the same
value of 72 F / 72 F. Unit currently is
THE SUPPLY FAN SPEED SHALL BE MODULATED TO MAINTAIN
controlling to maintain a 55 F coil
THE ROOM TEMPERATURE AT THE COOLING SET POINT (USER
discharge temperature (LAT). This is
ADJUSTABLE). THE FAN SPEED
causing problems of cycle overshoot
SHALL BE MODULATED FROM A MINIMUM OF 65% (39 HZ) TO A
in the control system moving rapidly
MAXIMUM OF 100% (60 HZ). ONCE THE FAN SPEED FALLS TO
from cooling to heating modes.
THE MINIMUM AND THE SPACE TEMPERATURE CONTINUES TO
Recommended to place a deadband
FALL, THE SUPPLYAIR SET POINT SHALL BE RESET TO
between cooling -heating setpoints,
MAINTAIN THE ROOM TEMPERATURE AT THE HEATING SET
provide a coil LAT reset, as noted in
POINT (USER ADJUSTABLE). THE ELECTRIC DUCT HEATER
dsn sequence and provide a
SHALL BE STAGED TO MAINTAIN THE HEATING DISCHARGE
compressor delay to ensure both
TEMPERATURE (USER ADJUSTABLE).
don't slam on simultaneously.
Cooling and heating setpoints have
been readjusted to 72 (CLG) and 70
(HTG). Compressor reset and delay
needs to be programmed.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
2
LAT Control / SPD ctrl
Supply fan VFD
CLG Set oink LAT =55
CLG LAT—
71.5
HTG Setpoint: LAT=
HTG LAT=
OCC COOLING SP=72 71-73
OCC COOLING T=
OCC HEATING SP=70 69-71
OCC HEATING T=
OCC RH o/ SP =
OCC RH %=
32.38
VFD MIN speed = 66% 39 Hz
VFD MIN speed =
We
ECM motor- NO VFD - HI SPEED
VFD MAX speed = 100% 60 Hz
VFD MAX speed =
n/a
MIXED AIR TEMP
MAT=
RETURN AIR TEMP
RAT=
70.66
AIR FILTER DP SP =
FILTER DP =
0.35
3
OA damper position
Verify operation
AFMS =400 CFM MIN
OPEN/CLOSED
80% OP
AFMS CFM=
374
93.5%dsn
4
Electric Heater
Verify operation
Fan speed - minimum at heating
HEATING STAGES = 2
ON / OFF
ON
Forced ON
to test
VFD speed =
We
HEATING STAGES =
1
ROOM T=
65
LAT =
93.8
5
Supply Temp Sensor
Instrument
BAS:
6
Duct SP Sensor
Instrument SP STPT =
Instrument: SP =
n/a
not a required control point
Compressor#1
Compressor #2
COND UNIT FAN
NO.STAGES=
1
Coil LAT =40 F; SAT =45F
7
DX Compressor
BAS:
ON
Compressor activates when htg
room temp is satisfied, going directly
into cooling mode to satisfy 55 F coil
LAT, no temp reset evident.
- Need to reset pgm.
ON / OFF
8
OSA AFMS
Verify calibration of OSA airflow station.
Measure OSA and modulate OSA DMPR to allow MIN OA (ached)
DSN MIN OSA (Sched) =
ACTUAL OSA CFM =
400
341
85%dsn; Need to verify RA damper
operation.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017. 08 -10
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS EQUAL
TO OR LESS THAN 28 BTU/LB OF AIR, THE OUTSIDE AIR
DAMPER SHALL FULLY OPEN AND THE RETURN AIR DAMPER
SHALL FULLY CLOSE TO ALLOW 100 % OUTSIDE AIR TO THE
ECONOMIZER MODE sequence is
not programmed into the control
system, per owner request
- Forced system into Economizer
UNIT.
mode to check points.
THE AIR HANDLING UNIT FAN SPEED SHALL CONTINUE TO
CONTROL TO MAINTAIN SPACE TEMPERATURE SET POINT AS
DETERMINED BY THE AVERAGING THERMOSTAT AND TEMPER
ATURE SENSORS AND THE COMPRESSOR STAGES SHALL
MODULATE OR TURN ON/OFF TO MAINTAIN OFF COIL
9
ECONOMIZER MODE
TEMPERATURE SET POINT.
WHEN THE OUTSIDE AIR ENTHALPY, AS MEASURED BY THE
OUTSIDE AIR DUCT MOUNTED ENTHALPYSENSOR, IS
GREATER THAN 28 BTU/LB, THE OUTSIDE AIR DAMPER SHALL
RETURN TO THE MINIMUM OUTSIDEAIR POSITION OR TO
THAT POSITION NEEDED TO MAINTAIN THE MINIMUM
OUTDOOR AIRFLOW REQUIRED AS MEASURED BY THE
OUTSIDE AIR AIR FLOW MONITORING STATION.
THE UNIT RETURN AIR DAMPER SHALL OPEN TO ALLOW
RETURN AIR BACK TO THE UNIT TO MIX WITH THE OUTSIDE
AIR.
No sequence programmed into the
system for economizer operation.
- Sensor not operating,
repair/replace.
OA ENTHALPY SP = 28 BTUILB
OA ENTHALPY =
54.5
-OA Enthalpy = 21.21 btu/Ib as
measured by TAR
OA DAMPER POSITION = O/C
OA DAMPER =
100% OP
OA FLOW = MAX DESIGN CFM = 2000
AFMS =
1296
64.8% dsn—low airflow
RELIEF HOOD BAROM DAMPER POSITION = O/C
REL DAMPER POS =
Verify operation, pgm shows damper
RETURN DAMPER POSITION = O/C
RA DAMPER POS =
CL
is closed in this mode.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 -2017 - 08 -10
MO t0:00PM to 5:00 AM
Building
CLOSED
TU
Building
CLOSED
WE
Building
CLOSED
TH
Building CLOSED
10
Scheduled Occupancy -
UNOCCUPIED MODE
Running according to BMS Schedule
FR
Building CLOSED
SA
Building CLOSED
SU
Building CLOSED
IN THE UNOCCUPIED MODE THE AHU SUPPLY FAN SHALL
OPER ATE ONLY ON A CALL FOR COOLING OR HEATING.
OUTSIDE AIR DAMPER SHALL REMAIN CLOSED.
ON A CALL FUR COOLING I HE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
Unoccupied temperature sequence
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
is not programmed, per owner
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
request.
ONCE THE UNOCCUPIED SPACE TEMPERATURE SET POINT IS
ACHIEVED THE COOLING COIL SHALL CLOSE AND THE SUPPLY
FAN SHALL STOP.
ON A CALL FOR HEATING, THE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
Forced into unoccupied mode to lest.
HEATER SHALL BE STAGED TO MAINTAIN THE DISCHARGE AIR
TEMPERATURE SET POINT. ONCE THE UNOCCUPIED SPACE
TEMPER ATURE SET POINT IS ACHIEVED THE HEATER SHALL
BE DISABLED AND THE SUPPLY FAN SHALL STOP.
SUPPLY FAN STATUS - ON / OFF
SF STATUS =
OFF
UNOCC COOLING SP = 80
CLG MODE _
UNOCC HEATING SP = 60
HTG MODE _
CA DAMPER POSITION = O/C
CA DMPR POS =
CL
AFMS CFM =
AFMS CFM =
85
Iminimum airflow.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
11
HUMIDITY CONTROL
(UNOCCUPIED)
IF THE ROOM HUMIDITY RISES ABOVE THE UNOCCUPIED
MAXIMUM SPACE RELATIVE HUMIDITY SET POINT DURING THE
UNOCCUPIED PERIOD, PROVIDE NOTIFICATION AND THE
SUPPLY FAN SHALL BE STARTED AND ALLOWED TO ADJUST
FAN SPEED BASED ON SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED, AND THE
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
ONCE THE SPACE HUMIDITY FALLS BELOW 55%THE COOLING
COIL SHALL CLOSEAND THE SUPPLY FAN SHALL STOP.
RH setpoint at 65%.
-Need to reprogram this sequence. -
Forced system off to test points.
SF = START/STOP
STOP
OA DMPR POS-= O/C
CL
UNOCC RH %=60
RH % =
31.11
COOLING T =
48.56
HEATING T=
12
LAT Control/SPD ctrl
Supply fan VFD
CLG Setoint: LAT =55
CLG LAT=
46
HTG Set pint: LAT =
HTG LAT =
VFD MIN
speed = 65% 39 Hz
VFD s eed =
n/a
no VFD
VFD MAX
speed = 100% 60Hz
13
ALARMS
No alarms programmed. Advised
controls contractor to verify with
owner for alarm setpoinls.
Hi h RH %
RH%> 60
BAS alarm activated.
OA Alarm
10%+/- DSN MIN OA
BAS alarm activated.
Supply Fan Failure
BAS alarm
BAS alarm activated.
OA Damper failure
BAS alarm
BAS alarm activated.
RA Damper failure
BAS alarm
BAS alarm activated.
High Supply Duct SP
BAS alarm
BAS alarm activated.
High SAT
BAS alarm
BAS alarm activated.
Low SAT
BAS alarm
BAS alarm activated.
Filter Dirty
BAS alarm
BAS alarm activated.
14
EMERGENCY SHUTDOWN
SHUTDOWN
(Smoke Detector)
WHEN ANY ONE OF THE SYSTEM DUCT SMOKE DETECTORS IS
ACTIVATED, THE UNIT SHALL SHUT DOWNUPON RECEIVING
AN EMERGENCY SHUTDOWN / SMOKE DETECTIONSIGNAL
FROM THE FIRE ALARM PANEL.
SMOKE DETECTOR INDICATION =
Smoke
tector/AHU shutdown e de
de and passed by Fire
Inspector, per owner.
OA Damper
OA Damper status
OA Damper status =
RA Damper
RA Damper status
RA Damper status=
SAFETY SHUTDOWN
STATIC PRESSURE
SP =
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 00 -10
Test— AHU-3/CU-7
Step
Test Description
Acceptance Criteria
Measurement/Setpoint
Result
Date
Test Notes
Final, approved report received by
-TAB Complete and report provided
chk
12/11/2017
Anatom today.
Pre Function Testing Prereq
- BMS point-to-point complete and report provided
n/a
Point-to-point listing received today.
n/a
Checking programming today
-Control program checkout complete
Running according to BMS Schedule
MO 5:00 AM TO 10:00 PM
12/11/2017
Building
CLOSED
TU
Building
OPEN
WE
Building OPEN
TH
Building OPEN
FR
Building OPEN
SA
Building OPEN
SU
Building CLOSED
OPERATE CONTINUOUSLY AND THE OUTDOOR AIR DAMPER
Unit forced into cooling mode to test
i
Scheduled Occupancy -OCCUPIED
MODE
SHALL BE IN THE FULLY OPEN POSITION. EITHER THE STAGES
OF COMPRESSION SHALL BE TURNED ON OR OFF OR THE
ELECTRIC HEATER SHALL BE STAGED TO MAINTAIN THE
points.
