HomeMy WebLinkAboutAgenda 07.22.2025S�,Il m
EROSION DISTRICT
AGENDA
ST. LUCIE COUNTY
Regular Meeting
Tuesday, July 22, 2025
9:01 AM
St. Lucie County Commission Chambers
2300 Virginia Avenue
3rd Floor of Roger Poitras Building
Fort Pierce, FL 34982
BOARD MEMBERS
District No. 1, Chair
JAMES CLASBY
District No. 2, Vice -Chair
LARRY LEET
District No. 3
ERIN LOWRY
District No. 4
JAMIE FOWLER
District No. 5
CATHY TOWNSEND
Mission Statement
Committed To Service, Focused On Our Future, Grounded By Tradition
*Final on 7/17
Page 1 of 47
Regular Meeting Tuesday, July 22, 2025 9:01 AM
WELCOME
All meetings are televised.
All meetings provided with wireless internet access for public convenience.
Please turn off all cell phones and pagers prior to entering the commission chambers.
Please mute the volume on all laptops and PDAs while in use in the commission chambers.
GENERAL RULES AND PROCEDURES —Attached is the agenda, which will determine the order of business conducted at today's Board
meeting.
INVOCATION -PLEDGE —To bring order and decorum to its meeting, the Board begins its meetings with an invocation followed by the
Pledge of Allegiance. Participation is voluntary.
CONSENT AGENDA — These items are considered routine and are enacted by one motion. There will be no separate discussion of
these items unless a Commissioner so requests.
REGULAR AGENDA — Proclamations, Presentations, Public Hearings, and Department requests are items, which the Commission will
discuss individually, usually in the order listed on the agenda.
PUBLIC HEARINGS — These items are usually heard on the first Tuesdays at 6 p.m. or as soon thereafter as possible. However, if a
public hearing is scheduled for a meeting on the third Tuesday, which begins at 9 a.m., then public hearings will be heard at 9
a.m. or as soon thereafter as possible. These time designations are intended to indicate that an item will not be addressed prior
to the listed time. The Chair will open each public hearing and asks anyone wishing to speak to come forward, one at a time.
Comments will be limited to five minutes, and must be pertinent to the agenda item being considered by the Board.
As a general rule, when issues are scheduled before the Commission under department request or public hearing, the order
of presentation is: (1) County staff presents the details of the Board item (2) Commissioners comment (3) if a public hearing, the
Chair will ask for public comment, (4) further discussion and action by the Board.
ADDRESSING THE COMMISSION — Please state your name and address, speaking clearly into the microphone. If you have backup
material, please have eight copies ready for distribution.
NON -AGENDA ITEMS — These items are presented by an individual Commissioner or staff as necessary at the conclusion of the
printed agenda.
PUBLIC COMMENT — Time is allotted at the beginning of each meeting for general public comment. Please limit comments to three
minutes. Comments may pertain to any matter related to the Board's duties as the County's governing body. Comments in support or
opposition to candidates for public office are not pertinent to the Board's duties. This includes any speaker identifying himself or herself as a
candidate for public office.
DECORUM — Please be respectful of others' opinions.
MEETINGS — All Board meetings are open to the public and are held on the first Tuesdays of each month at 6 p.m. and on the third
Tuesdays at 9 a.m., unless otherwise advertised. Meetings are held in the County Commission Chambers in the Roger Poitras
Administration Annex at 2300 Virginia Ave., Fort Pierce, Fla. 34982. The Board schedules additional workshops throughout the year
necessary to accomplish their goals and commitments. Notice is provided of these workshops. Anyone with a disability requiring
accommodation to attend this meeting should contact the St. Lucie County Human Resources Department at 772-462-1456,
HumanResources@stlucieco.gov or TDD 772-462-1428 at least 48 hours prior to the meeting.
z1P,:
Page 2 of 47
Regular Meeting Tuesday, July 22, 2025 9:01 AM
1. CALL TO ORDER
2. GENERAL PUBLIC COMMENT
3. APPROVAL OF MINUTES
A. Board of County Commissioners minutes for the Erosion District Meeting of June 3, 2025.
B. Board of County Commissioners minutes for the Erosion District Meeting of July 1, 2025.
4. CONSENT AGENDA
A. WARRANTS
Warrant Lists 35 - 40
B. PORT, INLET & BEACHES
2025 St. Lucie County (SLC)/U.S. Army Corps of Engineers (USACE)/Bureau of Ocean Energy
Management (BOEM) Tri-Party Memorandum of Agreement (MOA) for Use of Outer
Continental Shelf Sand Resources Located within the St. Lucie Shoal Complex (a Pre -defined
Offshore Sand Resource)
Staff recommends Board approval of the attached Tri-Party Memorandum of Agreement
(MOA) between the Bureau of Ocean Energy Management (BOEM, Department of the
Interior), the U.S. Army Corps of Engineers (USACE), and St. Lucie County (SLC), for approval
to use up to 700k cubic yards of beach -compatible sands from federal waters to complete the
2025/26 federal beach rehabilitation effort with the USACE, and authorization for the Chair
to sign those documents as approved by the County Attorney. This is in accordance with
Strategic Plan Policy ES 6.1.4.
Resolution — State Beach Funding Request
Staff recommends Board approval to 1) submit the Beach Management Funding Assistance
(BMFA) Program funding application request(s) to the State of Florida (FDEP) for FY-2026/27
along with the attached supporting Resolution (RES-2025-137), and 2) authorization for the
Chair to sign documents as approved by the County Attorney. This is in accordance with
Strategic Plan Policy ES 6.1.4.
3 1 P, :
Page 3 of 47
Regular Meeting Tuesday, July 22, 2025 9:01 AM
S. REGULAR AGENDA
There are no items scheduled.
6. MOTION TO ADJOURN
4 1 P, :
Page 4 of 47
SM ELL C-�'
BOARD OF COUNTY COMMISSIONERS
ST. LUCIE COUNTY, FLORIDA
Erosion District Meeting
June 3, 2025 Convened: 6:02 PM
Adjourned: 6:02 PM
1. CALL TO ORDER
The meeting was called to order at 6:02 PM by Chair James Clasby, District No. 1.
Present
Commissioner Jamie Fowler, District 4; Commissioner Larry Leet, District 2; Commissioner James Clasby,
District 1; Commissioner Erin Lowry, District 3; Commissioner Cathy Townsend, District 5
Also Present
Dan McIntyre, County Attorney
George Landry, County Administrator
Mayte Santamaria, Deputy County Administrator
Benjamin Balcer, Planning & Development Services Director
Kori Benton, Planning & Development Services Planning Manager
Patrick Dayan, Public Works Director
Joshua Revord, Port Director
Daniel Zrallack, County Engineer
Cameron Howard, Airport Director
Rebecca Olson, Solid Waste & Public Utilities Director
Sydney Halleran, Agenda Coordinator
Vera Smith, Deputy Clerk Recording Secretary
2. GENERAL PUBLIC COMMENT
Chair Clasby opened the meeting for public comment at this time. With no one wishing to address the
Board, Chair Clasby closed public comment.
3. APPROVAL OF MINUTES
H iiivuUii WdJ IIIc1UC LU CIPPIUVC dll IIIIIIUIC JCIJ, GIIU IL PC1bb1=U Uiiainiiivuaiy.
RESULT:
APPROVE
MOVER:
Commissioner District 2 Larry Leet
SECONDER:
Commissioner District 4 Jamie Fowler
AYES:
Jamie Fowler, Larry Leet, James Clasby, Erin Lowry, Cathy Townsend
NAYS:
None
EXCUSED:
None
Page 5 of 47
Erosion District Meeting Tuesday, June 3, 2025 6:01 PM
A. Board of County Commissioners minutes for the Erosion District Meeting of May 20, 2025.
4. CONSENT AGENDA
A motion was mace to aaopt the consent agenca, ana it passea unanimously.
RESULT:
APPROVE
MOVER:
Commissioner District 2 Larry Leet
SECONDER:
Commissioner District 4 Jamie Fowler
AYES:
Jamie Fowler, Larry Leet, James Clasby, Erin Lowry, Cathy Townsend
NAYS:
None
EXCUSED:
None
A. WARRANTS
1. Warrant Lists 33 - 34
Adopted by Consent Vote
5. REGULAR AGENDA
There were no items scheduled.
6. MOTION TO ADJOURN
With no other information to be brought for consideration before the Board, the meeting was adjourned at
6:02 PM.
Please note: Final minutes are recorded in the official minute books filed with the Clerk of the Circuit Court
and Comptroller, which are available for inspection upon request.
2 1 p„
Page 6 of 47
SM ELL C-�'
BOARD OF COUNTY COMMISSIONERS
ST. LUCIE COUNTY, FLORIDA
Erosion District Meeting
July 1, 2025 Convened: 6:01 PM
Adjourned: 6:02 PM
1. CALL TO ORDER
The meeting was called to order at 6:01 PM by Chair James Clasby, District No. 1.
JPresent
Commissioner Jamie Fowler, District 4; Commissioner Larry Leet, District 2; Commissioner James Clasby,
District 1; Commissioner Erin Lowry, District 3; Commissioner Cathy Townsend, District 5
Also Present
Dan McIntyre, County Attorney
George Landry, County Administrator
Mayte Santamaria, Deputy County Administrator
Eric Gill, Communications Director
Jean Stasio, Assistant County Attorney III
Katherine Barbieri, Assistant County Attorney
Benjamin Balcer, Planning & Development Services Director
Kori Benton, Planning & Development Services Planning Manager
Rebecca Ventrella, Public Utilities & Solid Waste Director
Sydney Halleran, Agenda Coordinator
Vera Smith, Deputy Clerk Recording Secretary
2. GENERAL PUBLIC COMMENT
Chair Clasby opened the meeting for public comment at this time. With no one wishing to address the
Board, Chair Clasby closed public comment.
