HomeMy WebLinkAboutMISC EMAILDebra Zampetti
From: Netz, Harrison <NetzH@bv.com> 6GANNED
Sent: Tuesday, March 28, 2017 10:00 AM Sl. LUC e COUf1ty
BY
To: Debra Zampetti
Subject: RE: Construction Permits Required for Utility Scale Solar Generation Facility
Hey Debra,
We are looking to submit our Temporary Electrical Permit application by the end of the week. I was wondering, roughly
how long does it take to turn the application around and have a permit in hand? I'm just trying to plan my trailer
mobilization accordingly.
Thank you,
Harrison Netz, E.I.T. ( Project Coordinator, Construction & Procurement
Black & Veatch 111401 Lamar Avenue, Overland Park, KS 66211
+1913-458-9419 P 1 +1913-458-2934 F I NetzH@BV.com
Building a World of Difference.®
Please consider the environment before printing my email
Please note that the information and attachments in this email are intended for the exclusive use of the addressee and may contain confidential or privileged
information. Ifyou are not the intended recipient, please do not forward, copy or print the message or its attachments. Notify me at the above address, and
delete this message. and any attachments. Thank you.
From: Debra Zampetti [mailto:ZampettiD@stlucieco.org]
Sent: Tuesday, March 14, 2017 7:53 AM
To: Netz, Harrison
Subject: RE: Construction Permits Required for Utility Scale Solar Generation Facility
Harrison,
Since the fence is not an over the counter permit, you will need to come in person. We are working on electronic
submittals, but we have a long way to go 1
Let me now if you have any other questions.
Kind Regards,
Debra Zampetti
Zoning & Permitting Supervisor
Building & Code Regulation
2300 Virginia Ave., Suite 201
Fort Pierce, FL 34982
(772) 462-1558- --- - — - -
(772) 462-1578 (fax)
How are we doing? Submit your feedback to
Monica Graziani, Mgr. at arazionim@stlucieco.ora
From: Netz, Harrison [mailto:NetzH@bv.coml
Sent: Monday, March 13, 2017 4:17 PM
To: Debra Zampetti <ZampettiD@stlucieco.org>
Subject: RE: Construction Permits Required for Utility Scale Solar Generation Facility
Hey Debra,
Thank you for resending that email as I hadn't received it. I will get working on the permits you have listed below. I
appreciated you taking the time to speak with your building official on these permits. You have been a tremendous
help!
Do you need me to bring these in in person, or can I simply email them or submit them online somehow?
Thank you,
Harrison Netz, E.I.T. I Project Coordinator, Construction & Procurement
Black & Veatch 111401 Lamar Avenue, Overland Park, KS 66211
+1913-458-9419 P 1 +1913-458-2934 F I NetzH@BV.com
Building a World of Difference.®
Please consider the environment before printing my email
Please note that the information and attachments in this email are intended for the exclusive use of the addressee and may contain confidential or privileged
information. If you are not the intended recipient, please do not forward, copy or print the message or its attachments. Notify me at the above address, and
delete this message and any attachments. Thank you.
From: Debra Zampetti[mailto:ZampettiDColst!ucieco.org]
Sent: Monday, March 13, 2017 8:25 AM
To: Netz, Harrison
Subject: FW: Construction Permits Required for Utility Scale Solar Generation Facility
Harrison,
Our email google system has been down. Many emails have not been delivered. I did have something to add: the
temp bulk storage of fuel need to contact DEP Dept of Health in W. Palm Beach in addition to Fire Dept.
1 am resending, hope this gets to you.
Happy Monday
From: Debra Zampetti
Sent: Friday, March 10, 2017 3:57 PM
To:'Netz, Harrison' <NetzH@bv.com>
Subject: RE: Construction Permits Required for Utility Scale Solar Generation Facility
Harrison,
I talked with the Building Official and you do not need a permit for the office trailers since they are for
construction workers.
You will need to get ar lectrica-I�per_mi`.
The temp Bulk Fuel storage, you need to contact DEP as well as fire, but don't need a permit from us.
