SCOPE OF WORK: ADVANCE AUTO PARTS 9507
SCANNED
BY
St. Lucie Countv
1. Install one (1) layer of 2.3" polyisocyanurate insulation board. New insulation shall be loose laid on
existing metal roof deck.
2. Install one (1) layer of 2.3" polyisocyanurate insulation board. New insulation shall be mechanically
fastened through the loose laid insulation layer and into the metal roof deck utilizing manufacturer's HD
fasteners and InvisiWeld plates.
3. Install Firestone white .060 R TPO membrane (approx. 6,552 sq.ft.) onto the new insulation. The new
membrane will be mechanically fastened according to manufacturer specifications.
4. Flash all walls, scuppers, roof top penetrations according to Firestone's 15-year warranty requirements.
CP Rankin Inc. will flash roof projections that are in place prior to the installation of roofing. Penetrations
not installed prior to the execution of this Agreement, or required after installation of roofing, shall be
considered an order for extra work, and CP Rankin Inc. shall be compensated at is customary time and
material rates for additional expense resulting from additional penetrations.
4. Install approx. 82 In.ft. of manufacturer's walk pad.