3. APPROVAL OF MINUTES
There were no items scheduled.
4. CONSENT AGENDA
A motion was made to adopt the consent agenda, and it passed unanimously.
RESULT: APPROVE
MOVER: Commissioner District 2 Larry Leet
SECONDER: Commissioner District 3 Erin Lowry
AYES: Jamie Fowler, Larry Leet, James Clasby, Erin Lowry, Cathy Townsend
NAYS: None
Page 7 of 47
Erosion District Meeting Tuesday, July 1, 2025 6:01 PM
I EXCUSED: None I
A. PORT, INLET & BEACHES
1. Erosion District Funding Approval for the Multi -Purpose Staging and Commercial Waterfront
Design/Permitting Effort - Amendment No. 2 to Contract C24-06-879 (Taylor Engineering) -
Companion Item 2025-4299
Staff recommended Board approval to contribute $181,621.00 from the Erosion District (Fund
184) for the proposed design and permitting effort associated with the Harbour Pointe Regional
Boat Ramp Phase 2 Multi -Purpose Staging and Commercial Waterfront area project element, to
ensure a future staging area for all future Erosion District projects and initiatives.
Adopted by Consent Vote
5. REGULAR AGENDA
There were no items scheduled.
6. MOTION TO ADJOURN
With no other information to be brought for consideration before the Board, the meeting was adjourned at
6:02 PM.
Please note: Final minutes are recorded in the official minute books filed with the Clerk of the Circuit Court
and Comptroller, which are available for inspection upon request.
2 1 p„
Page 8 of 47
05/30/25 ST. LUCIE COUNTY - BOARD
FZABWARR WARRANT LIST #35- 24-MAY-2025 TO 30-MAY-2025
FUND SUMMARY- EROSION
FUND TITLE EXPENSES
184 Erosion Control Operating Fund 533.72
GRAND TOTAL: 533.72
PAGE 1
PAYROLL
0.00
0.00
Page 9 of 47
06/06/25 ST. LUCIE COUNTY - BOARD
FZABWARR WARRANT LIST #36- 31-MAY-2025 TO 06-JUN-2025
FUND SUMMARY- EROSION
FUND TITLE EXPENSES
184 Erosion Control Operating Fund 2,000.00
GRAND TOTAL: 2,000.00
PAGE 1
PAYROLL
8,204.00
8,204.00
Page 10 of 47
06/13/25 ST. LUCIE COUNTY - BOARD
FZABWARR WARRANT LIST #37- 07-JUN-2025 TO 13-JUN-2025
FUND SUMMARY- EROSION
FUND TITLE EXPENSES
184 Erosion Control Operating Fund 764.93
GRAND TOTAL: 764.93
PAGE 1
PAYROLL
0.00
0.00
Page 11 of 47
06/20/25 ST. LUCIE COUNTY - BOARD
FZABWARR WARRANT LIST #38- 14-JUN-2025 TO 20-JUN-2025
FUND SUMMARY- EROSION
FUND TITLE EXPENSES
184 Erosion Control Operating Fund 7,387.75
GRAND TOTAL: 7,387.75
PAGE 1
PAYROLL
8,404.00
8,404.00
Page 12 of 47
06/27/25 ST. LUCIE COUNTY - BOARD
FZABWARR WARRANT LIST #39- 21-JUN-2025 TO 27-JUN-2025
FUND SUMMARY- EROSION
FUND TITLE EXPENSES
184 Erosion Control Operating Fund 308.72
GRAND TOTAL: 308.72
PAGE 1
PAYROLL
0.00
0.00
Page 13 of 47
07/03/25 ST. LUCIE COUNTY - BOARD
FZABWARR WARRANT LIST #40- 28-JUN-2025 TO 03-JUL-2025
FUND SUMMARY- EROSION
FUND TITLE EXPENSES
184 Erosion Control Operating Fund 42,756.50
GRAND TOTAL: 42,756.50
PAGE 1
PAYROLL
8,204.00
8,204.00
Page 14 of 47
TO:
PRESENTED BY
SUBMITTED BY:
SUBJECT:
BACKGROUND:
2025-4388
DATE: 7/22/2025
AGENDA REQUEST
Erosion District
Joshua Revord, Port, Inlet & Beaches Director
Port, Inlet & Beaches
2025 St. Lucie County (SLC)/U.S. Army Corps of Engineers (USACE)/Bureau of Ocean
Energy Management (BOEM) Tri-Party Memorandum of Agreement (MOA) for Use
of Outer Continental Shelf Sand Resources Located within the St. Lucie Shoal
Complex (a Pre -defined Offshore Sand Resource)
In November 2002, the U.S. Army Corps of Engineers (USACE) completed a "Section 905(b) analysis for a "St.
Lucie County, Florida — Hurricane and Storm Damage Reduction Study" including the Study Area from just
south of Blind Creek (FDEP Monument R-77) to the Martin County Line (FDEP Monument R-115). This
reconnaissance report recommended that the "study proceed into the feasibility phase", which was
eventually initiated in 2004. Shortly afterward, the USACE re-scoped the Federal project (reducing the
proposed project area) and approved it as part of their 3x3x3 Plan; eventually, receiving federal funding to
move the study forward.
While in the feasibility phase, storm events (including Hurricane Sandy) impacted South County Beaches. The
storm damage experienced after these events warranted swift/specific action. St. Lucie County, with support
from the State of Florida and local stakeholders, initiated construction of a one-time, non-federal beach
restoration project in April 2013 (while federal efforts continued). The project consisted of the nourishment of
3.4 miles of FDEP-designated "critically eroded" Atlantic shoreline from FDEP monument R-98 (Normandy
Beach) to the Martin County line (R-115). The project included the placement of approximately 635,164 cubic
yards of beach -compatible sand from St. Lucie Shoal and was partially funded through a Special Assessment
District (SAD) created specifically for the one-time project. A nearshore limestone boulder mitigation reef was
also completed to offset project -related hard -bottom resource impacts.
Eventually, the South St. Lucie County, Florida, Coastal Storm Risk Management (CSRM) Project Feasibility
Study was completed and approved, receiving a signed Chief's Report (December 15, 2017) and federal
Congressional authorization (2018 WRDA Bill). In addition, Erosion District staff diligently pursued and secured
approximately $6.4 million in state grant funds from the Florida Department of Environmental Protection
(FDEP) for the initial, proposed construction (FDEP Grants 19SL4 and 20SL3) and unilaterally increased the
level of federal participation for the project by 7% by improving public beach access at County owned beach
parks. To address the balance of proposed funding, St. Lucie County BOCC drafted and subsequently approved
the South Hutchinson Island Municipal Service Taxing Unit (SHI MSTU); encompassing all landowners both
east and west of A1A (adjacent to the proposed project area).
Page 15 of 47
As such, St. Lucie County's Erosion District Board moved forward with a Project Partnership Agreement (PPA)
with the USACE to formalize the County's intent to pursue the long-term stability of St. Lucie County's
southern Atlantic shoreline (December 2, 2020). This agreement includes fifty (50) years of federal
participation. Subsequently, design plans and specifications were drafted for the proposed 2021/22 "initial
start" project, permit modifications were pursued for the County's active state beach nourishment permit
(USACE as a co-permittee), and a USACE required land certification effort (including perpetual construction
easements) was requested by (December 2020) and subsequently provided to the USACE (June 2021) for the
proposed project. A Tri-Party Memorandum of Agreement (MOA) was drafted by the Bureau of Ocean Energy
Management (BOEM) for the use of outer continental shelf sand resources for the project and was
subsequently executed by BOEM/SLC/USACE. The sand proposed was located within the St. Lucie Shoal
Complex.
In March 2022, the contractor, Great Lakes Dredge & Dock Company, began to mobilize equipment and by
May 7, 2022, the initial federal beach project was completed with the placement of approximately 387,035
cubic yards of sand onto south county beaches. Following completion of the Federal Project in 2022,
Hurricane Ian and Hurricane Nicole both impacted Florida beaches and the project area. These impacts led to
a federal disaster declaration and an opportunity for the county to request federal rehabilitation assistance.
On October 28, 2022, the County formally requested federal disaster assistance and was subsequently
approved for rehabilitation based on the level of impact those storms had on the recently completed federal
beach project. With the acquisition of the last perpetual easement in 2024, the rehabilitation project was
subsequently designed and is currently in the process of being bid out.
The attached Tri-Party Memorandum of Agreement (MOA) drafted by BOEM, to be executed by
BOEM/SLC/USACE, outlines specific requirements for the use of Outer Continental Shelf sand resources for
this 100% federally funded rehabilitation project. The proffered MOA is a non-competitive lease and includes
approval to remove up to 700k cubic yards of beach -compatible sand from the proposed borrow area. It
requires the USACE and the County to participate in certain pre- and post -construction monitoring efforts.
The proposed area contains beach -compatible sand consistent with the native beach and the previously
completed projects.
PREVIOUS ACTION:
1999 - St. Lucie County's Erosion District initiated a process to seek federal support and management of St.
Lucie County's southern beaches (at the request of South Hutchinson Island residents).