- Max Room Temp sets operating
mode, per program.
REQUIRED DISCHARGE AIR TEMPERATURE.
Cooling and heating setpoints were
adjusted per owner request from
default of 75 F f72 F. to the same
value of 72 F 172 F. Unit currently is
THE SUPPLY FAN SPEED SHALL BE MODULATED TO MAINTAIN
controlling to maintain a 55 F coil
THE ROOM TEMPERATURE AT THE COOLING SET POINT (USER
discharge temperature (LAT). This is
ADJUSTABLE). THE FAN SPEED
causing problems of cycle overshoot
SHALL BE MODULATED FROM A MINIMUM OF 65% (39 HZ) TO A
in the control system moving rapidly
MAXIMUM OF 100% (60 HZ). ONCE THE FAN SPEED FALLS TO
from cooling to heating modes.
THE MINIMUM AND THE SPACE TEMPERATURE CONTINUES TO
Recommended to place a deadband
FALL, THE SUPPLY AIR SET POINT SHALL BE RESET TO
between cooling -heating setpoints,
MAINTAIN THE ROOM TEMPERATURE AT THE HEATING SET
provide a coil LAT reset, as noted in
POINT (USER ADJUSTABLE). THE ELECTRIC DUCT HEATER
dsn sequence and provide a
SHALL BE STAGED TO MAINTAIN THE HEATING DISCHARGE
compressor delay to ensure both
TEMPERATURE (USER ADJUSTABLE).
don't slam on simultaneously.
Cooling and heating setpoints have
been readjusted to 72 (CLG) and 70
(HTG). Compressor reset and delay
needs to be programmed.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
2
LAT Control/ SPD ctri
Supply fan VFD
CLG Setpoint: LAT = 55
CLG LAT =
54.85
SAT = 60
HTG Setpoint: LAT =
HTG LAT =
93
OCC COOLING SP=72 71.73
OCC COOLING ?=
OCC HEATING SP = 70 69-71
OCC HEATING T =
OCC RH %SP=
OCC RH o/ =
32.21
VFD MIN speed = 65% 39 Hz
VFD MIN speed =
VFD MAX speed =100% 60 Hz
VFD MAX speed =
100%
MIXED AIR TEMP
MAT =
RETURN AIR TEMP
RAT =
74
AIR FILTER DP SP =
FILTER DP =
-0.05
Point not operating. Repair/replace.
3
CA damper position
Verify operation
AFMS = 700 CFM MIN
OPEN / CLOSED
43% OP
at 40% OP = 656 cfm
AFMS CFM =
715
4
Electric Heater
Verify operation
Fan speed - minimum at heating
HEATING STAGES = 2
ON / OFF
ON
VFD speed =
65
HEATING STAGES =
1,2
ROOM T =
70.64
LAT =
95
5
Supply Temp Sensor
Instrument
BAS:
59 F setpoint
6
Duct SP Sensor
Instrument: SP STPT =
Instrument: SP =
n/a
not a required control point
Compressor#1
Compressor#2
COND UNIT FAN
NO. STAGES =
none
7
DX Compressor
BAS:
OFF
ON/OFF
8
OSA AFMS
Verify calibration of OSA airflow station.
Measure OSA and modulate OSA DMPR to allow MIN CA (sched)
DSN MIN OSA (Sched) =
ACTUAL OSA CFM =
700
705
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017.08 -10
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS EQUAL
ECONOMIZER MODE sequence is
TO OR LESS THAN 28 BTU/LB OF AIR, THE OUTSIDE AIR
not programmed into the control
DAMPER SHALL FULLY OPEN AND THE RETURN AIR DAMPER
system, per owner request
SHALL FULLY CLOSE TO ALLOW 100% OUTSIDE AIR TO THE
- Forced system into Economizer
UNIT.
mode to check points.
THE AIR HANDLING UNIT FAN SPEED SHALL CONTINUE TO
CONTROL TO MAINTAIN SPACE TEMPERATURE SET POINT AS
DETERMINED BY THE AVERAGING THERMOSTAT AND TEMPER
ATURE SENSORS AND THE COMPRESSOR STAGES SHALL
MODULATE OR TURN ON/OFF TO MAINTAIN OFF COIL
9
ECONOMIZER MODE
TEMPERATURE SET POINT.
WHEN THE OUTSIDE AIR ENTHALPY, AS MEASURED BY THE
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS
GREATER THAN 28 BTU/LB, THE OUTSIDE AIR DAMPER SHALL
RETURN TO THE MINIMUM OUTSIDEAIR POSITION OR TO
THAT POSITION NEEDED TO MAINTAIN THE MINIMUM
OUTDOOR AIRFLOW REQUIRED AS MEASURED BY THE
OUTSIDE AIR AIR FLOW MONITORING STATION.
THE UNIT RETURN AIR DAMPER SHALL OPEN TO ALLOW
RETURN AIR BACK TO THE UNIT TO MIX WITH THE OUTSIDE
AIR.
- Sensor not operating,
repair/replace.
- OA Enthalpy = 21.21 btu/lb as
OA ENTHALPY SP = 28 BTU/LB
OA ENTHALPY =
54
measured by TAB
OA DAMPER
POSITION = O/C
OA DAMPER =
OA FLOW = MAX DESIGN CFM = 5000
AFMS =
3600
72%dsn. Low airflow.
RELIEF HOOD BAROM DAMPER POSITION = O/C
REL DAMPER POS =
RETURN DAMPER POSITION = O/C
RA DAMPER POS =
CL
Verify operation of damper.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
MO 10:0OPM to 5:00 AM
Building CLOSED
TU
Building CLOSED
WE
Building CLOSED
10
Scheduled Occupancy -
Running according to BMS Schedule
UNOCCUPIED MODE
TH
Building CLOSED
FR
Building
CLOSED
SA
Building
CLOSED
SU
Building
CLOSED
IN THE UNOCCUPIED MODE THE AHU SUPPLY FAN SAL
OPER ATE ONLY ON A CALL FOR COOLING OR HEATING.
OUTSIDE AIR DAMPER SHALL REMAIN CLOSED.
ON A CALL FUH CUULING I Ht SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPER ATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
ONCE THE UNOCCUPIED SPACE TEMPERATURE SET POINT IS
Unoccupied temperature sequence
is not programmed, per owner
request.
ACHIEVED THE COOLING COIL SHALL CLOSE AND THE SUPPLY
FAN SHALL STOP.
ON A CALL FOR HEATING, THE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPER ATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
HEATER SHALL BE STAGED TO MAINTAIN THE DISCHARGE AIR
Forced into unoccupied mode to lest.
TEMPERATURE SET POINT. ONCE THE UNOCCUPIED SPACE
TEMPER ATURE SET POINT IS ACHIEVED THE HEATER SHALL
BE DISABLED AND THE SUPPLY FAN SHALL STOP.
RH%=
32.86
SPat65%
SUPPLY FAN STATUS - ON I OFF
SF STATUS =
OFF
UNOCC COOLING SP = 80
CLG MODE =
ma
UNOCC HEATING SP = 60
HTG MODE =
ma
CA DAMPER POSITION = O/C
CA DMPR POS =
CL
RA damper 100% OF
minimum airflow.
-AFMS showing TROUBLE in
screen.
AFMS CFM =
AFMS CFM =
35
- Need to verify operation
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
11
HUMIDITY CONTROL
(UNOCCUPIED)
'
IF THE ROOM HUMIDITY RISES ABOVE THE UNOCCUPIED
MAXIMUM SPACE RELATIVE HUMIDITY SET POINT DURING THE
UNOCCUPIED PERIOD, PROVIDE NOTIFICATION AND THE
SUPPLY FAN SHALL BE STARTED AND ALLOWED TO ADJUST
FAN SPEED BASED ON SPACE TEMPERATURE.
THE OUIDOOR AIR DAMPER SHALL REMAIN CLOSED, AND THE
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
ONCE THE SPACE HUMIDITY FALLS BELOW 55%THE COOLING
COIL SHALL CLOSE AND THE SUPPLY FAN SHALL STOP.
Forced RH to activate program.
Need to program the SAS
notification, as stated in dsn
sequence, for High Humidity in
space.
- Sequence not operating. Both
compressors are slamming on
simultaneously.
- Recommend to utilize LAT reset
and (1) compressor at a time to
satisfy the requirement.
SF = START/STOP
OA DMPR POS=O/C
CL
UNOCC RH % = 60
RH % =
65
Range from 55-65 %
COOLING T =
HEATING T=
12
LAT Control I SPD ctrl
Supply fan VFD
CLG Setpoint: LAT = 55
CLG LAT =
46
HTG Set pint: LAT=
HTG LAT=
VFD MIN speed = 65 % 39 Hz
VFD speed =
VFD MAX sneed = 100% 60Hz
13
No alarms programmed. Advised
controls contractor to verify with
ALARMS owner for alarm setpoints.
High RH%
RH%>60
BAS alarm activated.
CA Alarm
10%+/- DSN MIN CA
BAS alarm activated.
Supply Fan Failure
BAS alarm
BAS alarm activated.
CA Damper failure
BAS alarm
BAS alarm activated.
RA Damper failure
BAS alarm
BAS alarm activated.
High Supply Duct SP
BAS alarm
RAS alarm activated.
High SAT
BAS alarm
BAS alarm activated.
Low SAT
BAS alarm
BAS alarm activated.
Filter Dirty
BAS alarm
BAS alarm activated.
14
EMERGENCY SHUTDOWN
SHUTDOWN
(Smoke Detector)
WHEN ANY ONE OF THE SYSTEM DUCT SMOKE DETECTORS IS
ACTIVATED, THE UNIT SHALL SHUT DOWNUPON RECEIVING
AN EMERGENCY SHUTDOWN / SMOKE DETECTIONSIGNAL
FROM THE FIRE ALARM PANEL.
SMOKE DETECTOR INDICATION =
Smoke detector I AHU shutdown
witnessed and passed by Fire
Inspector, per owner.
OA Damper
CA Damper status
OA Damper status =
RA Damper
RA Damper status
RA Damper status =
SAFETY SHUTDOWN
STATIC PRESSURE -
SP=
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 06 -10
Test= AHU-0/CU-4
Step
Test Description
Acceptance Criteria
Measurement I Setpoint
Result
Date
Test Notes
Final, approved report received by
-TAB Complete and report provided
chk
12111/2017
Anatom today.
n/a
Point-to-point listing received today.