You need to get a commercial,--., permit_
The burn permit— Division of Forestry.
I believe you have already worked on the other permits.
Let me know if you have any other questions.
Have a great weekend,
Debra Zampetti
Zoning & Permitting Supervisor
Building & Code Regulation
2300 Virginia Ave., Suite 201
Fort Pierce, FL 34982
(772)462-1558
(772) 462-1578 (fax)
How are we doing? Submit your feedback to
Monica Graziani, Mgr. at 4razianim0stlucfeco.ora
From: Netz, Harrison imailto:NetzH@bv.coml
Sent: Monday, March 06, 2017 2:08 PM
To: Debra Zampetti <Za_mpettiD@stlucieco.ore>
Subject: RE: Construction Permits Required for Utility Scale Solar Generation Facility
Hey Debra,
This helped a lot. Thank you!
I have been able to round up some of the permits that we will need off of your website per your suggestions
below. However, I am still having trouble locating a couple. I have commented below, in Red, on each item. Do you
think you would be able to send me a PDF or a link to the document?
Thank you in advance,
Harrison Netz, E.I.T. ( Project Coordinator, Construction & Procurement
Black & Veatch 111401 Lamar Avenue, Overland Park, KS 66211
+1913-458-9419 P 1 +1913-458-2934 F I NetzH@BV.com
Building a World of Difference
Please consider the environment before printing my email
Please note thatthe information and attachments in this email are intended for the exclusive use of the addressee and may contain confidential or privileged
information. Ifyou are not the intended recipient, please do not forward, copy or print the message or its attachments. Notify me atthe above address, and
delete this message and any attachments. Thank you.
From: Debra Zampetti [mailto:ZamoettiD@stlucieco.org
Sent: Monday, March 06, 2017 12:20 PM
To: Netz, Harrison
Subject: RE: Construction Permits Required for Utility Scale Solar Generation Facility
Hello Harrison,
Many of the permits listed below are not directly related to the transmission of electricity. I am glad you are breaking it
down.
Temp Office trailer, need permit. — Cannot locate permit.
Temp Power —For what? Trailer yes. —Yes, this is for the trailers. Cannot locate permit.
Temp fuel Storage Permit —for what? — For diesel and gas for construction equipment. Found permit with County Fire
Dept
Fence permit- yes — Cannot locate permit.
Burn Permit (not building code). Fire Dept/Fire Marshall — Located information.
Dewatering (not building code). DEP — Located information.
Right of way (not building code). Yes, we have applications in Permitting. — Located information.
Vegetation removal (not building Code). Yes, we have applications in Permitting. — Located information.
Let me know if you have any additional questions,
Debra Zampetti
Zoning & Permitting Supervisor
Building & Code Regulation
2300 Virginia Ave., Suite 201
Fort Pierce, FL 34982
(772)462-1558
(772) 462-1578 (fax)
How are we doing? Submit yourfeedback to
Monica Graziani, Mgr. at grazianim0stluciem.org
From: Netz, Harrison fmailto:NetzH@bv.coml
Sent: Friday, March 03, 2017 4:53 PM
To: Debra Zampetti <ZampettiD@stlucieco.org>
Subject: RE: Construction Permits Required for Utility Scale Solar Generation Facility
Hey Debra,
Thank you for your quick response to my email, it is much appreciated. I had identified the following possible permits
from your website as well as past projects. Can you just confirm that none of these permits will be needed due to
Florida Building Code for St. Lucie County?
TemporaryConstruction Facilities Permit (office trailers)
• Temporary Power Permit
• Temporary Bulk Fuel Storage Permit (gasoline and diesel)
• Permanent site perimeter chain -link fence
• Dewatering Permits (during construction)
• Burn Permits
• Right of Way Permit
• Vegetation Removal Permit
Thank you again for your quick response. If you would like to discuss, please feel free to contact me at 913-458-9419.