2004 - Erosion District and the U.S. Army Corps of Engineers (USACE) sign feasibility cost -sharing agreement,
initiating the first major step towards beach federalization. Major coastal storm impacts from Hurricanes
Frances and Jeanne.
2005-2007 - Emergency dune restoration along the project area takes place with both Florida Department of
Environmental Protection (FDEP) and Federal Emergency Management Agency (FEMA) funding.
2012-2013 - South County Beach impacted by Hurricane Sandy. Erosion District coordinates a one-time
(locally -funded) emergency beach nourishment project in response to beachfront residents' requests. Beach
and dune restoration was completed for approximately 3.4 miles of Atlantic shoreline from the Martin County
line, north to Normandy Beach Park.
2017-2018 — Federal feasibility report completed, and Congress authorizes the St. Lucie County, Florida
Page 16 of 47
Coastal Storm Risk Management (CRSM) Project in the 2018 Water Resources Development Act (WRDA);
including a proposed fifty (50) year project life. The federal share of initial construction was funded in the
Bipartisan Act of 2018 (PL 115-123).
March 2019 — St. Lucie County successfully petitioned for and received a construction timeline extension;
initial construction re -scheduled for winter 2021/spring 2022.
December 2019 — Public Hearing advertised and subsequent Board approval of Resolution 2019-286
establishing the definitions and physical boundaries of a proposed South Hutchinson Island Municipal Services
Taxing Unit (MSTU).
September 2020 - County approves the South Hutchinson Island MSTU during the final 2020-2021 budget
session meeting.
June 10, 2021— RFP solicitation for public financing to help fund proposed construction (to fund the
outstanding balance of the non-federal share required for the initial federal beach project).
June 2021— St. Lucie County completes and submits the USACE required land certification needed for the
proposed initial federal beach project. All but one perpetual easement was provided, and a one-time
exemption was provided to the County for the initial federal beach project.
July 6, 2021- St. Lucie County approves the execution of the Bureau of Ocean Energy Management (BOEM)
Tri-Party Memorandum of Agreement (MOA) for the use of Outer Continental Shelf sand resources needed
for the initial federal beach project.
March 2022—The initial federal beach project commences.
May 7, 2022 - The initial federal beach project is completed, with the placement of approximately 387,035
cubic yards of sand onto south county beaches.
September 2022 — Hurricane Ian.
November 2022 — Hurricane Nicole.
FINANCIAL IMPACT:
There are no direct financial impacts associated with the proposed Tri-Party Memorandum of Agreement
(MOA). The proposed project is a 100% federally funded rehabilitation effort (construction only). Compliance
with the terms of the agreement requires specific bathymetric surveys pre -/post -beach construction. These
surveys are inherent to the proposed construction effort (regardless of the borrow area location) and will be
performed by the USACE and St. Lucie County.
RECOMMENDATION:
Staff recommends Board approval of the attached Tri-Party Memorandum of Agreement (MOA) between the
Bureau of Ocean Energy Management (BOEM, Department of the Interior), the U.S. Army Corps of Engineers
(USACE), and St. Lucie County (SLC), for approval to use up to 700k cubic yards of beach -compatible sands
from federal waters to complete the 2025/26 federal beach rehabilitation effort with the USACE, and
authorization for the Chair to sign those documents as approved by the County Attorney. This is in accordance
with Strategic Plan Policy ES 6.1.4.
Page 17 of 47
COMMISSION ACTION:
RESULT:
MOVER:
None
SECONDER:
None
AYES:
None
NAYS:
None
EXCUSED:
None
Coordination/Signatures
Date: July 16, 2025
Daniel McIntyre, County Attorney
Date: July 16, 2025
Mayte Santamaria, Deputy County Administrator
Page 18 of 47
MEMORANDUM OF AGREEMENT
AMONG THE BUREAU OF OCEAN ENERGY MANAGEMENT
OF THE DEPARTMENT OF THE INTERIOR
AND THE CORPS OF ENGINEERS
OF THE DEPARTMENT OF THE ARMY
AND ST. LUCIE COUNTY, FLORIDA
REGARDING THE USE OF OUTER CONTINENTAL SHELF SAND RESOURCES
FOR CONSTRUCTION OF THE ST. LUCIE COUNTY, FLORIDA COASTAL STORM
RISK MANAGEMENT PROJECT
BOEM Negotiated Agreement No. OCS-A 05XX
Title I. Explanatory Recitals
A. Pursuant to the authority and in accordance with Section 1401(3) of the Water Resources
Development Act of 2018 (P.L. 115-270), and to the extent that appropriations provided under the
Construction heading, Title I, Division D of the Consolidated Appropriations Act of 2023 (PL 117-
328) enacted December 29, 2022, are obligated and used, the Department of the Army, acting through
the United States Army Corps of Engineers, Jacksonville District (USAGE), with the cooperation of
St. Lucie County, Florida (the "County"), represented by the Chair of the Erosion District, is
endeavoring to conduct the renourishment of the St. Lucie County, Florida Coastal Storm Risk
Management Project (the "Project").
B. USACE and the County are undertaking the Project, in furtherance of the goal to renourish the
shoreline of south St. Lucie County, Florida. Pursuant to Division D, Title I, of the Consolidated
Appropriations Act of 2023 (P.L. 117-328) provisions, USACE has determined that the Project is
technically feasible, economically justified, and environmentally acceptable. USACE will provide
funding and lead construction of the Project.
C. Prior to a notice -to -proceed for Project construction, USACE and the County will have
procured lands, easements, and rights -of -way (collectively, "Land Rights") as necessary from upland
landowners, other property rights holders, public entities, and other persons and entities, of appropriate
scope and duration, to facilitate the Project.
D. USACE, acting as the project manager for the Project, and the County now seek to obtain sand
in a manner that minimizes costs and leverages Federal resources.
Title H. Purpose and Authority
A. The Department of the Interior (DOI), acting through the Bureau of Ocean Energy
Management (BOEM), enters into this Memorandum of Agreement (MOA or "Agreement") with
USACE and the County (collectively with DOI or BOEM, the "Parties") providing for the use of up
to 700,000 cubic yards of Outer Continental Shelf sand resources ("OCS sand resources") for the
Project under the authority of Section 8(k)(2) of the Outer Continental Shelf Lands Act (OCSLA) (43
U.S.C. § 1337(k)(2)). The term "OCS sand resources" means the sediment deposits found on or below
the surface of the seabed on the Outer Continental Shelf (OCS), as defined in Section 2(a) of the
1
Page 19 of 47
OCSLA (43 U.S.C. § 1331(a)). This MOA authorizes the use of Borrow Areas Al and A2 on St.
Lucie Shoal, as designated and delineated in Table 1 and on the attached maps (Attachment 1), in
accordance with the terms of this MOA. After removal of the OCS sand resources and placement of
those resources as specified in this MOA, BOEM has no jurisdiction over those sand resources unless
they return to the OCS. Use and/or disposal of OCS sand resources outside the areas defined in the
Project is not expressly authorized as a qualified use; a modification to this Lease may be required to
authorize such use.
Table 1. Coordinates for Borrow Areas Al and A2 on St. Lucie Shoal
Point
Latitude
Longitude
Easting
Northing
1
27.3103550
-80.1502006
931,534
1,082,925
2
27.3103445
-80.1507279
931,949
1,082,924
3
27.3096195
-80.1504717
932,034
1,082,661
4
27.3075824
-80.1493109
932,416
1,081,923
5
27.3068632
-80.1490947
932,488
1,081,662
6
27.3047200
-80.1490248
932,516
1,080,883
7
27.3034094
-80.1492627
932,442
1,080,406
8
27.3021852
-80,1492381
932,453
1,079,961
9
27.3014992
-80.1495205
932,363
1,079,711
10
27.3003037
-80.1496897
932,311
1,079,276
11
27.3001937
-80.1492471
932,455
1,079,237
12
27.3020848
-80.1476562
932,967
1,079,928
13
27.3020451
-80.1470222
933,173
1,079,915
14
27.2990542
-80.1482213
932,791
1,078,825
15
27.2965275
-80.1497739
932,293
1,077,903
16
27.2965312
-80.1503773
932,097
1,077,903
17
27.2974291
-80.1514759
931,738
1,078,227
18
27.2993673
-80.1513164
931,785
1,078,932
19
27.3002929
-80.1515311
931,713
1,079,268
20
27.3022288
-80.1514425
931,737
1,079,972
21
27.3031327
-80.1521746
931,497
1,080,299
22
27.3042776
-80.1522644
931,465
1,080,715
23
27.3058312
-80.1521849
931,487
1,081,280
24
27.3068233
-80.1520264
931,536
1,081,641
25
27.3103264
-80.1477564
932,914
1,082,924
26
27.3083301
-80.1460719
933,466
1,082,202
27
27.3064300
-80.1461634
933,441
1,081,511
28
27.3038632
-80.1461061
933,466
1,080,578
Note: Longitude and Latitude in Geographic Coordinate System NAD 1983. Easting and Northing in Florida State Plane
East Coordinate System (11) NAD 1983
B. BOEM, under the authority delegated by the Secretary of the Interior, is authorized, pursuant
to Section 8(k)(2) of the OCSLA (43 U.S.C. § 1337(k)(2)), to enter into this MOA concerning the
potential use of OCS sand resources.
BOEM has determined that the Project meets the requirements of Section 8(k)(2)(A)(i) of the OCSLA.