Pre Function Testing Prereq
- BMS point-to-point complete and report provided
n/a
Checking programming today
- Control ro ram checkout complete
Running according to BMS Schedule
MO 5:00 AM TO 10:00 PM
1211112017
Building CLOSED
TU
Building OPEN
WE
Building
OPEN
TH
Building
OPEN
FR
Building
OPEN
SA
Building
OPEN
SU
Building
CLOSED
OPERATE CONTINUOUSLYAND THE OUTDOOR AIR DAMPER
1
Scheduled Occupancy - OCCUPIED
MODE
SHALL BE IN THE FULLY OPEN POSITION. EITHER THE STAGES
OF COMPRESSION SHALL BE TURNED ON OR OFF OR THE
ELECTRIC HEATER SHALL BE STAGED TO MAINTAIN THE
REQUIRED DISCHARGE AIR TEMPERATURE.
Cooling and heating setpoints were
adjusted per owner request from
default of 75 F 172 F, to the same
value of 72 F / 72 F. Unit currently is
THE SUPPLY FAN SPEED SHALL BE MODULATED TO MAINTAIN
controlling to maintain a 55 F coil
THE ROOM TEMPERATURE AT THE COOLING SET POINT (USER
discharge temperature (LAT). This is
ADJUSTABLE). THE FAN SPEED
causing problems of cycle overshoot
SHALL BE MODULATED FROM A MINIMUM OF 65% (39 HZ) TO A
in the control system moving rapidly
MAXIMUM OF 100% (60 HZ). ONCE THE FAN SPEED FALLS TO
from cooling to heating modes.
THE MINIMUM AND THE SPACE TEMPERATURE CONTINUES TO
Recommended to place a deadband
FALL, THE SUPPLYAIR SET POINT SHALL BE RESET TO
between cooling -heating setpoints,
MAINTAIN THE ROOM TEMPERATURE AT THE HEATING SET
provide a coil LAT reset, as noted in
POINT (USER ADJUSTABLE). THE ELECTRIC DUCT HEATER
dsn sequence and provide a
SHALL BE STAGED TO MAINTAIN THE HEATING DISCHARGE
compressor delay to ensure both
TEMPERATURE (USER ADJUSTABLE).
don't slam on simultaneously.
Cooling and heating setpoints have
been readjusted to 72 (CLG) and 70
(HTG). Compressor reset and delay
needs to be programmed.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
2
LAT Control I SPD old
Supply fan VFD
CLG Setpoint: LAT = 55
CLG LAT =
51.11
SAT = 52.14
HTG Setpoint: LAT=
HTG LAT=
OCC COOLING SP = 72 71 - 73
OCC COOLING T =
OCC HEATING SP= 70 69-71
OCC HEATING T=
OCC RH % SP =
OCC RH %=
33.95
VFD MIN speed = 65% 39 Hz
VFD MIN speed =
65
VFD MAX speed =100% 60 Hz
VFD MAX speed =
MIXED AIR TEMP
MAT=
RETURN AIR TEMP
RAT=
73.23
Temp satisfied.
AIR FILTER DP SP =
FILTER DP =
3
OA damper position
Verify operation
AFMS = 1250 CFM MIN
OPEN / CLOSED
AFMS CFM =
4
Electric Heater
Verify operation
Fan speed - minimum at heating
HEATING STAGES =2
ON/OFF
ON
Forced on to test points.
VFD speed =
65
HEATING STAGES =
1.2
ROOM T =
65.92
LAT =
98.8
5
Supply Temp Sensor
Instrument:
BAS:
53
6
Duct SP Sensor
Instrument: SP STPT =
Instrument: SP =
Compressor #1
Compressor#2
COND UNIT FAN
NO. STAGES =
1,2
7
DX Compressor
BAS:
1.2
ON'/ OFF
8
OSA AFMS
Verify calibration of OSA airflow station.
tY
Measure OSA and modulate OSA DMPR to allow MIN OA (ached)
DSN MIN OSA (Schad) =
ACTUAL OSA CFM =
1250
1332
RA damper shows 100% OPEN, OA
= 800 CFM. Forced RA damper
closed to obtain OA value shown.
- RA Damper is not closing, leaking
air. OA not maintaining airflow.
Found RA damper broken, (1) blade
fell away from shaft. Advised MC to
replace damper. -
Need to retest when damper is
replaced. - Forced RA damper
closed, result of OA at AFMS.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 -2017 - 08 -10
MODE
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS EQUAL
ECONOMIZER MODE sequence is
TO OR LESS THAN 28 BTU/LB OF AIR, THE OUTSIDE AIR
not programmed into the control
DAMPER SHALL FULLY OPEN AND THE RETURN AIR DAMPER
system, per ovmer request.
-DID NOT TEST.
SHALL FULLY CLOSE TO ALLOW 100% OUTSIDE AIR TO THE
THE AIR HANDLING UNIT FAN SPEED SHALL CONTINUE TO
CONTROL TO MAINTAIN SPACE TEMPER ATURE SET POINT AS
DETERMINED BY THE AVERAGING THERMOSTAT AND TEMPER
ATURE SENSORS AND THE COMPRESSOR STAGES SHALL
MODULATE OR TURN ON/OFF TO MAINTAIN OFF COIL
TEMPERATURE SET POINT.
WHEN THE OUTSIDE AIR ENTHALPY, AS MEASURED BY THE
OUTSIDE AIR DUCT MOUNTED ENTHALPYSENSOR, IS
GREATER THAN 28 BTUILB, THE OUTSIDE AIR DAMPER SHALL
RETURN TO THE MINIMUM OUTSIDE AIR POSITION OR TO
THAT POSITION NEEDED TO MAINTAIN THE MINIMUM
OUTDOOR AIRFLOW REQUIRED AS MEASURED BY THE
OUTSIDE AIR AIR FLOW MONITORING STATION.
THE UNIT RETURN AIR DAMPER SHALL OPEN TO ALLOW
RETURN AIR BACK TO THE UNIT TO MIX WITH THE OUTSIDE
BTU/LB
CA Enthalpy= 21.21 btuflb as
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 06 -10
MO 10:OOPM to 5:00 AM
Building CLOSED
TU
Building CLOSED
WE
Building CLOSED
TH
Building CLOSED
10
Scheduled Occupancy -
UNOCCUPIED MODE
Running according to BMS Schedule
FR
Building CLOSED
SA
Building CLOSED
SU
Building CLOSED
IN THE UNOCCUPIED MODE THE AHU SUPPLY FAN SHALL
OPER ATE ONLY ON A CALL FOR COOLING OR HEATING.
OUTSIDE AIR DAMPER SHALL REMAIN CLOSED.
ON A CALL FOR COOLING I HE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
Unoccupied temperature sequence
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
is not programmed, per owner
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
request.
ONCE THE UNOCCUPIED SPACE TEMPERATURE SET POINT IS
ACHIEVED THE COOLING COIL SHALL CLOSE AND THE SUPPLY
FAN SHALL STOP.
ON A CALL FOR HEATING, THE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
HEATER SHALL BE STAGED TO MAINTAIN THE DISCHARGE AIR
TEMPERATURE SET POINT. ONCE THE UNOCCUPIED SPACE
TEMPER ATURE SET POINT IS ACHIEVED THE HEATER SHALL
BE DISABLED AND THE SUPPLY FAN SHALL STOP.
SUPPLY FAN STATUS - ON I OFF
SF STATUS =
UNOCC COOLING SP = 60
CLG MODE _
UNOCC HEATING SP = 60
HTG MODE _
CA DAMPER POSITION = O/C
OA DMPR POS =
AFMS CFM =
AFMS CFM =
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 .2017 - 08 -10
11
HUMIDITY CONTROL
(UNOCCUPIED)
IF THE ROOM HUMIDITY RISES ABOVE THE UNOCCUPIED
MAXIMUM SPACE RELATIVE HUMIDITY SET POINT DURING THE
UNOCCUPIED PERIOD, PROVIDE NOTIFICATION AND THE
SUPPLY FAN SHALL BE STARTED AND ALLOWED TO ADJUST
FAN SPEED BASED ON SPACE TEMPERATURE.
THE OUIDOOR AIR DAMPER SHALL REMAIN CLOSED, AND THE
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
ONCE THE SPACE HUMIDITY FALLS BELOW 55% THE COOLING
COIL SHALL CLOSEAND THE SUPPLY FAN SHALL STOP.
Not able to lest. Control sequence
needs to be reprogrammed
SF = START/STOP
OA DMPR POS = O/C
UNOCC RH % = 60
RH % =
COOLING T =
HEATING T=
12
LAT Control / SPD ctrl
Supply fan VFD
CLG Setpoint: LAT = 55
CLG LAT =
HTG Setpoint: LAT =
HTG LAT =
VFD MIN speed = 65% 39 Hz
VFD speed =
VFD MAX speed = 100 % 6OHz
13
No alarms programmed. Advised
controls contractor to verify with
ALARMS owner for alarm setpoints.
High RH %
RH%> 60
BAS alarm activated.
OA Alarm
10%+l- DSN MIN OA
BAS alarm activated.
Supply Fan Failure
BAS alarm -
BAS alarm activated.
OA Damper failure
BAS alarm
BAS alarm activated.
RA Damper failure
BAS alarm
BAS alarm activated.
High Suppiy Duct SP
BAS alarm
BAS alarm activated.
High SAT
BAS alarm
BAS alarm activated.
Low SAT
BAS alarm
BAS alarm activated.
Filter Dirty
BAS alarm
BAS alarm activated.
14
EMERGENCY SHUTDOWN
SHUTDOWN
(Smoke Detector)
WHEN ANY ONE OF THE SYSTEM DUCT SMOKE DETECTORS IS
ACTIVATED, THE UNIT SHALL SHUT DOWNUPON RECEIVING
AN EMERGENCY SHUTDOWN / SMOKE DETECTIONSIGNAL
FROM THE FIRE ALARM PANEL.
SMOKE DETECTOR INDICATION =
Smoke detector/AHU shutdown
witnessed and passed by Fire
Inspector, per owner.
OA Damper
OA Damper status
OA Damper status =
RA Damper
RA Damper status
RA Damper status =
SAFETY SHUTDOWN
STATIC PRESSURE
SP=
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 .2017 - 08 -10
Test- AHU-51CU-5
Step
Test Description
Acceptance Criteria
Measurement/Setpoint
Result
Date
Test Notes
Pre Function Prereq
-TAB Complete and report provided
- BMS point-to-point complete and report provided
-Control program checkout complete
chk
12/11/2017
Final, approved report received by
Anatom today.
