HomeMy WebLinkAboutCONSTRUCTION OBSERVATION REPORTM L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37 ^ Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772) 569-4041 www.mleneineerineinc.com SCANNED BY St. Lucie County Project No. 17-122 Client: Architect: Contractor: SLC Bldg Dept File Report No. 3 Scott Deal, M13G Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File CONSTRUCTION OBSERVATION REPORT MAVERICK BOAT GROUP 4551 ST LUCIE BLVD. FORT PIERCE, FLORIDA 34946 SLC BUILDING PERMIT NO 1801-0678 PROJECT NAME: Maverick Boat Group DATE: June 26, 2018 CLIENT: Maverick Boat Group LOCATION: Vero Beach, Florida CONTRACTOR: R F Concrete PROJECT MGR: Jeremy Foulks INSPECTED BY: Mike Lue WEATHER: Sunny, +/- 90 degrees Partial inspection of the pre-engineered metal building framing. KSM has completed the testing of the bolt tensioning and welds. A report will be submitted when final. Kirby Building Systems provided an optional welded connection detail of the channel to the rigid columns or bolts. (See attached) OBSERVATIONS: • All metal building components are in place, which include the rigid frames, roof purlins, wall girts, flange braces and diagonal roof bracing and metal panel connections. • All column anchor bolts were found to have nuts and washers in place, and the loose nut at column G34 was corrected. • The connections of the channel to the top of the masonry walls were partially corrected. • The majority of channel girts have been welded to the steel columns. There are some connections that were bolted where the bolt holes are aligned. • There are some channel to column connections not completed and remains to be addressed. Col J23, one side bolt not in channel or welded. Col GI, G35, JI8 & J24 no bolts in the channel to channel connections at corners. • Channel girls to doorjambs at OH doors not connected. • The number of crane rails and lengths have been reduced from the permitted documents as directed by Owner. RECOMMENDATIONS: • Contractor to recheck and correct the channel connections to the top of the masonry walls and rigid frames. • Re -inspect when completed. Page 1 of 2 M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37' Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772) 569-4041 www mlengineerinoinc com Project No. 17-122 Client: Architect: Contractor: SLC Bldg Dept File Report No. 3 Scott Deal, MBG Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File Pic 1 Col J23 One end of channel is welded and the other is bolted. Bolt is not in the channel only in column flange. Provide weld connection at both sides. Pic 2 View looking down on top of channels at building comer. There are no bolts connecting the ends of the channels. Pic 3 Channel girls to ORD jambs to be connected, similar to all other wall girts. Page 2 of 2 FIELD FIX FOR WIND CHANNEL SUPPORTING MASONRY WALL NOT BEING BOLTED TO COLUMNS. NOTES: 1. (2) WELDS ARE REQUIRED AT EACH CHANNEL TO COLUMN CONNECTION AT SHOWN IN THE DETAILS BELOW. 2" OF HORIZONTAL WELD ACROSS TOP OF CHANNEL FLANGE 2" OF VERTICAL WELD DOWN THE SIDE OF CHANNEL FLANGE 2. ALL WELDS MUST BE PERFORMED BY AN AWS CERTIFIED WELDER USING MINIMUM E70XX ELECTRODES. TYPICAL F AT TOP OF CNANNNL PLAN06 TYPICAL WBLO OONN TM 6I08 OF CNANNSL PL = T• W W t mlI _WINO CNANNBL BITTING ON NABOMY WALL SECTION A -A MAVERICK BOAT GROUP FORT PIERCE, FL KIRBY BUILDING SYSTEMS 17BOI75A M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 3711 Avenue SCANNED Vero Beach, Florida 32960 Phone: (772) 569-1257 BY Fax: (772) 569-4041 St. Lucie Countv www. mlengineerin ginc.com Project No. 17-122 Client: Architect: Contractor: SLC Bldg Dept File Report No. 2 Scott Deal, MBG Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File CONSTRUCTION OBSERVATION REPORT MAVERICK BOAT GROUP 4551 ST LUCIE BLVD. FORT