BOEM determined that the Project qualified for a non-competitive negotiated agreement on April 21,
2
Page 20 of 47
2025 (see 30 CFR 583.305). BOEM completed the project evaluation process required by 30 CFR
583.310. Therefore, in accordance with Section 8(k)(2), and subject to the terms and conditions
contained herein, BOEM hereby authorizes the use of OCS sand resources from Borrow Areas Al and
A2 on St. Lucie Shoal, identified in Table 1, for the construction undertaken in furtherance of the
Project. The Parties acknowledge that under the terms of Section 8(k)(2)(B), BOEM will not assess
any fee against USACE and/or the County for the use of the OCS sand resources described herein.
Nothing in this MOA is intended to abrogate or diminish the Secretary of the Interior's authority under
the OCSLA to oversee and regulate the removal of OCS sand resources. Pursuant to 30 CFR 583.330,
failure to comply with any applicable law or any provision, term, or condition of this Agreement may
result in termination of the Agreement at the sole discretion of BOEM, referral to an appropriate
Federal or State agency with jurisdiction, or both. Failure to comply in a timely and satisfactory
manner with any provision, term or condition of this Agreement may also delay or prevent BOEM's
approval of future requests for use of OCS sand by the Parties to this Agreement.
The MOA may be terminated by BOEM consistent with provisions in 30 CFR 583.350. If BOEM
determines that USACE and/or the County violate any provisions of this MOA, BOEM may, by
written notice, suspend the MOA and order any further operations of USACE or the County under this
Agreement to cease, except such operations as may be necessary to remedy any violations. If USACE
and/or the County fails to remedy violations within thirty (30) calendar days after receipt of suspension
notice, BOEM may, by written notice, terminate this MOA. In the event that BOEM suspends or
terminates the MOA, neither USACE nor the County will be entitled to compensation as a result of
expenses or lost revenues resulting from the suspension or termination.
C. USACE enters into this MOA in compliance with the requirements of Sections 8(k)(2)(A)(i)
and 8(k)(2)(D) of the OCSLA. The County enters into this MOA in compliance with the requirements
of Section 8(k)(2)(A)(i) of the OCSLA. If appropriate, duties of USACE and/or the County may be
fulfilled through authorized representatives, such as a dredging contractor. Both USACE and the
County will ensure that any contractors or subcontractors operate in compliance with this MOA.
Nothing in this MOA is solely intended to impede or hinder the ability of USACE and/or the County
to complete the Project nor does any provision abrogate or diminish either Parties' authority or
responsibilities under applicable law, including but not limited to the Clean Air Act (CAA) (42 U.S.C.
§§ 7401 et seq.), Clean Water Act (CWA) (33 U.S.0 §§ 1251 et seq.), Coastal Zone Management Act
(CZMA) (16 U.S.C. §§ 1451 et seq.), Endangered Species Act (ESA) (16 U.S.C. §§ 1531 et seq.),
Magnuson -Stevens Fishery Conservation and Management Act (MSA) (16 U.S.C. §§ 801 et seq.),
Marine Mammal Protection Act (MMPA) (16 U.S.C. §§ 1361 et seq.), Migratory Bird Treaty Act
(MBTA) (16 U.S.C. §§ 703-712), National Environmental Policy Act (NEPA) (42 U.S.C. §§ 4321 et
seq.), National Historic Preservation Act (NHPA) (54 U.S.C. §§ 300101 et seq.), Section 1401(3)2 of
the Water Resources Development Act of 2018 (P.L. 115-270), and Division
D Title I, of the Consolidated Appropriations Act of 2023 (P.L. 117-328).
Title III. Description of the Authorized Activity
This MOA is intended to facilitate the renourishment of the St. Lucie County, Florida Coastal Storm
Risk Management Project in south St. Lucie County, Florida. This MOA authorizes USACE and/or the
County to dredge up to a total of 700,000 cubic yards of OCS sand resources from Borrow Areas Al
and A2 of St. Lucie Shoal for placement along 3.3 miles of shoreline between Florida Department of
3
Page 21 of 47
Environmental Protection (FDEP) Range Monument R-98.5 south to the Martin County line at R-1
(see Attachment 1).
Title 1V. Provisions
A. BOEM authorizes USACE and/or the County to dredge OCS sand resources from Borrow
Areas Al and A2 on St. Lucie Shoal for the Project and in Project designated areas. USACE and/or
the County may only extract, transport, and place such OCS sand resources from the borrow area in
accordance with the terms and conditions set forth below. Except as provided herein, the Parties agree
that all other aspects of the Project's execution and completion remain as described in the Project
Partnership Agreement between the Department of the Army and St. Lucie County, Florida, for
Construction of the St. Lucie County Coastal Storm Risk Management Project, entered into on the 2nd
of December, 2020, and any subsequent amendments thereto.
B. All written notifications, requests, submissions, and deliverables, unless otherwise stated,
should be sent to BOEM at:
Acting Manager, Marine Minerals Division
Attention: Geoffrey Wikel
Bureau of Ocean Energy Management
45600 Woodland Road, VAM-MMD
Sterling, VA 20166
(703)787-1283
eg offrey.wikel(a�boem.gov
All electronic notifications, submissions, and deliverables to BOEM should be sent to
dyed eg infokboem.gov.
All written notifications, requests, submissions, and deliverables to USACE should be sent to:
Jacksonville District
U.S. Army Corps of Engineers
Attn: Mr. James LaGrone, Project Manager
701 San Marco Blvd
Jacksonville, FL 32207
904-232-2437
James.W.Lagrone@usace.army.mil
All written notifications, requests, submissions, and deliverables to the County should be sent to:
Mr. Joshua Revord, PE, Director of Port, Inlet & Beaches
St. Lucie County, Florida
1001 Harbor Street
Fort Pierce, FL 34950
772-462-1269
Joshua.Revordkstlucieco.org
C. This MOA applies only to the extraction, transportation, and placement of OCS sand resources
as described above and in the "Construction Solicitation and Specifications Plan" required below in
4
Page 22 of 47
Title IV Provision (D)(1). This MOA will terminate or expire (a) upon USACE and/or the County
sending written notice that it has obtained sufficient OCS sand resources, up to 700,000 cubic yards,
to complete the Project, or (b) three (3) years from the date of execution of this MOA, whichever
occurs first. Upon request by USACE and/or the County, the Parties may agree in writing to extend
the term of this MOA as necessary to provide additional time to complete the Project.
The Parties acknowledge that there may be a need for future OCS sand resources for periodic
maintenance, augmentation, or construction purposes. BOEM, USACE, and the County may enter
into subsequent agreements, for the use of additional OCS sand resources for the Project, consistent
with each Party's responsibilities under applicable law.
D. BOEM, USACE, and the County recognize that planning and coordination among the Parties
will ensure that responsibilities related to OCSLA, other applicable Federal laws, and this Project are
carried out and accommodated in an efficient and timely manner so that the Project schedule will not
be unnecessarily delayed or compromised. All Parties recognize that BOEM, as a Bureau in the DOI,
has certain responsibilities for the orderly, timely, and efficient recovery of OCS minerals, including
sand resources, using the best available technology while ensuring environmental stewardship and
compliance. Moreover, the Parties further recognize that USACE has certain stewardship and
environmental compliance responsibilities that are separate and distinct from the responsibilities of
BOEM. To these ends, and with respect to the Project, BOEM, USACE, and the County agree to the
following terms:
1. Plans and Performance Requirements
USACE will include this MOA as a reference document in the advertised "Construction Solicitation
and Specifications Plan" (hereinafter referred to as the "Plan"). USACE will provide a copy of the
Plan to BOEM for review at least two weeks prior to construction contract advertisement to allow
sufficient time for BOEM to review and ensure that all provisions of this Agreement, including
environmental compliance requirements (Title IV Provision (D)(2)), are incorporated into the Plan, as
applicable. USACE and the County will ensure that all operations at Borrow Areas Al and A2 on St.
Lucie Shoal are conducted in accordance with the final BOEM-reviewed Plan and all terms and
conditions in this MOA, as well as all applicable statutes, regulations, orders, and any guidelines or
directives specified or referenced herein and any project design criteria, relevant terms and conditions
or reasonable and prudent measures of the latest Biological Opinions applicable to the activities
authorized in this MOA.
USACE will allow BOEM to review and comment on modifications to the Plan that may affect the
borrow area or pipeline corridors on the OCS, including the use of submerged or floated pipelines to
directly convey sediment from the borrow area to the placement site. BOEM will deliver these
comments in a timely fashion so as to not unnecessarily delay USACE's construction contract or
schedule.
Dredging, bottom disturbing activities, and/or conveyance methods (and areas of proposed use) will
be wholly consistent with those evaluated in relevant NEPA documents prepared by USACE and
BOEM for this Project, those included in the environmental and cultural resource consultations, and
those authorized by relevant project permits. If USACE or the County propose to change the dredging
method, additional environmental review may be necessary. If the additional NEPA, consultations,
or permit modifications would impact or otherwise supplement the provisions of the MOA, an
5
Page 23 of 47
amendment to the MOA may be required. Until BOEM determines if the proposed changes require an
amendment to the MOA, no changes to the authorized dredging and conveyance methods will be
implemented.
USACE will notify BOEM electronically at least 72 hours prior to the commencement, and within 24
hours after termination, of operations at Borrow Areas Al and A2 on St. Lucie Shoal. If BOEM is
aware of any OCS activity within the jurisdiction of the DOI that may adversely affect USACE's
and/or the County's ability to use OCS sand resources for the Project, BOEM will electronically notify
USACE and the County in a timely manner.