We
Point-to-point listing received today.
n/a
Checking programming today
1
Scheduled Occupancy - OCCUPIED
MODE
Running according to.BMS Schedule
MO 5:00 AM TO 10:00 PM
12111/2017
Building CLOSED
TU
Building OPEN
IWE
Building OPEN
TH
Building OPEN
FR
113uIlcling OPEN
SA
Building OPEN
SU
_
Building CLOSED
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
Units are not programmed as an
alternating system, per owner
AHU-5 AND AHU-6 UTILIZE A LEAD -LAG CONFIGURATION,
request. This system is not operating
IN THE OCCUPIED MODE THE LEAD AHU SUPPLY FAN SHALL OPERATE CONTINUOUSLYAND THE
as designed. They are programmed
LAG AHU SUPPLY FAN SHALL BE OFF.
to run simultaneously. - The
THE OUTDOOR AIR DAMPER OF THE LEAD AHU WILL BE IN THE MINIMUM POSITION AND THE
systems are sharing a temperature
OUTDOOR AIR DAMPER OF THE LAG AHU WILL BE IN THE CLOSED POSITION.
sensor in each pad of the Meeting
EITHER THE STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF OR THE ELECTRIC HEATER
Room #2 Room 36. - Only one
SHALL BE STAGED TO MAINTAIN THE REQUIRED DISCHARGE AIR TEMPERATURE OF THE LEAD
(1) temperature sensor and one (1)
UNIT. IF THE
CO2 sensor are installed in each
ROOM TEMPERATURE COOLING OR HEATING SET POINT CANNOT BE MAINTAINED WITH THE LEAD
side of the Meeting Room #2 (E &
FAN SPEED AT 100 % (SEE SEQUENCE BELOW), THE LAG AHU UNIT SHALL BE TURNED ON AND THE
W). - Maximum
OUTDOOR AIR DAMPER OPENED TO THE MINIMUM POSITION. FOR BOTH
room temperature is used to
UNITS, THE STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF OR THE ELECTRIC HEATER
determine system mode. -There
SHALL BE STAGED TO MAINTAIN THE REQUIRED DISCHARGE AIR TEMPERATURES.
is one (1) additional temperature
sensor located in Hall #2 Room 38,
near the outside door.
Cooling and heating setpoints were
THE SUPPLY FAN SPEED SHALL BE MODULATED TO MAINTAIN THE ROOM TEMPERATURE AT THE
adjusted per owner request from
COOLING SET POINT (USER ADJUSTABLE). THE FAN SPEED SHALL BE MODULATED FROM A
default of 75 F f72 F , to the same
MINIMUM OF 65% (39 HZ) TO A MAXIMUM OF 100% (60 HZ). IF
value of 72 F / 72 F. Unit currently is
THE FAN SPEED OF THE LEAD UNIT IS AT MAXIMUM AND THE COOLING OR HEATING SET POINT
controlling to maintain a 55 F coil
CANNOT BE MAINTAINED, THE LAG AHU SHALL BE TURNED ON, THE LAG AHU OUTDOOR AIR AIR
discharge temperature (LAT). This is
DAMPER OPENED TO THE MINIMUM POSITION AND THE FAN SPEED OF THE LEAD AHU SHALL
causing problems of cycle overshoot
BE SET TO THE MINIMUM (65%, 39HZ). THE SUPPLY FAN SPEED OF THE LAG
in the control system moving rapidly
SHALL BEGIN IN THE THE MINIMUM POSITION (65%, 39 HZ). THE SUPPLY FAN SPEED OF BOTH
from cooling to heating modes.
UNITS SHALL BE MODULATED TO MAINTAIN THE ROOM TEMPER ATURE AT THE COOLING SET
Recommended to place a deadband
POINT. ONCE THE FAN SPEED OF BOTH UNITS FALLS TO THE MINIMUM AND
between cooling -heating setpoints,
THE SPACE TEMPERATURE CONTINUES TO FALL, THE LAG AHU IS TO BE TURNED OFF AND THE
provide a coil LAT reset, as noted in
LAG OUTDOOR DAMPER CLOSED. ONCE THE FAN SPEED OF THE LEAD
dsn sequence and provide a
AHU FALLS TO THE MINIMUM AND THE SPACE TEMPERATURE CONTINUES TO FALL, THE SUPPLY
compressor delay to ensure both
AIR SET POINT SHALL BE RESET TO MAINTAIN THE ROOM TEMPERATURE AT THE HEATING SET
don't slam on simultaneously. ,
POINT (USER ADJUSTABLE). THE ELECTRIC DUCT
Cooling and heating setpoints have
HEATER SHALL BE STAGED TO MAINTAIN THE HEATING DISCHARGE TEMPERATURE (USER
been readjusted to 72 (CLG) and 70
ADJUSTABLE).
(HTG). Compressor reset and delay
needs to be programmed.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
1A
Alternating Status
AHU-5 &AHU-6 alternate LEAD/LEG on 7-day cycle
VERIFY ALT CYCLING
n/a
Units not programed as alternating.
2
LAT Control SPD ctrl
Supply fan VFD
CLG Set tint LAT =55
CLG LAT=
46
SAT =61.68
HTG Setpoint: LAT=
HTG LAT=
OCC COOLING SP = 72 71-73
OCC COOLING SP =
OCC HEATING SP=70 69-71
OCC HEATING SP=
OCC RH %=
OCC RH %=
26
VFD MIN speed =65% 39 Hz
VFD MIN speed =
65
VFD MAX speed =100% 60 Hz
VFD MAX speed =
ROOM T=
71.1
Forced Room Temp to 75 F for test
FILTER =
0.09
3
OA damper position
Verify operation
LEAD - O/C
61% OF
392 cfm OA
LAG - O/C
4
Electric Heater
Verify operation
Fan speed - minimum at heating
HEATING STAGES = 2
ONIOFF
fanspeed =
HEATING STAGES =
LAT =
5
Supply Temp Sensor
Instrument:
BAS:
6
D1uct SP Sensor
Instrument: SP STPT =
Instrument: SP =
7
DX Compressor
Compressor #1
Compressor#2
COND UNIT FAN
NO. STAGES =
1,2
BAS:
12
ON/ OFF
8
OSA AFMS
Verify calibration of OSA airflow station.
Measure OSA and modulate OSA DMPR to allow MIN OA (sched)
DSN MIN OSA (Sched) =
ACTUAL OSA CFM =
425
457
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
WHEN THE OUTSIDE AIR ENTHALPY, AS MEASURED BY THE
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS EQUAL
ECONOMIZER MODE sequence is
not programmed into the control
TO OR LESS THAN 28 BTU/LB OF AIR, THE OUTSIDE AIR
DAMPER SHALL FULLY OPEN AND THE RETURN AIR DAMPER
system, per ovmer request
- Forced system into Economizer
SHALL FULLY CLOSE TO ALLOW 100% OUTSIDE AIR TO THE
made to check points.
UNIT.
THE AIR HANDLING UNIT FAN SPEED SHALL CONTINUE TO
CONTROL TO MAINTAIN SPACE TEMPER ATURE SET POINT AS
DETERMINED BY THE AVERAGING THERMOSTAT AND TEMPER
ATURE SENSORS AND THE COMPRESSOR STAGES SHALL
9
ECONOMIZER MODE
MODULATE OR TURN ON/OFF TO MAINTAIN OFF -COIL
TEMPERATURE SET POINT.
WHEN THE OUTSIDE AIR ENTHALPY, AS MEASURED BY THE
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS
GREATER THAN 28 BTU/LB, THE OUTSIDE AIR DAMPER SHALL
RETURN TO THE MINIMUM OUTSIDE AIR POSITION OR TO
THAT POSITION NEEDED TO MAINTAIN THE MINIMUM
OUTDOOR AIRFLOW REQUIRED AS MEASURED BY THE
OUTSIDE AIR AIR FLOW MONITORING STATION.
THE UNIT RETURN AIR DAMPER SHALL OPEN TO ALLOW
RETURN AIR BACK TO THE UNIT TO MIX WITH THE OUTSIDE
AIR.
- Sensor not operating,
repair/replace.
- OA Enthalpy = 21.21 btu/lb as
ENTHALPY SENSOR (EN) SP = 28 BTU/LB
EN SENSOR = ••" BTU/LB
54
measured by TAB.
OA DMPR POS=O/C
38.96%OP
OA AFMS SP=425 MIN —850 MAX
Damper not closing. Need to verify
PRH (1,2,3,4) = OPEN/CLOSE WITH AMBIENT PRESSURE
RA DMPR POS = O/C
100 OF
operation.
OA AFMS=•"•CFM
525
PRH-1 = O/C
n/a
PRH-2 = O/C
n/a
PRH-3 = O/C
n/a
PRH-4 = O/C
n/a
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 -2017 - 08 -10
MO 10:OOPM to 5:00 AM
Building CLOSED
TU
Building CLOSED
WE
Building CLOSED
Scheduled Occupancy -
10
UNOCCUPIED MODE
Running according to BMS Schedule
TH
Building CLOSED
FR
Building CLOSED
SA
Building CLOSED
SU
Building CLOSED
IN THE UNOCCUPIED MODE THE AHU SUPPLY FAN SHALL
OPERATE ONLY ON.A CALL FOR COOLING OR HEATING.
OUTSIDE AIR DAMPER SHALL REMAIN CLOSED.
ON A CALL FOR COOLING THE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
Unoccupied temperature sequence
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
is not programmed, per owner
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
request.
ONCE THE UNOCCUPIED SPACE TEMPERATURE SET POINT IS
ACHIEVED THE COOLING COIL SHALL CLOSE AND THE SUPPLY
FAN SHALL STOP.
ON A CALL FOR HEATING, THE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
HEATER SHALL BE STAGED TO MAINTAIN THE DISCHARGE AIR
TEMPERATURE SET POINT. ONCE THE UNOCCUPIED SPACE
TEMPER ATURE SET POINT IS ACHIEVED THE HEATER SHALL
BE DISABLED AND THE SUPPLY FAN SHALL STOP.
IF THE ROOM HUMIDITY RISES ABOVE THE UNOCCUPIED
MAXIMUM SPACE RELATIVE HUMIDITY SET POINT DURING THE
UNOCCUPIED PERIOD, PROVIDE NOTIFICATION AND THE
SUPPLY FAN SHALL BE STARTED AND ALLOWED TO ADJUST
11
HUMIDITY CONTROL
(UNOCCUPIED)
FAN SPEED BASED ON SPACE TEMPERATURE.
THE OUIDOOR AIR DAMPER SHALL REMAIN CLOSED, AND THE
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
Forced into unoccupied mode to test.
Not able to test. -
Need to reprogram this sequence.
