HomeMy WebLinkAboutREQUEST FOR 30 DAY POWER RELEASEPlanning & Development Services
Building & Code Regulation Division
2300 Virginia Ave
Fort Pierce, FL 34982
772-462-2165 Fax 772-462-6443
SGANNLL)
Request for 30-Day Temporary Power Releaggr
Date: / P��-t y, / St ucn}}+
Permit Number: �1, ie e C�
. • .I• ■".l L V�
THE UNDERSI GNED HEREBY REQUEST RELEASE OF ELECTRI CAL POWER TO THE ABOVE DESCRI BED
PROPERTY, FOR A PERI OD NOT TO EXCEED THI RTY (30) DAYS, FOR THE PURPOSE OF TEST[ NG SYSTEMS
AND EQUIPMENT IN PREPARATION FOR A R NAL INSPECTION. IN CONS] DERATI ON OF APPROVAL OF THE
REQUEST WE HEREBY ACKNOWLEDGE AND AGREE AS FOLLOWS
1. This temporary power release is requested for the above stated purpose only, and there will be no
occupancy of any type, other than that permitted by construction during this time period.
2. As witness by our signatures, we hereby agree to abide by all terms and conditions of this agreement,
including Building Division Policy, which is incorporated herein by reference.
3. All conditions and requirements listed in the attached document entitled "Requirements for 30 Day
Power for Testing" have been fulfilled and the premise is ready for compliance inspection.
4. All requests for an extension beyond 30 days must be made in writing to the Building Offidal stating
the reason for the request. Power may be removed from the site and/or a Stop Work Order issued if
the Final I nspection has not been approved within 30 days. A fee of $100.00 will be required to lift
the Stop Work Order.
WE HEREBY RELEASE AND AGREE TO HOLD HARMLESS, ST. LUCI E COUNTY, AND THE] R EMPLOYEES FROM
ALL LI ABI LI TI ES AND CLAI MS OF ANY TYPE OF NATURE WHI CH MAY ARI SE NOW OR I N THE FUTURE OUT
OF THI S TRANSACT] ON, I NCLUDI NG ANY DAMAGE WHI CH MAY BE I NCURRED DUE TO THE
DI SOONN 10 ECTRI CAL POWER I N THE EVENT OF VI OLATI ON OF THI S AGREEMENT.
ZZI T-2 l,—� — / /
SIGNATURE
DATE]l /
y/(D (ig
DATE
St. Lucie County
Building and Zoning Department
Requirements for 30 Day Power for Testing
I. Form entitled "Request for 30-Day Temporary Power Release' must be fully executed and posted in
the Building Department record files prior to inspection.
II. Inspection Requirements:
1. Address numbers shall be posted per county Ord. No. 7.05.09.
2. All entrances, exits, windows and garage doors must be lockable.
3. All circuits on exterior shall be terminated in a box with weatherproof cover. The same applies
to a disconnect. If circuits are at or above 7' 6' from grade they may be capped with wire nuts
and taped.
4. All breakers must be installed. Any blank space must be closed by a breaker or approved filler
plates.
5. Interior Wiring: All receptacles, light fixtures and fans must be trimmed. Any fixture below
7' 6" from the fl oor or mezzani ne that i s not aver I abl a at the ti me of i nspecti on must have an
Inviso plate installed. Fixtures at or above that height may be capped with wire nuts and taped.
6. All smoke detectors must be installed.
7. Kitchen cabinets must be installed; any exception for special conditions or circumstances must
have an approval prior to scheduled inspection.
8. Sewer and water connections must be complete. Only well pumps are excluded from this
requirement.
9. Exterior construction must be complete and weather tight, including stucco, siding, roof and
soffit.
10. Permit work shall be substantially completed except for back orders, paint on exterior, carpet
and/or floor covering, pumps, air conditioners and driveway.