Prior to the commencement of construction, USACE and/or the County will electronically provide
BOEM with a summary of the construction schedule consistent with Title IV Provision (D)(15) of this
MOA. USACE and the County, at the reasonable request of BOEM or Bureau of Safety and
Environmental Enforcement (BSEE), will allow any authorized Federal inspector to access the site of
any operation, when permitted by safety regulations, and will provide BOEM any documents and
records that are pertinent to occupational or public health, safety, environmental protection,
conservation of natural resources, or other use of the OCS as may be requested. USACE and the
County agree to facilitate access for personnel authorized by BOEM or BSEE to the site of any
operation, where practicable and deemed safe by USACE and its contractor, including, but not limited
to, dredges and support equipment, fill areas, or turtle relocation trawlers, if warranted.
2. Environmental Responsibilities and Environmental Compliance
USACE and the County commit to avoiding, minimizing, or mitigating adverse effects during
construction activities. USACE and/or the County will prepare and provide to BOEM before
commencing construction an Environmental Compliance Matrix (ECM), in coordination with the
other remaining Parties, to document all environmental requirements and identify roles and
responsibilities to ensure compliance prior to, during, and after construction. The ECM must identify
where in the Plan the relevant environmental compliance measures are addressed. All environmental
commitments in the ECM will be reflected in the Plan. As indicated in Title IV Provision (D)(15),
BOEM also requires USACE and/or the County to verify implementation of all requirements in the
ECM in the Project Completion Report.
USACE is the lead agency on behalf of the Federal Government to ensure the Project complies with
applicable environmental laws, including but not limited to the CAA, CZMA, ESA, MSA, NEPA, and
NHPA, and any consultations or limitations imposed thereunder. USACE and/or the County will
implement the mitigation terms, conditions, and measures required by the U.S. Fish and Wildlife
Service (USFWS), National Marine Fisheries Service (NMFS), Florida Department of Environmental
Protection (FDEP), and BOEM pursuant to applicable Federal and State laws and regulations prior to
commencement of activities authorized under this MOA, including extraction, transportation and
placement of sand resources from Borrow Areas Al and A2 on St. Lucie Shoal. Electronic copies of
all relevant correspondence, monitoring data, and reports related to the activities covered by this MOA
will be provided electronically to BOEM within 14 calendar days of issuance (including, but not
limited to, observer and dredging reports, and reports required by relevant project permits) unless the
reports are required sooner by this MOA or applicable law, the permits, or the consultations.
Construction may not commence until the pre -construction requirements have been completed.
6
Page 24 of 47
3. Pre -Construction Notification of Activity in or near the Borrow Area
USACE and/or the County will invite BOEM to attend a pre -construction meeting that will describe
the Plan and schedule to construct the Project.
USACE and/or the County will notify BOEM at dredgeinfogboem. oovv at least 72 hours prior to the
commencement, and no later than 24 hours after termination, of operations at Borrow Areas Al and
A2 on St. Lucie Shoal.
4. Other Responsibilities
BOEM does not warrant that the OCS sand resources used in this Project are suitable for the purpose
for which they are intended by USACE and the County. BOEM's responsibility under this Project is
limited to the authorization of access to OCS sand resources from Borrow Areas Al and A2 on St.
Lucie Shoal as described in this MOA, and therefore BOEM disclaims any and all responsibility for
the physical and financial activities undertaken, damages or liabilities, incidents or injuries, or
negligence by the other Parties in pursuit of the Project.
To the extent permitted by law, the County hereby indemnifies BOEM for any claims for loss, costs,
damages, injuries to persons, or expenses caused by, or resulting from any operation under this MOA.
However, the County is not responsible to BOEM for any loss, cost, damage, injury, or expense that
directly results from (1) the sole negligence of BOEM, or (2) the County's non -negligent compliance
with a BOEM order or directive imposed under this MOA. Nothing in this section will be construed
as a waiver of any applicable statutory limitations of liability, including but not limited to Section
768.28, Florida Statutes, nor will this section operate as a waiver of the County's sovereign immunity.
USACE and/or the County must notify BOEM of any encounter of hazards on the OCS and any OCS
sediment placed on the beach that has unsuitable characteristics relative to native sediment
characteristics of the beach where it is placed (e.g., grain -size, color, composition). The specific
location where unsuitable sediment was dredged, or where hazards were encountered, within Borrow
Areas Al and A2 on St. Lucie Shoal must be delineated and said location must be provided to BOEM
in shapefile format, with applicable metadata detailing why it is recommended for avoidance, for
future planning purposes. This information will be provided consistent with the reporting requirements
in Title IV Provisions (D)(7) and (D)(13). Additionally, any encounter of ordnance must be reported
to BOEM using the process outlined in Title IV Provision (D) (10).
5. Dredge Positioning
During all phases of the Project, USACE and/or the County will ensure that the dredge and any bottom -
disturbing equipment is outfitted with an onboard global positioning system (GPS) to accurately
represent the position of the dredging operations in accordance with specifications developed by the
USACE National Dredging Quality Management (DQM) program.
USACE and/or the County will coordinate with the DQM program in advance of construction
commencement to provide appropriate project -specific information, inform them of BOEM's role in
the Project and relevant MOA stipulations, and develop a coordination plan to ensure that all DQM-
certified deliverables in accordance with this MOA are internally reviewed and delivered to BOEM
on time and in accordance with BOEM formatting requirements. USACE and/or the County will
provide BOEM, electronically, with all appropriate DQM data acquired during the Project using
7
Page 25 of 47
procedures jointly developed by USACE's National DQM Data Program Support Center and BOEM.
USACE and/or the County will submit the DQM data every two weeks.
Anchoring, spudding, or other bottom -disturbing activities are not authorized outside of the approved
borrow area on the OCS, unless there are immediate concerns of safety, navigation risks, or emergency
situations. USACE and/or the County will notify BOEM electronically as soon as possible if these
activities occur outside of the approved borrow area(s).
6. Dredge Operation
The final, BOEM-reviewed Plan (required pursuant to Title IV Provision (D)(1)) will include
provisions designed to maximize efficiency and conservation of the resource during the removal of
sand from Borrow Areas Al and A2 on St. Lucie Shoal. The purpose of these provisions is to avoid
"wasting" sediment on St. Lucie Shoal that could be used to nourish this and other beaches or wetlands,
now and in the future.
USACE and the County will conduct all dredging operations in accordance with requirements outlined
in the ECM. Any modification to this Plan will be submitted to BOEM for review prior to
commencement of dredging (pursuant to Title IV Provision (D)(1)).
7. Submittal of Production and Volume Information
In order for BOEM to monitor adherence to dredging within the leased borrow area boundaries
denoted in Table 1, USACE and/or the County will submit to BOEM a summary of the dredge track
lines, outlining any deviations from the Plan, every two weeks. This will include a color -coded plot
of the draghead, cutterhead, or other hydraulic or mechanical dredging device, showing any horizontal
or vertical dredge violations. The dredge track lines must show dredge status: hoteling, dredging,
transiting, or unloading. This map will be in PDF format.
At least every two weeks, USACE and/or the County will electronically provide a report of the
construction progress, including estimated volumetric production rates, to BOEM. The Project
Completion Report, as described in Title IV Provision (D)(13), will also include production and
volume information.
8. Local Notice to Mariners
USACE and/or the County will place a notice in the U.S. Coast Guard Local Notice to Mariners
regarding the timeframe and location of dredging and construction operations in advance of
commencement of dredging.
9. Marine Pollution Control and Contingency Plan
USACE and/or the County will prepare for and take all necessary precautions to prevent discharges
of oil and releases of waste or hazardous materials that may impair water quality. In the event of such
an occurrence, notification and response will be in accordance with applicable requirements of 40 CFR
Part 300. All dredging and support operations under this MOA will be compliant with U.S. Coast
Guard regulations and the U.S. Environmental Protection Agency's Vessel General Permit, as
applicable. USACE and/or the County will notify BOEM as soon as practicable of any noncompliant
0
Page 26 of 47
discharges and remedial actions taken, and USACE and/or the County will provide copies of reports
of the incident and resultant actions electronically.
10. Encountering of Munitions and Explosives of Concern (MEC)
Encountering Munitions and Explosives of Concern (MEC) of all types is possible on the OCS. MEC
includes unexploded ordnance, discarded military munitions, and munitions constituents. It is the
responsibility of USACE and/or the County to proactively manage and continuously evaluate this risk.
BOEM assumes no liability for the presence of MEC within Borrow Areas Al and A2, nor the
subsequent encounter, handling, or disposal of MEC in accordance with Title IV Provision (D)(4),
above.
The Plan developed per Title IV Provision (D)(1), above, roust include a protocol of MEC reporting,
safety, and response actions that USAGE, who is responsible for project construction, will implement
if MEC are encountered (herein "MEC Protocol"). The MEC Protocol should reflect the risk
assessment of encountering different MEC types prepared by USACE and considered by BOEM as
part of its technical evaluation. The MEC Protocol should address (1) notification to the relevant
federal and state agencies, (2) engagement of qualified MEC identification, inspection, handling, or
detonation specialists when warranted, and (3) MEC response measures and actions when
warranted. The MEC Protocol should describe measures or actions that USACE may take that will
investigate, identify, or decrease MEC risks, including MEC screening, MEC avoidance during
dredging, MEC relocation activities, and MEC detonation.
