HomeMy WebLinkAboutFIELD AND LABORATORY REPORTn � � � �vl,p✓ � 4
UNIVERSAL f?at TyUES ped: ect No October 27,25019 0
ENGINEERINGSCIENCES-EnvironmentalSCIENCES _
Consultants In: Geotechnical u
Geophysical Services • Materials Testing • Th'reshold Inspection
Building Code Administration, Compliance Inspection&Plan Review
820 Brevard Avenue, Rockledge, FL 32955 - P: 321.638.0808 - F: 321.638.0978
Construction Materials Testing Services
FIELD AND LABORATORY REPORT COVER I
Client: Ahrens Companies ---"
1461 Kinetic Road
Lake Park, FL 33403 OCT 2 9 �p±g
Project: MRO Hangar at Treasure Coast IA ST. Lucie County, Permitting
3191 Jet Center Terrace, Ft. Pierce, County, FL
As requested, Universal Engineering Sciences, Inc. (UES) representative(s) performed construction materials testing and/or
field inspection services on the above project. Testing results and/or inspection observations are reported on the attached
sheets. The contents of this package are summarized below:
Scope of Work
Work Order No.
Date
I Type of Report
117055.1
10/25/2019
In -Place Density Test Report w/ActMty Record
117055-2
1 1012512019
In -Place Density Test Report
We hope this information is sufficient for your immediate needs. If you have any questions, please do not hesitate to contact
the undersigned.
SCANNED
BY
St. Lucie County
48796
STATc OF
C�
Sincerely,
Universal Engineering Sciences, Inc.
Certificate of Authorization No. 00000549
Richard E
Hoaglin
2019.10.28
13.42:04
-04'00'
Richard E. Hoaglin, P.E.
FLORIDA
Professional Engineer No. 48796
This Item has been electronically signed and sealed by
Richard E. Hoaglin, P.E. using a Digital Signature. PAnted
copies of this document are not considered signed and
sealed and the signature must be verified on any electronic
copies.
[CC Email: Cpanebianco@ahrenscompanies.00m; Ljennings@ahrenscompanies.com; Rhatton@ahrenscompanles.com
UES Project No: 0310.1900175.0000
UES DOS No:
UNIVERSAL
UES Report No: 1170554 ARC 02519
ENGINEERING SCIENCES On -Site Time (hrs): 1.00
Consultants In: Geotechnical Engineering • Environmental Sciences Lab Time (hrs): 0.00
Geophysical Services @ Materials Testing s Threshold Inspection Travel Time (hrs): 1.25
Building Code Administration, Compliance Inspection & Plan Review Total Time (hrs): 2.25
820 Brevard Avenue, Rockledge, FL 32955 - P: 321.638.0808 - F: 321.638.0978
Activity Record
Client: Ahrens Companies
1461 Kinetic Road
Lake Park, FL 33403
Project: MRO Hangar at Treasure Coast IA
3191 Jet Center Terrace , Ft. Pierce, County, FL
Date of Activity: Friday, 25 October, 2019
Technician: Russell Brause
As requested, a Universal Engineering Sciences Technician was present at the above referenced project site for the purpose of
earthwork testing for the Tank pad., Dumpster pad.
While on site, the technician observed the general condition of the areas to be tested and performed 1 density test(s) for
Tank pad. All test(s) were performed in accordance with the ASTM D-6938 Nuclear Gauge Method and were found to meet
the project compaction requirements of 95% of the maximum dry density per ASTM D-1557.
Technician also tested and performed 1 density test(s) for Dumpster pad. All test(s) were performed in accordance with
the ASTM D-6938 Nuclear Gauge Method and were found to meet the project compaction requirements of 95% of the
maximum dry density per ASTM D-1557.
The Contractor was notified of the test results or a copy was left for their records.
I
UNIVERSAL
ENGINEERING SCIENCES
Consultants In: Geotechnical Engineering - Environmental Sciences
Geophysical Services - Materials Testing - Threshold Inspection
Building Code Administration, Compliance Inspection & Plan Review
820 Brevard Avenue, Rockledge, FL 32955 - P: 321.638.0808 - F: 321.638.0978
Client:
Project:
Area Tested:
Type of Test:
Technician:
Requirements:
In -Place Density Test Report
Ahrens Companies
1461 Kinetic.Road
Lake Park, FL 33403
MRO Hangar at Treasure Coast IA
3191 Jet Center Terrace, Ft. Pierce, County, FL
Tank pad
Field: ASTM D-6938 Nuclear Gauge Method
Lab: ASTM D1557 Modified Proctor
Russell Brause
UES Project No: 0310.1900176.0000
UES DOCS No:
UES Report No: 117055-1 DT 102519
Date of Test: 10/25/2019
95% of Proctor maximum dry density. These tests apply to the fill and/or surficial soil conditions
onlv and do not address the condition of the undedvino soils below the tested depths.
Field Dry
Field
Test
Depth
Proctor
Density
Moisture
I
%
Comments
No.
Location of Test
Range
(Inch)
(2)
(PCF)
%
Compaction
(3)
1
Ctr of pad.
0 to -1 ft
12.00
243M
108.E
1 5.6
1 97
A
(1) Ref. Datum: 0 = Top of Final Grade
(2)
Maximum
Optimum
Proctor
Dry
Moisture
#
Density
Content
24384
111.6
10.0
This test was performed without deviation from ASTM procedures.
(3) Comments Key
A. Compaction meets min. requirements
B. Compaction does not meet min, requirements-
C. Moisture does not meet requirements
D. Recompaction required
E. Recompacted, Retested, Meets Requirements
This report shall not be reproduced, except in full without the written approval of Universal Engineering Sciences.