ONCE THE SPACE HUMIDITY FALLS BELOW 55% THE COOLING
COIL SHALL CLOSE AND THE SUPPLY FAN SHALL STOP.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
12
LAT Control / SPD ctrl
CLG Setpoint: LAT = 55
CLG LAT=
Supply fan VFD
HTG Setpoint: LAT =
HTG LAT=
UNOCC COOLING SP=80
UNOCC COOLING T=
UNOCC HEATING SP = 60
UNOCC HEATING T =
UNOCC RH %=60
UNOCC RH %_
VFD MIN speed = 65% 39 Hz
VFD MIN speed =
VFD MAX speed = 100% 601-1z
VFD MAX speed =
A CO2 SENSOR SHALL BE MOUNTED IN THE SPACE. THE
CO2 SENSOR PROVIDES AN ANALOG SIGNAL PROPORTIONAL
TO THE CO2 CONCENTRATION. THE SENSOR SHALL BE WIRED
13
DEMAND CONTROL VENTILATION TO THE SIEMENS CONTROLLER AND PROGRAMMED TO
CONTROL THE OUTDOOR AIR DAMPER MIN./MAX POSITION.
THE LEAD AHU OUTDOOR AIR DAMPER SHALL BE ADJUSTED
TO PROVIDE THE MINIMUM OUTDOOR AIRFLOW (425 CFM)
WHEN THE CO2 SENSOR IS AT AMBIENT (400 PPM), AND THE
MAXIMUM OUTDOOR AIRFLOW (850 CFM) WHEN THE CO2
SENSOR CORRESPONDS TO 1,000 PPM.
IF THE LEAD AHU OUTDOOR AIRFLOW IS AT A MAXIMUM (850 CFM) AND THE CO2 SENSOR
CONTINUES TO INDICATE VALUES ABOVE 1,000 PPM, THE LAG AHU IS TO BE TURNED ON AND THE
LEAD AND LAG AHU OUTDOOR AIR DAMPERS ADJUSTED TO THE MINIMUM POSITION (425 CFM
EACH, 850 CFM TOTAL). IF THE CO2 SENSOR
CORRESPONDS TO 1,000 PPM OR GREATER, THE OUTDOOR AIR DAMPER OF THE LEAD AHU SHALL
BE OPENED TO THE MAXIMUM POSITION (850 CFM LEAD, 1275 CFM TOTAL).
Forced CO2 sensor to 1200 ppm for
testing.
IF THE CO2 SENSOR CONTINUES TO CORRESPOND TO 1,000 PPM OR GREATER, THE OUTDOOR
AIR DAMPER OF THE LAG AHU SHALL BE OPENED TO THE MAXIMUM POSITION AS WELL (850 CFM
EACH, 1700 CFM TOTAL).
WHEN THE CO2 SENSOR CORRESPONDS TO THE AMBIENT VALUE (400 PPM), THE LAG AHU
OUTDOOR AIR DAMPER IS TO BE ADJUSTED TO THE MINIMUM POSITION (425 CFM). IF THE CO2
SENSOR CONTINUES TO CORRESPOND TO THEAMBIENT VALUE (400 PPM), THE LAG AHU SHALL
TURN OFF. THE LAG AHU OUTDOOR AIR DAMPER SHALL CLOSE AND THE LEAD AHU OUTDOOR
AIR DAMPER SHALL OPEN TO THE MAXIMUM POSITION (850 CFM).
CO2 Set Dint = 400 PPM NORMAL; >=1000 PPM MAX
CO2 MIN =
415
CO2 Control
CO2 Control
CO2 MAX =
1200
5-At DMPRstatus=MIN/MAX OADMPRstatus=
100%OP
AFMS CFM = 4501850 AFMS CFM =
798
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
14
ALARMS
No alarms programmed. Advised
controls contractor to verify with
ovmer for elan setpoints.
CO2 Alarm
> +/-10% CO2 STPT
BAS=
High RH%
RH%> 60
BAS alarm activated.
OA Alarm
10%+/. DSN MIN OA
BAS alarm activated.
Supply Fan Failure
SAS alarm
SAS alarm activated.
OA Damper failure
BAS alarm
BAS alarm activated.
RA Damper failure
BAS alarm
BAS alarm activated.
Hi h Supply Duct SP
BAS alarm
BAS alarm activated.
High SAT
IBAS alarm
I PAS alarm activated.
Low SAT
BAS alarm
BAS alarm activated.
Filter Dirty
IBAS alarm
I HAS alarm activated.
Low O/A Ventilation
IBAS alarm
I BAS alarm activated.
15
EMERGENCY SHUTDOWN SHUTDOWN
Smoke detector/AHU shutdown
witnessed and passed by Fire
Inspector, per owner.
(Smoke Detector)
When any one of the system duct smoke detectors is activated, the
unit shall shut down upon receiving an emergency shutdovm / smoke
detection signal from the fire alarm panel.
OADam er
OA Damper status
OA Damper status=
RA Dam er
RA Damper status
RA Damper status =
SAFETY SHUTDOWN
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017. OB -10
Test= AHU-61CU-6
Step
Test Description
Acceptance Criteria
Measurement l Setpoint
Result
Date
Test Notes
Pre Function Prereq
-TAB Complete and report provided
- BMS point-to-point complete and report provided
- Control program checkout complete
chk
12111/2017
Final, approved report received by
Anatom today.
Na
Point-to-point listing received today.
We
Checking programming today
1
Scheduled Occupancy -OCCUPIED
MODE
Running according to BMS Schedule
MO 5:00 AM TO 10:00 PM
12111/2017
Building CLOSED
TU
Building OPEN
IWE
Building OPEN
TH
Building OPEN
FR
ISuilding OPEN
SA
ISuilding OPEN
SU
lBuilding CLOSED
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 .2017 - 08 -10
Units are not programmed as an
alternating system, per owner
IU-5 AND AHU-6 UTILIZE A LEAD -LAG CONFIGURATION.
request. This system is not operating
THE OCCUPIED MODE THE LEAD AHU SUPPLY FAN SHALL OPERATE CONTINUOUSLY AND THE
as designed. They are programmed
G AHU SUPPLY FAN SHALL BE OFF.
to run simultaneously. -The
IE OUTDOOR AIR DAMPER OF THE LEAD AHU WILL BE IN THE MINIMUM POSITION AND THE
systems are sharing a temperature
ITDOOR AIR DAMPER OF THE LAG AHU WILL BE IN THE CLOSED POSITION.
sensor in each part of the Meeting
rHER THE STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF OR THE ELECTRIC HEATER
Room #2 Room 36. - Only one
ALL BE STAGED TO MAINTAIN THE REQUIRED DISCHARGE AIR TEMPERATURE OF THE LEAD
(1) temperature sensor and one (1)
IIT. IF THE
CO2 sensor are installed in each
)OM TEMPERATURE COOLING OR HEATING SET POINT CANNOT BE MAINTAINED WITH THE LEAD
side of the Meeting Room #2 (E 8
N SPEED AT 100% (SEE SEQUENCE BELOW), THE LAG AHU UNIT SHALL BE TURNED ON AND THE
W). - Maximum
ITDOOR AIR DAMPER OPENED TO THE MINIMUM POSITION. FOR BOTH
room temperature is used to
ZITS, THE STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF OR THE ELECTRIC HEATER
determine system mode. - There
ALL BE STAGED TO MAINTAIN THE REQUIRED DISCHARGE AIR TEMPERATURES.
is one (1) additional temperature
sensor located in Hall #2 Room 38,
near the outside door.
Cooling and heating setpoints were
SUPPLY FAN SPEED SHALL BE MODULATED TO MAINTAIN THE ROOM TEMPERATURE AT THE
adjusted per owner request from
IDLING SET POINT (USER ADJUSTABLE). THE FAN SPEED SHALL BE MODULATED FROM A
default of 75 F /72 F , to the same
IIMUM OF 65% (39 HZ) TO A MAXIMUM OF 100% (60 HZ). IF
value of 72 F 172 F. Unit currently is
= FAN SPEED OF THE LEAD UNIT IS AT MAXIMUM AND THE COOLING OR HEATING SET POINT
controlling to maintain a 55 F coil
VNOT BE MAINTAINED, THE LAG AHU SHALL BE TURNED ON, THE LAG AHU OUTDOOR AIR AIR
discharge temperature (LAT). This is
VIPER OPENED TO THE MINIMUM POSITION AND THE FAN SPEED OF THE LEAD AHU SHALL
causing problems of cycle overshoot
SET TO THE MINIMUM (65%, 39HZ). THE SUPPLY FAN SPEED OF THE LAG
in the control system moving rapidly
4LL BEGIN IN THE THE MINIMUM POSITION (65%, 39 HZ). THE SUPPLY FAN SPEED OF BOTH
from cooling to heating modes.
ITS SHALL BE MODULATED TO MAINTAIN THE ROOM TEMPER ATURE AT THE COOLING SET
Recommended to place a deadband
INT. ONCE THE FAN SPEED OF BOTH UNITS FALLS TO THE MINIMUM AND
between woling-heating setpoints,
= SPACE TEMPERATURE CONTINUES TO FALL, THE LAG AHU IS TO BE TURNED OFF AND THE
provide a wil LAT reset, as noted in
3 OUTDOOR DAMPER CLOSED. ONCE THE FAN SPEED OF THE LEAD
dsn sequence and provide a
J FALLS TO THE MINIMUM AND THE SPACE TEMPERATURE CONTINUES TO FALL, THE SUPPLY
compressor delay to ensure both
SET POINT SHALL BE RESET TO MAINTAIN THE ROOM TEMPERATURE AT THE HEATING SET
don't slam on simultaneously.
INT (USER ADJUSTABLE). THE ELECTRIC DUCT
Cooling and heating setpoints have
4TER SHALL BE STAGED TO MAINTAIN THE HEATING DISCHARGE TEMPERATURE (USER
been readjusted to 72 (CLG) and 70
JUSTABLE).
(HTG). Compressor reset and delay
needs to be programmed.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 06 -10
1A
Alternating Status
AHU-5 & AHU-6 alternate LEAD/LEG on 7-day cycle
VERIFY ALT CYCLING
n/a
Units not programed as alternating.
2
LAT Control/SPD ctrl
Supply fan VFD
CLG Set oint: LAT=55
CLG LAT=
57
SAT =60.64
HTG Set pint: LAT=
HTG LAT=
OCC COOLING SP = 75
OCC COOLING SP =
OCC HEATING SP = 72
OCC HEATING SP =
OCC RH %=
OCC RH %=
26
VFD %%39 Hz)
VFD MIN speed
65
VFDM60 Hz
VFD MAX speed =
ROOM TEMP =
69
Forced Room Temp to 75 F for test
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
3
OA damper position
Verify operation
LEAD - O/C
LAG - O/C
4
Electric Heater
Verify operation
Fan speed - minimum at heating
HEATING STAGES = 2
ON / OFF
fan speed =
HEATING STAGES =
LAT =
5
Supply Temp Sensor
Instrument:
BAS:
6
Duct SP Sensor
Instrument: SP STPT =
Instrument: SP =
7
DX Compressor
Compressor #1
Compressor#2
COND UNIT FAN
NO. STAGES =
1,2
HAS:
1,2
ON / OFF
8
OSA AFMS
Verify calibration of OSA airflow station.