Upon first encounter of MEC or a change in type of MEC encountered while conducting operations
on the OCS, USACE will report the discovery within 24 hours to Geoffrey Wikel, Acting Division
Manager, BOEM Marine Minerals, at (703) 787-1283 and dred e�(a�boem.gov. USACE will
notate what actions were taken or will be taken. The notification will include a description of the
activities leading to the MEC encounter; the day, time, location, and load of the MEC encounter; the
type of MEC encountered; a description of its inert state or explosive quantity; and its disposition.
The BOEM Director reserves the right to immediately suspend OCS operations in accordance with 30
CFR 583.350(b)(3) should the threat of serious harm and damage warrant it. If issued, any such
suspension will be lifted once the threat is abated.
If the MEC Protocol must be modified to account for unexpected circumstances, USACE will notify
BOEM at dred eig nfo(cr),boem.gov and provide an updated MEC Protocol. Follow-on reports to BOEM
concerning subsequent encounters may be reported through consolidated periodic notifications if
agreed upon by BOEM.
If MEC are encountered within the material after it has been removed from the OCS, such as during
pump -out operations or within placed fill material, it is the responsibility of USACE to manage such
encounters. If MEC are unexpectedly discovered in the Project designated onshore areas after
completion of the Project, USACE and the County are solely responsible for any remediation.
11. Bathymetric Surveys
At a minimum, USACE and/or the County will provide BOEM with pre- and post -dredging
bathymetric surveys of Borrow Areas Al and A2 on St. Lucie Shoal. USACE and/or the County will
conduct a pre -dredging survey of Borrow Areas Al and A2 on St. Lucie Shoal within 60 calendar days
9
Page 27 of 47
prior to the commencement of dredging and will provide the data to BOEM for review via
dredgeinfo(a�,boem.gov, allowing for a minimum seven (7) business days for BOEM to determine if
the survey is acceptable before USACE and/or the County commences dredging. A qualified
hydrographic surveyor, independent from the dredging/construction contractor, will conduct and
oversee the survey, and must approve the survey results before transmitting them to BOEM. USACE
and/or the County will conduct post -dredging survey of Borrow Areas Al and A2 on St. Lucie Shoal
within 60 calendar days after the completion of dredging. BOEM recommends that USACE and/or
the County conduct additional bathymetric surveys of Borrow Areas Al and A2 on St. Lucie Shoal
both one (1) and three (3) years after the completion of dredging to document borrow area evolution
and provide information to inform future decisions and consultations regarding the use of OCS sand
resources. U SACE and/or the County will perform surveys, error analysis, and reporting in accordance
with the most recent edition of the National Oceanic and Atmospheric Administration's (NOAA's)
Office of Coast Survey Hydrographic Survey Field Procedure Manual. Survey standards and
requirements are specified in the manual and can be found on the Coast Survey Document Library
website.
For bathymetric surveys, 100 percent coverage using multi -beam bathymetric survey methods is
required. All bathymetric data will be roll, pitch, heave, and tide corrected using best practices. Sound
velocity corrections will be applied based on measurements made during and throughout the duration
of the survey using a profiling sound velocity meter to obtain water column sound velocities with casts
that log the entire water column to the seafloor. Survey lines of the specific dredge area will be
established at intervals necessary to provide 100 percent coverage. All survey lines will extend at
least 100 meters (328 feet) beyond the edge of the limits of Borrow Areas Al and A2 on St. Lucie
Shoal as defined in this MOA.
USACE and/or the County will collect all data in such a manner that post -dredging bathymetric
surveys are compatible with the pre -dredging bathymetric survey data to enable the latter to be
subtracted from the former to calculate the volume of sand removed, the shape of the excavation, and
the nature of post -dredging bathymetric change. Pre -dredge bathymetric survey transects must be
reoccupied during the post -dredging surveys. USACE and/or the County will conduct surveys using
kinematic GPS referenced to a GPS base station occupying an established monument (NAVD 88
vertical control) within 24 kilometers (15 miles) of the survey area, a National Geodetic Survey real-
time network, or a water -level gauge deployed within the vicinity of Borrow Areas Al and A2 on St.
Lucie Shoal and referenced to an established monument (NAVD 88 vertical control), unless alternative
methods are approved by BOEM. Pre- and post -dredging surveys must be referenced to the same
water -level gauge, tide gauge, real-time network, benchmark, or BOEM-approved method. An
uncertainty or error analysis will be conducted on the bathymetric dataset based on calculated
differences of measured elevations (depths) at all transect crossings.
If data accuracy, coverage, quality, or other parameters for either pre- or post -dredging surveys are
not sufficient to provide for accurate comparisons between the pre -dredge and post -dredge surveys
(e.g., do not meet specifications and standards discussed or referenced above), BOEM may require
USACE and/or the County to conduct a new survey at the pre -dredge and/or post -dredge phase.
The delivery format for bathymetry data submission is an ASCII file (e.g., .xyz, .txt, .csv, .dat)
containing x, y, z data and a digital elevation model (e.g., .bag, .tiff, .asc). The file name(s) of
bathymetric data submissions should be unambiguous and as a recommendation should include the
survey ID (e.g., USACE survey number) and/or borrow area name, bin spacing, acronym for vertical
10
Page 28 of 47
datum, units, and date of survey completion (example file name: SURVEYID_BorrowArea_
3x3AVG_NAVD88_ft_MMDDYYYY.xyz). The horizontal data will be provided in the NAD 83
Florida State Plane East, U.S. survey feet. Vertical data will be provided in the NAVD 88, U.S. survey
feet unless otherwise specified. USAGE and/or the County must submit a methods section and results
of the uncertainty analysis, field notes, and metadata record (FGDC-endorsed geographic metadata
standard, e.g., ISO 19115-2, XML encoding specifications ISO 19139) to BOEM with the processed
bathymetric data products. An 8.5 x 11-inch plan view plot of the pre- and post -construction data will
be provided showing the survey vessel navigation tracks, as well as contour lines at appropriate
elevation intervals. A plot of the digital elevation model will also be provided. These plots will be
provided in Adobe PDF format. Images and descriptions of any previously identified side scan sonar
targets or newly identified bathymetric anomaly targets will be included and identified on an index
map.
12. Avoidance of Archaeological and Other Resources
Offshore Prehistoric or Historic Resources
There are no known archaeological resources in Borrow Areas Al or A2.
If the Parties discover any previously unknown historic or archeological resources while
accomplishing the Project, USACE will serve as lead agency under NHPA Section 106. USACE will
initiate the Federal and State coordination required to determine if the remains warrant a recovery
effort or if the site is eligible for listing in the National Register of Historic Places. In the event that
the Parties and/or dredge operators discover any archaeological resources while conducting dredging
or other bottom -disturbing operations in Borrow Areas Al and A2 on St. Lucie Shoal, USACE will
immediately and electronically report the discovery to the Marine Minerals Division Chief at BOEM
(see contact information above). USACE will coordinate with BOEM on the measures needed to
evaluate, avoid, protect, and, if needed, mitigate adverse impacts from an unanticipated discovery. If
investigations determine that the resource is significant, the Parties will together determine if further
action is required and how best to protect the resource. BOEM will work with USACE, consistent
with the provisions in 30 CFR 583.350.
Offshore Benthic Habitat Resources
Borrow Area A 1 includes an area within the higher elevations of the shoal that must be avoided during
dredging operations ("avoidance area") (Table 2). Additionally, USACE will orient dredge cuts with
the long axis of the shoal and limit cut depths to avoid the creation of pits or deep furrows. If a
modification is needed to the avoidance area or dredge operational requirements, USACE may submit
a written request for a minor modification consistent with 30 CFR 583.345(b). Upon receipt of the
request, BOEM may grant and memorialize the minor modification via letter.
11
Page 29 of 47
Table 2. Coordinates for Area to be Avoided during Dredging Operations within
Borrow Area At (See Attachment 1)
Point
Latitude
Longitude
Easting
Northing
8
27.30218515
-80.14923812
932,453
1,079,961
9
27.30149920
-80.14952047
932,363
1,079,711
10
27.30030368
-80.14968969
932,311
1,079,276
11
27.30019371
-80.14924714
932,455
1,079,237
12
27.30208475
-80.14765620
932,967
1,079,928
Note: Longitude and Latitude in Geographic Coordinate System (decimal degrees) North American Datum (NAD) 1983.
Easting and Northing in Florida East State Plane Coordinates (feet) NAD 1983
13. Project Completion Report
Consistent with Title IV Provision (D)(15), USACE and/or the County will submit a project
completion report to BOEM within 120 calendar days following completion of the activities
authorized under this MOA. USACE and/or the County will send this report and supporting materials
electronically. The report will contain, at a minimum, the following information:
• the names and titles of the project managers overseeing the effort (as well as the
engineering firm (if applicable), and the contractor), including contact information (phone
numbers, mailing addresses, and email addresses);
• a narrative including the location, construction costs, and description of the Project, the
final, as -built features, boundaries, and acreage, including the restored beach width and
length;
• the final total volume of material extracted from the borrow area and the volume of material
actually placed on the beach or shoreline (including a description of the volume calculation
method used to determine these volumes);
• notation that USACE has confirmed that BOEM has received the full set of DQM data, in
ASCII files, containing the x, y, z coordinates and time stamp of the cutterhead or drag arm
locations;
• a narrative discussing major construction sequences and activities, and, if applicable, any
significant problems encountered and solutions implemented;
• a table showing the major types of construction equipment used and the nature of their use
by phase of the Project construction (e.g., dredge, booster pumps, bulldozer);
• a list and description of any safety -related issues or accidents reported during the life of
the Project, including any circumstances that required exercise of the MEC Protocol and
detailed after -action information regarding the MEC encounter and application of the MEC
Protocol. This should include any daily reports and a final summary from the entity
handling MEC encounters;
• a narrative and any appropriate information to verify implementation of ECM requirements
and describe any environmental monitoring associated with the Project;
• a narrative and any appropriate shapefrles defining areas of the borrow area deemed
unsuitable during the course of the Project (if applicable);
12
Page 30 of 47
• a table listing significant construction dates beginning with bid opening and ending with
final acceptance of the Project by USACE;
• digital appendices containing the as -built Project footprint (.shp /.gdb), and bathymetric
survey data outlined in Section 11 above;
• metadata appropriate to geospatial deliverables; and
• any additional pertinent Project photo or video documentation in high -resolution format.