Regards,
Harrison Netz, E.I.T. [ Project Coordinator, Construction & Procurement
Black & Veatch 111401 Lamar Avenue, Overland Park, KS 66211
+1 913-458-9419 P 1 +1913-458-2934 F I NetzH@BV.com
Building a World of Difference.®
Please consider the environment before printing my email
Please note that the information and attachments in this email are intended for the exclusive use of the addressee and may contain confidential or privileged
information. Ifyou are not the intended recipient, please do not forward, copy or print the message or its attachments. Notify me at the above address, and
delete this message and any attachments. Thank you.
From: Debra Zampetti[mailto:ZampettiD(a)stlucieco.org]
Sent: Friday, March 03, 2017 1:28 PM
To: Netz, Harrison
Subject: FW: Construction Permits Required for Utility Scale Solar Generation Facility
Hello Mr. Netz:
The project you describe below appears to fall within an exemption in the Florida Building Code, 102.2 (f) those
structures or facilities of electric utilities, as defined in Section 366.02, FS, which are directly involved in the
transmission, generations or distribution of electricity.
No building permits are needed from us.
Let me know if you have any questions.
Debra Zampetti
Zoning & Permitting Supervisor
Building & Code Regulation
2300 Virginia Ave., Suite 201
Fort Pierce, FL 34982
(772) 462-1558
(772) 462-1578 (fax)
How are we doing? Submit your feedback to
Monica Graziani, Mgr. at arazianim@stlucieco.ora
From: Joe Cicio
Sent: Friday, March 03, 20171:31 PM
To: Debra Zampetti <ZampettiD@stlucieco.ore>
Subject: RE: C&nst—ruction Permits Required for Utility Scale Solar Generation Facility
As per FBC 102.2 [ note f ] these facilities are exempt from the FBC Guidelines / also as per FS 366.02 FPL would not be a
Co -Op guided by the Rural Electric Co-operative law or owned by the community
Thanks
pogbi X. etch
Plans Examiner II
Standard Building Inspector
Building Plans Examiner
One and Two Family Dwelling Inspector
One and Two Family Plans Examiner
St 1 1AZ; I& C V4149 pLawwi," a*L& DeVtt4r4V4,0_4-Set-VUt
From: Debra Zampetti
Sent: Friday, March 03, 201712:37 PM
To: Joe Cicio <cicioi@stlucieco.ore>
Subject: FW: Construction Permits Required for Utility Scale Solar Generation Facility
Anything special needed for submittal requirements for solar powered electric generation facility? See below.
Debra Zampetti
Zoning & Permitting Supervisor
Building & Code Regulation
2300 Virginia Ave., Suite 201
Fort Pierce, FL 34982
(772)462-1558
(772) 462-1578 (fax)
How are we doing? Submit your feedback to
Monica Groziani, Mgr. at arazianim0stlucieco.ora
From: Netz, Harrison (mailto:NetzH@bv.coml
Sent: Friday, March 03, 2017 12:04 PM
To: Debra Zampetti <ZampettiDC@stlucieco.ors>
Subject: Construction Permits Required for Utility Scale Solar Generation Facility
Good afternoon Debra,
Black & Veatch has been awarded a contract to engineer, procure, and construct a utility -scale solar powered electric
generation facility for Florida Power & Light Company (FPL) in St. Lucie County. The facility is known as the FPL
Loggerhead Solar Energy Center. As the principle contractor for the site, Black & Veatch would like to kindly request St.
Lucie County's assistance in determining what permits will be required for the construction of the abovementioned
Facility. -
I understand that the question is broad at this point, but high-level requirements would be a very helpful starting point
to determine site -specific permits Black & Veatch many need. Please feel free to contact me for any questions you may
have.
Regards,
Harrison Netz, E.I.T. I Project Coordinator, Construction & Procurement
Black & Veatch 111401 Lamar Avenue, Overland Park, KS 66211
+1913-458-9419 P 1 +1913-458-2934 F I NetzHCo)BV.com
Building a World of Difference.®
Please consider the environment before printing my email
Please note that the information and attachments in this email are intended for the exclusive use of the addressee and may contain confidential or privileged
information. If you are not the intended recipient, please do not Forward, copy or print the message or its attachments. Notify me at the above address, and
delete this message and any attachments. Thinkyou.