Measure OSA and modulate OSA DMPR to allow MIN CA (ached)
DSN MIN OSA (Sched) =
ACTUAL OSA CFM =
425
538
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
WHEN THE OUTSIDE AIR ENTHALPY, AS MEASURED BY THE
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS EQUAL
TO OR LESS THAN 28 BTU/LB OF AIR, THE OUTSIDE AIR
DAMPER SHALL FULLY OPEN AND THE RETURN AIR DAMPER
SHALL FULLYCLOSE TO ALLOW 100 % OUTSIDE AIR TO THE
UNIT.
THE AIR HANDLING UNIT FAN SPEED SHALL CONTINUE TO
CONTROL TO MAINTAIN SPACE TEMPER ATURE SET POINT AS
DETERMINED BY THE AVERAGING THERMOSTAT AND TEMPER
ATURE SENSORS AND THE COMPRESSOR STAGES SHALL
9 ECONOMIZER MODE
MODULATE OR TURN ON/OFF TO MAINTAIN OFF -COIL
TEMPERATURE SET POINT.
WHEN THE OUTSIDE AIR ENTHALPY, AS MEASURED BY THE
OUTSIDE AIR DUCT MOUNTED ENTHALPY SENSOR, IS
GREATER THAN 28 BTU/LB, THE OUTSIDE AIR DAMPER SHALL
RETURN TO THE MINIMUM OUTSIDE AIR POSITION OR TO
THAT POSITION NEEDED TO MAINTAIN THE MINIMUM
OUTDOOR AIRFLOW REQUIRED AS MEASURED BY THE
OUTSIDE AIR AIR FLOW MONITORING STATION.
THE UNIT RETURN AIR DAMPER SHALL OPEN TO ALLOW
RETURN AIR BACK TO THE UNIT TO MIX WITH THE OUTSIDE
AIR.
- Sensor not operating,
repair/replace.
ENTHALPYSENSOR (EN) SP = 28 BTU/LB
EN SENSOR = •'• BTU/LB
54
- OA Enthalpy = 21.21 btu/Ib as
Imeasured by TAB,
OA AFMS SP=425 MIN —850 MAX
OA DMPR POS=O/C
38.76%OP
Damper not closing. Need to verify
PRH(1,2,3,4)=OPEN/CLOSE WITH AMBIENT PRESSURE
RA DMPR POS=O/C
100%OP
operation.
OA AFMS=•'••CFM
525
PRH-1 = O/C
N/A
PRH-2 = O/C
N/A
PRH•3 = O/C
N/A
PRH-4 = O/C
N/A
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
MO 10:OOPM to 5:00 AM
Building CLOSED
TU
Building CLOSED
WE
Building CLOSED
Scheduled Occupancy -
10
UNOCCUPIED MODE
Running according to BMS Schedule
TH
Building CLOSED
FR
Building CLOSED
SA
Building CLOSED
SU
Building CLOSED
IN THE UNOCCUPIED MODE THE AHU SUPPLY FAN SHALL
OPERATE ONLY ON A CALL FOR COOLING OR HEATING.
OUTSIDE AIR DAMPER SHALL REMAIN CLOSED.
ON A CALL FOR COOLING THE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
Unoccupied temperature sequence
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
is not programmed, per owner
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT,
request.
ONCE THE UNOCCUPIED SPACE TEMPERATURE SET POINT IS
ACHIEVED THE COOLING COIL SHALL CLOSE AND THE SUPPLY
FAN SHALL STOP.
ON A CALL FOR HEATING, THE SUPPLY FAN SHALL BE
STARTED AND ALLOWED TO ADJUST FAN SPEED BASED ON
SPACE TEMPERATURE.
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED. THE
HEATER SHALL BE STAGED TO MAINTAIN THE DISCHARGE AIR
TEMPERATURE SET POINT. ONCE THE UNOCCUPIED SPACE
TEMPER ATURE SET POINT IS ACHIEVED THE HEATER SHALL
BE DISABLED AND THE SUPPLY FAN SHALL STOP.
IF THE ROOM HUMIDITY RISES ABOVE THE UNOCCUPIED
MAXIMUM SPACE RELATIVE HUMIDITY SET POINT DURING THE
UNOCCUPIED PERIOD, PROVIDE NOTIFICATION AND THE
SUPPLY FAN SHALL BE STARTED AND ALLOWED TO ADJUST
FAN SPEED BASED ON SPACE TEMPERATURE.
11
HUMIDITY CONTROL
(UNOCCUPIED)
THE OUTDOOR AIR DAMPER SHALL REMAIN CLOSED, AND THE
STAGES OF COMPRESSION SHALL BE TURNED ON OR OFF TO
Not able to test. This sequence
needs to be reprogrammed.
MAINTAIN THE LEAVING COIL TEMPERATURE SET POINT.
ONCE THE SPACE HUMIDITY FALLS BELOW 55 % THE COOLING
COIL SHALL CLOSE AND THE SUPPLY FAN SHALL STOP.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
12
LAT Control / SPD ctrl
CLG Setpoint: LAT= 55
CLG LAT=
Supply fan VFD
HTG Setpoint: LAT =
HTG LAT =
UNOCC COOLING SP = 80
UNOCC COOLING T =
UNOCC HEATING SP = 60
UNOCC HEATING T =
UNOCC RH %= 60
UNOCC RH % _
VFD MIN speed = 65% 39 Hz
VFD MIN speed =
VFD MAX speed = 100 % 60Hz
VFD MAX speed =
A CO2 SENSOR SHALL BE MOUNTED IN THE SPACE. THE
CO2 SENSOR PROVIDES AN ANALOG SIGNAL PROPORTIONAL
TO THE CO2 CONCENTRATION. THE SENSOR SHALL BE WIRED
13
TO THE SIEMENS CONTROLLER AND PROGRAMMED TO
DEMAND CONTROL VENTILATION CONTROL THE OUTDOOR AIR DAMPER MIN./MAX POSITION.
THE LEAD AHU OUTDOOR AIR DAMPER SHALL BE ADJUSTED
TO PROVIDE THE MINIMUM OUTDOOR AIRFLOW (425 CFM)
Forced system into high CO2 mode
for testing. Set CO2 at 1200 ppm for
testing purposes.
WHEN THE CO2 SENSOR IS AT AMBIENT (400 PPM), AND THE
MAXIMUM OUTDOOR AIRFLOW (850 CFM) WHEN THE CO2
SENSOR CORRESPONDS TO 1,000 PPM.
IF THE LEAD AHU OUTDOOR AIRFLOW IS ATA MAXIMUM (850 CFM) AND THE CO2 SENSOR
CONTINUES TO INDICATE VALUES ABOVE 1,000 PPM, THE LAG AHU IS TO BE TURNED ON AND THE
LEAD AND LAG AHU OUTDOOR AIR DAMPERS ADJUSTED TO THE MINIMUM POSITION (425 CFM
EACH, 850 CFM TOTAL). IF THE CO2 SENSOR
CORRESPONDS TO 1,000 PPM OR GREATER, THE OUTDOOR AIR DAMPER OF THE LEAD AHU SHALL
BE OPENED TO THE MAXIMUM POSITION (850 CFM LEAD, 1276 CFM TOTAL).
IF THE CO2 SENSOR CONTINUES TO CORRESPOND TO 1,000 PPM OR GREATER, THE OUTDOOR
AIR DAMPER OF THE LAG AHU SHALL BE OPENED TO THE MAXIMUM POSITION AS WELL (850 CFM
EACH, 1700 CFM TOTAL).
WHEN THE CO2 SENSOR CORRESPONDS TO THE AMBIENT VALUE (400 PPM}, THE LAG AHU
OUTDOOR AIR DAMPER IS TO BE ADJUSTED TO THE MINIMUM POSITION (425 CFM). IF THE CO2
SENSOR CONTINUES TO CORRESPOND TO THE AMBIENT VALUE (400 PPM), THE LAG AHU SHALL
TURNOFF. THE LAG AHU OUTDOOR AIR DAMPER SHALL CLOSE AND THE LEAD AHU OUTDOOR
AIR DAMPER SHALL OPEN TO THE MAXIMUM POSITION (850 CFM).
CO2 Set oint= 400 PPM NORMAL; >=1000 PPM MAX
CO2 MIN =
415
CO2 Control
CO2 Control
CO2 MAX =
1200
OA DMPR status =MIN /MAX
CA DMPR status =
100
AFMS CFM = 450/850
IAFMS CFM =
825
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 08 -10
14
ALARMS
No alarms programmed. Advised
controls contractor to verify Wth
ovmer for alarm set pints.
CO2 Alarm
> +/-10 % CO2 STPT
BAS=
High RH%
RH%> 60
BAS alarm activated.
CA Alarm
10%+/- DSN MIN CA
BAS alarm activated.
Supply Fan Failure
BAS alarm
BAS alarm activated.
CA Damper failure
BAS alarm
BAS alarm activated.
RA Damper failure
BAS alarm
BAS alarm activated.
Hi h Stmotv Duct SP
BAS alarm
BAS alarm activated.
High SAT
BAS alarm
BAS alarm activated.
Low SAT
BAS alarm
BAS alarm activated.
Filter Dirty
I BAS alarm
I BAS alarm activated.
Low O/A Ventilation
I BAS alarm
I BAS alarm activated.
15
EMERGENCY SHUTDOWN SHUTDOWN
Smoke detector / AHU shutdown
vAtnessed and passed by Fire
Inspector, per owner.
(Smoke Detector)
When any one of the system duct smoke detectors is activated, the
unit shall shut down upon receiving an emergency shutdown / smoke
detection signal from the fire alarm panel.