14. Reporting Compliance
In addition to a point of contact identified in Title IV Provision (B) for receipt of notifications, USACE
and / or the County will designate in advance of construction a single point of contact (and preferably
a back-up contact) who is responsible for facilitation of compliance with all MOA requirements. This
person will serve as the Compliance Officer. USACE and / or the County will provide this contact
information to BOEM, electronically, at least 30 calendar days in advance of dredging and
construction operations.
The Parties will attempt to reasonably comply with the provisions of this MOA. Should there be an
allegation of a failure to comply, the alleged failure will be corrected as soon as possible and/or
resolved jointly among BOEM, USACE, and the County, including through the dispute resolution
process identified in Title IV Provision (D)(16).
15. Sharing of Information
Consistent with the purpose stipulated by the Parties in Title 11, and to the extent allowed by law,
policy and regulation, BOEM, USACE, and the County agree to: (1) share all information needed for
or generated from the Project, including the sharing of implementation and other applicable schedules
and (2) provide such information to the requesting Party as expeditiously as possible, and (3) agree to
work to ensure that all required completion report information is received.
The Parties to this MOA acknowledge that information and reports required by and/or exchanged
pursuant to the subject Project may include confidential business information, proprietary information,
or other sensitive information that should be protected from disclosure.
Any Party requesting that information or reports provided pursuant to this MOA be treated as
confidential, will prominently mark the information and report as "Confidential" along with providing
the basis for the claim of confidentiality. Any cover correspondence submitted with the information
or report will likewise note the claim of confidentiality. To the extent practicable, a Party to this MOA
may only request information that has been marked as "Confidential" and is in the possession of
another Party to this MOA if the information is needed by the requesting Party to carry out its
obligations under this MOA or if the information is necessary for the requesting Party to fulfill its
obligations under the law. The Party in possession of the information requested may work with the
requesting party to determine if the information may be shared without waiving the confidential nature
of the material.
The Parties further agree that they will notify the other Parties as soon as possible, in writing, of any
request by any person seeking the release or disclosure of information marked "Confidential" in whole
or in part, including, but not limited to, requests pursuant to Court orders, discovery, subpoenas, or
other compulsory process, or public access requests under applicable Federal or State law.
13
Page 31 of 47
Notification will be considered timely if it provides the Parties or individuals claiming the information
or report is confidential a reasonable opportunity to seek a Court order to prevent release or disclosure.
Any disputes among the Parties regarding requests for information or the confidential nature of the
information requested will be resolved according to applicable law and through the dispute resolution
process identified in Title IV Provision (D)(16). With regard to third -party requests for information
produced or shared in accordance with this MOA, the request will be addressed in accordance with
applicable law. If the Party claiming the information or report is confidential fails to obtain a timely
Court order preventing the release or disclosure of the information, the Party in possession of the
information will release it to the extent required by applicable law.
16. Resolution of Disputes
The Parties agree to make every attempt to settle any disputes regarding this MOA at the lowest
operational level within seven (7) business days. In the case of (1) a substantial disagreement between
BOEM and USACE or between BOEM and the County with respect to any aspect of BOEM's
authorization of the use of OCS sand resources in accordance with the terms and conditions as
specified or (2) any alleged breach by a Party of the terms and conditions as specified herein, the Party
alleging the disagreement or breach will state the area(s) of disagreement or alleged breach in writing
and present such statement to the other Parties for consideration. If dispute resolution is not successful
within thirty (30) calendar days and if appropriate under 30 CFR 583.330 and 583.350, BOEM may
suspend or terminate the Agreement, refer the matter to appropriate Federal or State agency for
enforcement, or both. The BOEM Director reserves the right to immediately suspend and subsequently
terminate this Agreement pursuant to 30 CFR 583.350(b).
17. Miscellaneous
This MOA is not intended to affect any pre-existing or independent relationships or obligations among
DOI, USAGE, and the County, including any other relationships or obligations between BOEM and
USACE, or any other units of DOI or the Department of the Army.
All rights in Borrow Areas Al and A2 on St. Lucie Shoal not expressly granted to USACE and the
County are hereby reserved to BOEM. BOEM reserves the right to authorize other uses in Borrow
Areas Al and A2 on St. Lucie Shoal that will not unreasonably interfere with activities authorized
under this MOA. BOEM will allow USACE and the County to review and comment on any proposed
authorizations for the use of OCS sand resources in any portion of St. Lucie Shoal while this MOA is
in effect. If any Party to this MOA makes a request for a separate negotiated agreement for the use of
OCS sand resources in any portion of St. Lucie Shoal, then it must share the request with all the Parties
to this MOA, and BOEM will consider comments on the request from the other Parties.
Nothing herein is intended to conflict with current DOI, USACE, or State statutes or regulations. If
the terms of this MOA are inconsistent with existing statutes or regulations of any of the Parties
entering into this MOA, then those portions of this Agreement which are determined to be inconsistent
will be invalid, but the remaining terms and conditions not affected by the inconsistency will remain
in full force and effect. At the first opportunity for review of the MOA after such inconsistency is
identified, all necessary changes will be accomplished either by an amendment to this MOA or by
entering into a new MOA. Any MOA amendment can be requested in writing by any Party and will
not go into effect unless and until the other Party agrees.
14
Page 32 of 47
This Agreement may be executed in two (2) or more counterparts, each of which will be deemed an
original. The signatures to this Agreement may be executed on separate pages, and when attached to
this Agreement will constitute one complete document.
[Signature Pages to follow.]
15
Page 33 of 47
MEMORANDUM OF AGREEMENT
AMONG THE BUREAU OF OCEAN ENERGY MANAGEMENT
OF THE DEPARTMENT OF THE INTERIOR
AND THE CORPS OF ENGINEERS
OF THE DEPARTMENT OF THE ARMY
AND ST. LUCIE COUNTY, FLORIDA
REGARDING THE USE OF OUTER CONTINENTAL SHELF SAND RESOURCES
FOR CONSTRUCTION OF THE ST. LUCIE COUNTY, FLORIDA COASTAL STORM
RISK MANAGEMENT PROJECT
BOEM Negotiated Agreement No. OCS-A 05XX
Megan Carr, PhD, CPG
Chief, Office of Strategic Resources
Bureau of Ocean Energy Management
Department of the Interior
Date:
Signatory Page
Brandon L. Bowman
Colonel, U.S. Army
District Commander
Date:
St. Lucie County, Florida
LI-A
Date:
, Erosion District Chair
Page 34 of 47
MEMORANDUM OF AGREEMENT
AMONG THE BUREAU OF OCEAN ENERGY MANAGEMENT
OF THE DEPARTMENT OF THE INTERIOR
AND THE CORPS OF ENGINEERS
OF THE DEPARTMENT OF THE ARMY
AND ST. LUCIE COUNTY, FLORIDA
REGARDING THE USE OF OUTER CONTINENTAL SHELF SAND RESOURCES
FOR CONSTRUCTION OF THE ST. LUCIE COUNTY, FLORIDA COASTAL STORM
RISK MANAGEMENT PROJECT
BOEM Negotiated Agreement No. OCS-A 05XX
Megan Carr, PhD, CPG
Chief, Office of Strategic Resources
Bureau of Ocean Energy Management
Department of the Interior
Date:
Signatory Page
Brandon L. Bowman
Colonel, U.S. Army
District Commander
Date:
St. Lucie County, Florida
LI-A
Date:
, Erosion District Chair
Page 35 of 47
MEMORANDUM OF AGREEMENT
AMONG THE BUREAU OF OCEAN ENERGY MANAGEMENT
OF THE DEPARTMENT OF THE INTERIOR