PIERCE, FLORIDA 34946 SLC BUILDING PERMIT NO 1801-0678 PROJECT NAME: Maverick Boat Group DATE: May 30, 2018 CLIENT: Maverick Boat Group LOCATION: Vero Beach, Florida CONTRACTOR: R F Concrete PROJECT MGR: Jeremy Foulks INSPECTED BY: Mike Lue WEATHER: Overcast , rain Partial inspection of the pre-engineered metal building framing . Column grid lines G&J from 1-35 This area was inspected first because the interior framing is in process and when completed will conceal much of the metal building components. KSM was on site in the process of verifying the bolt tensions at the rigid frame connections. OBSERVATIONS: • All metal building components at this area are in place, which include but are not limited to the rigid frames, roof purlins, wall girts, flange braces and diagonal roof bracing. • The fire rated metal stud wall above the masonry wall up to the underside of the metal roof deck is in place along line G from lines 18 to 24. All column anchor bolts were found to have nuts and washers in place, with the exception of Column G34 which had a loose nut at one of the anchor bolts. Some loose bolts were found at the channel girt to the top of the masonry walls. The steel channel girts at the top of the masonry walls are not bolted to the columns. RECOMMENDATIONS: • Contractor to recheck and correct the channel connections to the top of the masonry walls and rigid frames. Tighten the loose nut at the anchor bolt at column G34. Re -inspect when completed. ,t'2121e1jo.ry �` NSHONy '•.. o?L Page 1 of 3 M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 3711 Avenue Vero Beach, Florida 32960 Phone: (772)569-1257 Fax: (772)569-4041 www.mlen2ineeringine.com Project No. 17-122 Client: Architect: Contractor: SLC Bldg Dept File Report No. 2 Scott Deal, MBG Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File Pic I View looking west from column line 25 between column lines G & J. View looking west from column line 23 between column lines G & J. Page 2 of 3 . . , M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 371 Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772)569-4041 www.mlengincerin.gine.com Project No. 17-122 Client: Architect: Contractor: SLC Bldg Dept File Report No. 2 Scott Deal, MBG Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File Page 3 of 3 M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37' Avenue Vero Beach, Florida 32960 Phone: (772)569-1257 Fax: (772)569-4041 www.mlenginecringinc.com Project No. 17-122 Client: Architect: Contractor: SLC Bldg Dept File Report No. 4 Scott Deal, MBG Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File CONSTRUCTION OBSERVATION REPORT MAVERICK BOAT GROUP 4551 ST LUCIE BLVD. FORT PIERCE, FLORIDA 34946 SLC BUILDING PERMIT NO 1801-0678 PROJECT NAME: Maverick Boat Group DATE: July 17, 2018 CLIENT: Maverick Boat Group LOCATION: Vero Beach, Florida CONTRACTOR: R F Concrete PROJECT MGR: Jeremy Foulks INSPECTED BY: Mike Lue WEAT14ER: Sunny, +/- 95 degrees pre-engineered KSM has completed the testing of the bolt tensioning, inspection of welds and other connections. See attached certified report dated July 12, 2018 OBSERVATIONS: • All metal building components are in place, which include the rigid frames, roof purlins, wall girts, flange braces and diagonal roof and wall bracing and metal panel connections. • All column anchor bolts, nuts and washers are in place. • The channel connections at the top of the masonry walls to the rigid frames, door jambs and at comers have been corrected. Roof and Wall Sheathing • The standing seam roof panels have been installed as indicated per the NOA with clips at each purlin. • The wall panels have been installed with self drilling screws to the wall girls and framing as indicated on sheet D4 of 5 of the Kirby Metal Building plans Doors and windows • All OHD, swing doors and windows have been installed as per the permit documents Based our observations and the certification from KSM Engineering and testing, it's our opinion the structural components of the pre-engineered building have been installed in substantial accordance with the design and permitted documents. Encl. KSM Certification dated July 12, 2018 Page 1 of 3 M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37' Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772)569-4041 www.mlenginecringinc.com Project No.17-122 Client: Architect: Contractor: SLC Bldg Dept File Report No. 4 Scott Deal, MBG Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File Pic 1 Typical C8 channel to channel bolted connection at comers with masonry walls. Pic 2 View looking down on top of a channel clip connection to steel overhead doorjamb. Clips were welded to doorjamb and screwed to channel Page 2 of 3 M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37" Avenue Vero Beach, Florida 32960 Phone: (772)569-1257 Fax: (772)569-4041 www.mlengineerin ginc.com Project No. 17-122 Client: Architect: Contractor: SLC Bldg Dept File Report No. 4 Scott Deal, MBG Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File Pic 4 Smaller OHD steel jamb assemblies were screwed to the steel jambs and are acceptable Pic 5 Roof Panel Attachment Standing seam metal roof clips at each purlin as plan Pic 6 Wall Sheathing Attachment Wall panels were screwed to purlins as indicated on sheet Page 3 of 3 111�iYi K'ELLER,.SCHLEICHERA MacWILLIAM ENGINEERING AND TESTING, INC-. MARTIN (772) 337-7755 p O. BOX 78-1377 SEBASTIAN- FL 32978-1377 SEBASTIAN (772) 589-a712 PALM BEACH (561) 845-7445 ' ' MELBouF NE (321) 768-8488 FAX '(Sr1) 645-8876 www.ksmengineedng:net ST. LUGIE,(772) 228.9 A E-Mail: KSM®KSMENGINEERING.NET CA: 5693 FAX:(772) 589-6469 July 12, 2018 RF Concrete Construction, Inc. j P. O. Box 650789 Vero Beach, FL 32965 Re: Maverick Boat 131,000 SF Steel Building 4561 St. Lucie Boulevard Ft. Pierce, Florida Permit #: 1801-0678 KSM #: 162366-11 insp Dear Sir: As requested, we have re -inspected the primary structural steel bolted connections, that were found to be loose and the block wall top plate which was not attached to the steel columns during our May 23, 30 and 31,12018 inspections at the referenced project. We also inspected the monorail support bracket attachment to the steel frame of the building for the proposed monorail beam (by others). Based on our June 21, and July 12, 2018 inspections, this letter shall serve as confirmation that the primary structural steel bolted and welded connections, steel framing and wind bracing was installed in accordance to the structural drawings excluding the monorail beam . If you have any questions, please feel free to contact the office. Ronald G. Keller, P.E.:,37293 /.SI Lic, Nosh 860 / Julie E. Keller. P.E.: 68366 M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37h Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772) 569-4041 www.mlengineeringine.com Project No. 17-122 Report No. 4 Client: Scott Deal, MBG Jim Leffew, MBG Architect: John Brenner, Brenner & Assoc. Contractor: Jeremy Foulks, BF Concrete SLC Bldg Dept Mr. Joe Cicio, SLC Bldg. Dept. File File CONSTRUCTION OBSERVATION REPORT MAVERICK BOAT GROUP 4551 ST LUCIE BLVD. FORT PIERCE, FLORIDA 34946 SLC BUILDING PERMIT NO 1801-0678 PROJECT NAME: Maverick Boat Group CLIENT: Maverick Boat Group CONTRACTOR: R F Concrete INSPECTED BY: Mike Lue Final inspection of the pre-engineered metal building framing. DATE: LOCATION: PROJECT MGR: WEATHER: July 17, 2018 Vero Beach, Florida Jeremy Foulks Sunnv. +/- 95 degree KSM has completed the testing of the bolt tensioning, inspection of welds and other connections. See attached certified report dated July 12, 2018 