CA Damper
CA Damper status
CA Damper status=
RA Damper
RA Damper status
RA Damper status =
SAFETY SHUTDOWN
SAFETY SHUTDOWN
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 -12 -11
Test= AHU-7 / CU-7
Step
Test Description
Acceptance Criteria
Measurement / Setpolnt
Result
Date
Test Notes
Pre Function Prereq
-TAB Complete and report provided
- BIAS point-to-point complete and
report provided
- Control program checkout complete
chk
12111/2017
Final, approved report received by
Anatom today.
n/a
Paint -to -point listing received today.
n/a
Checking programming today
Running according to
1 BMS Schedule
Scheduled Occupancy - OCCUPIED
MODE
Mon:
24 HOUR
12111/2017
UNIT RUNNING ON REMOTE
Tue:
SENSOR
Wed:
"
Thum:
"
Fri:
Sat:
Sun:
2
REMOTE SENSOR
SPACE TEMP SP =
70 F
SPACE TEMP =
70.84 F
BAS SENSOR
IOVER TEMPERATURE OF SPACE
SPACE TEMP =
71 F
3
CONDENSATE
OVERFLOW
SENSOR IN PAN
SENSOR SHUTDOWN
N/A
NO OVERFLOW SENSOR
INSTALLED IN AIR HANDLER,
CHANGE ORDER NOT ACCEPTED
PER MC
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 -12 -11
Test= EF4
step I Test Descri tion
Acceptance Criteria
Measurement/ Set olnt Result
Date Test Notes
Pre Function Prereq
-TAB Complete and report provided
- Control program checkout complete
1 CONTROL
Runs from Occupancy Sensor
OCC SENSOR = ON ON
TIMER = OFF
12/11/2017 TESTED ON WITH LIGHT
OFF WITH TIMER
2 BDD
Verify BDD closes on shutdown
BDD = closed
NOT ABLE TO VERIFY
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 -12 -11
Test= EF-2
Stop I Test Description
Acceptance Criteria
Measurement / Set olnt Result
Date Test Notes
Pre Function Prereq
-TAB Complete and report provided
- Control program checkout complete
1 CONTROL
Runs from Occupancy Sensor
OCC SENSOR = ON ON
TIMER = OFF
12/11/2017 TESTED ON WITH LIGHT
OFF WITH TIMER
2 BOD
Verify BDD closes on shutdown
BDD = closed
NOT ABLE TO VERIFY
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 -2017 -12 -11
Test-- EF3
Step I Test Descri tion
Acceptance Criteria
Measurement / Setpoint Result
Date Test Notes
Pre Function Prereq
-TAB Complete and report provided
-Control program checkout complete
1 CONTROL
Runs from Occupancy Sensor
OCC SENSOR = ON ON
TIMER = OFF
12/1112017 TESTED ON WITH LIGHT
OFF WITH TIMER
2 BDD
Verify BDD closes on shutdown
BDD = closed
NOT ABLE TO VERIFY
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 12 - 11
Test= EF-4
Step I Test Descri tion
Acceptance Criteria
Measurement / Set olnt Result
Date Test Notes
Pre Function Prereq
-TAB Complete and report provided
- Control program checkout complete
12111/2017 NEW TIMECLOCK WAS
1 CONTROL
Runs continuous w bldg schedule
BLDG = ON RUNNING
INSTALLED, LOCATED IN MECH
TIME CLOCK = OFF CONTINUOUS
ROOM #2 (ROOM 28)
2 BDD
Verify BDD closes on shutdown
BDD = closed
NOT ABLE TO VERIFY
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 -12 -11
Test-- EF-5
Stop I Test Descrl tion
Acceptance Criteria
Measumment/ Set oint Result
Date Test Notes
Pre Function Prereq
-TAB Complete and report provided
- Control program checkout complete
NEW TIMECLOCK WAS
1 CONTROL
Runs continuous w bldg schedule
BLDG = ON
12/11/2017 INSTALLED, LOCATED IN MECH
TIME CLOCK =OFF RUNNING
ROOM #2(ROOM 28)
CONTINUOUS
2 BDD
Verify BDD closes on shutdown
BDD = closed
NOT ABLE TO VERIFY
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017.12 -11
Test= EF-6
Stop I Test Description
Acceptance Criteria
Measurement / Set oint Result Date Test Notes
Pre Function Prereq
-TAB Complete and report provided
-Control program checkout complete
1 CONTROL
Runs from Occupancy Sensor
OCC SENSOR = ON 12111/2017 NOT TESTED
TIMER = OFF
2 BDD
Verify BDD closes on shutdown
BDD = closed
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 -12 -11
Test= OAD -1
Step I Test Description Acceptance Criteria
Measurement / Setpoint
Result Date
Test Notes
Pre Function Prereq -TAB Complete and report provided
1 BAROMETRIC VERIFY OPERATION
OPEN WITH AHU CALL
12/11/2017
NOT OBSERVED
DAMPER
CLOSED WAHU-OFF
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 - 12 - 11
Test-- EAH -1
—Da—te--1
Step I Test Descriptlon Acceptance Criteria
Measurement / Setpolnt
Result
Test Notes
Pre Function Prereq -TAB Complete and report provided
1 BAROMETRIC VERIFY OPERATION
OPEN WITH EF CALL
12/11/2017
NOT OBSERVED
DAMPER
CLOSED W EF-OFF
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 .2017 -12 -11
Test= PRH-1
Step Test Description Acceptance Criteria
Measurement/Setpoint Result
Date
Test Notes
Pre Function Prereq -TAB Complete and report provided
BUILDING TESTED WITH ALL
AHUs IN FULL OPEN MODE
OBSERVED OPEN GAP AROUND
BACKDRAFT DAMPER INSTALLATION
AT RELIEF HOOD.
12/11/2017
- DAMPER BLADES WERE NOT
BALANCED TO DESIGN PRESSURE.
- NEED TO REMOUNT DAMPER OR
SEAL OPENING, BALANCE DAMPER
BAROMETRIC VERIFY OPERATION
OPEN IN RELIEF SLIGHT OPEN
BLADES AND RETEST.
DAMPER
CLOSED IN NORMAL
OPERATION
BLDG PRESSURE @0.03'WG MAX
PER TAB MEASUREMENT.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 .2017 -12 -11
Test= PRH - 2
Step Test Description Acceptance Criteria
Measurement/Setpoint Result
Date
Test Notes
Pre Function Prereq -TAB Complete and report provided
BUILDING TESTED WITH ALL
AHUs IN FULL OPEN MODE
OBSERVED OPEN GAP AROUND
BACKDRAFT DAMPER INSTALLATION
AT RELIEF HOOD.
- DAMPER BLADES WERE NOT
BALANCED TO DESIGN PRESSURE.
- NEED TO REMOUNT DAMPER OR
SEAL OPENING, BALANCE DAMPER
BAROMETRIC VERIFY OPERATION
OPEN IN RELIEF SLIGHT OPEN
12/11/2017
BLADES AND RETEST.
DAMPER
CLOSED IN NORMAL
OPERATION
BLDG PRESSURE @0.03'WG MAX
PER TAB MEASUREMENT.
_
SUSPECT RA DAMPER PROB
Lucie County
sser Blvd Public Library
'AC Functional Acceptance Test
vision 1 .2017 -12 -11
PRH -3
IN FULL OPEN MODE
OBSERVED OPEN GAP AROUND
BACKDRAFT DAMPER INSTALLATION
AT RELIEF HOOD.
- DAMPER BLADES WERE NOT
BALANCED TO DESIGN PRESSURE.
- NEED TO REMOUNT DAMPER OR
SEAL OPENING, BALANCE DAMPER
BAROMETRIC VERIFY OPERATION OPEN IN RELIEF SLIGHT OPEN 12/1112017 BLADES AND RETEST.
DAMPER CLOSED IN NORMAL
OPERATION
BLDG PRESSURE @0.03'WG MAX
PER TAB MEASUREMENT.
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017.12 -11
Test= PRH-4
Step Test Description Acceptance Criteria
Measurement/Setpoint Result
Date
Test Notes
Pre Function Prereq -TAB Complete and report provided
BUILDING TESTED WITH ALL
AHUs IN FULL OPEN MODE
OBSERVED OPEN GAP AROUND
BACKDRAFT DAMPER INSTALLATION
AT RELIEF HOOD.
- DAMPER BLADES WERE NOT
BALANCED TO DESIGN PRESSURE.
- NEED TO REMOUNT DAMPER OR
SEAL OPENING, BALANCE DAMPER
BAROMETRIC VERIFY OPERATION
OPEN IN RELIEF SLIGHT OPEN
12111/2017
BLADES AND RETEST.
DAMPER
CLOSED IN NORMAL
OPERATION
BLDG PRESSURE @0.03'WG MAX
PER TAB MEASUREMENT.