Please Note: Florida has very broad public records laws. Most written communications to or from County officials regarding County business are public records
available to the public and media upon request. It is the policy of St. Lucie County that all County records shall be open for personal inspection, examination and /
or copying. Your e-mail communications will be subject to public disclosure unless an exemption applies to the communication. If you received this email in error,
please notify the sender by reply e-mail and delete all materials from all computers.
Please Note: Florida has very broad public records laws. Most written communications to or from County officials regarding County business are public records
available to the public and media upon request. It is the policy of St. Lucie County that all County records shall be open for personal inspection, examination and /
or copying. Your e-mail communications will be subject to public disclosure unless an exemption applies to the communication. If you received this email in error,
please notify the sender by reply e-mail and delete all materials from all computers.
Please Note: Florida has very broad public records laws. Most written communications to or from County officials regarding County business are public records
available to the public and media upon request. It is the policy of St. Lucie County that all County records shall be open for personal inspection, examination and /
or copying. Your e-mail communications will be subject to public disclosure unless an exemption applies to the communication. If you received this email in error,
please notify the sender by reply e-mail and delete all materials from all computers.
Please Note: Florida has very broad public records laws. Most written communications to or from County officials regarding County business are public records
available to the public and media upon request. It is the policy of St. Lucie County that all County records shall be open for personal inspection, examination and /
or copying. Your e-mail communications will be subject to public disclosure unless an exemption applies to the communication. If you received this email in error,
please notify the sender by reply e-mail and delete all materials from all computers.
Please Note: Florida has very broad public records laws. Most written communications to or from County officials regarding County business are public records
available to the public and media upon request. It is the policy of St. Lucie County that all County records shall be open for personal inspection, examination and /
or copying. Your e-mail communications will be subject to public disclosure unless an exemption applies to the communication. If you received this email in error,
please notify the sender by reply e-mail and delete all materials from all computers.
Please Note: Florida has very broad public records laws. Most written communications to or from County officials regarding County business are public records
available to the public and media upon request. It is the policy of St. Lucie County that all County records shall be open for personal inspection, examination and /
or copying. Your e-mail communications will be subject to public disclosure unless an exemption applies to the communication. If you received this email in error,
please notify the sender by reply e-mail and delete all materials from all computers.
Debra Zampetti
From: Hendricks, Kim S. <HendricksKS@overlandcontracting.com>
Sent: Wednesday, April 12, 2017 2:27 PM
To: Debra Zampetti; McFarlane, Lindale
Subject: RE: Building Permit Application for Temporary Power at FPL Loggerhead Solar Energy
Center
Debra,
Here is my contact information.
KIM HENDRICKS
PROCUREMENT REPRESENTATIVE
OVERLAND CONTRACTING INC.
600 North Greenfield Parka+•ay I Garner, NC 27529
P/F (919) 329-9461
E HendricksKS(o')OverlandContractinz.com
W OverlanclContracting.com
THINK. PLAN. ACC. ZERO INJURIES TODAY.
BUILDING VITAL INFRASTRUCTURE
From: Debra Zampetti [mailto:ZampettiD@stlucieco.org]
Sent: Wednesday, April 12, 2017 10:37 AM
To: McFarlane, Lindale
Subject: RE: Building Permit Application for Temporary Power at FPL Loggerhead Solar Energy Center
Hello Lindale,
We can do credit card. I haven't received originals yet, but I can start with the email copies.
Debra Zampetti
Zoning & Permitting Supervisor
Building & Code Regulation
2300 Virginia Ave., Suite 201
Fort Pierce, FL 34982
(772)462-1558
(772) 462-1578 (fax)
How are we doing? Submit your feedback to
Monica Graziani, Mgr. at grazianim@stlucleco.ora
From: McFarlane, Lindale [mailto:McFarlaneL@bv.coml
Sent: Tuesday, April 11, 2017 4:22 PM