OBSERVATIONS: • All metal building components are in place, which include the rigid frames, roof purlins, wall girts, flange braces and diagonal roof and wall bracing and metal panel connections. • All column anchor bolts, nuts and washers are in place. • The channel connections at the top of the masonry walls to the rigid frames, doorjambs and at corners have been corrected. Roof and Wall Sheathing • The standing seam roof panels have been installed as indicated per the NOA with clips at each purlin. • The wall panels have been installed with self drilling screws to the wall girts and framing as indicated on sheet D4 of 5 of the Kirby Metal Building plans Doors and windows • All OHD, swing doors and windows have been installed as per the permit documents Based our observations and the certification from KSM Engineering and testing, it's our opinion the structural components of the pre-engineered building have been installed in substantial accordance with the design and permitted documents. r�.•�•�•r,c OR Encl. KSM Certification dated July 12, 2018 I JUL 19 2018 PerMittin•epa I Page 1 of 3 ., M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 37' Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772) 569-4041 w v.mleneineerineinc.com Project No. 17-122 Client: Architect: Contractor: SLC Bldg Dept File Report No. 4 Scott Deal, MBG Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File Typical CS channel to channel bolted connection at corners with masonry walls. View looking down on top of a channel clip connection to steel overhead doorjamb. Clips were welded to doorjamb and screwed to channel Pic 3 The larger OHD steel anglejamb assemblies were plug welded to the steel jambs and are acceptable Page 2 of 3 M L Engineering Inc. Consulting Engineers Threshold Inspector 2030 371h Avenue Vero Beach, Florida 32960 Phone: (772) 569-1257 Fax: (772) 569-4041 www.mlemineeringinc.com eineeringinc.com Project No. 17-122 Client: Architect: Contractor: SLC Bldg Dept File . Report No. 4 Scott Deal, MBG Jim Leffew, MBG John Brenner, Brenner & Assoc. Jeremy Foulks, RF Concrete Mr. Joe Cicio, SLC Bldg. Dept. File Pic 4 Smaller OHD steel jamb assemblies were screwed to the steel jambs and are acceptable Pic 5 Roof Panel Attachment Standing seam metal roof clips at each purlin as plan Pic 6 Wall Sheathing Attachment Wall panels were screwed to purlins as indicated on sheet Page 3 of 3 . 1 l .. ' IWO i11i.7jYi KELLER, S.CH;LEICHER &, MacWILLIAM ENGINEERING. AND TESTING, INC: MARTIN (772) 337:7755 RO. BOX 78-1377, SEBASTIAN, FL 32978-1377 SEeASTlM(772) 589-0712 PALM BEACH (561) 845-7445 wwwAsmengineering.net MELBOURNE (321) 768-8488 FAX (561) 845-8876 E-Mail:KSM®KSMENGINEERING.NET S . LUCIE (772) 229:9093 C.A.: 5693' FAX (772) 589-64.69 July 12, 2018 s RF Concrete Construction, Inc. P. O. Box 650789 Vero Beach, FL 32965 Re: Maverick Boat 131,000 SF Steel Building 4661 St. Lucie Boulevard Ft. Pierce, Florida Permit #: 1801-0678 KSM #: 162366-11insp Dear Sir: As requested, we have re -inspected the primary structural steel bolted connections, that were found to be loose and the block wall top plate which was not attached to the steel columns during our May 23, 30 and 31,> 2018 inspections at the referenced project. We also inspected the monorail support bracket attachment to the steel frame of the building for the proposed monorail beam (by others). Based on our June 21, and July 12, 2018 inspections, this letter shall serve as confirmation that the primary structural steel bolted and welded steel framing and wind bracing was installed in accordance to drawings excluding the monorail beam . If you have any questions, please feel free to contact the office. I connections, the structural Ronald G. Keller, P.E..'31293 / SI Lic. No.: 860' / Julie.E.•Keller. P.E.:.68366