St Lucie County
Rosser Blvd Pu611c Library
HVAC Functional Acceptance Test
Revision 1 -2017 -12 -11
AHU-1
Test- BMS SYSTEM POINT TO POINT LABELS
Step
Test Description
Acee Lance Crttarla
Measurement /Set oint
Result
Data
Test Notes
Pre Function Pmmq
- pom-o-porn compeean
report provided
- Control program checkout
complete
1
VFD S/S
1
12/11/2017
2
SFAN AMPS
3
VFD STATUS
1
4
VFD SPO Hz
1
5
SFAN VFD STPT
6
Return PJrTemp
1
7
ICC LAT
1
8
SATEMP
1
9
SPACE TEMP STPT
75180-72/60
10
SPACETEMP
1
11
SPACE RH STPT
60 MAX
12
SPACE RH %
1
13
SPACE TEMP STPT
75/80-72/60
14
SPACETEMP
1
15
SPACE RH STPT
60 MAX
16
SPACE RH%
1
17
SPACE TEMP STPT
75180-72/60
18
SPACETEMP
-
1
19
ISPACE RH STPT
60 MAX
20
SPACE RH %
1
21
SPACE TEMP STPT
75180-72/60
22
SPACETEMP
1
23
SPACE RH STPT
60 MAX
24
SPACE RH %
1
21
SPACE TEMP STPT
75180-72160
22
SPACETEMP
1
23
SPACE RH STPT
60 MAX
24
SPACE RH %
1
25
ELEC HTR STAGE
1
1
26
ELEC HTR STAGE
2
1
27
ELEC HTR STAGE
3
28
FILTER STATUS
1
29
OA EN BTU/LB
28
30
OA DMPR%
1
31
OAAIRFLOW
600
1
32
RA DMPR %
33
DUCT ST PR
34
RA SO SHUTDOWN
35
SA SO SHUTDOWN
36
COMP91
37
COMP 02
38
FA SHUTDOWN
SAFETY SHUTDOWN
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017.12.11
AHU-2 BMS
Test= SYSTEM POINT TO POINT LABELS
Step
Test Description
Acca'snce Criteria
Measurement/Set oint
Result
Data
Test Notes
Pre Function Prereq
BMS pom- pon compeean
report provided
_ Contrail program checkout
complete
1
VFD S/S
1
12H7/2017
1EXTRA POINT FAN PROOF
2
SFAN AMPS
3
VFD STATUS
1
4
VFO SPD Hz
ECM MOTOR NO VFD
5
SFAN VFD STPT
6
RelumAyTemp
1
7
CC LAT
1
8
SATEMP
1
9
SPACE TEMP STPT
75180-72/60
10
SPACETEMP
1
11
SPACE RH STPT
60 MAX
12
SPACE RH %
1
13
SPACE TEMP STPT
75/80-72160
14
SPACE TEMP
1
15
SPACE RH STPT
60 MAX
16
SPACE RH %
1
17
SPACE TEMP STPT
75180-72/6D
-
18
SPACE TEMP
1
19
SPACE RH STPT
60 MAX
20
SPACE RH%
1
21
SPACE TEMP STPT
75180-72/60
22
SPACE TEMP
1
23
SPACE RH STPT
60 MAX
24
SPACE RH%
1
25
ELEC HTR STAGE
1
9
26
ELEC HTR STAGE
2
0
27
ELEC HTR STAGE
3
0
28
FILTER STATUS
1
29
CA EN BTU/LB
28
30
CA DMPR %
- 1
31
OAAIRFLOW
400
1
32
RA DMPR %
1
33
DUCT ST PR
34
RA SO SHUTDOWN
35
SA SO SHUTDOWN
36
COMP#1
1
37
COMP#2
0
38
FASHUTDOWN
SAFETY SHUTDOWN
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 -12. 11
AHU4 BMS
Test= SYSTEM POINT TO POINT LABELS
Step
Test Descri Uon
Aeee ten se Criteria
Measurement/Set olnt
Result
Date
Test Notes
Pre FuncOon Prereq
pom o-pom compa Mir
report provided
- Control program checkout
complete
1
VFD S/S
1
12/112017
2
SFAN AMPS
3
VFD STATUS
1
4
VFD SPD Hz
1
5
SFAN VFD STPT
6
Retum AirTem
1
7
CC LAT
1
8
SATEMP
1
9
SPACE TEMP STPT
75/80-72/60
10
SPACETEMP
1
11
SPACE RH STPT
60 MAX
12
SPACE RH %
1
13
SPACE TEMP STPT
75180-72160
14
SPACETEMP
1
15
SPACE RH STPT
60 MAX
16
SPACE RH %
1
17
SPACE TEMP STPT-
75180-72/60
18
SPACETEMP
1
19
SPACE RH STPT
60 MAX
20
SPACE RH %
1
21
SPACE TEMP STPT
75180-72160
22
SPACETEMP
1
23
SPACE RH STPT
60 MAX
1
24
SPACE RH %
25
ELEC HTR STAGE
1
1
26
ELEC HTR STAGE
2
1
27
ELEC HTR STAGE
3
26
FILTER STATUS
1
29
CA EN BTU/LB
28
30
OADMPR%
1
31
OAAIRFLOW
700
1
32
RADMPR%
1
33
DUCT ST PR
34
RA SO SHUTDOWN
35
SA SO SHUTDOWN
36
COMP#1
1
37
COMPQ
1
38
FA SHUTDOWN
SAFETY SHUTDOWN
St Lucie County
Rosser Blvd Public Libmry
HVAC Functional Acceptance Test
Revision 1-2017-12-11
AHU4
Test= BMS SYSTEM POINT TO POINT LABELS
Step
Test Description
Acce Lance Criteria
Measurement/Sat oinl
Result
Date
Test Notes
Pre Function Prereq
polo-o-poin compee an
report provided
- Control program checkout
complete
1
VFD S/S
1
12/11/2017
2
SFAN AMPS
3
VFD STATUS
1
4
VFD SPD Hz
1
5
SFAN VFD STPT
6
ReWmAirTemp
1
7
CC LAT
1
8
SATEMP
i
9
SPACE TEMP STPT
75/80-72160
10
SPACETEMP
1
11
SPACE RH STPT
60 MAX
12
SPACE RH %
1
13
SPACE TEMP STPT
75/80-72/60
14
SPACETEMP
1
15
SPACE RH STPT
60 MAX
16
SPACE RH %
1
17
SPACE TEMP STPT
75/80-72/60
18
SPACETEMP
1
19
SPACE RH STPT
60 MAX
20
SPACE RH %
1
21
SPACE TEMP STPT
75/80-72/65
22
SPACETEMP
1
23
SPACE RH STPT
60 MAX
24
SPACE RH %
1
25
SPACE TEMP STPT
75180-72160
26
SPACETEMP
1
27
SPACE RH STPT
60 MAX
28
SPACE RH %
1
29
ELEC HTR STAGE
1
1
30
ELEC HTR STAGE
2
1
31
ELEC HTR STAGE
3
1
32
FILTER STATUS
1
33
CA EN BTU/LB
28
1
34
CA DMPR %
1
35
CA AIRFLOW
1250
1
35.5
OA TEMP
1
36
RA DMPR%
1
37
DUCT ST PR
38
RA SO SHUTDOWN
39
SA SD SHUTDOWN
40
COMP#1
1
41
COMP#2
1
42
FASHUTDOWN
SAFETY SHUTDOWN
St Lucia County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 - 2017 -12 -11
AHU-6
Test-- BMS SYSTEM POINT TO POINT LABELS
Step
Test Description
Acceptance Criteria
Measurement l Setpoint
Result
Data
Test Notes
Pre Function Prereq
-BMS point-o-pom complete an
report provided
- Control program checkout
complete
1
VFD S/S
1
12/112017
1 EXTRA POINT FAN PROOF
2
SFAN AMPS
3
VFD STATUS
1
- 4
VFD SPD Ha
1
5
SFAN VFD STPT
6
Return AjrTemp
1
7
ICC LAT
1
B
ISATEMP
1
9
SPACE TEMP STPT
75180-72/60
10
SPACE TEMP
11
SPACE RH STPT
60 MAX
12
SPACE RH %
13
SPACE TEMP STPT
75/BO-72160
14
SPACE TEMP
1
MEETING ROOM (WES
15
SPACE RH STPT
60 MAX
16
SPACE RH%
7
MEETING ROOM S
17
CO2 STPT
400/1000
18
CO2PPM
1
WESTSENSOR
19
CO2 STPT
400 / 1000
20
CO2 PPM
ELEC HTR STAGE
1
1
ELEC HTR STAGE
2
1
ELEC HTR STAGE
3
FILTER STATUS
1
CA EN BTU/LB
2B
1
CA DMPR 6
1
$30
OA AIRFLOW
425/850
1
RA DMPR %
1
DUCT ST PR
RASDSHUTDSA
SO SHUTDOWN
COMP 01COMP
02
34
iFAsHviuuWN
I SAFETY SHUTDOWN
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1-2017-12-11
AHU4i
Test= EMS SYSTEM POINT TO POINT LABELS
Step
Test Description
Aece tance Criteria
Measurement/Set pint
Result
Date
Test Notes
Pre Function Prereq
BMS pom-o-poin compee an
report provided
-Control program checkout
complete
1
VFD S/S
1
12/1120171
EXTRA POINT (FAN PROOF
2
SFAN AMPS
3
VFD STATUS
1
4
VFD SPD Hz
1
5
SFAN VFD STPT
6
Retum Air Tem
1
7
CC LAT
1
8
SATEMP
9
SPACE TEMP STPT
75180-72160
10
SPACE TEMP
1
RM1(EAST)
11
SPACE RH STPT
60 MAX
12
SPACE RH %
1
RM 1 EAST
13
SPACE TEMP STPT
751 BO-72/60
14
SPACE TEMP
15
SPACE RH STPT
60 MAX
16
SPACE RH %
15A
HALL 2 RH%
1
RM 38
169
HALL 2 TEMP
1
RM 38
16C
KITCHEN RH%
1
IRM 39
160
KITCHEN TEMP
1
RM 39
17
CO2 STPT
40011000
18
CO2 PPM
1
RM 36(EAST)
19
CO2 STPT
40011000
2D
CO2PPM
21
ELEC HTR STAGE
1
1
22
ELEC HTR STAGE
2
1
23
ELEC HTR STAGE
3
24
FILTER STATUS
1
25
CA EN BTU/LB
28
1
26
CA DMPR%
1
27
OAAIRFLOW
425/850
1
28
RA DMPR%
1
29
DUCT ST PR
30
RA SD SHUTDOWN
31
SA SO SHUTDOWN
32
COMPC7
1
33
COMP#2
1
34
FA SHUTDOWN
SAFETY SHUTDOWN
St Lucie County
Rosser Blvd Public Library
HVAC Functional Acceptance Test
Revision 1 -2017 -12 -11
AHU-7
Test- BMS SYSTEM
POINT TO POINT LABELS
Step
Test Description
Acce lance Critorla
Measurement/ Set olnt
Result
Dalc
Test Notes
Pre Function Prereq
porn-o-Pmn compeeen
report provided
- Control program checkout
complete
1
DATAROOMTEMP
1
1211712017
St. Lucie County
Rosser Blvd Public Library
Port St. Lucie, FL.
COMMISSIONING 1 DEFICIENCY LOG
These items will need to be addressed prior to Final Functional Acceptance Testing
Issue Date - 12/11/2017 Revision 1
St. Lucie County Rosser Blvd Public Library SWC Project No. 16021
I.D. #
Date
Location /
Observation / Deficiency
Response / Resolution
Date
Issue
Entered
TAG
rechecked
cleared
(Y/N)
1
12-11-17
ALL
Room cooling —heating set points need a
SYSTEMS
dead band and SA reset sequence to
prevent excessive cycling..
2
Need to program unoccupied humidity
control sequence of operation and BAS
notification.
3
System common enthalpy sensor is not
calibrated. Repair/replace.
4
Coordinate system alarm programming
with owner.
1
12-11-17
AHU-1
One (1) room sensor is not reading
correctly. Replace or repair sensor.
2
RA damper shaft and actuator needs
readjusting. Needed for proper balance of
RA/OA for the system. Verify operation of
damper.
3
There may be an issue with the operation
of compressor #1. LAT was not reacting to
he compressor activation. Verify proper
operation of compressor #1.
1
12-11-17
AHU-2
OA airflow low. Verify RA damper
operation.
1
12-11-17
AHU-3
Airfilter DP sensor not operating.
Repair/replace.
2
Low airflow on simulated economizer
cycle. RA damper shows closed on BAS.
Verify operation of RA damper.
FMS showing TROUBLE indication. Verify
operation of AFMS.
e ,
1
12-11-17
AHU-4
Found RA damper broken in place. Blades
broke away from the damper shaft.
Replace damoer and retest system,
1
12-11-17
AHU-5
RA damper is not closing upon program
command. Verify RA damper operation.
2
DA damper position indicator is not
installed on actuator. Repair/replace.
1
12-11-17
AHU-6
RA damper is not closing upon program
command. Verify RA dam er o eration.
2
OA damper position indicator is not
installed on actuator. Repair/replace.
1
12-11-17
AHU-7
No condensate overflow sensor is
installed. Recommend to install sensor to
protect room and equipment. AHU is
located above the door entrance.
1
12-11-17
PRH-1,2,3,4
All relief hoods are fitted with backdraft
damper installed in neck of hood with
observed air gap around the perimeter.
Reseat damper and/or seal air gap
opening.
2
Damper counter weights were not
balanced to design pressure as noted on
equipment schedule. Provide damper
balance for proper relief operation.