AND THE CORPS OF ENGINEERS
OF THE DEPARTMENT OF THE ARMY
AND ST. LUCIE COUNTY, FLORIDA
REGARDING THE USE OF OUTER CONTINENTAL SHELF SAND RESOURCES
FOR CONSTRUCTION OF THE ST. LUCIE COUNTY, FLORIDA COASTAL STORM
RISK MANAGEMENT PROJECT
BOEM Negotiated Agreement No. OCS-A 05XX
Megan Carr, PhD, CPG
Chief, Office of Strategic Resources
Bureau of Ocean Energy Management
Department of the Interior
Date:
Signatory Page
Brandon L. Bowman
Colonel, U.S. Army
District Commander
Date:
St. Lucie County, Florida
LI-A
Date:
, Erosion District Chair
Page 36 of 47
MEMORANDUM OF AGREEMENT
AMONG THE BUREAU OF OCEAN ENERGY MANAGEMENT
OF THE DEPARTMENT OF THE INTERIOR
AND THE CORPS OF ENGINEERS
OF THE DEPARTMENT OF THE ARMY
AND ST. LUCIE COUNTY, FLORIDA
REGARDING THE USE OF OUTER CONTINENTAL SHELF SAND RESOURCES
FOR CONSTRUCTION OF THE ST. LUCIE COUNTY, FLORIDA COASTAL STORM
RISK MANAGEMENT PROJECT
BOEM Negotiated Agreement No. OCS-A 05XX
Megan Carr, PhD, CPG
Chief, Office of Strategic Resources
Bureau of Ocean Energy Management
Department of the Interior
Date:
Signatory Page
Brandon L. Bowman
Colonel, U.S. Army
District Commander
Date:
St. Lucie County, Florida
I:
Date:
Erosion District Chair
Page 37 of 47
MEMORANDUM OF AGREEMENT
AMONG THE BUREAU OF OCEAN ENERGY MANAGEMENT
OF THE DEPARTMENT OF THE INTERIOR
AND THE CORPS OF ENGINEERS
OF THE DEPARTMENT OF THE ARMY
AND ST. LUCIE COUNTY, FLORIDA
REGARDING THE USE OF OUTER CONTINENTAL SHELF SAND RESOURCES
FOR CONSTRUCTION OF THE ST. LUCIE COUNTY, FLORIDA COASTAL STORM
RISK MANAGEMENT PROJECT
BOEM Negotiated Agreement No. OCS-A 05XX
Megan Carr, PhD, CPG
Chief, Office of Strategic Resources
Bureau of Ocean Energy Management
Department of the Interior
Date:
Signatory Page
Brandon L. Bowman
Colonel, U.S. Army
District Commander
Date:
St. Lucie County, Florida
LI-A
Date:
, Erosion District Chair
Page 38 of 47
MEMORANDUM OF AGREEMENT
AMONG THE BUREAU OF OCEAN ENERGY MANAGEMENT
OF THE DEPARTMENT OF THE INTERIOR
AND THE CORPS OF ENGINEERS
OF THE DEPARTMENT OF THE ARMY
AND ST. LUCIE COUNTY, FLORIDA
REGARDING THE USE OF OUTER CONTINENTAL SHELF SAND RESOURCES
FOR CONSTRUCTION OF THE ST. LUCIE COUNTY, FLORIDA COASTAL STORM
RISK MANAGEMENT PROJECT
BOEM Negotiated Agreement No. OCS-A 05XX
Megan Carr, PhD, CPG
Chief, Office of Strategic Resources
Bureau of Ocean Energy Management
Department of the Interior
Date:
Signatory Page
Brandon L. Bowman
Colonel, U.S. Army
District Commander
Date:
St. Lucie County, Florida
LI-A
Date:
, Erosion District Chair
Page 39 of 47
[This page intentionally left blank]
Page 40 of 47
d0 3doas
S3SOd
A'INO aOd21t1d WinnowWinnowNmom
";
7a
Noiio 'dISNOO UOd LON
4
fr /
F
1
0"
i//
1 P" ON-/
Y07 NC
BR
� Pv
P�
c°
Z z
Z z
i)
O
CY U
w
4`
Z
'..
U) U
rn
R`JFP
c¢
O
ct
U
_O
ct
U
ct
O
O
U
U
O
O
U
U
I-�
C/1
IA N%nd 'VgVV MOMMOO
d
-ij 'AiNnoo mon-vis
N0110MU qNO') HOJ ION ONVISI NOSimpinm minos
I.I. ilhH,"3d,')OMd"30"1 103rOHd IN3W30VNVW MSIH WWOIS IVISVOO
Cf)
Lu
Z y
)
Lli
"�1�ttiti� � 1 6 1 � I��il�f
If
'41
4,
—Z
v oz,
0
0
lu
0
V P
�t
11
R
R
R S.
�Kt
N
N E
'hN
R
WC
',7
muni
it
A 1818FaH
cz
U
ct
ap
4.1
Z3
O
ct
0
t-
0
0
CN
Nt
W
0)
M
a_
[This page intentionally left blank]
Page 43 of 47
TO:
PRESENTED BY
SUBMITTED BY:
SUBJECT:
BACKGROUND:
AGENDA REQUEST
Erosion District
Joshua Revord, Port, Inlet & Beaches Director
Port, Inlet & Beaches
Resolution — State Beach Funding Request
2025-4394
DATE: 7/22/2025
The Beach Management Funding Assistance Program (BMFA) is a Long -Range Budget Plan administered
through the Florida Department of Environmental Protection (FDEP) to assist eligible local governments with
their beach erosion control projects. Each application request must include a detailed project description, cost
estimate, and a supporting resolution from the governing body. Individual projects then receive a priority
ranking based upon several criteria. The application submittal deadline for consideration of FY-2026/27 State
funding is July 31, 2025. A Board resolution must be received prior to September 26, 2025. More detailed
information will accompany the actual funding applications to FDEP. Staff intend on requesting funding for
the following projects/efforts:
Project: Fort Pierce Beach
Effort: 2026 Physical and Biological Monitoring
FDEP Funding Request (est.): $175,000 (50%)
Local Match Share (est.): $175,000 (50%)
Project: Fort Pierce Beach
Effort: 2026 Fort Pierce Section 203/403 PED
FDEP Funding Request (est.): $280,000.00 (50%)
Local Match Share (est.): $280,000.00 (50%)
Federal Share (est.): $1,040,000 (Total project cost estimated at $1,600,000)
Project: South County Beach
Effort: 2026 Physical and Biological Monitoring - Year 1 (Post -Construction)
FDEP Funding Request (est.): $ 228,322.50 (43.49%)
Local Match Share (est.): $296,677.50 (56.51%)
Please note that the funding request values above are estimated, utilizing the best available information at
the time of consideration. Generally, staff intends on pursuing post -construction monitoring assistance for the
project application above. Specific funding requests are subject to change based on project specific needs at
the time of final application submission.
Page 44 of 47
PREVIOUS ACTION:
The Erosion District has annually submitted beach funding requests to the State of Florida Department of
Environmental Protection (FDEP) to sustain a very successful beach and inlet management program.
FINANCIAL IMPACT:
This agenda item is for approval to submit a 2026/2027 Beach Management Funding Assistance (BMFA)
request(s) and a supporting resolution to the State of Florida (FDEP). There are no financial impacts to the
County at this time. If the funding request(s) are approved by the State, staff will return to the Erosion District
Board for acceptance of funding and to confirm that there are sufficient local matching funds.
RECOMMENDATION:
Staff recommends Board approval to 1) submit the Beach Management Funding Assistance (BMFA) Program
funding application request(s) to the State of Florida (FDEP) for FY-2026/27 along with the attached
supporting Resolution (RES-2025-137), and 2) authorization for the Chair to sign documents as approved by
the County Attorney. This is in accordance with Strategic Plan Policy ES 6.1.4.
COMMISSION ACTION:
RESULT:
MOVER:
None
SECONDER:
None
AYES:
None
NAYS:
None
EXCUSED:
None
Coordination/Signatures
Date: July 14, 2025
Joshua Revord, Port, Inlet & Beaches Director
Date: July 14, 2025
Jennifer Hill, Office of Management & Budget Director
x
Date: July 15, 2025
Daniel McIntyre, County Attorney
Date: July 15, 2025
Mayte Santamaria, Deputy County Administrator
Page 45 of 47
Page 46 of 47
RESOLUTION 2025-137
A RESOLUTION OF THE ST. LUCIE COUNTY EROSION DISTRICT
AUTHORIZING THE SUBMITTAL OF AN APPLICATION TO THE
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
FOR FISCAL YEAR 2026/27 FUNDS UNDER THE FLORIDA BEACH
MANAGEMENT FUNDING ASSISTANCE PROGRAM; SETTING
FORTH FINDINGS; AND PROVIDING FOR AN EFFECTIVE DATE.
WHEREAS, the St. Lucie County Erosion District ("District") and the Florida Department
of Environmental Protection (11FDEP11) have adopted the Fort Pierce Inlet Management Plan and
desires to implement the recommendations contained therein; and,
WHEREAS, the District has established a Long -Range Budget Plan for the Florida Beach
Management Funding Assistance Program and desires to implement specific projects contained
therein; and,
WHEREAS, under the provisions of Section 161.101, Florida Statutes, FDEP accepts and
processes applications for the Florida Beach Management Funding Assistance Program; and,
WHEREAS, under the Program guidelines of the Florida Beach Management Funding
Assistance Program, the District is required to submit a supporting resolution with their
application request.
NOW, THEREFORE, BE IT RESOLVED by the St. Lucie County Erosion District as follows:
1. FDEP is requested to approve and support the maximum State funding allowed
for this application request for Fiscal Year 2026/27. The District will provide the required local
share in accordance with the State Legislature's appropriation.
2. This Resolution shall take effect immediately upon its adoption.
AFTER MOTION AND SECONDED, the vote on this Resolution was as follows:
Chair James Clasby
Vice -Chair Larry Leet
Commissioner Jamie Fowler
Commissioner Cathy Townsend
Commissioner Erin Lowery
PASSED AND DULY ADOPTED this 22 day of July
ATTEST:
ST. LUCIE COUNTY EROSION DISTRICT
BY:
DEPUTY CLERK CHAIR
APPROVED AS TO FORM AND
CORRECTNESS:
BY:
COUNTY ATTORNEY